This document provides details for a federal contract opportunity for the installation of a digital governor at Fort Peck, Montana. Solicitation number W9128F21R0003 was issued by the Department of the Army Corps of Engineers Engineering District Omaha to support the installation. Interested vendors are invited to respond with proposals by the specified deadline to undertake the project, which involves installing a digital governor to modernize control systems at Fort Peck. The opportunity description indicates the solicitation and supporting documents are now available for review as agencies seek bids from qualified contractors.

View the file

Other files for this federal contract opportunity

Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Welcome

Fort peck Dam Digital governor install site visit Solicitation: W9128F21R0003 24 nov 2020

Conference line: 1-844-800-2712 (Toll-Free) Access Code: 199 455 2703 Photo courtesy of visitmt.com

Agenda – Nov 19, 2020

1000 – 1005Introductions / Project Overview
1005 – 1010Contracting Briefing / Rules of Engagement
1010 – 1020Project Site Specifics
1020 – 1045Statement of Work / Project Specs
1045 – 1100Q&A

introductions USACE, Omaha District Office

Ryan BrockmanProject Manager
Robin PuskarProgram Manager
Nadine CataniaContract Officer
Tim BoyteContracting Specialist
Nile LimbachElectrical Engineer

Fort Peck

Dale PughMaintenance and Operations Manager
Tim ZabrockiAssistant Maintenance and Operations Manager

Missouri River Resident Office (Bismarck, ND) Tom Westenburg Resident Engineer

Hydroelectric Design Center (HDC), Portland OR

Kwadwo Amankwa-PokuElectrical Engineer
Alex KorobeinikovElectrical Engineer
Zachary ReyesMechanical Engineer

Projected Project schedule Due Date of Proposals 8 Dec 2020

Contractor Site Visit 24 Nov 2020

Anticipated Award January 2021

Outage Period On-site installation work must begin no later than 1 June 2021

USACE, Omaha District Contracting Nadine Catania, contracting officer Rules of Engagement Contract Specialist is the government authority during visit All questions or concerns must be directed to the Contract Specialist No side bars or independent conversations between contractors and government personnel No discussions relating to other Corps acquisitions No corporate denigration or sabotage will be tolerated All questions should be entered into ProjNet (Bidder key: AETC6F-2X23K8) All questions will be documented and posted on beta.SAM (www.beta.sam.gov)

Contract and evaluation information

Contract Information Contract Type: Firm-Fixed Price Construction Solicitation Type: Request for Proposal (RFP) Contract Magnitude: $1M-$5M Period of Performance:

Pre-Construction Submittals submitted/approved within 85 calendar days after NTP is issued On-site installation work must begin no later than 1 June 2021

Evaluation Factors Experience Past Performance Technical Approach Personnel Qualifications and Experience Small Business Participation Price

Projnet and contact information

ProjNet Used for contractor submitted questions Web site: https://www.projnet.org Bidder Inquiry Key: AETC6F-2X23K8 Questions must be submitted ten (10) calendar days prior to proposal due date

Contract Specialist Contact Information Tim Boyte Email: Timothy.B.Boyte@usace.army.mil

File Name

Project SITE Specifics

Ft. Peck Digital Governor Install

Ft Peck Project Brief Tim Zabrocki, Assistant Maintenance and Operations Manager

Project overview

Project overview

File Name

Statement of work and project Specs

Hydroelectric design center Kwadwo amankwa-poku, electrical engineer

Statement of Work Work includes installation of the following:

GFE: digital governor control cabinet, Gate Position Transducers (MLDTs), Speed Probes (ZVPUs), Electric-Hydraulic Interface (EHI) control manifold, distributing valve position transducer (LVDT), Watt transducers, and 2 HMIs in the control room for governor control/monitoring of all 5 units.

Refurbishment of distribution valves.

Utilize existing exciter PT’s and CT’s for unit speed and MW feedback.

Re-plumbing all new piping in the governor cabinet per contract drawings.

Repurpose Partial Shutdown (86P) Lock-out to be a Mechanical Shutdown (86M) Lock-out .

Install fiber cables from existing patch panels to digital governor cabinet, PPCS server room:

PP1 – BFV corridor & spreader room (directly below control room) PP2 – Comm cab. at turbine floor (El. 2049) & spreader room (directly below control room) Replacement of the existing snap-action unloader control valves with solenoid operated unloader valves and new controls. GFE - solenoid operated unloader valve kits.

Installation of auto air balancing equipment. GFE – automatic air balancing kits.

Mounting brackets required for following: MLDTs, LVDTs, EHI

Statement of Work Distributing Valves Site visit to the Project for the purpose of performing existing gate distributing valve component measurements.

Measurements shall be taken of the existing spare components for each of the three different unit families in advance of full mobilization.

Disassembly, cleaning, final valve body measurements, final component machining, and re-assembly of the distributing valves is required

Powerhouse 1 – Plan View – PP1-G-005

Powerhouse 1 – Unit 1

Powerhouse 1 – Erection Bay Door

Powerhouse 1 – Unit 1 Generator Floor

Powerhouse 1 – Unit 1 PMG

Powerhouse 1 – actuator cabinets (1&2) and crane

Powerhouse 1 – Unit 1 gov Control cabinet

Powerhouse 1 – Unit 1 Gov Control

Powerhouse 1 – Unit 1 Control Cabinet Right side

Powerhouse 1 – Unit 1 Brake air valve and controls

Powerhouse 1 – Brake Air Valve

Powerhouse 1 – Unit 1 Pump control

Powerhouse 1 – Unit 1 actuator cabinet

Powerhouse 1 – Unit 1 Pump Control cabinet internal

Powerhouse 1 – Unit 1 turbine pit

Powerhouse 1 – Unit 1 Servo

Powerhouse 1 – Unit 2 turbine and governor equipment area

Powerhouse 1 – Unit 2 Pump cabinet

Powerhouse 1 – butterfly valve corridor – Fiber patch panel

Powerhouse 1 – Unit 1 fiber patch panel

Powerhouse 1 – Control Boards

Powerhouse 1 – Unit 1 Control Boards

Powerhouse 1 – Unit 1 Control Board

Powerhouse 1 – Unit 1 ARB Boards

Powerhouse 2 – erection bay and floor hatch

Powerhouse 2 – turbine floor plan

Powerhouse 2

Powerhouse 2 – Erection bay, crane and floor hatch

Powerhouse 2

Powerhouse 2 – Unit 5 PMG

Powerhouse 2 – floor access

Powerhouse 2 – governor work area

Powerhouse 2 – Unit 5 Gov Cabinet

Powerhouse 2 – Unit 5 Gov Cabinet Upstream

Powerhouse 2 – Unit 5 Gov Cabinet internal downstream

Powerhouse 2 – Unit 4 comm cabinet, turbine pit access

Powerhouse 2 – Unit 5 fiber patch panel

Powerhouse 2 – Unit 4 turbine pit

Powerhouse 2 – Unit 5 Servo

Powerhouse 2 – Unit 4 turbine pit

Powerhouse 2 – Unit 4 & 5 control board

Powerhouse 2 – Unit 5 Control board

Powerhouse 2 – Unit 5 Control board

Virtual site visit Q & A image5.jpeg image6.jpeg image7.png image8.png image9.emf image10.png image11.png image12.jpeg image13.jpeg image14.jpeg image15.jpeg image16.jpeg image17.jpeg image18.jpeg image19.jpeg image20.jpeg image21.jpeg image22.jpeg image23.jpeg image24.jpeg image25.jpeg image26.jpeg image27.png image28.jpeg image29.jpeg image30.jpeg image31.jpeg image32.jpeg image33.png image34.jpeg image35.jpeg image36.jpeg image37.png image38.png image39.jpeg image40.jpeg image41.jpeg image42.jpeg image43.jpeg image44.jpeg image45.jpeg image46.jpeg image47.jpeg image48.jpeg image49.jpeg image50.jpeg image51.jpeg image52.jpeg image53.jpeg image54.jpeg image55.jpeg image1.png image2.png image3.png image4.tiff