About this file
This document provides details for a federal contract opportunity for the installation of a digital governor at Fort Peck, Montana. Solicitation number W9128F21R0003 was issued by the Department of the Army Corps of Engineers Engineering District Omaha to support the installation. Interested vendors are invited to respond with proposals by the specified deadline to undertake the project, which involves installing a digital governor to modernize control systems at Fort Peck. The opportunity description indicates the solicitation and supporting documents are now available for review as agencies seek bids from qualified contractors.
View the file
Other files for this federal contract opportunity
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Welcome
Fort peck Dam Digital governor install site visit Solicitation: W9128F21R0003 24 nov 2020
Conference line: 1-844-800-2712 (Toll-Free) Access Code: 199 455 2703 Photo courtesy of visitmt.com
Agenda – Nov 19, 2020
| 1000 – 1005 | Introductions / Project Overview |
| 1005 – 1010 | Contracting Briefing / Rules of Engagement |
| 1010 – 1020 | Project Site Specifics |
| 1020 – 1045 | Statement of Work / Project Specs |
| 1045 – 1100 | Q&A |
introductions USACE, Omaha District Office
| Ryan Brockman | Project Manager |
| Robin Puskar | Program Manager |
| Nadine Catania | Contract Officer |
| Tim Boyte | Contracting Specialist |
| Nile Limbach | Electrical Engineer |
Fort Peck
| Dale Pugh | Maintenance and Operations Manager |
| Tim Zabrocki | Assistant Maintenance and Operations Manager |
Missouri River Resident Office (Bismarck, ND) Tom Westenburg Resident Engineer
Hydroelectric Design Center (HDC), Portland OR
| Kwadwo Amankwa-Poku | Electrical Engineer | |
| Alex Korobeinikov | Electrical Engineer | |
| Zachary Reyes | Mechanical Engineer |
Projected Project schedule Due Date of Proposals 8 Dec 2020
Contractor Site Visit 24 Nov 2020
Anticipated Award January 2021
Outage Period On-site installation work must begin no later than 1 June 2021
USACE, Omaha District Contracting Nadine Catania, contracting officer Rules of Engagement Contract Specialist is the government authority during visit All questions or concerns must be directed to the Contract Specialist No side bars or independent conversations between contractors and government personnel No discussions relating to other Corps acquisitions No corporate denigration or sabotage will be tolerated All questions should be entered into ProjNet (Bidder key: AETC6F-2X23K8) All questions will be documented and posted on beta.SAM (www.beta.sam.gov)
Contract and evaluation information
Contract Information Contract Type: Firm-Fixed Price Construction Solicitation Type: Request for Proposal (RFP) Contract Magnitude: $1M-$5M Period of Performance:
Pre-Construction Submittals submitted/approved within 85 calendar days after NTP is issued On-site installation work must begin no later than 1 June 2021
Evaluation Factors Experience Past Performance Technical Approach Personnel Qualifications and Experience Small Business Participation Price
Projnet and contact information
ProjNet Used for contractor submitted questions Web site: https://www.projnet.org Bidder Inquiry Key: AETC6F-2X23K8 Questions must be submitted ten (10) calendar days prior to proposal due date
Contract Specialist Contact Information Tim Boyte Email: Timothy.B.Boyte@usace.army.mil
File Name
Project SITE Specifics
Ft. Peck Digital Governor Install
Ft Peck Project Brief Tim Zabrocki, Assistant Maintenance and Operations Manager
Project overview
Project overview
File Name
Statement of work and project Specs
Hydroelectric design center Kwadwo amankwa-poku, electrical engineer
Statement of Work Work includes installation of the following:
GFE: digital governor control cabinet, Gate Position Transducers (MLDTs), Speed Probes (ZVPUs), Electric-Hydraulic Interface (EHI) control manifold, distributing valve position transducer (LVDT), Watt transducers, and 2 HMIs in the control room for governor control/monitoring of all 5 units.
Refurbishment of distribution valves.
Utilize existing exciter PT’s and CT’s for unit speed and MW feedback.
Re-plumbing all new piping in the governor cabinet per contract drawings.
Repurpose Partial Shutdown (86P) Lock-out to be a Mechanical Shutdown (86M) Lock-out .
Install fiber cables from existing patch panels to digital governor cabinet, PPCS server room:
PP1 – BFV corridor & spreader room (directly below control room) PP2 – Comm cab. at turbine floor (El. 2049) & spreader room (directly below control room) Replacement of the existing snap-action unloader control valves with solenoid operated unloader valves and new controls. GFE - solenoid operated unloader valve kits.
Installation of auto air balancing equipment. GFE – automatic air balancing kits.
Mounting brackets required for following: MLDTs, LVDTs, EHI
Statement of Work Distributing Valves Site visit to the Project for the purpose of performing existing gate distributing valve component measurements.
Measurements shall be taken of the existing spare components for each of the three different unit families in advance of full mobilization.
Disassembly, cleaning, final valve body measurements, final component machining, and re-assembly of the distributing valves is required
Powerhouse 1 – Plan View – PP1-G-005
Powerhouse 1 – Unit 1
Powerhouse 1 – Erection Bay Door
Powerhouse 1 – Unit 1 Generator Floor
Powerhouse 1 – Unit 1 PMG
Powerhouse 1 – actuator cabinets (1&2) and crane
Powerhouse 1 – Unit 1 gov Control cabinet
Powerhouse 1 – Unit 1 Gov Control
Powerhouse 1 – Unit 1 Control Cabinet Right side
Powerhouse 1 – Unit 1 Brake air valve and controls
Powerhouse 1 – Brake Air Valve
Powerhouse 1 – Unit 1 Pump control
Powerhouse 1 – Unit 1 actuator cabinet
Powerhouse 1 – Unit 1 Pump Control cabinet internal
Powerhouse 1 – Unit 1 turbine pit
Powerhouse 1 – Unit 1 Servo
Powerhouse 1 – Unit 2 turbine and governor equipment area
Powerhouse 1 – Unit 2 Pump cabinet
Powerhouse 1 – butterfly valve corridor – Fiber patch panel
Powerhouse 1 – Unit 1 fiber patch panel
Powerhouse 1 – Control Boards
Powerhouse 1 – Unit 1 Control Boards
Powerhouse 1 – Unit 1 Control Board
Powerhouse 1 – Unit 1 ARB Boards
Powerhouse 2 – erection bay and floor hatch
Powerhouse 2 – turbine floor plan
Powerhouse 2
Powerhouse 2 – Erection bay, crane and floor hatch
Powerhouse 2
Powerhouse 2 – Unit 5 PMG
Powerhouse 2 – floor access
Powerhouse 2 – governor work area
Powerhouse 2 – Unit 5 Gov Cabinet
Powerhouse 2 – Unit 5 Gov Cabinet Upstream
Powerhouse 2 – Unit 5 Gov Cabinet internal downstream
Powerhouse 2 – Unit 4 comm cabinet, turbine pit access
Powerhouse 2 – Unit 5 fiber patch panel
Powerhouse 2 – Unit 4 turbine pit
Powerhouse 2 – Unit 5 Servo
Powerhouse 2 – Unit 4 turbine pit
Powerhouse 2 – Unit 4 & 5 control board
Powerhouse 2 – Unit 5 Control board
Powerhouse 2 – Unit 5 Control board
Virtual site visit Q & A image5.jpeg image6.jpeg image7.png image8.png image9.emf image10.png image11.png image12.jpeg image13.jpeg image14.jpeg image15.jpeg image16.jpeg image17.jpeg image18.jpeg image19.jpeg image20.jpeg image21.jpeg image22.jpeg image23.jpeg image24.jpeg image25.jpeg image26.jpeg image27.png image28.jpeg image29.jpeg image30.jpeg image31.jpeg image32.jpeg image33.png image34.jpeg image35.jpeg image36.jpeg image37.png image38.png image39.jpeg image40.jpeg image41.jpeg image42.jpeg image43.jpeg image44.jpeg image45.jpeg image46.jpeg image47.jpeg image48.jpeg image49.jpeg image50.jpeg image51.jpeg image52.jpeg image53.jpeg image54.jpeg image55.jpeg image1.png image2.png image3.png image4.tiff