Site Visit Feb 25 2021- Questions - Little Bend.pdf
PDF 113 KB Posted
- Attached to
- Oahe Little Bend Bank Stabilization Federal contract opportunity
- Solicitation number
- W9128F21B0004
About this file
This document contains questions and answers from a pre-bid site visit for a federal contract to perform bank stabilization work along approximately 5,800 linear feet of shoreline on Lake Oahe in Sully County, South Dakota. The scope of work involves regrading and compacting the existing bank, installing geotextile fabric, and placing approximately 13,000 tons of riprap stone. Equipment will be restricted to operating below the high bank. Excess embankment material derived from excavating the toe and sloughed material below the high bank must remain along the shoreline. The contractor will be responsible for proper offsite disposal of all removed trees and vegetation. Award of the contract is through solicitation number W9128F21B0004 issued by the U.S. Army Corps of Engineers Omaha District. The period of performance is 365 days from notice to proceed.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| KO W9128F21B0004 Little Bend Bid Abstract.pdf | ||
| 2nd Signup Sheet 3.10.2021 - Little Bend.pdf | ||
| Am0001 W9128F21B0004.pdf | ||
| PreBid Signup Sheet - Little Bend.pdf | ||
| W9128F21B0004 - Little Bend Specification.pdf | ||
| Site Visit Location Map-1.pdf | ||
| W9128F21B0004 - Little Bend Dwgs.pdf | ||
| Little Bend Directions.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Little Bend Bank Stab.
Pre-Bid Site Visit Questions
W9128F21B0004
Oahe Project
2-25-2021
Question #1 – Will the large tree at Sta. 0+00 require removal?
Answer#1 – No, this tree shall remain in place.
Question #2 – Is the Contractor required to provide fill material?
Answer#2 – No, all fill material shall be comprised of excavated material from the toe and sloughed material below the high bank.
Question #3 – What elevation is the toe?
Answer #3 – There is no set elevation for the toe. The toe shall be 2’ deep into the existing ground and elevation shall vary along project length.
Question #4 – Can equipment be above the high bank?
Answer #4- Equipment shall be restricted to operating below the high bank.
Question #5 – Is there a seed specification?
Answer #5 – No, Contractor shall coordinate with SD Game Fish & Parks for seeding mixtures.
Question #6- Where will excess embankment material be placed?
Answer #6- Excess embankment material derived from the toe and sloughed material below the high bank shall remain along the shoreline.
Question #7- Is there a set stockpile size?
Answer #7 – No.
Question #8 – Where are the access and exit locations?
Answer #8 – A drawing sheet for the access and exit locations shall be provided via amendment.
Question #9 – Can trees be pulled or must they be cut?
Answer #9 – Trees growing out of the high bank must be cut flush. Trees below the high bank on the shoreline maybe pulled. Contractor shall become responsible for the proper offsite disposal of all removed trees and vegetation.