Solicitation
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Am0003.pdf | ||
| Am0002.pdf | ||
| FR_Dig_Gov_Reference_Schedule.pdf | ||
| Am0001.pdf | ||
| Am0001_Ft_Randall_Digital_Gov_Dwgs.pdf | ||
| FTR_Dig_Gov_Solicitation_Drawings_U1_and_U2.pdf | ||
| Fort_Randall_Dig_Gov_Contract_Reference_Drawings.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIFICATIONS
(Request For Proposal)
Solicitation No W9128F19R0053
Install Digital Governors
Fort Randall Dam, SD
July 2019
US Army Corps of Engineers Omaha District
This page was intentionally left blank for duplex printing.
Install Digital Governors Fort Randall Dam, SD
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 10 00 SOLICITATION, OFFER AND AWARD
00 10 00-3 PRICING SCHEDULE
00 21 00 INSTRUCTIONS TO OFFERORS (RFP)
00 22 00 PROPOSAL INSTRUCTIONS, SUBMISSION REQUIREMENTS,
EVALUATION, AND BASIS FOR AWARD
00 45 00 REPRESENTATIONS AND CERTIFICATIONS
00 72 00 GENERAL CONDITIONS (CONTRACT CLAUSES - RFP)
00 73 00 SUPPLEMENTARY CONDITIONS (SPECIAL CONTRACT REQUIREMENTS)
DIVISION 01 - GENERAL REQUIREMENTS
01 12 00 CONSTRUCTION GENERAL
01 22 00.00 26 MEASUREMENT AND PAYMENT
01 30 00.24 OTHER ADMINISTRATIVE AND SPECIAL REQUIREMENTS
01 32 01.00 10 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 45 00.00 10 QUALITY CONTROL
01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE(RMS CM)
01 57 20.00 10 ENVIRONMENTAL PROTECTION
01 78 39.00 24 AS-BUILT DRAWINGS
01 91 00.00 26 DIGITAL GOVERNOR COMMISSIONING
DIVISION 02 - EXISTING CONDITIONS
02 41 19.00 26 REMOVAL OF HYDRAULIC-MECHANICAL GOVERNOR
02 82 00 ASBESTOS-CONTAINING MATERIALS
02 83 00 LEAD-CONTAINING PAINT REMOVAL AND DISPOSAL
DIVISION 09 - FINISHES
09 90 00.00 26 PAINTING
DIVISION 26 - ELECTRICAL
26 10 00.00 26 EQUIPMENT INSTALLATION AND WIRING
DIVISION 27 - COMMUNICATIONS
27 21 10.00 26 FIBER OPTIC DATA TRANSMISSION SYSTEM
DIVISION 48 - ELECTRICAL POWER GENERATION
48 19 01.00 26 GOVERNOR REPLACEMENT INSTALLATION
-- End of Project Table of Contents --
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
CODE
6. PROJECT NUMBER
8. ADDRESS OFFER TO
4. CONTRACT NUMBER
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 8/2014)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
3. DATE ISSUED PAGE OF PAGES
W9128F19R0053
U.S.ARMY CORPS OF ENGINEERS, OMAHA
Contracting Division (CENWO-CT) 1616 Capitol Ave Omaha, Nebraska 68102-4901
The offeror hereby agrees to do all work described in the documents entitled:
Install Digital Governors, Fort Randall Dam, SD
RETURN WITH OFFER: INFORMATION REQUIRED BY SECTION 00 10 00 (SF1442), SECTION 00 22 00, AND SECTION
00 45 00. ELECTONIC COPIES OF OFFER ARE ACCEPTABLE.
THIS SOLICITATION IS UNRESTRICTED AND IS OPEN TO BOTH LARGE AND SMALL BUSINESS PARTICIPITATION
U.S.ARMY CORPS OF ENGINEERS, OMAHA
POC: Lynne Reed (W9128F19R00xx) Contracting Division (CENWO-CT) 1616 Capitol Ave Omaha, Nebraska 68102-4901
CT
Lynne Reed (402) 995-2039
07/17/2019 local time 08/16/2019
2:00 pm
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT
NUMBER
DATE.
AWARD (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 8/2014) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
27. PAYMENT WILL BE MADE BY
10 U.S.C. 2304(c) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
DUNS Number or Unique Entity Identifier Number:
U.S. Army Engineer District, Omaha 1616 Capitol Ave.
Omaha, Nebraska 68102-4901
USAED Omaha c/o USACE Finance Center 5722 Integrity Drive Millington, TN 38054-5005
SEE ATTACHED CLIN PRICING SCHEDULE
Contractor’s Fax No.____________ CAGE CODE ________________ Contractor’s E-Mail address_______________
Install Digital Governors, Fort Randall, SD FRF4
SECTION 00 10 00
PRICING SCHEDULE
00 10 00 page 3
CLIN DESCRIPTION QTY UNIT UNIT PRICE AMOUNT
BASE ITEMS
0001 Site Visit to Measure 1st Unit Distributing Valve 1 JOB XXX $_______________
0002 Mobilization and Demobilization 1 JOB XXX $_______________
0003 Remove And Dispose Of Existing Governor Controls 8 JOB $_________ $_______________
0004 Install New Governor Controls And Accessories 8 JOB $_________ $_______________
0005 Distributing Valve Refurbishment 8 JOB $__________ $_______________
0006 Furnish Gate Distributing Valve Parts Set 8 EA $__________ $_______________
0007 Kidney Loop Filtration 8 JOB $__________ $_______________
Replace Governor Oil Pump Feeder Cables, Breaker, Contactors, and Control Transformers
8 JOB $__________ $_______________
SUB-TOTAL BASE (Items 0001 thru 0008) $_______________
OPTIONAL ITEMS
0009 Distributing Valve Wiper Seal Modification
0009AA Generator Unit #1 1 JOB XXX $_______________
SECTION 00 10 00
PRICING SCHEDULE
00 10 00 page 4
0009AB Generator Unit #2 1 JOB XXX $_______________
0009AC Generator Unit #3 1 JOB XXX $_______________
0009AD Generator Unit #4 1 JOB XXX $_______________
0009AE Generator Unit #5 1 JOB XXX $_______________
0009AF Generator Unit #6 1 JOB XXX $_______________
0009AG Generator Unit #7 1 JOB XXX $_______________
0009AH Generator Unit #8 1 JOB XXX $_______________
SUB-TOTAL OPTION (Item 0009 (0009AA thru 0009AH)) $_______________
TOTAL BASE + OPTIONS (Items 0001 thru 0009) $_______________
1. See SECTION 00 21 00, INSTRUCTIONS, CONDITIONS, & NOTICES TO BIDDERS for evaluation of options.
The Government may exercise an option by written notice to the Contractor commencing from the date of contract award thru the date the contract is closed, unless otherwise specified herein.
2. Prices must be entered for all items of the schedule. Total amounts submitted without prices being entered on individual items will be rejected. Additions will be subject to verification by the Government. In case of variation between the Job (lump-sum) prices and the total amount, the lump-sum prices will be considered the price submitted.
3. A modification to a proposal which provides for a single adjustment to the total amount submitted, should state the application of the adjustment to each respective lump-sum price affected. If the modification is not so apportioned, the single adjustment will be applied to Item Nos. 0001 thru 0008.
4. See Section 01 22 00.00 26 MEASUREMENT AND PAYMENT for more information.
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 00 21 00
INSTRUCTIONS TO OFFERORS (RFP)
3/19
PART 1 GENERAL
1.1 (FAR 52.211-2) AVAILABILITY OF SPECIFICATIONS, STANDARDS, AND DATA
ITEM DESCRIPTIONS LISTED IN THE ACQUISITION STREAMLINING AND
STANDARDIZATION INFORMATION SYSTEM (ASSIST) (APR 2014)
1.2 FAR 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS-SECONDARY SITE
OF THE WORK (MAY 2014)
1.3 (DFARS 252.204-7008) COMPLIANCE WITH SAFEGUARDING COVERED DEFENSE
INFORMATION CONTROLS (OCT 2016)
1.4 (DFARS 252.215-7008) ONLY ONE OFFER (OCT 2013)
1.5 (FAR 52.204-7) SYSTEM FOR AWARD MANAGEMENT (OCT 2018)
1.6 (FAR 52.204-16) COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING
(JUL 2016)
1.7 (FAR 52.215-1) INSTRUCTIONS TO OFFERORS--COMPETITIVE ACQUISITION
(JAN 2017)
1.8 FAR 52. 215-20 REQUIREMENTS FOR CERTIFIED COST OR PRICING DATA AND
DATA OTHER THAN CERTIFIED COST OR PRICING DATA (OCT 2010)
1.9 (FAR 52.216-1) TYPE OF CONTRACT (APR 1984)
1.10 *FAR 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT-CONSTRUCTION
MATERIALS (MAY 2014)
1.11 (FAR 52.232-18) AVAILABILITY OF FUNDS (APR 1984)
1.12 (FAR 52.233-2) SERVICE OF PROTEST (SEPT 2006)
1.13 (FAR 52.236-27) SITE VISIT (CONSTRUCTION) (FEB 1995).
1.14 (FAR 52.252-1) SOLICITATION PROVISIONS INCORPORATED BY REFERENCE
(FEB 1998)
1.15 SOLICITATION RESTRICTIONS
1.15.1 GENERAL CONTRACTOR
1.15.2 ESTIMATED CONSTRUCTION COST
1.15.3 SUBMISSION, MODIFICATION, REVISION, AND WITHDRAWAL OF PROPOSALS
1.15.4 SUBMISSION DEADLINE
1.15.5 RETURN ADDRESS REQUIREMENTS
1.16 COPIES OF SOLICITATION DOCUMENT AND AMENDMENTS
1.17 OFFEROR'S QUESTIONS AND COMMENTS
1.17.1 BIDDER INQUIRY
1.17.2 PLAN HOLDER'S LIST
1.18 GENERAL DESCRIPTION OF WORK
1.19 PROPOSAL SUBMISSION REQUIREMENTS, EVALUATION AND CONTRACT AWARD
1.20 SOURCE SELECTION BOARD (SSB)
1.21 FEDERAL, STATE AND LOCAL TAXES
1.22 TAXES - STATE OF SOUTH DAKOTA
1.22.1 EXCISE TAX
1.22.2 USE TAX
1.22.3 INFORMATION
1.23 SUBCONTRACTING PLAN/SUBCONTRACTING GOALS REGARDING THE UTILIZATION
OF SMALL BUSINESS CONCERNS
DOCUMENT 00 21 00 Page 1
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
-- End of Section Table of Contents --
DOCUMENT 00 21 00 Page 2
SECTION 00 21 00
INSTRUCTIONS TO OFFERORS (RFP)
3/19
PART 1 GENERAL
PROVISIONS INCORPORATED BY REFERENCE (IBR)
1.1 (FAR 52.211-2) AVAILABILITY OF SPECIFICATIONS, STANDARDS, AND DATA ITEM
DESCRIPTIONS LISTED IN THE ACQUISITION STREAMLINING AND STANDARDIZATION
INFORMATION SYSTEM (ASSIST) (APR 2014)
1.2 FAR 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS-SECONDARY SITE OF
THE WORK (MAY 2014)
1.3 (DFARS 252.204-7008) COMPLIANCE WITH SAFEGUARDING COVERED DEFENSE
INFORMATION CONTROLS (OCT 2016)
1.4 (DFARS 252.215-7008) ONLY ONE OFFER (OCT 2013)
PROVISIONS IN FULL TEXT
1.5 (FAR 52.204-7) SYSTEM FOR AWARD MANAGEMENT (OCT 2018)
(a) Definitions. As used in this provision-
“Electronic Funds Transfer (EFT) indicator” means a fourcharacter suffix to the unique entity identifier. The suffix is assigned at the discretion of the commercial, nonprofit, or Government entity to establish additional System for Award Management records for identifying alternative EFT accounts (see subpart 32.11) for the same entity.
"Registered in the System for Award Management (SAM)" means that-
(1) The Offeror has entered all mandatory information, including the unique entity identifier and the EFT indicator, if applicable, the Commercial and Government Entity (CAGE) code, as well as data required by the Federal Funding Accountability and Transparency Act of 2006 (see subpart 4.14) into SAM;
(2) The offeror has completed the Core, Assertions, and Representations and Certifications, and Points of Contact sections of the registration in SAM;
(3) The Government has validated all mandatory data fields, to include validation of the Taxpayer Identification Number (TIN) with the Internal Revenue Service (IRS). The offeror will be required to provide TIN validation to the Government as a part of the SAM registration process;
and
(4) The Government has marked the record "Active".
“Unique entity identifier” means a number or other identifier used to identify a specific commercial, nonprofit, or Government entity. See www.sam.gov for the designated entity for establishing unique entity identifiers.
(b)(1) An Offeror is required to be registered in SAM when submitting an offer or quotation, and shall continue to be registered until time of award, during performance, and through final payment of any contract, basic agreement, basic ordering
DOCUMENT 00 21 00 Page 3 agreement, or blanket purchasing agreement resulting from this solicitation.
(2) The Offeror shall enter, in the block with its name and address on the cover page of its offer, the annotation “Unique Entity Identifier” followed by the unique entity identifier that identifies the Offeror’s name and address exactly as stated in the offer. The Offeror also shall enter its EFT indicator, if applicable. The unique entity identifier will be used by the Contracting Officer to verify that the Offeror is registered in SAM.
(c) If the Offeror does not have a unique entity identifier, it should contact the entity designated at www.sam.gov for establishment of the unique entity identifier directly to obtain one. The Offeror should be prepared to provide the following information:
(1) Company legal business.
(2) Tradestyle, doing business, or other name by which your entity is commonly recognized.
(3) Company Physical Street Address, City, State, and Zip Code.
(4) Company Mailing Address, City, State and Zip Code (if separate from physical).
(5) Company Telephone Number.
(6) Date the company was started.
(7) Number of employees at your location.
(8) Chief executive officer/key manager.
(9) Line of business (industry).
(10) Company Headquarters name and address (reporting relationship within your entity).
(d) Processing time should be taken into consideration when registering. Offerors who are not registered in SAM should consider applying for registration immediately upon receipt of this solicitation.
See https://www.sam.gov for information on registration.
(End of provision)
1.6 (FAR 52.204-16) COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING (JUL
2016)
(a) Definition. As used in this provision –
“Commercial and Government Entity (CAGE) code” means –
(1) An identifier assigned to entities located in the United States or its outlying areas by the Defense Logistics Agency (DLA) Commercial and Government Entity (CAGE) Branch to identify a commercial or government entity; or
(2) An identifier assigned by a member of the North Atlantic
Treaty Organization (NATO) or by the NATO Support and Procurement Agency (NSPA) to entities located outside the United States and its outlying areas that the DLA Commercial and Government Entity (CAGE) Branch records and maintains in the CAGE master file. This type of code is known as a NATO CAGE (NCAGE) code..
(b) The Offeror shall enter its CAGE code in its offer with its name and address or otherwise include it prominently in its proposal. The CAGE code entered must be for that name and address. Enter “CAGE” before the number. The CAGE code is required prior to award.
DOCUMENT 00 21 00 Page 4
(c) CAGE codes may be obtained via–
(1) Registration in the System for Award Management (SAM) at www.sam.gov. If the Offeror is located in the United States or its outlying areas and does not already have a CAGE code assigned, the DLA Commercial and Government Entity (CAGE) Branch will assign a CAGE code as a part of the SAM registration process. SAM registrants located outside the United States and its outlying areas shall obtain a NCAGE code prior to registration in SAM (see paragraph (c)(3) of this provision).
(2) The DLA Contractor and Government Entity (CAGE) Branch. If registration in SAM is not required for the subject procurement, and the offeror does not otherwise register in SAM, an offeror located in the United States or its outlying areas may request that a CAGE code be assigned by submitting a request at https://cage.dla.mil.
(3) The appropriate country codification bureau. Entities located outside the United States and its outlying areas may obtain an NCAGE code by contacting the Codification Bureau in the foreign entity’s country if that country is a member of NATO or a sponsored nation. NCAGE codes may be obtained from the NSPA at https://eportal.nspa.nato.int/AC135Public/scage/CageList.aspx if the foreign entity’s country is not a member of NATO or a sponsored nation.
Points of contact for codification bureaus, as well as additional information on obtaining NCAGE codes, are available at http://www.nato.int/structur/AC/135/main/links/contacts.htm.
(d) Additional guidance for establishing and maintaining CAGE codes is available at https://cage.dla.mil.
(e) When a CAGE Code is required for the immediate owner and/or the highest-level owner by 52.204-17 or 52.212-3(p), the Offeror shall obtain the respective CAGE Code from that entity to supply the CAGE Code to the Government.
(f) Do not delay submission of the offer pending receipt of a CAGE code.
(End of provision)
1.7 (FAR 52.215-1) INSTRUCTIONS TO OFFERORS--COMPETITIVE ACQUISITION (JAN
2017)
(a) Definitions. As used in this provision- "Discussions" are negotiations that occur after establishment of the competitive range that may, at the Contracting Officer's discretion, result in the offeror being allowed to revise its proposal.
"In writing," "writing," or "written" means any worded or numbered expression that can be read, reproduced, and later communicated, and includes electronically transmitted and stored information.
"Proposal modification" is a change made to a proposal before the solicitation's closing date and time, or made in response to an amendment, or made to correct a mistake at any time before award.
"Proposal revision" is a change to a proposal made after the solicitation closing date, at the request of or as allowed by a Contracting Officer as the result of negotiations.
"Time," if stated as a number of days, is calculated using calendar days, unless otherwise specified, and will include Saturdays, Sundays, and legal holidays. However, if the last day falls on a Saturday, Sunday, or
DOCUMENT 00 21 00 Page 5 legal holiday, then the period shall include the next working day.
(b) Amendments to solicitations. If this solicitation is amended, all terms and conditions that are not amended remain unchanged. Offerors shall acknowledge receipt of any amendment to this solicitation by the date and time specified in the amendment(s).
(c) Submission, modification, revision, and withdrawal of proposals.
(1) Unless other methods (e.g., electronic commerce or facsimile) are permitted in the solicitation, proposals and modifications to proposals shall be submitted in paper media in sealed envelopes or packages (i) addressed to the office specified in the solicitation, and (ii) showing the time and date specified for receipt, the solicitation number, and the name and address of the offeror. Offerors using commercial carriers should ensure that the proposal is marked on the outermost wrapper with the information in paragraphs (c)(1)(i) and (c)(1)(ii) of this provision.
(2) The first page of the proposal must show-
(i) The solicitation number;
(ii) The name, address, and telephone and facsimile numbers of the offeror (and electronic address if available);
(iii) A statement specifying the extent of agreement with all terms, conditions, and provisions included in the solicitation and agreement to furnish any or all items upon which prices are offered at the price set opposite each item;
(iv) Names, titles, and telephone and facsimile numbers (and electronic addresses if available) of persons authorized to negotiate on the offeror's behalf with the Government in connection with this solicitation; and
(v) Name, title, and signature of person authorized to sign the proposal. Proposals signed by an agent shall be accompanied by evidence of that agent's authority, unless that evidence has been previously furnished to the issuing office.
(3) Submission, modification, revision, and withdrawal of proposals.
(i) Offerors are responsible for submitting proposals, and any modifications or revisions, so as to reach the Government office designated in the solicitation by the time specified in the solicitation.
If no time is specified in the solicitation, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that proposal or revision is due.
(ii)(A) Any proposal, modification, or revision received at the Government office designated in the solicitation after the exact time specified for receipt of offers is "late" and will not be considered unless it is received before award is made, the Contracting Officer determines that accepting the late offer would not unduly delay the acquisition; and-
(1) If it was transmitted through an electronic commerce method authorized by the solicitation, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of proposals; or
(2) There is acceptable evidence to establish that it was received at the Government installation designated for receipt of offers and was under the Government's control prior to the time set for receipt of offers; or
(3) It is the only proposal received.
(B) However, a late modification of an otherwise successful proposal that makes its terms more favorable to the Government, will be considered at any time it is received and may be accepted.
(iii) Acceptable evidence to establish the time of receipt at the Government installation includes the time/date stamp of that
DOCUMENT 00 21 00 Page 6 installation on the proposal wrapper, other documentary evidence of receipt maintained by the installation, or oral testimony or statements of Government personnel.
(iv) If an emergency or unanticipated event interrupts normal Government processes so that proposals cannot be received at the office designated for receipt of proposals by the exact time specified in the solicitation, and urgent Government requirements preclude amendment of the solicitation, the time specified for receipt of proposals will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume.
(v) Proposals may be withdrawn by written notice received at any time before award. Oral proposals in response to oral solicitations may be withdrawn orally. If the solicitation authorizes facsimile proposals, proposals may be withdrawn via facsimile received at any time before award, subject to the conditions specified in the provision at 52.215-5, Facsimile Proposals. Proposals may be withdrawn in person by an offeror or an authorized representative, if the identity of the person requesting withdrawal is established and the person signs a receipt for the proposal before award.
(4) Unless otherwise specified in the solicitation, the offeror may propose to provide any item or combination of items.
(5) Offerors shall submit proposals in response to this solicitation in English, unless otherwise permitted by the solicitation, and in U.S. dollars, unless the provision at FAR 52.225-17, Evaluation of Foreign Currency Offers, is included in the solicitation.
(6) Offerors may submit modifications to their proposals at any time before the solicitation closing date and time, and may submit modifications in response to an amendment, or to correct a mistake at any time before award.
(7) Offerors may submit revised proposals only if requested or allowed by the Contracting Officer.
(8) Proposals may be withdrawn at any time before award.
Withdrawals are effective upon receipt of notice by the Contracting Officer.
(d) Offer expiration date. Proposals in response to this solicitation will be valid for the number of days specified on the solicitation cover sheet (unless a different period is proposed by the offeror).
(e) Restriction on disclosure and use of data. Offerors that include in their proposals data that they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes, shall-
(1) Mark the title page with the following legend:
This proposal includes data that shall not be disclosed outside the Government and shall not be duplicated, used, or disclosed-in whole or in part-for any purpose other than to evaluate this proposal. If, however, a contract is awarded to this offeror as a result of-or in connection with-the submission of this data, the Government shall have the right to duplicate, use, or disclose the data to the extent provided in the resulting contract. This restriction does not limit the Government's right to use information contained in this data if it is obtained from another source without restriction. The data subject to this restriction are contained in sheets insert numbers or other identification of sheets; and
(2) Mark each sheet of data it wishes to restrict with the following legend:
Use or disclosure of data contained on this sheet is subject to the restriction on the title page of this proposal.
(f) Contract award. (1) The Government intends to award a contract or contracts resulting from this solicitation to the responsible offeror(s) whose proposal(s) represents the best value after evaluation in accordance with the factors and subfactors in the solicitation.
DOCUMENT 00 21 00 Page 7
(2) The Government may reject any or all proposals if such action is in the Government's interest.
(3) The Government may waive informalities and minor irregularities in proposals received.
(4) The Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). Therefore, the offeror's initial proposal should contain the offeror's best terms from a cost or price and technical standpoint. The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. If the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.
(5) The Government reserves the right to make an award on any item for a quantity less than the quantity offered, at the unit cost or prices offered, unless the offeror specifies otherwise in the proposal.
(6) The Government reserves the right to make multiple awards if, after considering the additional administrative costs, it is in the Government's best interest to do so.
(7) Exchanges with offerors after receipt of a proposal do not constitute a rejection or counteroffer by the Government.
(8) The Government may determine that a proposal is unacceptable if the prices proposed are materially unbalanced between line items or subline items. Unbalanced pricing exists when, despite an acceptable total evaluated price, the price of one or more line items is significantly overstated or understated as indicated by the application of cost or price analysis techniques. A proposal may be rejected if the Contracting Officer determines that the lack of balance poses an unacceptable risk to the Government.
(9) If a cost realism analysis is performed, cost realism may be considered by the source selection authority in evaluating performance or schedule risk.
(10) A written award or acceptance of proposal mailed or otherwise furnished to the successful offeror within the time specified in the proposal shall result in a binding contract without further action by either party.
(11) If a post-award debriefing is given to requesting offerors, the Government shall disclose the following information, if applicable:
(i) The agency's evaluation of the significant weak or deficient factors in the debriefed offeror's offer.
(ii) The overall evaluated cost or price and technical rating of the successful and the debriefed offeror and past performance information on the debriefed offeror.
(iii) The overall ranking of all offerors, when any ranking was developed by the agency during source selection.
(iv) A summary of the rationale for award.
(v) For acquisitions of commercial items, the make and model of the item to be delivered by the successful offeror.
(vi) Reasonable responses to relevant questions posed by the debriefed offeror as to whether source-selection procedures set forth in the solicitation, applicable regulations, and other applicable authorities were followed by the agency.
(End of provision)
DOCUMENT 00 21 00 Page 8
1.8 FAR 52. 215-20 REQUIREMENTS FOR CERTIFIED COST OR PRICING DATA AND
DATA OTHER THAN CERTIFIED COST OR PRICING DATA (OCT 2010)
(a) Exceptions from certified cost or pricing data.
(1) In lieu of submitting certified cost or pricing data, offerors may submit a written request for exception by submitting the information described in the following paragraphs.The Contracting Officer may require additional supporting information, but only to the extent necessary to determine whether an exception should be granted, and whether the price is fair and reasonable.
(i) Identification of the law or regulation establishing the price offered.
If the price is controlled under law by periodic rulings, reviews, or similar actions of a governmental body, attach a copy of the controlling document, unless it was previously submitted to the contracting office.
(ii) Commercial item exception. For a commercial item exception, the offeror shall submit, at a minimum, information on prices at which the same item or similar items have previously been sold in the commercial market that is adequate for evaluating the reasonableness of the price for this acquisition. Such information may include-
(A) For catalog items, a copy of or identification of the catalog and its date, or the appropriate pages for the offered items, or a statement that the catalog is on file in the buying office to which the proposal is being submitted. Provide a copy or describe current discount policies and price lists (published or unpublished), e.g., wholesale, original equipment manufacturer, or reseller. Also explain the basis of each offered price and its relationship to the established catalog price, including how the proposed price relates to the price of recent sales in quantities similar to the proposed quantities;
(B) For market-priced items, the source and date or period of the market quotation or other basis for market price, the base amount, and applicable discounts. In addition, describe the nature of the market;
(C) For items included on an active Federal Supply Service Multiple Award Schedule contract, proof that an exception has been granted for the schedule item.
(2) The offeror grants the Contracting Officer or an authorized representative the right to examine, at any time before award, books, records, documents, or other directly pertinent records to verify any request for an exception under this provision, and the reasonableness of price. For items priced using catalog or market prices, or law or regulation, access does not extend to cost or profit information or other data relevant solely to the offeror’s determination of the prices to be offered in the catalog or marketplace.
(b) Requirements for certified cost or pricing data. If the offeror is not granted an exception from the requirement to submit certified cost or pricing data, the following applies:
(1) The offeror shall prepare and submit certified cost or pricing data, data other than certified cost or pricing data, and supporting attachments in accordance with the instructions contained in Table 15-2 of FAR 15.408, which is incorporated by reference with the same force and effect as though it were inserted here in full text. The instructions in Table 15-2 are
DOCUMENT 00 21 00 Page 9 incorporated as a mandatory format to be used in this contract, unless the Contracting Officer and the Contractor agree to a different format and change this clause to use Alternate I.
(2) As soon as practicable after agreement on price, but before contract award (except for unpriced actions such as letter contracts), the offeror shall submit a Certificate of Current Cost or Pricing Data, as prescribed by FAR 15.406-2.
(End of provision)
1.9 (FAR 52.216-1) TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a firm fixed price contract resulting from this solicitation.
(End of provision)
1.10 *FAR 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT-CONSTRUCTION
MATERIALS (MAY 2014)
(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American-Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American Statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers. (1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at
FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers. (1) When an offer includes foreign construction material not listed by the Government in this solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on
DOCUMENT 00 21 00 Page 10 use of the foreign construction material for which an exception was requested-
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
(End of provision)
1.11 (FAR 52.232-18) AVAILABILITY OF FUNDS (APR 1984)
Funds are not presently available for this contract. The Government's obligation under this contract is contingent upon the availability of appropriated funds from which payment for contract purposes can be made.
No legal liability on the part of the Government for any payment may arise until funds are made available to the Contracting Officer for this contract and until the Contractor receives notice of such availability, to be confirmed in writing by the Contracting Officer.
(End of clause)
1.12 (FAR 52.233-2) SERVICE OF PROTEST (SEPT 2006)
(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from District Counsel, 1616 Capitol Avenue, Omaha, Nebraska 68102-4901.
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
(End of provision)
1.13 (FAR 52.236-27) SITE VISIT (CONSTRUCTION) (FEB 1995).
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) A site visit is scheduled for 06 August 2019 at 9:00 am.
Contractors interested in seeing the site need to make reservation with Michael Schenkel telephone (605) 487-7845 X 3003 or by e-mail at Michael.A.Schenkel@usace.army.mil. Contractors are to meet at the Powerhouse.
(End of provision)
1.14 (FAR 52.252-1) SOLICITATION PROVISIONS INCORPORATED BY REFERENCE
(FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at
DOCUMENT 00 21 00 Page 11 this/these address(es):
http://acquisition.gov/comp/far/index.html http://www.acq.osd.mil/dpap/ (End of provision)
1.15 SOLICITATION RESTRICTIONS
1.15.1 GENERAL CONTRACTOR
This solicitation is unrestricted and open to both large and small business participation.
1.15.2 ESTIMATED CONSTRUCTION COST
The estimated construction cost of this project is between $2,500,000 and $5,000,000.
1.15.3 SUBMISSION, MODIFICATION, REVISION, AND WITHDRAWAL OF PROPOSALS
See FAR 52.215-1 INSTRUCTIONS TO OFFERORS-COMPETITIVE ACQUISTION, subparagraph "(c) Submission, modification, revision, and withdrawal of proposals." below for acceptable methods.
1.15.4 SUBMISSION DEADLINE
Offers shall be submitted as stated and by the time and date as specified in Section 00 10 00, Page 1.
Submit proposals, via AMRDEC SAFE FTP Site:
https://safe.amrdec.army.mil/safe/
AMRDEC TO:
Lynne.D.Reed@usace.army.mil Nadine.L.Catania@usace.army.mil
1.15.5 RETURN ADDRESS REQUIREMENTS
Offeror(s) must ensure that ALL mail sent to the Omaha District, U.S. Army Corps of Engineers, either pre-contract or post-contract award, has a return mailing address on the outside of the envelope, package, box, etc.
ANY MAIL addressed to the U.S. Army Corps of Engineers, including but not limited to proposals, revised proposals, bid guarantees, bonds, correspondence, etc., will be REJECTED by the US Army Corps of Engineers mail room facility located at 1616 Capitol Avenue, Omaha, Nebraska 68102-4901 if it does not contain a return mailing address. THERE WILL BE
NO EXCEPTIONS.
1.16 COPIES OF SOLICITATION DOCUMENT AND AMENDMENTS
Copies of the solicitation and amendments are available by INTERNET ACCESS ONLY. All solicitation documents will be posted to the Federal Business Opportunities website at:
https://www.fbo.gov
It shall be the Contractor's responsibility to check the websites for any amendments. The offeror shall submit in the proposal all requested
DOCUMENT 00 21 00 Page 12 information specified in this solicitation. There will be no public opening of the proposals received as a result of this solicitation.
A list of interested vendors (potential offerors and subcontractors) is available on the federal business opportunities web site listed above (registration required).
1.17 OFFEROR'S QUESTIONS AND COMMENTS
Questions and/or comments relative to these documents should be submitted via Bidder Inquiry as indicated below. See instructions on when e-mail or AMRDEC is appropriate. Mailing address is shown on the Standard Form SF 1442, Item 8, unless directed otherwise.
Contract Specialist - Primary POC:
Lynne Reed Lynne.D.Reed@usace.army.mil 402-995-2039 (Telephone)
1.17.1 BIDDER INQUIRY
Questions relating to the proposal are to be submitted via Bidder Inquiry in ProjNet at: https://www.projnet.org/projnet/ No Later Than ten (10) calendar days before due date of proposals, in order that they may be given consideration or actions taken prior to receipt of offers. The Bidder Inquiry system is to be used to ask and receive answers to all non-proprietary questions.
To submit and review inquiry items, prospective vendors will need to use the Bidder Inquiry Key presented below and follow the instructions listed below. A prospective vendor who submits a comment /question will receive an acknowledgement of their comment/question via ProjNet email notification after an answer to the comment/question after it has been processed by our technical team.
All timely questions and approved answers will be made available through ProjNet.
The Solicitation Number is: W9128F19R0053
The Bidder Inquiry Key is: AZEVQD-7466SK
a. Registration for ProjNet Bidder Inquiry Access
If you are already registered, go to Entering Bidder Inquiries in ProjNet Bidder Inquiry System below.
1. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.
2. Identify the Agency. This should be marked as USACE.
3. Key. Enter the Bidder Inquiry Key listed above.
4. Email. Enter the email address you would like to use for communication.
5. Click Continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.
DOCUMENT 00 21 00 Page 13
6. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret Question, Secret Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.
7. Click Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.
b. Entering Bidder Inquiries in ProjNet Bidder Inquiry System
1. For future access to ProjNet, you will not be emailed any type of password. You will utilize your Secret Question and Secret Answer to log in.
2. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.
3. Identify the Agency. This should be marked as USACE.
4. Key. Enter the Bidder Inquiry Key listed above.
5. Email. Enter the email address you used to register previously in ProjNet.
6. Click Continue. A page will then open asking you to enter the answer to your Secret Question.
7. Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.
8. Follow online screen instructions to enter specific bidder inquiries for the project.
c. The Bidder Inquiry System will be unavailable for new inquires after ten
(10) calendar days in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary.
d. Offerors are requested to review the specification in its entirety, review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.
e. The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.
f. Offers will NOT be publicly opened. Information concerning the status of the evaluation and/or award will NOT be available after receipt of proposals.
1.17.2 PLAN HOLDER'S LIST
For Viewing a List of Interested Vendors (i.e. planholders List) and Receiving Notifications or e-mail of changes regarding a solicitation, Federal Business Opportunities has these features available ( https://www.fbo.gov/). For this solicitation, go to https://www.fbo.gov/ and register as a vendor or enter user name and password to login. If you wish for General Contractors, Subcontractors, Suppliers, Plan Rooms or Print Shops to have the ability to contact you, click on the "Add me to Interested Vendors" for the solicitation.
DOCUMENT 00 21 00 Page 14
1.18 GENERAL DESCRIPTION OF WORK
Scope of project includes all work required to install digital governors at Fort Randall Dam. Work shall be in accordance with plans and specifications issued with this solicitation.
1.19 PROPOSAL SUBMISSION REQUIREMENTS, EVALUATION AND CONTRACT AWARD
See Section 00 22 00 SUPPLEMENTARY INSTRUCTIONS, PROPOSAL SUBMISSION AND
EVALUATION.
1.20 SOURCE SELECTION BOARD (SSB)
The Contracting Officer has established a Source Selection Board to conduct an evaluation of each proposal received in response to this Solicitation.
The evaluation will be based exclusively on the merits and content of the proposal and any subsequent discussion required. The identities of the SSB personnel are confidential, and any attempt by the proposers to contact these individuals is prohibited.
1.21 FEDERAL, STATE AND LOCAL TAXES
It is the Contractor's responsibility to investigate applicable federal, state and local taxes and any specific exemptions that may exist. This includes any applicable Value-Added Taxes (VAT), sales, use, and excise taxes. See General Conditions (Contract Clause) 52.229-3 FEDERAL, STATE
AND LOCAL TAXES.
1.22 TAXES - STATE OF SOUTH DAKOTA
1.22.1 EXCISE TAX
There is an excise tax on the total gross receipts of all prime contractors and subcontractors engaged in realty improvement contracts.
1.22.2 USE TAX
Government furnished construction material used by the Contractor in the performance of the work is subject to use tax. The value of the material furnished is set forth in the SECTION 01 30 00.24 OTHER ADMINISTRATIVE AND SPECIAL REQUIREMENTS provision "Government Furnished Property."
1.22.3 INFORMATION
The "excise" and "use" taxes shall be included in the price or prices bid.
For information concerning the taxes contact: http://dor.sd.gov/
1.23 SUBCONTRACTING PLAN/SUBCONTRACTING GOALS REGARDING THE UTILIZATION OF
SMALL BUSINESS CONCERNS
See Section 00 22 00 PROPOSAL INSTRUCTIONS, SUBMISSION REQUIREMENTS, EVALUATION, AND BASIS FOR AWARD for Small Business Goals.
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
-- End of Section --
DOCUMENT 00 21 00 Page 15
Install Digital Governors, Ft Randall Dam, SD FRF4
DOCUMENT 00 22 00 Page 1
SECTION 00 22 00
PROPOSAL INSTRUCTIONS,
SUBMISSION REQUIREMENTS, EVALUATION, AND BASIS FOR AWARD
1. WHO MAY SUBMIT
2. GENERAL REQUIREMENTS
3. BIDDER INQUIRY
4. FORMAT SIZE OF SUBMISSIONS
5. PROPOSAL SUBMITTAL INSTRUCTIONS
Table 1 - AMRDEC Proposal Submittals AMRDEC SAFE Electronic Submission
6. SUBMISSION DEADLINE
7. PROPOSAL CRITERIA
8. EVALUATION OF PROPOSALS
Evaluation Definitions
9. EVALUATION FACTORS FOR AWARD
VOLUME 1 - PROPOSAL REQUIREMENTS AND SUBMISSION FORMAT
VOLUME 2 - PRICE AND PRO FORMA INFORMATION
10. FACTOR 1 – EXPERIENCE
Submission Requirements Evaluation
11. FACTOR 2 – PAST PERFORMANCE
Submission Requirements Evaluation Method
12. FACTOR 3 - TECHNICAL APPROACH
Submission Requirements Evaluation
13. FACTOR 4- PERSONNEL QUALIFICATIONS AND EXPERIENCE
Submission Requirements Evaluation
14. FACTOR 5 – SMALL BUSINESS PARTICIPATION
15. VOLUME 2 - PRICE
Submission Requirements
16. EVALUATION OF PRICE
Evaluated Price Price Reasonableness Unbalanced Pricing Price Realism
17. COMPETITIVE RANGE
18. CLARIFICATIONS AND DISCUSSIONS
19. FINAL PROPOSAL REVISIONS
20. DEBRIEFING
ATTACHMENT 1
ATTACHMENT 2
Install Digital Governors, Ft Randall Dam, SD FRF4
DOCUMENT 00 22 00 Page 2
SECTION 00 22 00
PROPOSAL INSTRUCTIONS,
SUBMISSION REQUIREMENTS AND EVALUATION
1. WHO MAY SUBMIT
This solicitation is for Full and Open competition.
All Offerors, including joint ventures, must be registered in the System for Award Management (SAM).
There will be no public opening. All proposals submitted will become, upon receipt, the property of the U.S.
Government and will not be returned. After evaluation of proposals, the original will be…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it.