This document is an Amendment (0001) to a Multiple Award Task Order Contract (MATOC) solicitation for the Bank Stabilization and Navigation Project (BSNP) River Structure Maintenance. The solicitation (W9128F25R0043) is exclusively for small businesses and seeks contractors to perform river maintenance work along the Missouri River between River Mile 498.2 and 750.0. Work includes excavation, stone placement, and constructing river structure features like revetments, roots, reverse sills, chevrons, dikes, L-heads, and kickers, primarily accessible via floating plant.
Key amendment details include updates to Sections 00 21 00 and 00 22 00, wage determinations, and revised instructions for offerors. The solicitation requires a two-volume proposal: Volume 1 covering technical capabilities, stone quality, and past performance, and Volume 2 containing pricing details. The U.S. Army Corps of Engineers Omaha District intends to award approximately five contracts, with bids due on 31 July 2025 at 2:00 PM CST. The contract period is anticipated to be five years, with the primary NAICS code 237990 and a small business size standard of $45,000,000.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| BSNP MATOC Contractor Sign In Sheet 07152025.pdf | ||
| W9128F25R0043_BSNP MATOC Specifications for BASE 4of4.pdf | ||
| W9128F25R0043_BSNP MATOC Specifications for TO 2of4.pdf | ||
| W9128F25R0043_BSNP MATOC Solicitation 1of4.pdf | ||
| W9128F25R0043_BSNP MATOC Specifications for TO 2of4.pdf | ||
| MRPO00101_2025 BSNP MATOC Drawings 3of4.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment are as follow s:
1. Section 00 21 00 and 00 22 00 updates are listed in red text.
2. The w age determinations are updated to the current versions.
All other terms and conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 43
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 23-Jul-2025
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9128F25R0043
X 9B. DATED (SEE ITEM 11)
25-Jun-2025
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
23-Jul-2025
CODE
U.S. ARMY CORPS OF ENGINEERS, OMAHA DIST
CONTRACTING OFFICE
1616 CAPITOL AVENUE
OMAHA NE 68102-4901
W9128F 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W9128F25R0043
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 21 00 - INSTRUCTIONS
The following have been modified:
INSTRUCTIONS TO OFFERORS
Section 00 21 00 - Instructions to Offerors
INSTRUCTIONS TO OFFERORS (RFP)
PART 1 GENERAL
1. GENERAL SOLICITATION INFORMATION:
This Request for Proposal (RFP) is for solicitation of a Multiple Award Task Order Contract (MATOC). This solicitation is restricted to small business participants only.
2. SUBMISSION DEADLINE:
Offers shall be submitted as stated and by the time and date as specified in Block 13, Page 1 of the 1442 Solicitation. Only an electronic proposal will be accepted.
ELECTRONIC DELIVERY TO:
Contract Specialist – Clinton Russell at clinton.e.russell@usace.army.mil Contracting Officer – Nadine Catania at nadine.l.catania@usace.army.mil
See Section 00 22 10 SUPPLEMENTARY INSTRUCTIONS (SUBMISSION REQUIREMENTS AND EVALUATION) for additional submission details.
3. COPIES OF SOLICITATION DOCUMENT AND AMENDMENTS:
Copies of the solicitation and amendments are available by INTERNET ACCESS ONLY. All solicitation documents will be posted to the SAM.gov website. https://sam.gov/
3.1.It shall be the Contractor's responsibility to check the websites for any amendments. The offeror shall submit in the proposal all requested information specified in this solicitation.
There will be no public opening of the proposals received as a result of this solicitation.
4. OFFEROR'S QUESTIONS AND COMMENTS:
Questions and/or comments relative to these documents should be submitted via Bidder Inquiry as indicated below.
For any other administrative matters regarding this RFP, please contact:
Contract Specialist – Clinton Russell at clinton.e.russell@usace.army.mil and
Contracting Officer – Nadine Catania at nadine.l.catania@usace.army.mil
5. BIDDER INQUIRY
Questions relating to the proposal are to be submitted via Bidder Inquiry in ProjNet at:
https://www.projnet.org/projnet/ No Later Than 4pm Central Time on 21 July 2025, in order that they may be given consideration or actions taken prior to receipt of offers. The Bidder Inquiry system is to be used to ask and receive answers to all non-proprietary questions.
To submit and review inquiry items, prospective vendors will need to use the Bidder Inquiry Key presented below and follow the instructions listed below. A prospective vendor who submits a comment /question will receive an acknowledgement of their comment/question via ProjNet email notification after an answer to the comment/question after it has been processed by our technical team.
All timely questions and approved answers will be made available through ProjNet.
The Solicitation Number is: W9128F25R0043
The Bidder Inquiry Key is: 52DTRD-48EPCZ
a. Registration for ProjNet Bidder Inquiry Access
If you are already registered, go to Entering Bidder Inquiries in ProjNet Bidder Inquiry System below.
1. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.
2. Identify the Agency. This should be marked as USACE.
3. Key. Enter the Bidder Inquiry Key listed above.
4. Email. Enter the email address you would like to use for communication.
5. Click Continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.
6. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret
Question, Secret Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.
7. Click Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.
b. Entering Bidder Inquiries in ProjNet Bidder Inquiry System
1. For future access to ProjNet, you will not be emailed any type of password. You will utilize your Secret Question and Secret Answer to log in.
2. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.
3. Identify the Agency. This should be marked as USACE.
4. Key. Enter the Bidder Inquiry Key listed above.
5. Email. Enter the email address you used to register previously in ProjNet.
6. Click Continue. A page will then open asking you to enter the answer to your Secret Question.
7. Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.
8. Follow online screen instructions to enter specific bidder inquiries for the project.
c. The Bidder Inquiry System will be unavailable for new inquires as stated above in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary.
d. Offerors are requested to review the specification in its entirety, review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.
e. The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.
f. Offers will NOT be publicly opened. Information concerning the status of the evaluation and/or award will NOT be available after receipt of proposals.
6. GENERAL DESCRIPTION OF WORK
The work includes all work required for a wide range of construction services including river work, dredging, habitat creation, stabilization, rock placement, earth moving activities and incidental related work located along the Missouri River Valley from Rulo, NE (River Mile 498.2) to Lower Ponca Bend (River Mile 750.0).
7. PROPOSAL SUBMISSION REQUIREMENTS, EVALUATION AND CONTRACT
AWARD
See Section 00 22 00 SUBMISSION REQUIREMENTS AND EVALUATION
7.1. In order to be considered for award of a contract for the requirements of this solicitation, the Offeror must submit a proposal with its offer. Failure to submit a complete proposal may result in the entire offer being rejected. The proposal shall consist of two Volumes:
Volume 1, Technical Proposal / Past Performance
Factor 1 – Technical Capabilities- Construction Equipment, Staff, and Rock Placement Capacity
Factor 2 – Stone Quality and Capacity Factor 3 – Past Performance
Volume 2, Price Proposal Factor 4 – Price Proposal, consisting of an original signed
Standard Form 1442 “Solicitation, Offer, and Award”;
providing a price for all line items for the first Task Order in the corresponding price schedule and price breakout; and acknowledgment of all amendments to the solicitation.
Proposal Characteristics Each Volume shall contain a table of contents. All text must be legible and easily read. The page size of the Offeror’s proposal shall not exceed 8-1/2 by 11 inches. Diagrams, charts and tables shall conform to the paper size. All text shall be typed single-spaced. Margins (1-inch) shall be clean and clear. Offerors shall limit Volume 1, Technical / Past Performance Proposal, to a maximum of 40 pages. *The CPARS, Past Performance Questionaaires (PPQ), certification documents, cover page, table of content and tabbed pages will not count towards the 40 pages limit for Volume 1. Pages in excess of 40 pages will not be evaluated. Each Volume of the proposal shall be identified on the cover by the Solicitation Number, project title, name, address, and telephone number of the Offer, and one of the following on each volume in bold letters:
VOLUME 1: TECHNICAL / PAST PERFORMANCE PROPOSAL
VOLUME 2: PRICE PROPOSAL
7.2. The Proposal’s clarity, organization and cross referencing are mandatory. No material shall be incorporated by reference. General cross-references or cross referencing guides will not be considered appropriate cross-references.
7.3. The Proposal shall be organized by factors. They shall be described in separate sections, appropriately tabbed in a report form. All pages of each factor shall be sequentially numbered. Elaborate or lengthy presentations are not necessary or desirable.
7.4. The Technical narrative shall be written in a way to demonstrate a clear understanding of the requirements, but should not simply parrot the specifications. The Technical proposal shall not refer the reviewer to information contained in the Price proposal.
7.5. Additional Information to Be Provided in Volume 2.
Pro Forma Requirements. This information should be submitted electronically with the proposal in an envelope labeled “Pro Forma Requirements”. Provide an original and two copies.
This information consists of the following:
- The Offeror will submit a cover letter containing:
1) Solicitation number.
2) Name, address, email, and telephone and fax numbers of the Offeror.
3) Names, title, email, and telephone and fax numbers of persons authorized to negotiate on the Offeror’s behalf with the Government in connection with this RFP.
4) Name, title and signature of the person authorized to sign the proposal.
5) A statement specifying agreement with all terms, conditions and provisions included in the RFP.
- The Offer (the SF1442) duly executed with an original signature by an official authorized to bind the company. Include the Offeror’s UEI number in block 14.
- Acknowledgement of all amendments to the RFP in accordance with the instructions on the Standard Form 30 (amendment form).
- The completed Section 00 45 00 of the RFP (Representations and Certifications) and the
- Payment and Performance Bonds are required within ten (10) days of Task Oder Award. for each Task Order for which the Offeror is submitting a price proposal.
- Financial statement and bank letter that verify that sufficient funds will be available to finance the work.
8. JOINT VENTURES
8.1. Joint Ventures shall submit the following additional documentation regarding their business entities:
A certified copy of their Joint Venture agreement.
A detailed statement outlining the following in terms of percentages, where appropriate:
The relationship of the joint venture parties in terms of business ownership, capital contribution, and profit distribution or loss sharing.
The management approach of the joint venture in terms of who will conduct, direct, supervise and control the project and have custody and control of the assets of the joint venture and perform the duties necessary to complete the work.
The structure of the joint venture and decision-making responsibilities of the joint venture parties in terms of who will control the manner and method of performance of the work.
The bonding responsibilities of the joint venture parties.
Identification of the key personnel having authority to legally bind the joint venture to subcontracts and state who will provide or contract for the labor and materials for the joint venture.
Identification of party maintaining the joint venture bank accounts for the payment of all expenses and the deposits of all receipts, keep the books and records, and pay applicable taxes for the joint venture.
Identification of party furnishing the facilities, such as office supplies and telephone service.
Identification of party having overall control of the joint venture.
Joint Venture CAGE code.
8.2. Other sections of the proposal shall identify, where appropriate, whether key personnel are employees of the individual joint venture parties and identify the party, or hired as employees of the joint venture.
8.3. If one of the joint venture parties possesses experience and/or past performance as a Federal Government contractor or as a Corps of Engineers contractor, that experience and/or past experience will be included as the experience and/or past experience of the joint venture.
8.4. If subcontractor experience is submitted for consideration as part of the proposal, the offeror should include a commitment signed by offeror and subcontractor certifying that if a contract is awarded resulting from the proposal, the parties commit to joint performance as proposed. If the signed commitment is not fully executed by both parties and provided with the Past Performance Proposal, subcontractor references will not be evaluated or considered.
8.4.1. Affiliate companies, sister companies, teaming arrangements, joint venture agreement, etc., will be considered provided that sufficient documentation is included in the proposal. The primary offering entity must demonstrate that the affiliate will perform significant and critical aspects of the contract if awarded.
Documentation includes a copy of the signed arrangement such as documented affiliation, a copy of the teaming agreement, a copy of the joint venture agreement, etc.
9. BASIS FOR AWARD
9.1. The Government intends to establish a multiple award ID/IQ contract that will enable it to allow members of the contract pool to compete for future task orders. The Government intends to award a target of five (5) ID/IQ contracts from this solicitation to the responsible offeror(s) whose proposal conforms to the solicitation and is determined to be the Lowest Priced/Technically acceptable (LPTA) value to the Government. Award will be made on the basis of the lowest evaluated price of those proposals meeting or exceeding the acceptability standards for non-cost factors.
The Government reserves the right to award fewer contracts, more contracts, or none at all based on the proposals received. The Government intends to make its decision without discussions, but reserves the right to do so if the Contracting Officer determines it is necessary.
9.2. The Contracting Officer may establish a competitive range and conduct discussions with all the most highly rated proposals, unless the range is further reduced for purposes of efficiency pursuant to FAR 15.306(c)(2). At the conclusion of discussions, each offeror still in the competitive range shall be given an opportunity to submit a final proposal revision.
9.3. The Government will base its evaluation on the following factors.
9.4. There are two Technical Factors – Technical Capabilities, Stone Quality and Quantity, and one Past Performance Factor. All non-price factors are of equal importance.
Proposals are evaluated for acceptability, but not ranked using the non-price factors.
In order to be considered awardable, there must be an acceptable rating in every non-price factor. For the purpose of awarding the base ID/IQ contract(s), the price factor will be determined using the price submitted by the offeror(s) for the seed project provided along with this solicitation.
9.5. The first task order is included with this package. The Government intends to award a task order concurrently or very soon after award of the base contract(s). Offerors must submit a price for the first task order in order to be considered eligible for award of a base ID/IQ contract.
9.6. As stated, award of the base ID/IQ contracts will be based on the evaluation of pricing for the first task order only. The first task order will be awarded to the lowest price offered for the first task order from among those offerors selected for a base contract award.
10. SUBMISSION REQUIREMENTS
10.1 VOLUME I – FACTOR 1 – CONSTRUCTION EQUIPMENT, STAFF, AND ROCK
PLACEMENT CAPABILITY
10.1.1 The Contractor shall prepare and submit a narrative demonstrating adequate floating plant and equipment to perform the work. The narrative shall not exceed three pages in length.
The contractor shall submit copies of all licenses and certificates required in Factor 1 in addition to the narrative. The total narrative for Factor One shall be no more than three pages in length and shall include, as a minimum, the following elements and sub-elements.
10.1.2 The narrative shall identify ownership or access to floating plant equipment, pilots, operators, and crew including the following:
A. Floating plant consisting of tow vessels, material barge(s), work barge(s), excavator(s), support vessels.
1. At least two tow vessels, 27 feet long or longer.
2. 4 equipment barges.
3. Mechanisms to load and place rock (loaders and excavators).
4. Support vessel such as a skiff.
5. Equipment type, manufacturer, make, model, year, dimensions, draft, propulsion engine horsepower, maximum load capacity.
B. Tow Vessel Pilots and Licenses. Identify all tow vessel pilots that may operate the tow vessels. All pilots shall be appropriately licensed. Contractor shall provide copies of all proposed tow vessel pilots’ current license. A minimum of two (2) pilots shall be provided.
C. Certificates of Inspection for vessels listed in 10.1.2.A
10.1.3 The narrative shall also indicate the experience of the contractor and a description of means and methods for transporting to the placement locations on the Missouri River.
The narrative shall include a means and methods paragraph(s) that provides an overview discussion that demonstrates the Contractor understands the necessary means and methods to accomplish the work. Relevant information would include assumed means and methods of transport, weekly or monthly placement rates, and transport time from the rock source. Capability shall account for an annual placement period that matches the navigation flow support season on the Missouri River. The annual placement period will include less than 8 months, from 1 April through 20 November for the entire reach of river.
10.1.4 Provide in the proposal, a list and quantity of equipment with capabilities that the
Offeror’s shop(s) currently possess in accordance with Technical Capabilities listed below. The equipment list provided as part of the proposal shall include; type of equipment (make, model, year, and relevant accessories (draft, HP, bucket type/capacity, reach, load limits, etc.), number available, description providing narrative showing equipment meets functional needs of project. Proposals will be considered technically acceptable if the Offeror provides a list and quantity of equipment to be used and has all of the following capabilities:
A. Must have barge(s) that are equipped to deliver and operate equipment which allows for the placement of stone to repair or modified specific river rock structures.
B. Must have towboats and barge(s) able to access, in low draft and/or high flow areas behind or around structures with a draft of 6 feet of water for loaded rock and equipment barges, and tow boats.
C. Must be able to use mooring piles, anchors, or spud barges to obtain proper alignment and configuration while placing stone.
D. Must have dock barge or similar loading equipment to ensure proper rock loading. Load systems and/or methods that do not prevent rock loss into river, and/or causes channel obstructions and/or impede commercial navigation are not acceptable.
E. Equipment used to place stone must be capable of accurately placing stone on structures and accurately placing stone below water to a depth of 20 feet below water surface.
10.1.5 If an Offeror is not currently in possession of the required equipment, Offeror must adequately demonstrate they can acquire the equipment in time to perform the work required under the first task order, which is to be awarded concurrently with award of the base ID/IQ contract, and demonstrate they can acquire the equipment required to satisfy all requirements in the base contract for any subsequent task order. Offerors must acquire the requisite equipment through ownership, lease, subcontract, etc., in time to perform the work.
10.2 VOLUME I – FACTOR 2 – STONE QUALITY AND CAPACITY
10.2.1 The contract will require placement of stone meeting USACE specifications within the
Missouri River at multiple locations. Specific structures, and locations will be provided with the seed project and subsequent task orders. All stone to be placed in all locations in the seed project and following task orders will be subject to the specification provided in seed task order, specification 35 31 19 of this solicitation requires investigations and a narrative describing the results of the investigations. The investigations and the narrative shall address the items specified below in the Factor 2 submission requirements. The current stone specification, in its entirety, is provided for reference in seed task order, specification 35 31 19.
10.2.2 The Contractor shall review and fully comprehend the specification. Questions should be submitted via Projnet, as described in the earlier portion of this solicitation. Contractors shall expect the Corps to perform quality testing of the stone supplied during performance of any Task Orders issued from a resulting contract. The seed project and task order Plans and Specifications will include additional and substantial project requirements. Submittal and acceptance of the Contractor listed stone sources does not imply any Government acceptance of Contractor identified stone sources for project use.
10.2.3 Submission Requirements:
A. Narrative. The Contractor shall provide a brief narrative, no more than 1 page in length, summarizing the stone investigation and including all the following items.
B. The narrative shall identify and include the names of the quarries and contact information for the representatives of the quarries that were coordinated with during the investigation.
C. The narrative shall indicate whether the contractor has secured a preliminary agreement with a quarry that can supply or has previously supplied stone that meets the requirements (or similar requirements) of the specification in seed task order, specification 35 31 19.
D. Previously supplied stone must have been supplied within the last one year.
10.2.4 Testing Results - All stone that will be allowed for use on the job must meet the stone quality specification requirements in seed task order, specification 35 31 19. In addition to the 1-page narrative, the Contractor shall also provide available stone test results as demonstration of quality. However, no new testing is required for this submittal. Offerors who fail to provide previous, similar test results, may be rated as unacceptable. Test results shall be substantially similar to those required in the seed task order, specification 35 31 19, Stone specification.
10.3 VOLUME I – FACTOR 3 – PAST PERFORMANCE
10.3.1 OBTAINING PAST PERFORMANCE RECORDS
A. Accessing Past Performance information directly from Contractor Performance
Assessment Reporting System (CPARS) website at https://www.cpars.gov/ for CCASS completed before 27 June 2014 and for merged CPARS completed after 1 July 2014. CPARS is an electronic repository of performance information collected by all the major federal performance reporting systems and can be accessed at the website.All Department of Defense (DoD) employees (military and civilian), including DoD Contractors that are working on site (military/government facilities) or contractors working offsite using Government Furnished Equipment (GFE) are required to use certificates from DoD Public Key Infrastructure (PKI) to access CPARS. If the contractor doesn't work on site or with GFE they are encouraged to obtain and use a certificate from an External Certificate Authority (ECA). For DoDusers, the use of PKI Login is Mandatory. Federal and Contractor users can use the PKI login category if they have PKI.
B. External Certificate Authority
1. External Certificate Authorities (ECAs) and Interim External Certificate Authorities (IECAs) provide digital certificates to the DoD's private industry partners, contractors using their own equipment or working in non-government facilities, allied partners, and other agencies.
2. Additional information about the PKI certificate is at https://www.cpars.gov/pki_info.htm web page. You will also need your UEI number and Marketing Partner Identification Number (MPIN) to log onto CPARS. The MPIN number was selected by whoever registered your company in the System for Award Management (SAM) Registry at https://sam.gov. If you do not know your MPIN number, you will need to contact the SAM help desk by emailing them from the email link on the SAM web page. Please be aware that they will only release the MPIN number to the person who originally registered your company. Additional instructions on locating your MPIN is located in the Frequently Asked Questions (FAQs) section under the Help tab, or –
C. Past Performance Questionnaires (PPQs) may be used to provide or supplement a firm’s past performance with other than U.S. Governmental clients (see Attachment 3). Contact your client point of contact (POC) for the project you need a past performance record and request the POC to complete the PPQ. The PPQ included in this solicitation is provided for the Offeror to submit to the client for each project the Offeror may need a past performance record for to meet the requirements in this synopsis. Ensure correct phone numbers and email addresses are provided for the client POC. Completed PPQs should be submitted with your proposal. If the Offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the Offeror should complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the respective project(s). It is the Offeror’s responsibility to follow-up with client POCs to ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government’s point of contact, Contract Specialist, via email at clinton.e.russell@usace.army.mil prior to proposal closing date. Offerors must not incorporate by reference into their proposal PPQs previously submitted for other RFPs; this does not preclude an Offeror submitting a previously completed PPQ as long as the full PPQ is submitted and completed in its entirety. This also does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation. If a PPQ is to be submitted for a project, the complete PPQ must be submitted (either by the client POC or the Offeror) prior to proposal closing date.
D. The Government reserves the right to contact any persons who may be knowledgeable about the project or projects (this is not limited to contracts identified by the offeror) submitted in an offeror’s proposal. In addition, the Government may review and take into consideration other sources of information pertinent to the evaluation of the offeror’s Past Performance, including both the previous experience projects and other similar projects performed by the offeror. Other sources may include, but are not limited to, Past Performance information retrieved through the Contractor Performance Assessment Reporting System (CPARS), using all Commercial and Government Entity (CAGE)/UEI numbers of team members
(partnership, Joint Venture, teaming arrangement, or parent firm/subsidiary/affiliate) identified in the Offeror's proposal, inquiries of owner representative(s), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the offeror.
E. While the Government may elect to consider data from other sources, the burden of ensuring detailed, current, accurate and complete Past Performance information rests with the offeror.
10.3.2 The Offeror shall provide a minimum of three (3) projects and a maximum of five (5) projects completed within the last five (5) years that demonstrate experience as they relate to Factor 1- CONSTRUCTION EQUIPMENT, STAFF, AND ROCK PLACEMENT CAPABILITY. For each project, provide the following: Project name, a short description of the work, contract amount, owner’s name and telephone number, completion date and percentage of project completed using your own forces.
The projects shall be of similar type and complexity as this project. Acceptable projects of similar type and complexity are projects valued over $1,000,000 that were performed from a floating barge, involved rock placement, and demonstrates experience in at least one of the following areas:
A. Placing stone on specified structures and under water to a specified depth using floating plant within an inland river system.
B. Using barges with equipment to draft 6 feet of water or less to access areas behind or around structures with faster moving water.
C. Loading barges safely with mobile loading system or dock barge.
10.3.3 If the Offeror represents the combining of two or more companies, state if this project represents a joint venture of the listed parties.
10.3.4 The contractor must submit signed copies of all interim and final ratings received within the last five (5) years during the time period of March 1, 2018, to May 1, 2023 as included in the Past Performance Information Retrieval System (PPIRS), Federal Awardee Performance and Integrity Information System (FAPIIS), Contractor Assessment Reporting System (CPARS) or other databases using all CAGE/UEI numbers of team members (joint venture, teaming arrangement, or parent company/subsidiary/affiliate) that will be performing the work identified in Factor 1 above. All ratings must include the contact information, e-mail or phone, of the rating official.
10.4 VOLUME II – FACTOR 4 – PRICE
Provide a complete price in the proposal, the Price Proposal Schedule, and Price Breakout
Schedule from the first Task Order. Proposed prices must be entered for all items of the Price Proposal Schedule and a detailed price breakout must be submitted.
Price will be analyzed using the price analysis techniques provided in FAR 15.404- 1(b). In the event of a discrepancy between the unit price and the price total, the unit price will prevail.
SECTION 00 72 00 - GENERAL CONDITIONS
The following have been modified:
WAGE DETERMINATIONS
General Decision Number: NE20250046 07/04/2025 Superseded General Decision Number: NE20240046 State: Nebraska Construction Type: Heavy Counties: Boyd, Brown, Burt, Cedar, Colfax, Cuming, Holt, Keya Paha, Knox, Madison, Pierce, Platte, Rock, Stanton and Wayne Counties in Nebraska.
HEAVY CONSTRUCTION PROJECTS
Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.
Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(1).
|If the contract is entered |. Executive Order 14026 | |into on or after January 30, | generally applies to the | |2022, or the contract is | contract. | |renewed or extended (e.g., an |. The contractor must pay | |option is exercised) on or | all covered workers at | |after January 30, 2022: | least $17.75 per hour (or | | | the applicable wage rate | | | listed on this wage | | | determination, if it is | | | higher) for all hours | | | spent performing on the | | | contract in 2025. | |If the contract was awarded on|. Executive Order 13658 | |or between January 1, 2015 and| generally applies to the | |January 29, 2022, and the | contract. | |contract is not renewed or |. The contractor must pay all| |extended on or after January | covered workers at least | |30, 2022: | $13.30 per hour (or the | | | applicable wage rate listed| | | on this wage determination,| | | if it is higher) for all | | | hours spent performing on |
| | that contract in 2025. |
The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.
Additional information on contractor requirements and worker protections under the Executive Orders is available at http://www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/03/2025 1 03/14/2025 2 07/04/2025
* ELEC0022-022 06/01/2025
Burt, Colfax, Cuming, Madison, Platte and Stanton Counties
Rates Fringes
ELECTRICIAN......................$ 46.40 20.89
ELEC0231-008 05/30/2024
Cedar, Knox, Pierce and Wayne Counties
Rates Fringes
ELECTRICIAN......................$ 38.93 18.67
ELEC0265-007 03/03/2025
Boyd, Brown, Holt, Keya Paha, and Rock Counties
Rates Fringes
Electricians:
Zone 1......................$ 33.50 18.20 Zone 2......................$ 33.80 18.24 Zone 3......................$ 34.10 18.27 Zone 4......................$ 34.50 18.31
ZONE DEFINITIONS [Mileage from main Post Office in Lincoln] Zone 1: 0 to 35 miles Zone 2: 36 to 50 miles Zone 3: 51 to 75 miles Zone 4: 76 miles and over
FOOTNOTE:
Work on scaffolds, hanging scaffolds, boatswains chairs or ladders, etc., in any area where the worker is in a position to fall 40 ft. or more, or where objects above the worker can fall 40 ft. or more: to be paid one and one-half times the straight- time rate of pay.
* SUNE2011-013 08/31/2011
Rates Fringes
CEMENT MASON/CONCRETE FINISHER...$ 18.75 3.25
LABORER: Common or General......$ 11.69 ** 1.31
LABORER: Pipelayer..............$ 14.23 ** 0.39
OPERATOR: Backhoe/Excavator.....$ 18.23 2.31
OPERATOR: Bobcat/Skid Steer/Skid Loader................$ 19.47 4.07
OPERATOR: Bulldozer.............$ 15.95 ** 3.04
OPERATOR: Loader................$ 16.79 ** 1.09
OPERATOR: Scraper...............$ 14.89 ** 2.06
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
** Workers in this classification may be entitled to a higher minimum wage under Executive Order 14026 ($17.75) or 13658 ($13.30). Please see the Note at the top of the wage determination for more information. Please also note that the minimum wage requirements of Executive Order 14026 are not currently being enforced as to any contract or subcontract to which the states of Texas, Louisiana, or Mississippi, including their agencies, are a party.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (iii)).
The body of each wage determination lists the classifications and wage rates that have been found to be prevailing for the type(s) of construction and geographic area covered by the wage determination. The classifications are listed in alphabetical order under rate identifiers indicating whether the particular rate is a union rate (current union negotiated rate), a survey rate, a weighted union average rate, a state adopted rate, or a supplemental classification rate.
Union Rate Identifiers
A four-letter identifier beginning with characters other than ""SU"", ""UAVG"", ?SA?, or ?SC? denotes that a union rate was prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2024. PLUM is an identifier of the union whose collectively bargained rate prevailed in the survey for this classification, which in this example would be Plumbers.
0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. The date, 07/01/2024 in the example, is the effective date of the most current negotiated rate.
Union prevailing wage rates are updated to reflect all changes over time that are reported to WHD in the rates in the collective bargaining agreement (CBA) governing the classification.
Union Average Rate Identifiers
The UAVG identifier indicates that no single rate prevailed for those classifications, but that 100% of the data reported for the classifications reflected union rates. EXAMPLE:
UAVG-OH-0010 01/01/2024. UAVG indicates that the rate is a weighted union average rate. OH indicates the State of Ohio.
The next number, 0010 in the example, is an internal number used in producing the wage determination. The date, 01/01/2024 in the example, indicates the date the wage determination was updated to reflect the most current union average rate.
A UAVG rate will be updated once a year, usually in January, to reflect a weighted average of the current rates in the collective bargaining agreements on which the rate is based.
Survey Rate Identifiers
The ""SU"" identifier indicates that either a single non-union rate prevailed (as defined in 29 CFR 1.2) for this classification in the survey or that the rate was derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As a weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SUFL2022-007 6/27/2024. SU indicates the rate is a single non-union prevailing rate or a weighted average of survey data for that classification. FL indicates the State of Florida. 2022 is the year of the survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. The date, 6/27/2024 in the example, indicates the survey completion date for the classifications and rates under that identifier.
?SU? wage rates typically remain in effect until a new survey is conducted. However, the Wage and Hour Division (WHD) has the discretion to update such rates under 29 CFR 1.6(c)(1).
State Adopted Rate Identifiers
The ""SA"" identifier indicates that the classifications and prevailing wage rates set by a state (or local) government were adopted under 29 C.F.R 1.3(g)-(h). Example: SAME2023-007 01/03/2024. SA reflects that the rates are state adopted. ME refers to the State of Maine. 2023 is the year during which the state completed the survey on which the listed classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination.
The date, 01/03/2024 in the example, reflects the date on which the classifications and rates under the ?SA? identifier took effect under state law in the state from which the rates were adopted.
WAGE DETERMINATION APPEALS PROCESS
1) Has there been an initial decision in the matter? This can be:
a) a survey underlying a wage determination
b) an existing published wage determination
c) an initial WHD letter setting forth a position on a wage determination matter
d) an initial conformance (additional classification and rate) determination
On survey related matters, initial contact, including requests for summaries of surveys, should be directed to the WHD Branch of Wage Surveys. Requests can be submitted via email to davisbaconinfo@dol.gov or by mail to:
Branch of Wage Surveys Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
Regarding any other wage determination matter such as conformance decisions, requests for initial decisions should be directed to the WHD Branch of Construction Wage Determinations.
Requests can be submitted via email to BCWD-Office@dol.gov or by mail to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2) If an initial decision has been issued, then any interested party (those affected by the action) that disagrees with the decision can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7).
Requests for review and reconsideration can be submitted via email to dba.reconsideration@dol.gov or by mail to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210.
END OF GENERAL DECISION
General Decision Number: NE20250042 03/14/2025 Superseded General Decision Number: NE20240042 State: Nebraska Construction Type: Heavy County: Thurston County in Nebraska.
HEAVY CONSTRUCTION PROJECTS
Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.
Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(1).
|If the contract is entered |. Executive Order 14026 | |into on or after January 30, | generally applies to the | |2022, or the contract is | contract. | |renewed or extended (e.g., an |. The contractor must pay | |option is exercised) on or | all covered workers at | |after January 30, 2022: | least $17.75 per hour (or | | | the applicable wage rate | | | listed on this wage | | | determination, if it is | | | higher) for all hours | | | spent performing on the | | | contract in 2025. |
|If the contract was awarded on|. Executive Order 13658 | |or between January 1, 2015 and| generally applies to the | |January 29, 2022, and the | contract. | |contract is not renewed or |. The contractor must pay all| |extended on or after January | covered workers at least | |30, 2022: | $13.30 per hour (or the | | | applicable wage rate listed| | | on this wage determination,| | | if it is higher) for all | | | hours spent performing on | | | that contract in 2025. |
The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.
Additional information on contractor requirements and worker protections under the Executive Orders is available at http://www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/03/2025 1 03/14/2025
* ELEC0265-006 03/03/2025
Rates Fringes
Electricians:
Zone 1......................$ 33.50 18.20 Zone 2......................$ 33.80 18.24 Zone 3......................$ 34.10 18.27 Zone 4......................$ 34.50 18.31
ZONE DEFINITIONS [Mileage from main Post Office in Lincoln] Zone 1: 0 to 35 miles Zone 2: 36 to 50 miles Zone 3: 51 to 75 miles Zone 4: 76 miles and over
FOOTNOTE:
Work on scaffolds, hanging scaffolds, boatswains chairs or ladders, etc., in any area where the worker is in a position to fall 40 ft. or more, or where objects above the worker can fall 40 ft. or more: to be paid one and one-half times the straight- time rate of pay.
* SUNE2011-009 08/31/2011
Rates Fringes
CEMENT MASON/CONCRETE FINISHER...$ 18.75 3.25
LABORER: Common or General......$ 11.69 ** 1.31
LABORER: Pipelayer..............$ 14.23 ** 0.39
OPERATOR: Backhoe/Excavator.....$ 18.23 2.31
OPERATOR: Bobcat/Skid Steer/Skid Loader................$ 19.47 4.07
OPERATOR: Bulldozer.............$ 15.95 ** 3.04
OPERATOR: Loader................$ 16.79 ** 1.09
OPERATOR: Scraper...............$ 14.89 ** 2.06
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
** Workers in this classification may be entitled to a higher minimum wage under Executive Order 14026 ($17.75) or 13658 ($13.30). Please see the Note at the top of the wage determination for more information. Please also note that the minimum wage requirements of Executive Order 14026 are not currently being enforced as to any contract or subcontract to which the states of Texas, Louisiana, or Mississippi, including their agencies, are a party.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (iii)).
The body of each wage determination lists the classifications and wage rates that have been found to be prevailing for the type(s) of construction and geographic area covered by the wage determination. The classifications are listed in alphabetical order under rate identifiers indicating whether the particular rate is a union rate (current union negotiated rate), a survey rate, a weighted union average rate, a state adopted rate, or a supplemental classification rate.
Union Rate Identifiers
A four-letter identifier beginning with characters other than ""SU"", ""UAVG"", ?SA?, or ?SC? denotes that a union rate was prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2024. PLUM is an identifier of the union whose collectively bargained rate…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .