| ABSTRACT OF OFFERS - CONSTRUCTION | 1. SOLICITATION NUMBER | 2. DATE ISSUED | 3. DATE OPENED | Page 1 of 6 | |||||
| W9128F-12-B-0007 | 21-Mar-12 | 24-Apr-12 | |||||||
| 4. ISSUING OFFICE | I CERTIFY THAT I HAVE OPENED, READ AND | NAME AND TITLE OF CERTIFYING OFFICIAL (Type) | |||||||
| US ARMY CORPS OF ENGINEERS | RECORDED ON THIS ABSTRACT ALL OFFERS | Justine Womboldt, Contract Specialist | |||||||
| CONTRACTING DIVISION (CENWO-CT) | RECEIVED IN RESPONSE TO THIS SOLICITATION | SIGNATURE | DATE SIGNED | ||||||
| 1616 Capitol Avenue | * | ||||||||
| OMAHA, NE 68102 | |||||||||
| 5. PROJECT TITLE | 8. GOVERNMENT ESTIMATE | 9. OFFERS | |||||||
| (Check A, B or C AND COMPLETE D, E AND F) | NO. 1 | NO. 2 | |||||||
| SOF Operations and Storage Facility | A. HIRED LABOR | Purgatoire Valley Construction | Mesan, Inc | ||||||
| PN80234-FY12 | |||||||||
| Fort Carson, CO | |||||||||
| B. REASONABLE CONTRACT | B. BID SECURITY | B. BID SECURITY | |||||||
| (Without Profit) | 20% | 20% | |||||||
| 6. NUMBER OF AMENDMENTS ISSUED | C. REASONABLE CONTRACT | C. AMENDMENTS ACKNOWLEDGED | C. AMENDMENTS ACKNOWLEDGED | ||||||
| (Including Profit) | 4 | 4 | |||||||
| 7A | 7B | 7C | D. | E. | F. | E. | F. | E. | F. |
| ITEM # | DESCRIPTION OF OFFER ITEM | EST. QTY | UNIT | UNIT PRICE | ESTIMATED AMOUNT | UNIT PRICE | ESTIMATED AMOUNT | UNIT PRICE | ESTIMATED AMOUNT |
| 0001 | Construction of the SOF Operations and Storage Facility, PN 80234; excluding Item Nos. 0002 and Option Items listed below. | Job | LS | $1,055,752.00 | $1,165,100.00 | $1,302,445.00 | |||
| 0002 | Construction of SITEWORK AND UTILITIES, complete from the five-foot line of the SOF Operations and Storage Facility, PN 80234; excluding Option Items listed below. | Job | LS | $523,281.00 | $905,025.00 | $660,156.00 | |||
| TOTAL AMOUNT - (Basic Items 0001 & 0002) | $1,579,033.00 | $2,070,125.00 | $1,962,601.00 | ||||||
| 0003 (Option 1) | Entire work complete to provide the mezzanine as shown on drawing sheet S-100. | Job | LS | $39,649.00 | $42,950.00 | $10,961.00 | |||
| 0004 (Option 2) | Entire work complete to design and construct the antenna tower including the concrete base as shown in CS100 and A-300. | Job | LS | $49,099.00 | $44,950.00 | $53,567.00 | |||
| 0005 (Option 3) | Entire work complete to provide bituminous paving in lieu of gravel paving as shown on drawing sheet CS100. | Job | LS | $42,654.00 | $62,050.00 | $66,363.00 | |||
| 0006 (Option 4) | Entire work complete to provide the bio-retention pond and associated revised grading as shown on drawing sheets CG102, CG203, CG402, CG403, CG505, and CG506. | Job | LS | $25,262.00 | $38,150.00 | $49,258.00 | |||
| 0007 (Option 5) | Entire work complete to provide 6” concrete hardstand as shown on drawing sheet CS100. | Job | LS | $5,175.00 | $13,500.00 | $10,378.00 | |||
| 0008 (Option 6) | Provide and install engine generator set and enclosure as described in Section 26 32 14.00 10 and shown on sheet CS101. | Job | LS | $88,864.00 | $72,500.00 | $60,062.00 | |||
| 0009 (Option 7) | Entire work complete for the contractor to obtain LEED Silver Certification including all required coordination with USGBC for the SOF Operations and Storage Facility, PN 80234. See Note 5. | Job | LS | $10,000.00 | $6,500.00 | $26,967.00 | |||
| TOTAL AMOUNT (BASIC ITEMS 0001 AND 0002, and ALL Option Items) | $1,839,736.00 | $2,350,725.00 | $2,240,157.00 |
| ABSTRACT OF OFFERS - CONSTRUCTION | 1. SOLICITATION NUMBER | 2. DATE ISSUED | 3. DATE OPENED | Page 2 of 5 | |||||
| W9128F-12-B-0007 | 21-Mar-12 | 24-Apr-12 | |||||||
| 4. ISSUING OFFICE | I CERTIFY THAT I HAVE OPENED, READ AND | ||||||||
| US ARMY CORPS OF ENGINEERS | RECORDED ON THIS ABSTRACT ALL OFFERS | Justine Womboldt, Contract Specialist | |||||||
| CONTRACTING DIVISION (CENWO-CT) | RECEIVED IN RESPONSE TO THIS SOLICITATION | ||||||||
| 1616 Capitol Avenue | * | ||||||||
| OMAHA, NE 68102 | |||||||||
| 5. PROJECT TITLE | 9. OFFERS | ||||||||
| NO.3 | NO. 4 | NO. 5 | |||||||
| SOF Operations and Storage Facility | Ford Construction | DRG Construction | Aztec General Contractors | ||||||
| PN80234-FY12 | (Intentionally left blank) | ||||||||
| Fort Carson, CO | |||||||||
| B. BID SECURITY | B. BID SECURITY | B. BID SECURITY | |||||||
| 20% | 20% | 20% | |||||||
| 6. NUMBER OF AMENDMENTS ISSUED | C. AMENDMENTS ACKNOWLEDGED | C. AMENDMENTS ACKNOWLEDGED | C. AMENDMENTS ACKNOWLEDGED | ||||||
| 4 | 4 | 4 | |||||||
| 7A | 7B | 7C | D. | E. | F. | E. | F. | E. | F. |
| ITEM # | DESCRIPTION OF OFFER ITEM | EST. QTY | UNIT | UNIT PRICE | ESTIMATED AMOUNT | UNIT PRICE | ESTIMATED AMOUNT | UNIT PRICE | ESTIMATED AMOUNT |
| 0001 | Construction of the SOF Operations and Storage Facility, PN 80234; excluding Item Nos. 0002 and Option Items listed below. | Job | LS | $1,928,805.00 | $1,521,000.00 | ||||
| 0002 | Construction of SITEWORK AND UTILITIES, complete from the five-foot line of the SOF Operations and Storage Facility, PN 80234; excluding Option Items listed below. | Job | LS | $606,419.00 | $815,000.00 | ||||
| TOTAL AMOUNT - (Basic Items 0001 & 0002) | $2,535,224.00 | $2,336,000.00 | |||||||
| 0003 (Option 1) | Entire work complete to provide the mezzanine as shown on drawing sheet S-100. | Job | LS | $43,697.00 | $75,000.00 | ||||
| 0004 (Option 2) | Entire work complete to design and construct the antenna tower including the concrete base as shown in CS100 and A-300. | Job | LS | $97,582.00 | $35,000.00 | ||||
| 0005 (Option 3) | Entire work complete to provide bituminous paving in lieu of gravel paving as shown on drawing sheet CS100. | Job | LS | $59,278.00 | $165,000.00 | ||||
| 0006 (Option 4) | Entire work complete to provide the bio-retention pond and associated revised grading as shown on drawing sheets CG102, CG203, CG402, CG403, CG505, and CG506. | Job | LS | $69,543.00 | $55,000.00 | ||||
| 0007 (Option 5) | Entire work complete to provide 6” concrete hardstand as shown on drawing sheet CS100. | Job | LS | $9,023.00 | $10,000.00 | ||||
| 0008 (Option 6) | Provide and install engine generator set and enclosure as described in Section 26 32 14.00 10 and shown on sheet CS101. | Job | LS | $69,278.00 | $55,000.00 | ||||
| 0009 (Option 7) | Entire work complete for the contractor to obtain LEED Silver Certification including all required coordination with USGBC for the SOF Operations and Storage Facility, PN 80234. See Note 5. | Job | LS | $2,438.00 | $125,000.00 | ||||
| TOTAL AMOUNT (BASIC ITEMS 0001 AND 0002, and ALL Option Items) | $2,886,063.00 | $2,856,000.00 |
| ABSTRACT OF OFFERS - CONSTRUCTION | 1. SOLICITATION NUMBER | 2. DATE ISSUED | 3. DATE OPENED | Page 3 of 5 | |||||
| W9128F-12-B-0007 | 21-Mar-12 | 24-Apr-12 | |||||||
| 4. ISSUING OFFICE | I CERTIFY THAT I HAVE OPENED, READ AND | ||||||||
| US ARMY CORPS OF ENGINEERS | RECORDED ON THIS ABSTRACT ALL OFFERS | ||||||||
| CONTRACTING DIVISION (CENWO-CT) | RECEIVED IN RESPONSE TO THIS SOLICITATION | ||||||||
| 1616 Capitol Avenue | * | ||||||||
| OMAHA, NE 68102 | |||||||||
| 5. PROJECT TITLE | 9. OFFERS | ||||||||
| NO.6 | NO. 7 | NO. 8 | |||||||
| SOF Operations and Storage Facility | Bosco Constructors, Inc | Iron Mike Construction | Alvarado Construction, Inc | ||||||
| PN80234-FY12 | |||||||||
| Fort Carson, CO | |||||||||
| B. BID SECURITY | B. BID SECURITY | B. BID SECURITY | |||||||
| 20% | 20% | 20% | |||||||
| 6. NUMBER OF AMENDMENTS ISSUED | C. AMENDMENTS ACKNOWLEDGED | C. AMENDMENTS ACKNOWLEDGED | C. AMENDMENTS ACKNOWLEDGED | ||||||
| 3 | 4 | 4 | |||||||
| 7A | 7B | D. | E. | F. | E. | F. | E. | F. | |
| ITEM # | DESCRIPTION OF OFFER ITEM | EST. QTY | UNIT | UNIT PRICE | ESTIMATED AMOUNT | UNIT PRICE | ESTIMATED AMOUNT | UNIT PRICE | ESTIMATED AMOUNT |
| 0001 | Construction of the SOF Operations and Storage Facility, PN 80234; excluding Item Nos. 0002 and Option Items listed below. | Job | LS | $1,311,681.00 | $1,362,237.00 | $1,289,678.00 | |||
| 0002 | Construction of SITEWORK AND UTILITIES, complete from the five-foot line of the SOF Operations and Storage Facility, PN 80234; excluding Option Items listed below. | Job | LS | $595,776.00 | $662,920.00 | $696,581.00 | |||
| TOTAL AMOUNT - (Basic Items 0001 & 0002) | $1,907,457.00 | $2,025,157.00 | $1,986,259.00 | ||||||
| 0003 (Option 1) | Entire work complete to provide the mezzanine as shown on drawing sheet S-100. | Job | LS | $55,585.00 | $41,900.00 | $44,008.00 | |||
| 0004 (Option 2) | Entire work complete to design and construct the antenna tower including the concrete base as shown in CS100 and A-300. | Job | LS | $21,154.00 | $54,300.00 | $42,796.00 | |||
| 0005 (Option 3) | Entire work complete to provide bituminous paving in lieu of gravel paving as shown on drawing sheet CS100. | Job | LS | $62,532.00 | $45,900.00 | $82,838.00 | |||
| 0006 (Option 4) | Entire work complete to provide the bio-retention pond and associated revised grading as shown on drawing sheets CG102, CG203, CG402, CG403, CG505, and CG506. | Job | LS | $67,470.00 | $52,000.00 | $11,350.00 | |||
| 0007 (Option 5) | Entire work complete to provide 6” concrete hardstand as shown on drawing sheet CS100. | Job | LS | $6,577.00 | $19,000.00 | $17,270.00 | |||
| 0008 (Option 6) | Provide and install engine generator set and enclosure as described in Section 26 32 14.00 10 and shown on sheet CS101. | Job | LS | $48,063.00 | $72,400.00 | $64,829.00 | |||
| 0009 (Option 7) | Entire work complete for the contractor to obtain LEED Silver Certification including all required coordination with USGBC for the SOF Operations and Storage Facility, PN 80234. See Note 5. | Job | LS | $8,188.00 | $7,000.00 | $4,944.00 | |||
| TOTAL AMOUNT (BASIC ITEMS 0001 AND 0002, and ALL Option Items) | $2,177,026.00 | $2,317,657.00 | $2,254,294.00 |
| ABSTRACT OF OFFERS - CONSTRUCTION | 1. SOLICITATION NUMBER | 2. DATE ISSUED | 3. DATE OPENED | Page 4 of 5 | |||||
| W9128F-12-B-0007 | 21-Mar-12 | 24-Apr-12 | |||||||
| 4. ISSUING OFFICE | I CERTIFY THAT I HAVE OPENED, READ AND | ||||||||
| US ARMY CORPS OF ENGINEERS | RECORDED ON THIS ABSTRACT ALL OFFERS | ||||||||
| CONTRACTING DIVISION (CENWO-CT) | RECEIVED IN RESPONSE TO THIS SOLICITATION | ||||||||
| 1616 Capitol Avenue | * | ||||||||
| OMAHA, NE 68102 | |||||||||
| 5. PROJECT TITLE | 9. OFFERS | ||||||||
| NO. 9 | NO. 10 | NO.11 | |||||||
| SOF Operations and Storage Facility | White Construction | Facilities Contracting, Inc | Komada, LLC | ||||||
| PN80234-FY12 | Apparent Low | ||||||||
| Fort Carson, CO | |||||||||
| B. BID SECURITY | B. BID SECURITY | B. BID SECURITY | |||||||
| 20% | 20% | 20% | |||||||
| 6. NUMBER OF AMENDMENTS ISSUED | C. AMENDMENTS ACKNOWLEDGED | C. AMENDMENTS ACKNOWLEDGED | C. AMENDMENTS ACKNOWLEDGED | ||||||
| 4 | 4 | 4 | |||||||
| 7A | 7B | 7C | D. | E. | F. | E. | F. | E. | F. |
| ITEM # | DESCRIPTION OF OFFER ITEM | EST. QTY | UNIT | UNIT PRICE | ESTIMATED AMOUNT | UNIT PRICE | ESTIMATED AMOUNT | UNIT PRICE | ESTIMATED AMOUNT |
| 0001 | Construction of the SOF Operations and Storage Facility, PN 80234; excluding Item Nos. 0002 and Option Items listed below. | Job | LS | $1,299,000.00 | $1,227,000.00 | $1,448,000.00 | |||
| 0002 | Construction of SITEWORK AND UTILITIES, complete from the five-foot line of the SOF Operations and Storage Facility, PN 80234; excluding Option Items listed below. | Job | LS | $709,000.00 | $595,000.00 | $506,000.00 | |||
| TOTAL AMOUNT - (Basic Items 0001 & 0002) | $2,008,000.00 | $1,822,000.00 | $1,954,000.00 | ||||||
| 0003 (Option 1) | Entire work complete to provide the mezzanine as shown on drawing sheet S-100. | Job | LS | $43,820.00 | $38,250.00 | $45,000.00 | |||
| 0004 (Option 2) | Entire work complete to design and construct the antenna tower including the concrete base as shown in CS100 and A-300. | Job | LS | $35,000.00 | $33,550.00 | $73,000.00 | |||
| 0005 (Option 3) | Entire work complete to provide bituminous paving in lieu of gravel paving as shown on drawing sheet CS100. | Job | LS | $50,720.00 | $51,330.00 | $69,000.00 | |||
| 0006 (Option 4) | Entire work complete to provide the bio-retention pond and associated revised grading as shown on drawing sheets CG102, CG203, CG402, CG403, CG505, and CG506. | Job | LS | $27,000.00 | $55,650.00 | $44,000.00 | |||
| 0007 (Option 5) | Entire work complete to provide 6” concrete hardstand as shown on drawing sheet CS100. | Job | LS | $21,000.00 | $6,890.00 | $15,000.00 | |||
| 0008 (Option 6) | Provide and install engine generator set and enclosure as described in Section 26 32 14.00 10 and shown on sheet CS101. | Job | LS | $71,500.00 | $69,750.00 | $69,000.00 | |||
| 0009 (Option 7) | Entire work complete for the contractor to obtain LEED Silver Certification including all required coordination with USGBC for the SOF Operations and Storage Facility, PN 80234. See Note 5. | Job | LS | $16,666.00 | $4,685.00 | $45,000.00 | |||
| TOTAL AMOUNT (BASIC ITEMS 0001 AND 0002, and ALL Option Items) | $2,273,706.00 | $2,082,105.00 | $2,314,000.00 |
| ABSTRACT OF OFFERS - CONSTRUCTION | 1. SOLICITATION NUMBER | 2. DATE ISSUED | 3. DATE OPENED | Page 5 of 5 | ||||||
| W9128F-12-B-0007 | 21-Mar-12 | 24-Apr-12 | ||||||||
| 4. ISSUING OFFICE | I CERTIFY THAT I HAVE OPENED, READ AND | |||||||||
| US ARMY CORPS OF ENGINEERS | RECORDED ON THIS ABSTRACT ALL OFFERS | |||||||||
| CONTRACTING DIVISION (CENWO-CT) | RECEIVED IN RESPONSE TO THIS SOLICITATION | |||||||||
| 1616 Capitol Avenue | * | |||||||||
| OMAHA, NE 68102 | ||||||||||
| 5. PROJECT TITLE | 9. OFFERS | |||||||||
| NO. 12 | NO. 13 | NO. 14 | NO. 15 | |||||||
| SOF Operations and Storage Facility | GFC Contracting | Alutiiq | The Copestone Compnay | Growling Bear Co. | ||||||
| PN80234-FY12 | ||||||||||
| Fort Carson, CO | ||||||||||
| B. BID SECURITY | B. BID SECURITY | B. BID SECURITY | B. BID SECURITY | |||||||
| 20% | 20% | 20% | 20% | |||||||
| 6. NUMBER OF AMENDMENTS ISSUED | C. AMENDMENTS ACKNOWLEDGED | C. AMENDMENTS ACKNOWLEDGED | C. AMENDMENTS ACKNOWLEDGED | C. AMENDMENTS ACKNOWLEDGED | ||||||
| 4 | 4 | 4 | 4 | |||||||
| 7A | 7B | 7C | D. | E. | F. | E. | F. | E. | F. | F. |
| ITEM # | DESCRIPTION OF OFFER ITEM | EST. QTY | UNIT | UNIT PRICE | ESTIMATED AMOUNT | UNIT PRICE | ESTIMATED AMOUNT | Estimated Amount | ESTIMATED AMOUNT | ESTIMATED AMOUNT |
| 0001 | Construction of the SOF Operations and Storage Facility, PN 80234; excluding Item Nos. 0002 and Option Items listed below. | Job | LS | $1,430,000.00 | $1,181,193.20 | $1,236,720.00 | $ | $1,349,711.00 | ||
| 0002 | Construction of SITEWORK AND UTILITIES, complete from the five-foot line of the SOF Operations and Storage Facility, PN 80234; excluding Option Items listed below. | Job | LS | $561,000.00 | $783,881.80 | $596,460.00 | $ | $633,331.00 | ||
| TOTAL AMOUNT - (Basic Items 0001 & 0002) | $1,991,000.00 | $1,965,075.00 | $1,833,180.00 | $1,983,042.00 | ||||||
| 0003 (Option 1) | Entire work complete to provide the mezzanine as shown on drawing sheet S-100. | Job | LS | $18,000.00 | $33,825.00 | $68,080.00 | $ | $57,962.00 | ||
| 0004 (Option 2) | Entire work complete to design and construct the antenna tower including the concrete base as shown in CS100 and A-300. | Job | LS | $58,000.00 | $47,353.00 | $40,410.00 | $ | $44,397.00 | ||
| 0005 (Option 3) | Entire work complete to provide bituminous paving in lieu of gravel paving as shown on drawing sheet CS100. | Job | LS | $65,000.00 | $14,235.00 | $72,660.00 | $ | $138,216.00 | ||
| 0006 (Option 4) | Entire work complete to provide the bio-retention pond and associated revised grading as shown on drawing sheets CG102, CG203, CG402, CG403, CG505, and CG506. | Job | LS | $43,000.00 | $19,276.00 | $43,200.00 | $50,592.00 | |||
| 0007 (Option 5) | Entire work complete to provide 6” concrete hardstand as shown on drawing sheet CS100. | Job | LS | $16,000.00 | $15,249.00 | $17,140.00 | $23,669.00 | |||
| 0008 (Option 6) | Provide and install engine generator set and enclosure as described in Section 26 32 14.00 10 and shown on sheet CS101. | Job | LS | $67,000.00 | $69,241.00 | $72,180.00 | $70,743.00 | |||
| 0009 (Option 7) | Entire work complete for the contractor to obtain LEED Silver Certification including all required coordination with USGBC for the SOF Operations and Storage Facility, PN 80234. See Note 5. | Job | LS | $70,000.00 | $3,568.00 | $14,660.00 | $47,743.00 | |||
| TOTAL AMOUNT (BASIC ITEMS 0001 AND 0002, and ALL Option Items) | $2,328,000.00 | $2,167,822.00 | $2,161,510.00 | $ | $2,416,364.00 |
| NO. 16 | ||||
| Bridagier Construction Company | ||||
| B. BID SECURITY | ||||
| 20% | ||||
| C. AMENDMENTS ACKNOWLEDGED | ||||
| 4 | ||||
| 7A | 7B | |||
| ITEM # | DESCRIPTION OF OFFER ITEM | Estimated Amount | ||
| 0001 | Construction of the SOF Operations and Storage Facility, PN 80234; excluding Item Nos. 0002 and Option Items listed below. | Job | LS | $1,388,265.00 |
| 0002 | Construction of SITEWORK AND UTILITIES, complete from the five-foot line of the SOF Operations and Storage Facility, PN 80234; excluding Option Items listed below. | Job | LS | $697,348.00 |
| TOTAL AMOUNT - (Basic Items 0001 & 0002) | $2,085,613.00 | |||
| 0003 (Option 1) | Entire work complete to provide the mezzanine as shown on drawing sheet S-100. | Job | LS | $69,136.00 |
| 0004 (Option 2) | Entire work complete to design and construct the antenna tower including the concrete base as shown in CS100 and A-300. | Job | LS | $39,210.00 |
| 0005 (Option 3) | Entire work complete to provide bituminous paving in lieu of gravel paving as shown on drawing sheet CS100. | Job | LS | $41,714.00 |
| 0006 (Option 4) | Entire work complete to provide the bio-retention pond and associated revised grading as shown on drawing sheets CG102, CG203, CG402, CG403, CG505, and CG506. | Job | LS | $51,307.00 |
| 0007 (Option 5) | Entire work complete to provide 6” concrete hardstand as shown on drawing sheet CS100. | Job | LS | $5,781.00 |
| 0008 (Option 6) | Provide and install engine generator set and enclosure as described in Section 26 32 14.00 10 and shown on sheet CS101. | Job | LS | $65,667.00 |
| 0009 (Option 7) | Entire work complete for the contractor to obtain LEED Silver Certification including all required coordination with USGBC for the SOF Operations and Storage Facility, PN 80234. See Note 5. | Job | LS | $5,753.00 |
| TOTAL AMOUNT (BASIC ITEMS 0001 AND 0002, and ALL Option Items) | $2,364,181.00 |