A.07.24_Amendment_0003_17R6031.pdf
PDF 1 MB Posted
- Attached to
- Tricare Prime Clinic - Suffolk
- Solicitation number
- W9127S-17-R-6031
About this file
Amendment 0003
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Revised_Suffolk_Bid_Schedule.xlsx | XLSX spreadsheet | |
| A.07.24_Amendment_0002_17R6031.pdf | ||
| A.07.24_Amendment_0001_17R6031.pdf | ||
| A.01.30_Suffolk_Bid_Schedule.xlsx | XLSX spreadsheet | |
| A.07.23_Final_Solicitation_17R6031.pdf | ||
| A.01.30_Attachment_D_Master_Move_Schedule_Example.xls | XLS spreadsheet | |
| A.01.30_Attachment_H_Suffolk_Drawing-18_May2017.pdf | ||
| A.01.30_Attachment_B_Weekly_Report_Format.xls | XLS spreadsheet | |
| A.01.30_Attachment_G_Cut_Sheets.pdf | ||
| A.01.30_Attachment_I_New_FFE.pdf | ||
| A.01.30_Attachment_F_Project_Delivery_Team.xlsx | XLSX spreadsheet | |
| A.01.30_Attachment_C_Change_Tracker.xlsx | XLSX spreadsheet | |
| A.01.30_Attachment_A_Submittal_Requirements.pdf |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to provide the projnet inquiriies, site visit minutes, site visit attendance sheet and site visit slides. The submission requirements for the Non Prince Proposal have been revised. The bid schedule has also been revised.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 8
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 21-Aug-2017
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9127S-17-R-6031
X 9B. DATED (SEE ITEM 11)
11-Jul-2017
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
21-Aug-2017
CODE
CONTRACTING DIVISION
USACE, LITTLE ROCK (W9127S)
700 W. CAPITOL AVE, RM 7315
LITTLE ROCK AR 72201-3225
W9127S 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
UNCLASSIFIED\\FOR OFFICIAL USE ONLY
Bid Inquiry Contracting Officers Report Closed Inquiries
Project: FY17 Tricare Prime Clinic Suffolk Review: Tricare Prime Clinic Suffolk Bidder Inquiry (00001) (sorted by CommentID ) Displaying 61 inquiries.
Id Discipline Sheet Detail Spec 7067699 General Resume Requirements Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Would years of experience in the industry and on comparable projects be accepted as an alternative to the requirement for the PM to have a 4-year degree?
By: Tiffany Masura; Strategic Initial Outfitting Transition Solutions (SIOTS) - Charleston, SC; (847-637-0034). On: Jul 17 2017.
Forward request by email.
1-0 Evaluation Concurred. No. By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 01 2017 1-1 Government Response. No. By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 01 2017
Current Request Status: Request Closed Information for this report is procurement sensitive.
7067702 IO Medical Equipment, non OP Build Out Access Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Will there be early access allowed to start build-out of the Radiology Suite prior to BOD?
By: Tiffany Masura; Strategic Initial Outfitting Transition Solutions (SIOTS) - Charleston, SC; (847-637-0034). On: Jul 17 2017.
Forward request by email.
1-0 Evaluation Concurred. Yes By: TJ Lee; SWL Programs and Project Management Division; (501-340-1030) On: Jul 27 2017 1-1 Government Response. Yes By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 01 2017
Current Request Status: Request Closed Information for this report is procurement sensitive.
7067703 General Resume Requirements Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Required resumes listed on page 9 include the PM, Medical Equipment Planner, Interior Designer, and Equipment Installers. However, on page 53 the solicitation states that personnel "shall" also include a Low Voltage Consultant and QC Manager. Please confirm it is not the Government's expectation to see resumes for all personnel, but only those listed on page 9.
By: Tiffany Masura; Strategic Initial Outfitting Transition Solutions (SIOTS) - Charleston, SC; (847-637-0034). On: Jul 17 2017.
Forward request by email.
1-0 Evaluation Concurred. Yes. It is the Government's expectation to only see resumes listed under the submission requirements for Sub Factor 1.2 - Personnel By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 01 2017
1-1 Government Response. Yes. It is the Government's expectation to only see resumes listed under the submission requirements for Sub Factor 1.2 - Personnel By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 01 2017 Current Request Status: Request Closed
Information for this report is procurement sensitive.
7067704 General Resume Requirements Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please clarify if the Equipment/Product Installer resume is to be for the medical equipment installer specifically, the furniture installer, or both.
By: Tiffany Masura; Strategic Initial Outfitting Transition Solutions (SIOTS) - Charleston, SC; (847-637-0034). On: Jul 17 2017.
Forward request by email.
1-0 Evaluation Concurred. Please submit one resume for your lead equipment installer By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 01 2017
1-1 Government Response. Please submit one resume for your lead equipment installer By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 01 2017 Current Request Status: Request Closed
Information for this report is procurement sensitive.
7067705 Contracting Bid Schedule Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please provide the bid schedule, it was not included.
By: Tiffany Masura; Strategic Initial Outfitting Transition Solutions (SIOTS) - Charleston, SC; (847-637-0034). On: Jul 17 2017.
Forward request by email.
1-0 Evaluation Concurred. The bid schedule is included as an attachment to the solicitation on FBO. By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 01 2017
1-1 Government Response. The bid schedule is included as an attachment to the solicitation on FBO. By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 01 2017
Page 1 of 13ProjNet: Logged In User
8/21/2017https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicAdminClosedR...
Current Request Status: Request Closed Information for this report is procurement sensitive.
7067708 IO
Transition/Phasing/Security/Warehousing/DRMO Transition/Move Scope
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please clarify the extent of physical move scope. On page 45, the Introduction paragraph states: "While there is no physical transition of actual items, the Offeror shall use the IO-P portion to cover any costs associated with planning for the IO-C." On page 51, J5 and J6 reference move sequencing and move plans. It is unclear what exactly is moving, if anything, and if physical moves are required such as for supplies, records, personnel etc., is the IO Contractor planning the move but not executing it?
By: Tiffany Masura; Strategic Initial Outfitting Transition Solutions (SIOTS) - Charleston, SC; (847-637-0034). On: Jul 17 2017.
Forward request by email.
1-0 Evaluation Concurred. There is no items on Suffolk that are actually physically moving. The IO-P in Suffolk will be where the Contractor captures any cost association with planning the commodity purchase. By: TJ Lee; SWL Programs and Project Management Division; (501-340-1030) On: Jul 24 2017
1-1 Government Response. There is no items on Suffolk that are actually physically moving. The IO-P in Suffolk will be where the Contractor captures any cost association with planning the commodity purchase. By: Marcus Mitchell; SWL Contracting Division;
(501-340-1253) On: Aug 01 2017 Current Request Status: Request Closed
Information for this report is procurement sensitive.
7069692 General RFP Page 9 of 63 Factor 1: Sub-Factor 1.2 Personnel
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Will the Government please clarify how many resumes are expected for the "equipment installers" key personnel labor category?
By: Kelli McNamara; Martek Global Services, Inc.; (3014665255). On: Jul 18 2017. Forward request by email.
1-0 Evaluation Concurred. One resume should be submitted for your lead installer. By: Marcus Mitchell; SWL Contracting Division;
(501-340-1253) On: Aug 01 2017 1-1 Government Response. One resume should be submitted for your lead installer. By: Marcus Mitchell; SWL Contracting Division;
(501-340-1253) On: Aug 01 2017 Current Request Status: Request Closed
Information for this report is procurement sensitive.
7070424 General A6030-Vending Machine Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please confirm that the A6030-Vending Machine is to be purchased by the IO Contractor and not the Government.
By: Dyana Azzolino; Cazador; ((719) 387-7450). On: Jul 19 2017. Forward request by email.
1-0 Evaluation Concurred. Vending Machines are provide by separate service contract and are shown for coordination and transition purposes. By: TJ Lee; SWL Programs and Project Management Division; (501-340-1030) On: Jul 27 2017 1-1 Government Response. Vending Machines are provide by separate service contract and are shown for coordination and transition purposes. By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 01 2017 Current Request Status: Request Closed
Information for this report is procurement sensitive.
7073200 IO CID: Furniture/Furnishings U0117 Workstation Straight Freestanding
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
The cut sheet shows 4 different workstations - refer to the project contents list for details on size, overheads, and pedestal requirements. The project contents list does not show any details on size, overhead, and pedestal. Please clarify which workstation for this JSN.
By: Stephanie Hadiwibawa; Omega Group - San Diego, CA; (8585692420). On: Jul 20 2017. Forward request by email.
1-0 Evaluation Concurred. Assume 60"width 24" deep work surface with overhead storage and a Box/Box/File drawer on one side.
By: TJ Lee; SWL Programs and Project Management Division; (501-340-1030) On: Jul 27 2017 1-1 Government Response. Assume 60"width 24" deep work surface with overhead storage and a Box/Box/File drawer on one side.
By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 01 2017 Current Request Status: Request Closed
Information for this report is procurement sensitive.
7073201 IO Medical Equipment, non OP L1115 and L2600 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Both JSN L1115 and L2600 have the same cut sheets, please confirm that it will be for the same equipment.
By: Stephanie Hadiwibawa; Omega Group - San Diego, CA; (8585692420). On: Jul 20 2017. Forward request by email.
1-0 Evaluation Concurred. Cut sheets provided are by DHA through SEPS and are for general reference only. There is not a specific cut sheet at this time. By: TJ Lee; SWL Programs and Project Management Division; (501-340-1030) On: Jul 27 2017 1-1 Government Response. Cut sheets provided are by DHA through SEPS and are for general reference only. There is not a specific cut sheet at this time. By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 01 2017
Page 2 of 13ProjNet: Logged In User
7073207 IO CID: Furniture/Furnishings U0075 Workstation L-Shaped Freestanding
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
The cut sheet shows 2 different workstations - refer to the project contents list for details on size, handing, overhead, and pedestal requirements. The project contents list does not show any details. Please clarify which workstations for this JSN.
By: Stephanie Hadiwibawa; Omega Group - San Diego, CA; (8585692420). On: Jul 20 2017. Forward request by email.
1-0 Evaluation Concurred. Assume the largest layout shown for all. By: TJ Lee; SWL Programs and Project Management Division;
(501-340-1030) On: Jul 27 2017 1-1 Government Response. Assume the largest layout shown for all. By: Marcus Mitchell; SWL Contracting Division; (501-340-1253)
On: Aug 01 2017 Current Request Status: Request Closed
Information for this report is procurement sensitive.
7073913 Master Plan Schedule Schedule Schedule Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Based on the brief period between award and BOD it would be impossible to complete a 3 submittal plus corrected final design process and meet the proposed OFB. Will you allow us to propose an accelerated design/submittal process? Or would you prefer we continue with the submittal/design timeline outlined in the RFP showing when we would be able to complete all work, knowing OFB would slip to the right?
By: Dudley Strawn; Strategic Initial Outfitting Transition Solutions (SIOTS) - Charleston, SC; (9012885041). On: Jul 21 2017. Forward request by email.
1-0 Evaluation Concurred. Accelerated time lines will be entertained after award By: TJ Lee; SWL Programs and Project Management Division; (501-340-1030) On: Jul 27 2017
1-1 Government Response. Accelerated time lines will be entertained after award By: Marcus Mitchell; SWL Contracting Division;
(501-340-1253) On: Aug 01 2017 Current Request Status: Request Closed
Information for this report is procurement sensitive.
7074446 IO CID: Furniture/Furnishings E0665 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
E0665 Pharmacy bulk storage low volume, the cut sheet only shows "Bulk Storage" being highlighted with total quantity of 3 from bid sheet.
Does it mean 3 cabinets only or the P04 Bulk Storage configuration or P08 Bulk Storage configuration? Please clarify.
By: Stephanie Hadiwibawa; Omega Group - San Diego, CA; (8585692420). On: Jul 21 2017. Forward request by email.
1-0 Evaluation Concurred. Bulk storage in the pharmacy is just full height adjustable shelf units to be located in the center of the space. Quantity should be the amount required to adequately provided the maximum amount of storage the space will hold. By: TJ Lee; SWL Programs and Project Management Division; (501-340-1030) On: Jul 27 2017
1-1 Government Response. Bulk storage in the pharmacy is just full height adjustable shelf units to be located in the center of the space. Quantity should be the amount required to adequately provided the maximum amount of storage the space will hold. By:
Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 01 2017 Current Request Status: Request Closed
Information for this report is procurement sensitive.
7075335 IO Medical Equipment, non OP U5700 and X5700 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Is U5700 Digital Radiographic Unit with Wall Buck and Turnkey Installation and X5700 Radiographic Unit, 65 kW, Non-Tilt Table the same?
U5700 is found on the equipment list while X5700 is found under Radiology.
Please clarify.
By: Stephanie Hadiwibawa; Omega Group - San Diego, CA; (8585692420). On: Jul 21 2017. Forward request by email.
1-0 Evaluation Concurred. U5700 should be the information used. By: TJ Lee; SWL Programs and Project Management Division;
(501-340-1030) On: Jul 27 2017 1-1 Government Response. U5700 should be the information used. By: Marcus Mitchell; SWL Contracting Division; (501-340-1253)
On: Aug 01 2017 Current Request Status: Request Closed
Information for this report is procurement sensitive.
7075336 IO SID: Signage/Wayfinding/Finishes U0001 Way-finding/Signage Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Do we have to use Innerface for signage? Will substitute vendor be acceptable?
By: Stephanie Hadiwibawa; Omega Group - San Diego, CA; (8585692420). On: Jul 21 2017. Forward request by email.
1-0 Evaluation Concurred. Another vendor will be entertained as long as the product completely matches in style and construction and is greater than or equal to the specs provided. NMCP is currently set up to update signage based on the Innerface design. By: TJ Lee; SWL Programs and Project Management Division; (501-340-1030) On: Jul 27 2017
1-1
Page 3 of 13ProjNet: Logged In User
Government Response. Another vendor will be entertained as long as the product completely matches in style and construction and is greater than or equal to the specs provided. NMCP is currently set up to update signage based on the Innerface design. By:
Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 01 2017 Current Request Status: Request Closed
Information for this report is procurement sensitive.
7081584 Other VI. Initial Outfitting Personnel
Qualifications B. Medical Space/Equipment Planner pg 55 of
63 SOW
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Is the requirement to have the Medical Space/Equipment Planner as a direct employee of the Prime editable to not be required as the Prime's direct employee?
By: Randy Ramcharan; Indatatech; (8324522795). On: Jul 26 2017. Forward request by email.
1-0 Evaluation Concurred. No. By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 01 2017 1-1 Government Response. No. By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 01 2017
Current Request Status: Request Closed Information for this report is procurement sensitive.
7081593 Other (i) Sub Factor 1.1 - Experience pg 8 of
63 SOW
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Does the offeror's team have to have previous experience managing construction services similar to what is outlined in the PWS in order to be considered technically acceptable?
By: Randy Ramcharan; Indatatech; (8324522795). On: Jul 26 2017. Forward request by email.
1-0 Evaluation Concurred. Please refer to the submission requirements and evaluation criteria for Sub Factor 1.1 - Experience as it outlines the minimum acceptability standards. By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 01 2017 1-1 Government Response. Please refer to the submission requirements and evaluation criteria for Sub Factor 1.1 - Experience as it outlines the minimum acceptability standards. By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 01 2017 Current Request Status: Request Closed
Information for this report is procurement sensitive.
7081597 IO Casegoods / Casework II. Radiology Turnkey Overview pg 46 of
63 SOW
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please confirm casework is not required in this space.
By: Randy Ramcharan; Indatatech; (8324522795). On: Jul 26 2017. Forward request by email.
1-0 Evaluation Concurred. 5' cabinet with solid surface counter, integral sink and upper cabinets are required. By: TJ Lee; SWL
Programs and Project Management Division; (501-340-1030) On: Aug 16 2017 1-1 Government Response. 5' cabinet with solid surface counter, integral sink and upper cabinets are required. By: Marcus
Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 16 2017 Current Request Status: Request Closed
Information for this report is procurement sensitive.
7081598 Contracting II. Radiology Turnkey Overview pg 46 of
63 SOW
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please confirm the General contractor will provide the overhead steel supports in the X-Ray Room for the ceiling mounted radiology equipment.
By: Randy Ramcharan; Indatatech; (8324522795). On: Jul 26 2017. Forward request by email.
1-0 Evaluation Concurred. Any overhead steel supports shall be included in the X-ray Room turnkey build-out under this contract.
By: TJ Lee; SWL Programs and Project Management Division; (501-340-1030) On: Aug 16 2017 1-1 Government Response. Any overhead steel supports shall be included in the X-ray Room turnkey build-out under this contract. By:
Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 16 2017 Current Request Status: Request Closed
Information for this report is procurement sensitive.
7081601 Contracting II. Radiology Turnkey Overview pg 46 of
63 SOW
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please provide the door, frame and hardware schedule for the door openings the IOT contractor is required to provide.
By: Randy Ramcharan; Indatatech; (8324522795). On: Jul 26 2017. Forward request by email.
1-0 Evaluation Concurred. All design aspects of the X-ray room build out shall be included in proposal of the space under this contract. By: TJ Lee; SWL Programs and Project Management Division; (501-340-1030) On: Aug 16 2017 1-1 Government Response. All design aspects of the X-ray room build out shall be included in proposal of the space under this contract. By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 16 2017 Current Request Status: Request Closed
Page 4 of 13ProjNet: Logged In User
7081607 Contracting II. Radiology Turnkey Overview pg 46 of
63 SOW
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please advise if the construction/renovation work needs to occur prior to BOD to allow the General Contractor the opportunity to do final MEP drops, testing and balancing & commissioning of the GC's mechanical, fire protection, electrical systems.
By: Randy Ramcharan; Indatatech; (8324522795). On: Jul 26 2017. Forward request by email.
1-0 Evaluation Concurred. The space can be built out concurrently with the GC's construction once the studs have been installed and the space can be secured by this contract separate from the GC's remaining areas. By: TJ Lee; SWL Programs and Project Management Division; (501-340-1030) On: Aug 16 2017
1-1 Government Response. The space can be built out concurrently with the GC's construction once the studs have been installed and the space can be secured by this contract separate from the GC's remaining areas. By: Marcus Mitchell; SWL Contracting Division;
(501-340-1253) On: Aug 16 2017 Current Request Status: Request Closed
Information for this report is procurement sensitive.
7081617 Contracting II. Radiology Turnkey Overview pg 46 of
63 SOW
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please provide general specifications for the architectural work in this space. Ceilings, floors, etc.
By: Randy Ramcharan; Indatatech; (8324522795). On: Jul 26 2017. Forward request by email.
1-0 Evaluation Concurred. The space shall have luxury vinyl floor, vinyl wall base, painted GWB and ACT to match the adjacent spaces. By: TJ Lee; SWL Programs and Project Management Division; (501-340-1030) On: Aug 16 2017 1-1 Government Response. The space shall have luxury vinyl floor, vinyl wall base, painted GWB and ACT to match the adjacent spaces. By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 16 2017 Current Request Status: Request Closed
Information for this report is procurement sensitive.
7081628 Other II. Radiology Turnkey Overview pg 46 of
63 SOW
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Is the incidental light construction spend included in the Small Business 51% Self-Performance Percentage requirement?
By: Randy Ramcharan; Indatatech; (8324522795). On: Jul 26 2017. Forward request by email.
1-0 Evaluation Concurred. Yes By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 16 2017 1-1 Government Response. Yes By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 16 2017
Current Request Status: Request Closed Information for this report is procurement sensitive.
7081634 Other II. Radiology Turnkey Overview pg 46 of
63 SOW
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Will the Navy provide the physicist testing for the radiology equipment, or will the IO Contractor be responsible for this requirement? If the IO Contractor is responsible, are they able to use a Navy physicist to perform the testing of the radiology equipment?
By: Randy Ramcharan; Indatatech; (8324522795). On: Jul 26 2017. Forward request by email.
1-0 Evaluation Concurred. Navy Physicist will be providing all lead requirements and testing. This will be coordinated with the IO
Contractor and NMCP project manager. By: TJ Lee; SWL Programs and Project Management Division; (501-340-1030) On: Aug 16
1-1 Government Response. Navy Physicist will be providing all lead requirements and testing. This will be coordinated with the IO Contractor and NMCP project manager. By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 16 2017 Current Request Status: Request Closed
Information for this report is procurement sensitive.
7081785 Contracting II. Radiology Turnkey Overview pg 43-44 of 60 SOW
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Is this project subject to any union labor requirements or is this project a non-union territory and does government recognize that? Answer affects pricing. Is IO Contractor required to utilize union construction workers for the Radiology turnkey scope of work identified under Item II under the statement of work? Will the General Contractor be utilizing a union workforce?
By: Randy Ramcharan; Indatatech; (8324522795). On: Jul 26 2017. Forward request by email.
1-0 Evaluation Concurred. This requirement is not subject to any union labor requirements or non union territory. The IO Contractor is not required to utilize union construction workers. The Corps doesn't have any knowledge of whether the GC is utilizing a union workforce. By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 16 2017
1-1 Government Response. This requirement is not subject to any union labor requirements or non union territory. The IO Contractor is not required to utilize union construction workers. The Corps doesn't have any knowledge of whether the GC is utilizing a union workforce. By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 16 2017
Page 5 of 13ProjNet: Logged In User
7081786 Contracting II. Radiology Turnkey Overview pg 43-44 of 60 SOW
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please confirm the General Contractor is responsible for the following scopes of work related to the construction of the radiology rooms (X-Ray)
a. Mechanical and fire protection rough-in, final drops/connections with associated trim and all commissioning, testing & balancing of these systems. This includes any work within the walls or in the ceiling.
By: Randy Ramcharan; Indatatech; (8324522795). On: Jul 26 2017. Forward request by email.
1-0 Evaluation Concurred. Yes By: TJ Lee; SWL Programs and Project Management Division; (501-340-1030) On: Aug 16 2017 1-1 Government Response. Yes. That is correct. By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 16 2017
Current Request Status: Request Closed Information for this report is procurement sensitive.
7081790 General Attch G: Cut Sheets pg 528 of
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
The provided cut-sheet for the radiology equipment states the JSN as U5700 but the Bid Schedule (Radiology worksheet) states the JSN as X5700. We would like verification of the correct JSN.
By: Randy Ramcharan; Indatatech; (8324522795). On: Jul 26 2017. Forward request by email.
1-0 Evaluation Concurred. JSN U5700 is the correct JSN By: TJ Lee; SWL Programs and Project Management Division; (501-340-
1030) On: Aug 16 2017 1-1 Government Response. JSN U5700 is the correct JSN By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 16
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7083797 Other Amendment 1: Specific Instructions for the Price Proposal pg 4 of
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please verify if a hard copy of the Pricing Schedule is to be included in the hard copies of the Price Proposal or if an excel file on the CD ROMs will suffice.
By: Randy Ramcharan; Indatatech; (8324522795). On: Jul 27 2017. Forward request by email.
1-0 Evaluation Concurred. An amendment will be forthcoming that will require the submission of 1 hard copy & 2 CD ROM copies of the price proposal and 1 hard copy and 2 CD ROM copies of the Non-Price Proposal. By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 16 2017
1-1 Government Response. An amendment will be forthcoming that will require the submission of 1 hard copy & 2 CD ROM copies of the price proposal and 1 hard copy and 2 CD ROM copies of the Non-Price Proposal. By: Marcus Mitchell; SWL Contracting Division;
(501-340-1253) On: Aug 16 2017 Current Request Status: Request Closed
Information for this report is procurement sensitive.
7083799 Other Amendment 1: TAB 2: Factor 2.1, Past Performance pg 8 of
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Verify what information is required to be submitted under Sub Factor 2.1, Past Performance of the Non-Price Factor Proposal.
By: Randy Ramcharan; Indatatech; (8324522795). On: Jul 27 2017. Forward request by email.
1-0 Evaluation Concurred. No submission is required under this Sub Factor. By: Marcus Mitchell; SWL Contracting Division; (501-
340-1253) On: Aug 16 2017 1-1 Government Response. No submission is required under this Sub Factor. By: Marcus Mitchell; SWL Contracting Division; (501-
340-1253) On: Aug 16 2017 Current Request Status: Request Closed
Information for this report is procurement sensitive.
7083805 Other Amendment 1: Specific Instructions for the Non-Price Factor Proposal pg 5 of
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please verify if and where we include a technical write up in the Non-Price Factor Proposal. Is this included under Sub Factor 2.1, Past Performance? Or is a technical write up not required for this solicitation?
By: Randy Ramcharan; Indatatech; (8324522795). On: Jul 27 2017. Forward request by email.
1-0 Evaluation Concurred. A technical write up is not required for this solicitation. By: Marcus Mitchell; SWL Contracting Division;
(501-340-1253) On: Aug 16 2017 1-1 Government Response. A technical write up is not required for this solicitation. By: Marcus Mitchell; SWL Contracting Division;
(501-340-1253) On: Aug 16 2017
Page 6 of 13ProjNet: Logged In User
7083994 Interior Design A.07.23 Page 53 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Regarding Interior Designer Qualifications, page 53 of the A.07.23_Final_Solicitation_17R6032, the requirement in C.h. calls for an AAHID certification. Is an NCIDQ certification along with equivalent years of relevant healthcare experience an acceptable substitute?
By: Dudley Strawn; Strategic Initial Outfitting Transition Solutions (SIOTS) - Charleston, SC; (9012885041). On: Jul 27 2017. Forward request by email.
1-0 Evaluation Concurred. AAHID is a separated certification from NCIDQ. AAHID is the American Academy of Healthcare Interior Designer and is a certification specific to healthcare. By: TJ Lee; SWL Programs and Project Management Division; (501-340- 1030) On: Aug 16 2017
1-1 Government Response. AAHID is a separated certification from NCIDQ. AAHID is the American Academy of Healthcare Interior Designer and is a certification specific to healthcare. By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 16 Current Request Status: Request Closed
Information for this report is procurement sensitive.
7084065 IO
Transition/Phasing/Security/Warehousing/DRMO 1 1
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please confirm when IO construction can start the build out of the Radiology suite. At construction completion date 1 March, 2018? or does the IO build out need to be completed by 1 March?
By: Ken Mulligan; Cazador; (719-387-7450 ext 147). On: Jul 27 2017. Forward request by email.
1-0 Evaluation Concurred. The space can be built out concurrently with the GC's construction once the studs have been installed and the space can be secured by this contract separate from the GC's remaining areas. The space needs to be complete and ready for use once the facility has been outfitted. By: TJ Lee; SWL Programs and Project Management Division; (501-340-1030) On: Aug 16
1-1 Government Response. The space can be built out concurrently with the GC's construction once the studs have been installed and the space can be secured by this contract separate from the GC's remaining areas. The space needs to be complete and ready for use once the facility has been outfitted. By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 16 2017 Current Request Status: Request Closed
Information for this report is procurement sensitive.
7084119 IO
Transition/Phasing/Security/Warehousing/DRMO 1 1
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please confirm if there will be any transition of reuse items, personnel or contents needed by the IO contractor.
On Page 45 it states "While there is no physical transition of actual items,..." it then states on page 51, section J - "Transition Planning includes developing a plan for reused commodities..."
By: Ken Mulligan; Cazador; (719-387-7450 ext 147). On: Jul 27 2017. Forward request by email.
1-0 Evaluation Concurred. Suffolk has no reuse By: TJ Lee; SWL Programs and Project Management Division; (501-340-1030) On:
Aug 14 2017 1-1 Government Response. Suffolk has no reuse By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 16 2017
Current Request Status: Request Closed Information for this report is procurement sensitive.
7084308 Contracting II. Radiology Turnkey Overview pg 43-44 of 60 SOW
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
What is the height for the drywall and the lead shielding of the radiology suite? At what height does the ceiling start?
By: Randy Ramcharan; Indatatech; (8324522795). On: Jul 27 2017. Forward request by email.
1-0 Evaluation Concurred. Ceiling heights are 9'-0" drywall shall extend 6" about ceiling. By: TJ Lee; SWL Programs and Project
Management Division; (501-340-1030) On: Aug 16 2017 1-1 Government Response. Ceiling heights are 9'-0" drywall shall extend 6" about ceiling. By: Marcus Mitchell; SWL Contracting
Division; (501-340-1253) On: Aug 16 2017 Current Request Status: Request Closed
Information for this report is procurement sensitive.
7084309 Contracting II. Radiology Turnkey Overview pg 43-44 of 60 SOW
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
The RFP lists the room with a 480v/3 phase power line to the room with 6 ft. pigtail, however the cutsheets list the voltage to the room at 220v. Please advise.
By: Randy Ramcharan; Indatatech; (8324522795). On: Jul 27 2017. Forward request by email.
Page 7 of 13ProjNet: Logged In User
1-0 Evaluation Concurred. Since the equipment is being provided by the IO contractor, I do not have the exact requirements for the equipment since it is being purchased through this contract. Please coordinate with the information provided by the equipment vendor. By: TJ Lee; SWL Programs and Project Management Division; (501-340-1030) On: Aug 16 2017
1-1 Government Response. Since the equipment is being provided by the IO contractor, I do not have the exact requirements for the equipment since it is being purchased through this contract. Please coordinate with the information provided by the equipment vendor.
By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 16 2017 Current Request Status: Request Closed
Information for this report is procurement sensitive.
7085481 Other Factor 2 Past Performance Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Clarifying that there is not a submission requirement for Factor 2 Past Performance.
By: Molly Chasteen; Cazador; (913-433-3375). On: Jul 28 2017. Forward request by email.
1-0 Evaluation Concurred. Yes that is correct. By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 16 2017 1-1 Government Response. Yes that is correct. By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 16 2017
Current Request Status: Request Closed Information for this report is procurement sensitive.
7085515 IO Medical Equipment, non OP A.01.30_Suffolk_Bid Schedule Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please verify if we are to price the U5700 in both the equipment list tab and on the Radiology tab of the Bid Schedule. If so, we are including these costs in both CLIN 0002 and CLIN 0004. Please advise.
By: Randy Ramcharan; Indatatech; (8324522795). On: Jul 28 2017. Forward request by email.
1-0 Evaluation Concurred. Radiology should only be priced in the Radiology Tab By: TJ Lee; SWL Programs and Project
Management Division; (501-340-1030) On: Aug 14 2017 1-1 Government Response. Radiology should only be priced in the Radiology Tab By: Marcus Mitchell; SWL Contracting Division;
(501-340-1253) On: Aug 16 2017 Current Request Status: Request Closed
Information for this report is procurement sensitive.
7086094 Other Amendment 1: Specific Instructions for the Non-Price Factor Proposal
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please verify that a technical write up is NOT required in this proposal response. Previous proposals out of Little Rock have required technical write ups; offerors were evaluated on technical approach, past performance and pricing.
By: Randy Ramcharan; Indatatech; (8324522795). On: Jul 28 2017. Forward request by email.
1-0 Evaluation Concurred. A technical write up is not required for this solicitation. By: Marcus Mitchell; SWL Contracting Division;
(501-340-1253) On: Aug 16 2017 1-1 Government Response. A technical write up is not required for this solicitation. By: Marcus Mitchell; SWL Contracting Division;
(501-340-1253) On: Aug 16 2017 Current Request Status: Request Closed
Information for this report is procurement sensitive.
7086406 IO Project Management N/A Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
How many hard copies of the closeout documentation will be required?
By: Molly Chasteen; Cazador; (913-433-3375). On: Jul 29 2017. Forward request by email.
1-0 Evaluation Concurred. It will be the same for close-out as it is for the submittals By: TJ Lee; SWL Programs and Project
Management Division; (501-340-1030) On: Aug 14 2017 1-1 Government Response. It will be the same for close-out as it is for the submittals By: Marcus Mitchell; SWL Contracting Division;
(501-340-1253) On: Aug 16 2017 Current Request Status: Request Closed
Information for this report is procurement sensitive.
7086501 Contracting Page 6-7 Proposal Format Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please confirm that Cut sheets and Specifications for all commodities are not required for the Price Proposal.
By: Stephanie Hadiwibawa; Omega Group - San Diego, CA; (8585692420). On: Jul 30 2017. Forward request by email.
1-0 Evaluation Concurred. Cut Sheets are not required for the Price Proposal. By: Marcus Mitchell; SWL Contracting Division; (501-
340-1253) On: Aug 16 2017 1-1 Government Response. Cut Sheets are not required for the Price Proposal. By: Marcus Mitchell; SWL Contracting Division; (501-
340-1253) On: Aug 16 2017 Current Request Status: Request Closed
Information for this report is procurement sensitive.
Page 8 of 13ProjNet: Logged In User
7086686 IO Project Management N/A Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
There is a discrepancy on number of submittals required. Section III Initial Outfitting Overview states there will be 4 submittals, but Section IV, Item H says 3 submittals are required. Please advise as to the correct number of submittals.
By: Molly Chasteen; Cazador; (913-433-3375). On: Jul 31 2017. Forward request by email.
1-0 Evaluation Concurred. There will be 3 submittals By: TJ Lee; SWL Programs and Project Management Division; (501-340-
1030) On: Aug 14 2017 1-1 Government Response. There will be 3 submittals By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 16
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7086687 IO Public Relations N/A Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Is there a requirement for a Public Affairs/Public Relations person on this project? There is a brief mention of a ribbon cutting ceremony, but there was no other information provided, such as a list of deliverables or personnel requirements for this position.
By: Molly Chasteen; Cazador; (913-433-3375). On: Jul 31 2017. Forward request by email.
1-0 Evaluation Concurred. Coordination will need to be provided with the NMCP Public Affairs officer with regard to schedule, key dates, and general planning for a Grand Opening By: TJ Lee; SWL Programs and Project Management Division; (501-340-1030) On: Aug 16 2017
1-1 Government Response. Coordination will need to be provided with the NMCP Public Affairs officer with regard to schedule, key dates, and general planning for a Grand Opening By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 16 2017 Current Request Status: Request Closed
Information for this report is procurement sensitive.
7086710 IO Artwork Cut Sheet U6046 Artwork Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Artwork JSN U6046 is unclear and inconsistent in the requirement specifications. Cut sheet name for U6046 however specification states Float Mount and Exhibition Frame. What is meant by an "Exhibition Frame", and is this a requirement or all to be "frameless"? No sizes have been specified, please clarify requirements.
By: Jessica Martin; Workplace Solutions - Jacksonville, FL; (9049978878). On: Jul 31 2017. Forward request by email.
1-0 Evaluation Concurred. The intended type is 'Float Mount'. Disregard the 'Exhibition Frame' example. Sizes would be as appropriate by location of each artwork piece. By: TJ Lee; SWL Programs and Project Management Division; (501-340-1030) On:
Aug 16 2017
1-1 Government Response. The intended type is 'Float Mount'. Disregard the 'Exhibition Frame' example. Sizes would be as appropriate by location of each artwork piece. By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 16 2017 Current Request Status: Request Closed
Information for this report is procurement sensitive.
7086821 General RFP Award Date Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
What is the assumed award date for this submission?
By: Kelli McNamara; Martek Global Services, Inc.; (3014665255). On: Jul 31 2017. Forward request by email.
1-0 Evaluation Concurred. The IO contractor is required onsite as needed for design/planning purposes, when deliveries are being made, when installs are being completed. By: TJ Lee; SWL Programs and Project Management Division; (501-340-1030) On: Aug 16 2017
1-1 Government Response. PLEASE IGNORE THE RESPONSE ABOVE. By: TJ Lee; SWL Programs and Project Management Division; (501-340-1030) On: Aug 16 2017
1-2 Government Response. The projected award date is 30 September 2017 By: Marcus Mitchell; SWL Contracting Division; (501- 340-1253) On: Aug 16 2017 Current Request Status: Request Closed
Information for this report is procurement sensitive.
7086827 General RFP Period of Performance Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Page 50 of the SOW provides the Construction Schedule for the Chesapeake IO project. The BOD is scheduled for 1 March 2018. Is the IO Contractor expected to be onsite prior to the BOD date? Please provide detail regarding the IO period of performance so this may be considered when pricing this effort.
By: Kelli McNamara; Martek Global Services, Inc.; (3014665255). On: Jul 31 2017. Forward request by email.
1-0 Evaluation Concurred. The IO contractor is required onsite as needed for design/planning purposes, when deliveries are being made, when installs are being completed. By: TJ Lee; SWL Programs and Project Management Division; (501-340-1030) On: Aug 16 2017
1-1 Government Response. The IO contractor is required onsite as needed for design/planning purposes, when deliveries are being made, when installs are being completed. By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 16 2017 Current Request Status: Request Closed
Page 9 of 13ProjNet: Logged In User
7086829 General RFP A.01.30_Suffolk_Bid_Schedule Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Will the Government modify the Bid Schedule to include a Summary tab at the beginning of the spreadsheet?
By: Kelli McNamara; Martek Global Services, Inc.; (3014665255). On: Jul 31 2017. Forward request by email.
1-0 Evaluation Concurred. NO By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 16 2017 1-1 Government Response. No. By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 16 2017
Current Request Status: Request Closed Information for this report is procurement sensitive.
7086832 IO Artwork RFP A.01.30_Attachment_G_Cut_Sheets Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
The specification requirements do not state any required artwork sizes. Can the Government provide what size they prefer for artwork? If multiple sizes, please break it down by what quantity per size.
By: Kelli McNamara; Martek Global Services, Inc.; (3014665255). On: Jul 31 2017. Forward request by email.
1-0 Evaluation Concurred. Artwork shall be sized appropriate to the area that is going. For individual rooms, artwork will be sized appropriately, when in corridors it should be sized appropriately for the wall that it will be installed. Location will also dictate horizontal vs vertical. By: TJ Lee; SWL Programs and Project Management Division; (501-340-1030) On: Aug 16 2017
1-1 Government Response. Artwork shall be sized appropriate to the area that is going. For individual rooms, artwork will be sized appropriately, when in corridors it should be sized appropriately for the wall that it will be installed. Location will also dictate horizontal vs vertical. By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 16 2017 Current Request Status: Request Closed
Information for this report is procurement sensitive.
7086839 IO Artwork Bid Schedule and Attachment I - New FFE Quantity Differences
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
The bid schedule shows a quantity of 84 JSN's for U6046 - Artwork, Decorative, Frameless.
Attachment I - New FFE has a quantity of 81 for U6046 - Artwork, Decorative, Frameless.
Please clarify the quantity that should be priced for the bid submission.
By: Kelli McNamara; Martek Global Services, Inc.; (3014665255). On: Jul 31 2017. Forward request by email.
1-0 Evaluation Concurred. Use the bid schedule which shows a quantity of 84 JSN's for U6046 - Artwork, Decorative, Frameless By:
TJ Lee; SWL Programs and Project Management Division; (501-340-1030) On: Aug 16 2017 1-1 Government Response. Use the bid schedule which shows a quantity of 84 JSN's for U6046 - Artwork, Decorative, Frameless By:
Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 16 2017 Current Request Status: Request Closed
Information for this report is procurement sensitive.
7086851 IO CID: Furniture/Furnishings Bid Schedule and Attachment I - New FFE Quantity Differences
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
RFP SOW Page 53 states, "The IO Contractor is responsible for procuring all commodities indicated in the Bid Schedule. This information can also be found in the Master Room Contents List."
There are multiple discrepancies between the Equipment List in the Bid Schedule and Attachment I New FFE.
What document takes precedence in order to provide correct quantity pricing?
By: Kelli McNamara; Martek Global Services, Inc.; (3014665255). On: Jul 31 2017. Forward request by email.
1-0 Evaluation Concurred. the Attachment I NEW FFE should take precedence and you should include all of those items in the build schedule when you fill it in. By: TJ Lee; SWL Programs and Project Management Division; (501-340-1030) On: Aug 14 2017 1-1 Government Response. the Attachment I NEW FFE should take precedence and you should include all of those items in the build schedule when you fill it in. By: Marcus Mitchell; SWL Contracting Division; (501-340-1253) On: Aug 16 2017 Current Request Status: Request Closed
Information for this report is procurement sensitive.
7086856 General RFP Extension Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
The…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .