This abstract of offers is for a construction project to complete bank stabilization measures along Lake Oahe in Sully County, South Dakota. The project includes installing approximately 13,000 tons of riprap and bank stabilization materials along 5,800 linear feet of shoreline. Fourteen contractors submitted bids by the March 23rd deadline. Bid amounts ranged from $841,395 to $1,835,160.95 for the base project and options. The apparent low bidder was Southeast Construction, Inc. at $941,342.50. The government estimate was $1,203,464.95. Work must be completed within 365 days of notice to proceed. The contracting agency is the US Army Corps of Engineers Omaha District.

View the file

Other files for this federal contract opportunity

Other files attached to Oahe Little Bend Bank Stabilization, newest first.
File Type Posted
2nd Signup Sheet 3.10.2021 - Little Bend.pdf PDF
Am0001 W9128F21B0004.pdf PDF
PreBid Signup Sheet - Little Bend.pdf PDF
Site Visit Feb 25 2021- Questions - Little Bend.pdf PDF
W9128F21B0004 - Little Bend Dwgs.pdf PDF
W9128F21B0004 - Little Bend Specification.pdf PDF
Site Visit Location Map-1.pdf PDF
Little Bend Directions.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2. DATE ISSUED 3. DATE OPENED

12-Feb-21 23-Mar-21

I CERTIFY THAT I HAVE OPENED, READ AND

AND RECORDED ON THIS ABSTRACT

ALL OFFERS RECEIVED IN RESPONSE DATE SIGNED

X C. REASONABLE CONTRACT

7A. 7B. 7C. 7D. 7E. 7F. 7E. F. E. F.

ITEM # DESCRIPTION EST. QTY UNIT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT

CLIN Basic Items

All work to complete the supply and install Riprap as specified in the specification and drawing 12,825 TON 58.00$ 743,850.00$ 81.94$ 1,050,880.50$ 98.00$ 1,256,850.00$

All work complete to supply and install Geotextile Fabric as specified in the specifications and drawings. 10,410 SY 3.50$ 36,435.00$ 17.35$ 180,613.50$ 8.00$ 83,280.00$

All work to complete the supply, haul, place, and compact embankment

(Cut/Fill) for bank stabilization as specified in the specifications and drawings. 5,540 CY 22.25$ 123,265.00$ 18.63$ 103,210.20$ 35.00$ 193,900.00$

All remaining work including but not limited to mobilization, demobilization, access road, shaping, and maintenance, and all other work except the work listed in the items above and below listed in the options.

1 Job 89,200.00$ 89,200.00$ 104,775.51$ 104,775.51$ 15,000.00$ 15,000.00$

992,750.00$ 1,439,479.71$ 1,549,030.00$

OPTIONS -$ -$ -$

All work to complete the supply and install Riprap as specified in the specifications and drawings.

1,600

TON 58.00$ 92,800.00$ 99.11$ 158,576.00$ 90.00$ 144,000.00$

All work to complete the supply and install Geotextile Fabric as specified in the specifications and drawings.

1,290

SY 3.50$ 4,515.00$ 32.16$ 41,486.40$ 5.00$ 6,450.00$

All work complete to supply, haul, place, and compact embankment

(Cut/Fill) for bank stabilization as specified in the specifications and drawings.

CY 22.25$ 15,352.50$ 32.73$ 22,583.70$ 25.00$ 17,250.00$

112,667.50$ 222,646.10$ 167,700.00$

1,105,417.50$ 1,662,125.81$ 1,716,730.00$

OAHE LITTLE BEND BANK STABILIZATION

BASE + Option TOTAL AMOUNT (Items 0001 through 0007)

(Without Profit)

(Including Profit)

SUBTOTAL OPTIONS

SUBTOTAL BASE

6. NUMBER OF AMENDMENTS ISSUED

20%

B. BID SECURITY (Type & Amount)

20%

C. AMENDMENTS ACKNOWLEDGED

C. AMENDMENTS ACKNOWLEDGED

VANCOUVER, WA 98685 Des Moines, IA 50321

B. BID SECURITY (Type & Amount)B. REASONABLE CONTRACT

A. OFFEROR A. OFFEROR

201 NE 135TH ST 3018 Fox Run

A. HIRED LABOR

KEU, INC. Southeast Construction, Inc

NO. 1 NO. 2

ABSTRACT OF OFFERS - CONSTRUCTION

1. SOLICITATION NUMBER

W9128F21B0004

4. ISSUING OFFICE

8. GOVERNMENT ESTIMATE

(Check A, B or C AND COMPLETE D, E AND F)

5. PROJECT TITLE 9. OFFERS

TO THIS SOLICITATION

SIGNATURE

NAME AND TITLE OF CERTIFYING OFFICIAL (Type)

Dean P. Matuszewski

OMAHA, NE 68102-1618

1616 CAPITOL AVENUE

CONTRACTING DIVISION (CENWO-CT)

US ARMY CORPS OF ENGINEERS

l PAGE 4

X C. REASONABLE CONTRACT

7A. 7B. 7C. 7D. 7E. 7F. 7E. F. E. F. E. F.

ITEM # DESCRIPTION EST. QTY UNIT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT

Basic Items

All work to complete the supply and install Riprap as specified in the specification and drawing 12,825 TON 76.00$ 974,700.00$ 72.00$ 923,400.00$ 58.00$ 743,850.00$ 65.00$ 833,625.00$

All work complete to supply and install Geotextile Fabric as specified in the specifications and drawings. 10,410 SY 2.69$ 28,002.90$ 3.00$ 31,230.00$ 3.00$ 31,230.00$ 5.00$ 52,050.00$

All work to complete the supply, haul, place, and compact embankment (Cut/Fill) for bank stabilization as specified in the specifications and drawings. 5,540 CY 3.40$ 18,836.00$ 8.00$ 44,320.00$ 4.75$ 26,315.00$ 10.00$ 55,400.00$

All remaining work including but not limited to mobilization, demobilization, access road, shaping, and maintenance, and all other work except the work listed in the items above and below listed in the options. 1 Job 47,908.55$ 47,908.55$ 175,000.00$ 175,000.00$ 40,000.00$ 40,000.00$ 155,000.00$ 155,000.00$

1,069,447.45$ 1,173,950.00$ 841,395.00$ 1,096,075.00$

OPTIONS

All work to complete the supply and install Riprap as specified in the specifications and drawings. 1,600 TON 78.84$ 126,144.00$ 69.00$ 110,400.00$ 58.00$ 92,800.00$ 65.00$ 104,000.00$

All work to complete the supply and install Geotextile Fabric as specified in the specifications and drawings. 1,290 SY 2.83$ 3,650.70$ 5.00$ 6,450.00$ 3.00$ 3,870.00$ 5.00$ 6,450.00$

All work complete to supply, haul, place, and compact embankment (Cut/Fill) for bank stabilization as specified in the specifications and drawings. 690 CY 6.12$ 4,222.80$ 13.00$ 8,970.00$ 4.75$ 3,277.50$ 10.00$ 6,900.00$

134,017.50$ 125,820.00$ 99,947.50$ 117,350.00$

1,203,464.95$ 1,299,770.00$ 941,342.50$ 1,213,425.00$

20%

C. AMENDMENTS ACKNOWLEDGED6. NUMBER OF AMENDMENTS ISSUED

Jamestown, ND 58401

C. AMENDMENTS ACKNOWLEDGED

PO Box 2669

Sioux City, IA 51106

B. BID SECURITY (Type & Amount)

20%

507 Main Street N

Herreid, SD 57632

B. BID SECURITY (Type & Amount)

4. OFFERS (Continued)

NO. 3

A. OFFEROR

2511 17th Street SE

NO. 5

A. OFFEROR

NO. 6

ABSTRACT OF OFFERS -

CONTINUATION SHEET

CONSTRUCTION

OAHE LITTLE BEND BANK STABILIZATION

2. PROJECT TITLE

INSTRUCTIONS: Attach this form to Abstract of Offers - Construction, when more than 2 offers are received on a construction project. Each Continuation

1. SOLICITATION NUMBER

W9128F21B0004 sheet will accommodate 24 contract items to conform the number of items which can be entered . Use additional forms and continuation sheets as needed.

A. OFFEROR

NO. 4

RTS Shearing, LLC Fenton Construction, Inc.

A. OFFEROR

B. REASONABLE CONTRACT

Tunheim Construction, LLC

3950 25th St N.

Fargo, ND 58102

SUBTOTAL BASE

SUBTOTAL OPTIONS

BASE + Option TOTAL AMOUNT (Items 0001 through 0007)

Steve Lehrkamp Enterprises, Inc.

B. BID SECURITY (Type & Amount)

20%

C. AMENDMENTS ACKNOWLEDGED

20%

ITEM # DESCRIPTION EST. QTY UNIT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT

Basic Items

All work to complete the supply and install Riprap as specified in the specification and drawing 12,825 TON 51.85$ 664,976.25$ 94.72$ 1,214,784.00$ 77.00$ 987,525.00$ 52.00$ 666,900.00$

All work complete to supply and install Geotextile Fabric as specified in the specifications and drawings. 10,410 SY 2.75$ 28,627.50$ 13.43$ 139,806.30$ 3.55$ 36,955.50$ 2.50$ 26,025.00$

All work to complete the supply, haul, place, and compact embankment

(Cut/Fill) for bank stabilization as specified in the specifications and drawings. 5,540 CY 6.00$ 33,240.00$ 20.16$ 111,686.40$ 9.70$ 53,738.00$ 4.00$ 22,160.00$

All remaining work including but not limited to mobilization, demobilization, access road, shaping, and maintenance, and all other work except the work listed in the items above and below listed in the options. 1 Job 48,500.00$ 48,500.00$ 135,979.67$ 135,979.67$ 288,700.00$ 288,700.00$ 55,000.00$ 55,000.00$

775,343.75$ 1,602,256.37$ 1,366,918.50$ 770,085.00$

OPTIONS

All work to complete the supply and install Riprap as specified in the specifications and drawings. 1,600 TON 51.85$ 82,960.00$ 69.13$ 110,608.00$ 91.70$ 146,720.00$ 52.00$ 83,200.00$

All work to complete the supply and install Geotextile Fabric as specified in the specifications and drawings. 1,290 SY 2.75$ 3,547.50$ 14.52$ 18,730.80$ 3.55$ 4,579.50$ 2.50$ 3,225.00$

All work complete to supply, haul, place, and compact embankment

(Cut/Fill) for bank stabilization as specified in the specifications and drawings. 690 CY 6.00$ 4,140.00$ 33.29$ 22,970.10$ 9.70$ 6,693.00$ 4.00$ 2,760.00$

90,647.50$ 152,308.90$ 157,992.50$ 89,185.00$

865,991.25$ 1,754,565.27$ 1,524,911.00$ 859,270.00$

ABSTRACT OF OFFERS -

1. SOLICITATION NUMBER PAGE 3 OF 4

W9128F21B0004

CONSTRUCTION INSTRUCTIONS: Attach this form to Abstract of Offers - Construction, when more than 2 offers are received on a construction project. Each Continuation

CONTINUATION SHEET sheet will accommodate 24 contract items to conform the number of items which can be entered . Use additional forms and continuation sheets as needed.

2. PROJECT TITLE 4. OFFERS (Continued)

NO. 7 NO. 8 NO. 9 NO. 10

OAHE LITTLE BEND BANK STABILIZATION A. OFFEROR A. OFFEROR A. OFFEROR A. OFFEROR

Morris, Inc. STG Pacific, LLC HSG Park JV LLC Sharpe Enterprices, Inc.

PO Box 1162 3700 Centerpoint Drive, Ste 8155 2972 25th St NE / PO Box 213 3500 E Why 34

Pierre, SD 57501-1162 Anchorage, Alaska 99503 Harvey, ND 58341 Pierre, SD 57501

B. REASONABLE CONTRACT B. BID SECURITY (Type & Amount) B. BID SECURITY (Type & Amount) B. BID SECURITY (Type & Amount)

20% 20% 20% 20%

C. AMENDMENTS ACKNOWLEDGED

3 1 1 1 1

SUBTOTAL BASE

SUBTOTAL OPTIONS

6. NUMBER OF AMENDMENTS ISSUED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED

ITEM # DESCRIPTION EST. QTY UNIT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT

Basic Items

All work to complete the supply and install Riprap as specified in the specification and drawing 12,825 TON 73.00$ 936,225.00$ 72.25$ 926,606.25$ 95.93$ 1,230,302.25$ -$

All work complete to supply and install Geotextile Fabric as specified in the specifications and drawings. 10,410 SY 3.25$ 33,832.50$ 4.20$ 43,722.00$ 2.50$ 26,025.00$ -$

All work to complete the supply, haul, place, and compact embankment (Cut/Fill) for bank stabilization as specified in the specifications and drawings. 5,540 CY 12.00$ 66,480.00$ 4.40$ 24,376.00$ 14.95$ 82,823.00$ -$

All remaining work including but not limited to mobilization, demobilization, access road, shaping, and maintenance, and all other work except the work listed in the items above and below listed in the options. 1 Job 130,000.00$ 130,000.00$ 80,432.00$ 80,432.00$ 259,760.00$ 259,760.00$ -$

1,166,537.50$ 1,075,136.25$ 1,598,910.25$ -$

OPTIONS

All work to complete the supply and install Riprap as specified in the specifications and drawings. 1,600 TON 70.00$ 112,000.00$ 58.50$ 93,600.00$ 101.29$ 162,064.00$ -$

All work to complete the supply and install Geotextile Fabric as specified in the specifications and drawings. 1,290 SY 3.25$ 4,192.50$ 3.60$ 4,644.00$ 2.63$ 3,392.70$ -$

All work complete to supply, haul, place, and compact embankment (Cut/Fill) for bank stabilization as specified in the specifications and drawings. 690 CY 12.00$ 8,280.00$ 3.60$ 2,484.00$ 102.60$ 70,794.00$ -$

124,472.50$ 100,728.00$ 236,250.70$ -$

1,291,010.00$ 1,175,864.25$ 1,835,160.95$ -$

ABSTRACT OF OFFERS -

1. SOLICITATION NUMBER PAGE 4 OF 4

W9128F21B0004

CONSTRUCTION INSTRUCTIONS: Attach this form to Abstract of Offers - Construction, when more than 2 offers are received on a construction project. Each Continuation

CONTINUATION SHEET sheet will accommodate 24 contract items to conform the number of items which can be entered . Use additional forms and continuation sheets as needed.

2. PROJECT TITLE 4. OFFERS (Continued)

NO. 11 NO. 12 NO. 13 NO. 14

OAHE LITTLE BEND BANK STABILIZATION A. OFFEROR A. OFFEROR A. OFFEROR A. OFFEROR

A-G-E Corporation Moltron Meyer, LLC Air Control, Inc.

704 W. Highway 14 & 34 424 Winnetka Ave N 80 N. 14th Avenue

Fort Pierre, SD 57532 Minneapolis, MN 55427 Clinton, IA 52732

B. REASONABLE CONTRACT B. BID SECURITY (Type & Amount) B. BID SECURITY (Type & Amount) B. BID SECURITY (Type & Amount)

20% 20% 20% 20%

C. AMENDMENTS ACKNOWLEDGED

3 1 1 1 1

SUBTOTAL BASE

SUBTOTAL OPTIONS

6. NUMBER OF AMENDMENTS ISSUED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED

Bid Abstract Page 1
Bid Abstract Page 2
Bid Abstract Page 3
Bid Abstract Page 4
2021-03-24T12:53:07-0500
MATUSZEWSKI.DEAN.P.1100724550

File details come from the government source that posted it. Updated .