W9127S-17-R-6030_Amendment_0002.pdf

PDF 211 KB Posted

Attached to
WALTER REED SWING SPACE INITIAL OUTFITTING PROJECT Federal contract opportunity
Solicitation number
W9127S-17-R-6030
Issued by
Department of the Army Corps of Engineers Engineering District Little Rock

About this file

Amendment 0002

View the file

Other files for this federal contract opportunity

Other files attached to WALTER REED SWING SPACE INITIAL OUTFITTING PROJECT, newest first.
File Type Posted
AMENDMENT_0001.pdf PDF
W9127S-17-R-6030_SOLICITATION.pdf PDF
W9127S-17-R-6030_Site-Visit_attendance_list.pdf PDF
W9127S-17-R-6030_-_Site-Visit_minutes.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to extend the solicitation due date to May 31, 2017 at 12pm central time. This amendment w ill incorporate changes to the statement of w ork.

This amendment w ill also incorporate contractor questions and government responses from ProjNet. This amendment w ill incorporate the follow ing attachments: (Attach 1 - revised bid schedule, Attach 6 - Reuse Artw ork Tally, Attach 7 - DRMO list existing furniture, Attach 8 -leased equipment, Attach 9 - cut sheet M5562, Attach 10 - ProjNet Final, and Attach 11 - WRNMMC VCOE instructions).

All other terms and conditions of the solicitation remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 43

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 11-May-2017

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9127S-17-R-6030

X 9B. DATED (SEE ITEM 11)

29-Mar-2017

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

11-May-2017

CODE

CONTRACTING DIVISION

USACE, LITTLE ROCK (W9127S)

700 W. CAPITOL AVE, RM 7315

LITTLE ROCK AR 72201-3225

W9127S 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9127S-17-R-6030

Amendment 02

W9127S-17-R-6030

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 1449 - CONTINUATION SHEET

The following have been modified:

SOW

A MANDATORY SITE-VISIT was held February 22, 2017 at 1:00pm ET.

Only offers from contractors that attended the mandatory site-visit will be considered.

Award will be based on a Best Value, Lowest Price Technically Acceptable Source Selection Process, IAW FAR 15.101-2. It is the potential offeror's responsibility to monitor fbo.gov for updates to this solicitation. All work shall be performed in accordance with all requirements under this Statement of Work, other terms and conditions of the contract. Contractor employees shall not be considered government employees for any purposes under the contract.

STATEMENT OF WORK

INITIAL OUTFITTING FOR

DEFENSE HEALTH AGENCY, WALTER REED NATIONAL MILITARY MEDICAL

CENTER (WRNMMC), BETHESDA, MD

I. INTRODUCTION

Defense health Agency (DHA) is responsible for the programming, planning, construction and initial outfitting (IO) of Walter Reed national Military Medical Center (WRNMMC) temporary building Bldg. 85T. DHA is chartered with modernizing the Walter Reed National Military Medical Center through a major MILCON which builds 518K square feet of new construction and 140K square feet of renovation. This project requires 100K square feet of temporary building to be built in 2 phases. The IO SOW pertains to the initial outfitting and transitioning in phase II (approximately 80K square feet) of the temporary space. The terms “DHA” and “DHA Project Officers” may be used interchangeably within this document.

This SOW describes the IO services, procedures and personnel necessary to outfit the temporary building (bldg. 85T) at Walter Reed national Military Medical Center.

The new temporary building is currently under construction approximately 300 feet from to the existing Walter Reed outpatient clinical building. Items from the existing buildings being torn down selected for reuse shall be moved to the temporary building by the IO Contractor.

Development of the IO requirements and IO integration into the project shall be accomplished concurrently with construction of the Temporary Building (85T).

II. INITIAL OUTFITTING OVERVIEW

Defense Health Agency defines Initial Outfitting (IO) as any commodity-related planning, transition, procurement, installation, certifying, training and warranting required to outfit a new or newly renovated facility.

Initial Outfitting is a two-step acquisition process. The IO Contractor is ultimately responsible for providing Initial Outfitting Transition (IO-T) planning and validation, throughout the duration of the project. Once authorized to proceed based on the IO Master Schedule, the IO Contractor shall procure the approved commodities and complete all IO-C related tasks.

The currently proposed WRNMMC Temporary Building (85T) IO-T and IO-C planning dates as well as the Beneficial Occupancy Date (BOD) and Open for Business (OFB) dates are outlined below.

These dates are for information purposes only and are subject to change.

WRNMMC Temporary

Building Initial Outfitting (IO)

Schedule

Begin construction 1 APR 2016

Award IO Contract MAY 2017

Construction Completion DEC 2017

Beneficial Occupancy Date

(BOD)**

JAN 2018

** BOD– Date at which building system testing and commissioning, construction punch lists and other final work is complete. Date building is officially turned over by NAVFAC to DHA. Date the IO Contractor may begin installation of IO commodities.

Initial Outfitting includes planning, procurement, delivery and installation of project artwork, signage, way-finding, Furniture, Furnishings and Equipment (FF&E) -also known as “commodities,” medical equipment, case goods, low-voltage systems (communications, resource protection), and logistics (procurement, delivery, installation and certification).

Installation period is defined as the time between BOD and transition period during which installation of FF&E may be achieved. Transition period is defined as the time between BOD and close-out during which any reuse items and personnel and/or personnel belongings are moved from the existing WRNMMC buildings designated for demolition to the new Temporary Building (85T). Project close-out period is defined as the time immediately after transition until contract end date, unless a change in this duration is requested by DHA.

Initial Outfitting – Transition Planning & Validation (IO‐T)

1. Initial Outfitting (IO-T) includes:

a. Planning, project management, transition, and move planning services

b. Space planning

c. Refinement of commodities lists and requirements

d. Inventory of existing commodities, tracking of all reuse systems and commodities throughout project

e. Validating all commodities

f. Conducting User interviews and developing submittals

g. Planning and developing requirements for all new and reuse commodities.

h. Transition and relocation planning

i. Developing schedules for all IO requirements (submittals, transition, User meetings, etc.)

j. DRMO planning and coordination

2. Validation of Commodities means the IO Contractor must:

a. Complete a thorough inventory of the existing facilities and check the inventory against the Temporary Building commodities list;

b. Check all existing commodities to ensure they are listed and accounted for in all inventory and subsequent project documents;

c. Ensure all new and reuse commodities planned for the project meet the operability, durability and safety requirements for DHA and DoD facilities;

d. Ensure all new and reuse commodities are included in all room by room and master equipment lists;

e. Ensure all new and reuse commodities shall fit within allowable space in new facility, are supported by all necessary utilities to function in accordance with the manufacturer’s specifications, and ensure the commodities meet all current codes, including DHA and

Open for Business

OFB

AUG 2018

life safety requirements. (For example, ensure correct power voltage, power cords and placement of cords, shielding, exhausts, venting, floor drains, air temperature, water volume and temperature are available for the commodity to operate properly. Ensure commodities shall be located for proper operation by Users.)

f. Ensure all commodities have all attachments or accessories necessary for proper operation.

g. Ensure all new and reuse items can be delivered into the new facilities. (For example, ensure commodities to be placed in new facility shall fit through any doors, windows, elevators, stairwells, hallways, etc. as necessary to be placed in the specified locations without damage to building or commodities)

h. Ensure DHA Project Officers and Users are partners in the FF&E review for their respective departments. While the IO Contractor and User may make recommendations for commodities, selection and final approval for procurement of new commodities, or reuse of existing commodities, shall be made by the DHA Project Officers.

i. Following validation of commodities, reuse commodities should be denoted as “reuse- DRMO” or “reuse-move to new WRNMMC Temporary Building”

3. Initial Outfitting Master Schedule

a. IO Contractor shall develop an Initial Outfitting Master Schedule (IOMS) in coordination with the General Contractor (GC) construction schedule and DHA.

b. The Initial Outfitting Schedule must be provided to USACE and DHA for review within two weeks of receipt of the project construction schedule following IO contract award.

c. This schedule shall be updated to reflect any approved project schedule changes throughout the course of the project and within 10 days of the approved changes. Any schedule updates shall be submitted to the USACE Project Manager and DHA Project Officer for approval.

4. Submittals

a. IO-T key deliverables include a minimum of three IO Submittals: Submittal #1, Submittal #2, and Submittal #3. Should any minor changes result from the review of Submittal #3, the IO Contractor shall provide a revised Final Submittal, at no additional cost, within 14 days of Submittal #3 review completion. IO project schedule provided by the IO Contractor shall include submission dates for Submittal #1, #2 and #3. Each Submittal shall be completed to 100 percent by the dates specified in the Initial Outfitting Schedule.

b. IO Contractor shall explain in the proposal information that will be provided in each of

Submittals #1, #2 and #3. This information shall include a narrative description for deliverable items, including Room by Room (RBR) lists, floor plans with proposed location of commodities, commodity lists, commodity cut sheets/specifications, schedules for the project as well as any anticipated field verification and vendor visits.

c. Each submittal shall include drawings. Drawings shall include placement of CAT A (purchased and installed by GC, CAT B (purchased by IO Contractor, installed by GC) and CAT C (purchased and installed by IO Contractor). Drawings shall include composite as well as individual room/section/department as necessary to clearly illustrate placement of planned FF&E. All lettering in the Drawings shall be clearly legible and all drawings shall include legends for any colors, acronyms or symbols used.

FF&E placed within the drawings shall be clearly drawn, labeled with Joint Schedule Numbers (JSN’s) and descriptive information so Users can readily distinguish items on the floor plan for their departments.

d. Each submittal shall include a Room by Room list with JSN’s and quantities proposed by room. In addition, each submittal shall include a roll-up summary of total quantities per JSN developed from the Room by Room. Room by Room list shall be provided in both Excel and PDF formats.

e. Each submittal provided shall be quality reviewed and signed by the IO Contractor’s

Quality Control Manager for the project. Submittals #1, #2, and #3 shall include completed cut sheets for all proposed commodities as well as JSN’s. Pricing on each cut sheet shall be consistent with pricing provided on the Room by Room and JSN roll-up commodities lists submitted to the government for this project.

f. The government shall have at least 21 days to complete a review of each Submittal. This review time shall be reflected on the IO schedule.

Initial Outfitting – Commodities (IO‐C)

Initial Outfitting – Commodities (IO-C) includes:

1. Validating IO/T

2. Procurement (ordering, purchasing,) shipping, warehousing / storing commodities

3. Providing building protection before installation of commodities

4. Cleaning of new facilities prior to installation of commodities

5. Delivering and installing new commodities

6. Making final utility connections for commodities

7. Uninstalling reuse commodities from existing facilities and preparing them for move to new facilities

8. Certifying commodities

9. Providing final cleaning of new facilities prior to Beneficial Occupancy Date (BOD)

10. Training Users to properly operate equipment, providing Operation and Maintenance

(O&M) manuals

11. Warranting all new commodities, providing warranty information for Users / DHA.

See Attachment 1 – Bid Schedule.

1. For any discrepancies between the Drawings and the Attachment 1 – Bid Schedule, the

Bid Schedule takes precedence. NOTE: Some commodities may be identified on drawings that are not on the bid schedule. Only bid what is in the bid schedule.

2. GSA

A letter from the USACE Contracting Officer (KO) may be requested by the IO Contractor to support procurement of commodities through General Services Agency

(GSA).

3. Beneficial Occupancy

Beneficial Occupancy Date (BOD) date is the date NAVFAC completely turns over the newly constructed WRNMMC Temporary Building to DHA. Building construction, punch lists, commissioning and all HVAC, fire and emergency systems testing and removal of construction equipment shall be completed prior to BOD. IO Contractor may begin installation of commodities at BOD. After BOD, if any construction work by Contractor must continue, ALL Contractor construction work shall be coordinated with the IO Contractor through DHA.

4. Storage

All furniture, fixtures and equipment procured by the IO Contractor and not immediately installed in the WRNMMC Temporary Building to DHA must be stored in secure warehouse facilities and at the expense of the IO Contractor, unless otherwise specified.

These secure warehouse facilities must have climate controlled space for any sensitive equipment or furniture prior to delivery to the new facility. Sensitive shall be defined as any items that the manufacturer states will be at risk if stored in a non-climate controlled area. The contractor must provide proof of full value replacement insurance up to the value of the commodities being stored at any one time. All commodities provided by the IO Contractor to the WRNMMC Temporary Building to DHA shall be free from damage, including but not limited to damage from inclement weather.

5. Training and Transition of User Personnel

Training and transition of personnel shall follow immediately after complete outfitting of the new facility. IO Contractor shall coordinate with DHA and WRNMMC Departments to schedule training and ensure Users are properly trained to operate new FF&E. IO Contractor shall also support Users to operate in the new WRNMMC Temporary Building by providing ‘day in the life’ training to acclimate Users to the new facility and any new work flow patterns.

6. Government Acceptance

All FF&E installed in the WRNMMC Temporary Building by the IO Contractor belongs to, and is the responsibility of, the IO Contractor until the Government inspects, approves and accepts the commodities. Acceptance of installed commodities by the Government is effective when the Government inspects installation of the commodities and signs the DD250 form. Proposed dates for government acceptance of commodities shall be included in the IO Contractor’s project schedule, reviewed and approved by DHA. These dates should be re-coordinated with DHA and Users prior to any schedule revisions.

7. Billing / Invoicing

During IO-T, IO Contractor shall invoice upon inspection and acceptance of Submittals 1, 2, and 3. During IO-C, IO Contractor may issue an invoice for the installed commodities after the DD250 form for said commodities is signed by DHA. Typically, acceptance for commodities is conducted once all commodities are installed within the facility. Acceptance of uninstalled commodities shall be considered on a case by case basis and at the discretion of the COR and Contracting Officer (KO).

8. Warranty Date of Warranty for FF&E begins at acceptance of the FF&E by the government. IO Contractor shall replace or repair a warranty-covered defective item for at least one year from acceptance. The IO Contractor must provide, within 72 hours of the completed installation and punch, a spreadsheet to the government by department, room, and JSN, listing all damages, deficiencies or missing items. Once this has been presented and approved by the government, the contractor shall publish the formal list and shall provide its best effort to resolve all items within 45 calendar days. Any equipment or furniture furnished by the contractor found to be defective within the one year warranty period must also be resolved as soon as possible, preferably within 25 calendar days. In the case of missing items or items requiring replacement, IO Contractor must show to the government within 14 calendar days of completed installation and punch proof of reordering of the product and list the anticipated lead time to completion. For any damages, breakages beyond repair or missing items after the relocation of reuse, the IO Contractor shall have 48 hours to complete the evaluation and provide to the government the same list, as described above, and shall follow the same durations to remedy.

9. Post Move Help

IO Contractor shall provide post move assistance for Users immediately after transition.

This service shall be provided for a minimum of five business days. The Contractor shall be available to assist with locating relocated tagged materiel, trouble-shoot issues with furniture, disposal of packing materials, and other such activities to support full use of the outfitted space.

10. Kickoff Meeting: A Kickoff meeting will be held on-site at Walter Reed National

Military Medical Center. This meeting is to establish the rules of engagement related to IO process, introduce members of the PDT and provide an overview of the way forward. This meeting shall include an explanation of lines of communication within and across DHA, USACE, and IO Contractor organizations to ensure proper leadership and management support as well as efficient project execution. The USACE PM, IO Contractor PM, and DHA officers, at a minimum, shall attend the Kickoff meeting. Meeting onsite will provide the PDT and IO contractors familiarization of the construction site and pertinent support facilities on and off-base that are necessary in the execution of this contract.

11. Project is located in Bethesda Maryland. For this contract, the date of the contract

(notice to proceed, Period of Performance (POP)) will be based on Eastern U.S. time.

III. INITIAL OUTFITTING ‐TRANSITION (IO‐T) REQUIREMENT

The IO Contractor shall provide Initial Outfitting Project Management services for this project and a Project Manager (IO-PM) to execute these services.

A. Project Management DHA considers project management as a methodical approach to planning and guiding project processes from start to finish. Project management activities shall include, but are not limited to, facilitating the project while controlling resources, staffing, time, cost, quality, scope and risk for each project.

Project Management includes ensuring all IO staff meets all base access requirements, including required training, paperwork and certifications:

1. A Common Access Card (CAC) is required for IO Contractor personnel to access

WRNMMC network. The IO Contractor Project Manager, BMET, and Transition Planner must possess CAC cards to properly conduct their work at WRNMMC. IO Contractor Project Manager, BMET, and Transition Planner shall each possess a CAC card at the time of IO Contract award, or obtain CAC cards within two weeks of award.

2. Proof of Health Insurance Portability and Accountability Act (HIPAA) certification is required for all IO Contractor personnel who may work on the WRNMMC Temporary Building project. HIPPA certification is required in order for any IO Contractor personnel to complete paperwork to access any section of the Defense Health Agency Network.

B. Initial Outfitting Project Manager (IO‐PM)

Key objectives and the role of the IO Contractor Project Manager to oversee these objectives are presented, below.

1. Oversight

IO Contractor PM (IO-PM) shall oversee and guide project initiation, planning, execution, and closing of the project. The IO-PM is responsible to ensure all deliverables are submitted per contract.

2. On Project / On Site Time Periods

The PM must be identified and begin work with DHA/USACE on the project within 14 days of contract award. The PM shall be on site for the Kickoff meeting and User meetings. The PM shall be onsite at WRNMMC full time two weeks prior to BOD through the final “Post Move Help” date. DHA will provide an office area with electrical service for the IO-PM and Transition Planner to use through this time period of the project. All other office support (phones, computers, use of printers, copiers, fax machines, projectors, paper, Wi-Fi) shall be the responsibility of the IO-Contractor, unless otherwise indicated by DHA.

3. Close Out

During Close-out, IO-PM shall address any outstanding issues to complete project close-out, and provide the final procurement package, warranty information, and operation manuals to DHA for each commodity installed under this contract. Contractor proposal shall provide a narrative describing Project Manager’s work to ensure proper project close out.

4. Meetings

The IO-PM will direct the activities for each meeting described, below. The IO-PM must lead each of the following meetings:

a. Weekly PDT Meetings

b. User Requirement Meetings

c. User Review Meetings.

5. PDT Meetings

The IO Contractor shall provide a teleconference call-in number for the weekly PDT meetings. PDT meetings will include teleconference participation, and will be held at a time of the day to allow access for the entire PDT to participate, which will be led by the IO-PM. PDT meetings shall be listed in the IO project schedule. The IO-PM shall provide a draft meeting agenda and submit it to the Project Delivery Team (PDT) a minimum of three (3) calendar days prior to each meeting date. The IO PM shall coordinate feedback from the Project Delivery Team (PDT), finalize the agenda and confirm attendance of key participants two (2) calendar days prior to the meeting date.

Agendas shall state objective, expectations, risks, status of project/minutes/reports, action items, attendees/participants, dates, times and location of meeting, and required information at time of meeting. See Section XI. Deliverables, Attachment 10 - Weekly Report Format and Attachment 08 – Submittal Distribution List (PDT).

a. IO Schedule. IO Schedule shall be discussed at each PDT meeting. Schedule discussion shall include project progress, risks or issues and progress to resolve risks or issues, any possible schedule impacts, and any schedule impacts associated with contract modifications. All schedule changes must be incorporated via contract mod to become effective for the project.

b. Risk Report. Any project risks shall be discussed at each PDT meeting. Any items that have potential to impact the project schedule, cost or success should be noted on the Risk Report. The Risk Report shall include red, yellow and green color coding to indicate high risk, medium and low risk, respectively. Upon resolution of risk, risk shall remain on report with associated rows set to green highlight to indicate successful resolution within the Risk Report document.

c. Minutes. The IO-PM shall provide Meeting Minutes to the PDT within three (3) business days following any meeting related to this contract. Meeting minutes shall note PDT members present and non-present, as well as any other attendees, copy of the agenda, issues, action items and timeframes for resolution. All meeting minutes shall also be included in Submittal #1, Submittal #2 and Submittal #3. Action items discussed and agreed upon during the PDT shall be included in the minutes.

6. User Meetings. User meetings shall be held on site at Walter Reed National Military

Medical Center unless otherwise specified. User meetings shall include:

a. User Requirements Meetings. The IO-PM shall arrange all User Requirements Meetings in order to adequately complete the Submittal #1, Submittal #2 and Submittal #3 requirements. The objective of the User Requirements Meetings is to capture all known IO requirements related to the project.

i. At least two User Department representatives shall attend each User Requirements Meetings. DHA will also attend each User Requirements Meeting. IO Contractor shall ensure a designated representative from each department attending Users meetings signs a form indicating their concurrence with FF&E decisions discussed during each User Requirements meetings.

Reminder: DHA Project Officer must approve all User changes/requests from each User Requirements Meeting.

ii. Submittal review comments shall be posted in ProjNet/Dr. Checks prior to each of the User Review meetings for Submittal #1, Submittal #2 and Submittal #3. All PDT members must have their own individual Dr Checks/ProjNet account set up prior to submission of Submittal #1. IO Contractor Project Manager shall assist IO Contractor PDT staff with ProjNet registration, including providing the required Vendor ID. Once IO Contractor staff is registered, the USACE Project Manager must be contacted to assign IO

Contractor personnel and DHA personnel to the Walter Reed National Military Medical Center Temporary Building project within DrChecks/ProjNet.

iii. During User Requirements Meetings, at a minimum, IO Contractor Project Manager, Equipment/Space Planner and Interior Designer personnel shall be present to assist Users with review of FF&E for their respective Departments.

During these meetings, IO Contractor shall provide to Users an opportunity to see the floor plans (all floor plans must include room and department names) with proposed Department FF&E positioned on the floor plans, and completed cut sheets (specifications, colors, fabrications, manufacturer, model numbers).

Preferably, the IO Contractor shall project the floor plan section and cut sheets on a projector for Department Users / DHA during User meetings. Users shall have an opportunity to review cut sheets/specifications prior to User meetings so they are prepared to finalize FF&E decisions during the User meetings. IO Contractor shall answer User questions and inform Users / DHA of any costs for any changes that may be necessary as a result of any proposed changes during the User meetings.

b. User Review Meetings.

The IO-PM shall arrange Review Meetings as described herein:

i. A minimum of three (3) Review Meetings are required. These meetings shall be scheduled to begin within ten days of closing the ProjNet/Dr Checks review for each submittal (#1, #2 and #3).

ii. The first review meeting shall address Submittal #1 and shall be conducted on site* as well as via teleconference with at least one DHA Project Officer, User Department representatives, USACE PM, IO Contractor Project Manager and Equipment Planning / Interior Designer participating.

iii. The second review meeting shall address IO Submittal #2 and shall be conducted on site* as well as via teleconference with at least one DHA Project Officer, User Department representatives, USACE PM, IO Contractor Project Manager and Equipment Planning / Interior Designer participating.

iv. The third review meeting shall address IO Submittal #3 and shall be conducted on site* as well as via teleconference with at least one DHA Project Officer, User Department representatives, USACE PM, IO Contractor Project Manager and Equipment Planning / Interior Designer participating.

v. The IO Contractor shall provide to the DHA Project Officers a ‘Change Tracker’ spreadsheet of all commodity changes within 10 calendar days of the completion of each Review Meeting. A list of changes approved by DHA during User meeting shall be included in each subsequent Submittal. A Change Tracker of DHA approved changed shall be provided to the government after each Submittal Review meeting.

*On site review meetings are acceptable if they coincide with other on-site project activities and are held at no additional cost to government

c. Additional Meetings

i. IO Contractor PM shall be available to meet (in person if on site, or via phone/teleconference if off site) with DHA at any time during normal business hours throughout the duration of the IO project / contract.

7. Change Management The IO-PM shall oversee the IO Change Management process.

a. IO-PM shall track UCR’s and Change Tracker documents. All UCR’s and Change

Trackers should include a spreadsheet to clearly compare the original commodity list with the requested changes. Costs associated with the change must be presented with the spreadsheet. See XI. Deliverables, Attachment 10 - Weekly Report Format, Attachment 11 – IO-C Change Order Tracker, and XII Supplemental, Attachment 20 - User Change Request (UCR) form.

b. No changes may be made arbitrarily by the IO Contractor. A contract mod must be executed before any changes can be made to the IO contract. Any changes proposed by the IO Contractor must be reviewed and approved by DHA, then submitted to USACE for approval and execution via a contract mod before any action can be taken on the proposed changes. Only the USACE Contracting Officer has the authority to authorize and execute changes to the IO Contract. USACE will not authorize an IO Contractor to operate ‘at risk.’

c. Changes During IO‐T / Planning

For any changes to the IO contract after award and during the IO-T Planning phase, the following change management protocol applies:

1. For each User Requirements Meeting for each Department: IO Contractor, User representatives for each department and at least one DHA Project Officer will review the proposed commodity items and floor plans for the Walter Reed National Military Medical Center project.

2. Any changes proposed by either the Users or the IO Contractor must be reviewed and approved by the DHA Project Officer. IO Contractor shall advise Users and DHA of any associated work and potential additional costs associated with any change in IO commodities. (For example, any additional re-design of floor plans to accommodate a change in furnishings, any additional accessories necessary to make equipment operational, etc.) IO Contractor shall advise Users and DHA of any associated work and potential additional costs associated with decisions to reuse any commodities. Any changes which result in additional costs shall be fully explained by the IO Contractor, including any labor, materials, man hours, special equipment or considerations to accomplish the requested change.

3. During User meetings, all DHA Project Officer-approved changes must be noted on a meeting document by the IO Contractor. This document shall be signed by the User department representative, DHA Project Officer, and the IO Contractor before the conclusion of each User department meeting.

4. Upon completion of all each User meetings, the IO Contractor shall list all commodity changes for all departments within the Walter Reed National Military Medical Center Temporary Building on a Change Tracker. The Change Tracker shall be issued with each Submittal. See Section XI. Deliverables, Reference Attachment 11- IO-C Change Order Tracker. Commodities on the Change Order Tracker shall be listed as either a credit (for items eliminated or reduced in quantity) or an addition (for items increased in quantity).

A descriptive explanation shall be listed on the Change Tracker beside each approved change.

5. Within 10 calendar days of each User Submittal Review meeting, the updated Change

Order Tracker shall be provided by the IO Contractor to DHA, along with proposed pricing for all changes, for DHA review and approval. Upon DHA approval of the Change Order Tracker, DHA Project Officer shall submit a signed PDF version of the Change Order Tracker list to the IO Contractor. The IO Contractor shall submit the DHA-signed PDF version of the approved Change Tracker list, along with an Excel version of the same list, to the USACE PM for review. The final, approved Change Tracker shall be incorporated via contract mod.

6. USACE PM will:

a. Review proposed Change Tracker and coordinate with DHA, as needed, for any clarifications;

b. Consult with USACE Contracting on any items in questions;

c. Coordinate development of a cost estimate for the Change Tracker;

d. Provide final change documents to USACE Contracting; and

e. Coordinate funding for Change Tracker.

7. USACE Contracting will enter into negotiations with the IO Contractor regarding the proposal, if necessary.

8. USACE Contracting will compare cost estimate and IO Contractor Change Tracker to ensure proposed costs are fair and reasonable. USACE Legal Counsel will conduct legal sufficiency review of mod, if necessary.

9. USACE Contracting Officer will issue the proposed mod to the IO Contractor for review and approval.

10. Upon receipt of the IO Contractor-signed approval for the mod, the USACE Contracting

Officer will execute a contract mod to incorporate the proposed changes and copy the contract mod to DHA and the IO Contractor.

11. IO Contractor may act on changes included within the contract mod once mod is executed by the KO.

d. Changes During IO‐C, After Planning Phase

For any changes to the IO contract after the IO-T Planning phase, the following change management protocol applies:

1. Any IO project changes proposed by the IO Contractor shall be submitted to DHA for review and approval. IO Contractor shall include a description for the proposed work, a list of any associated commodities and a Rough Order of Magnitude cost estimate (ROM)). Upon DHA approval, DHA shall provide approved changes to the USACE PM. USACE PM will coordinate with USACE Contracting to ensure proposed changes are acceptable within the framework of the IO Contract. USACE PM and Contracting will coordinate with DHA for any necessary discussions.

2. Any commodity changes requested by DHA may be provided directly to the IO

Contractor for inclusion on a Change Tracker. Any changes requested by DHA which may require a scope of work shall be requested by DHA on a User Change Request (UCR) form and submitted to USACE PM and Contracting. These requests should include a description of the proposed work and a list of any associated commodities.

3. USACE PM will coordinate with DHA, IO Contractor and USACE Contracting, as necessary, for any discussions and additional information to finalize proposed change documents.

4. USACE PM will coordinate development of a cost estimate for all proposed changes.

5. USACE PM will coordinate and provide final change documents to USACE

Contracting.

6. USACE Contracting will issue an RFP to the IO Contractor and a copy of the RFP to DHA and USACE PM.

7. IO Contractor shall provide a proposal to USACE Contracting, who will then copy the proposal to DHA and USACE PM.

8. USACE Contracting will compare the IGE/cost estimate and IO Contractor cost proposal.

9. USACE Contracting will enter into negotiations with the IO Contractor regarding the proposal, if necessary.

10. Final proposal shall be provided to DHA and USACE PM for final review and sign off. USACE PM will coordinate funding with DHA.

11. USACE Legal Counsel will conduct legal sufficiency review of mod in the event a mod exceeds $500K.

12. USACE Contracting Officer will execute a contract mod to incorporate the proposed changes.

13. Contractor may act on changes included within the contract mod.

e. In the instance that an item (proposed for the project) is no longer available, a suitable replacement of equal or greater quality shall be provided at no additional cost to the Government. However, the IO Contractor shall submit the manufacturer's product data sheet for the replacement item for review and approval by DHA Project Officers, the Contracting Office (KO) or Contracting Officer's Representative (COR).

f. For each Commodity change proposed, the IO Contractor shall provide: Existing commodity (commodity being removed or replaced) and / or Proposed commodity (new or replacement) cut sheet with JSN; any accessories and utilities required for proper operation for new or replacement item; specifications, including but not limited to:

dimensions, colors and composition/fabrications; manufacturer; warranty information; all costs; and current location and proposed location for new/replacement commodities.

Room by Room list and floor plans shall be updated with the new or replacement commodities. Contractors are responsible for ensuring they compete each additional commodity amongst its subcontractors in order to achieve a best value determination for each commodity. All commodities shall be brand name or equal.

E. Quality Control.

1. IO Contractor shall maintain Quality Control for the IO project and ensure that all deliverables are provided in accordance with this scope of work.

2. The designated IO Contractor Quality Control manager will certify and initial next to every line item of the Schedule of Deliverables for all items provided and completed. In addition, QCM is responsible for ensuring all commodities in the design and for procurement are properly validated to meet the condition of the building for proper installation and operation.

3. Any discrepancies need to be brought up to the attention of DHA Project Officers.

4. A copy of the certified and initialed Schedule of Deliverables shall be included with

Submittal #1, Submittal #2 and Submittal #3.

F. Submittal #1, Submittal #2 and Submittal #3

The IO-PM shall ensure requirements for each Submittal #1, Submittal #2 and Submittal #3 are provided in accordance with this contract in both format and content. See Section XI. Deliverables, Reference, Attachment 02 - IO Submittal Requirements & Format.

Format for all submittals shall be as follows:

PROJECT INFORMATION

II. TABLE OF CONTENTS

III. MASTER IO SCHEDULE

Design Submittals & Review Periods/Conferences Key Milestones: Phased BODs, Move & Transition Periods, OFBs, Ribbon

Cutting Procurement Schedule (in relation to construction schedule)

IV. PROJECT DESIGN ANALYSIS

Resource Protection Communications Furniture/Furnishings Medical Equipment/Case goods Artwork

Change Tracker

V. MINUTES, BRIEFINGS & REPORTS

Departmental User Interview Meetings MTF Interview Meetings (BMET, Comm, Facility Management, etc).

Briefings Reports (include Projnet reports from previous reviews)

VI. TRANSITION PLANNING

Transition Plan/Master Move Schedule (see attached example) Storage/Warehousing Plan Security Plan Delivery/Installation Plan Cleanup Plan Training Schedule Excessing Plan Testing/Inspections/Acceptance Plan

VII. COMPREHENSIVE INTERIOR LAYOUT

CIL/Furniture & Furnishing Boards SIL/Finish Boards Signage/Way Finding Concept

VIII. PUBLIC RELATIONS/MEDIA SUPPORT (if awarded) n/a

IX. MASTER ROOM CONTENTS – DEPT (for every department) Departmental Budget (see attached example) – N/A Departmental/Room Move Schedule (see attached example)

Department/Room Relocation Schedule De-install/Reinstall/Reconfiguration of existing product Training Schedule

Room x Room Lists (see attached example) Room 1: Room x Room List Room 2: Room x Room List Room 3: Room x Room List Room _: Room x Room List

Departmental Product Information Manufacturer’s Summary List Cutsheets/Specifications Roll-up of total quantities per JSN List of JSN changes Order Data Sheet (CAT C)

Departmental Drawings/Placement Plans Placement Placement Plans (showing reuse & new of ALL commodities AND JSN’s color–coded (or identified by different fonts) by Category A, C, etc. on drawings)

***IMPORTANT NOTES:

1. ALL commodities shall be listed on the Room x Room list. Per IO SOW, Tab 1, this includes any commodity related to Resource Protection, Communications, Furniture/Furnishings, Medical Equipment/Case goods, Artwork, Signage/Way finding (if GFGI).

2. The Draft SEPS Equipment List provided at the time of Award shall be used as the source document for the Room x Room lists.

3. Corrected final submittal is required. After review and completion of the resolution conference for the Submittal #3, IO Contractor shall provide complete electronic corrected CDs and complete corrected hard copies for any required changes to the Final Submittal.

The IO Submittals are for the planners and vendors/buyers as much as they are for the Government. Their importance, thoroughness, and timeliness cannot be emphasized enough.

Inability to meet these requirements will have a direct impact on implementation, funding and the project schedule. They are the source documents for identifying who is responsible for providing what commodities, utilities and requirements necessary to install equipment, furniture and systems, costs to procure critical items, and identifies accessories and options to systems/equipment.

NOTE: The Room by Room List shall note what items/systems are being relocated, the room the items/systems are being moved from and the room they are being moved into.

The government shall have at least 21 days to complete Submittal reviews.

H. Additional Administrative Requirements

The name of the IO Contractor’s Project Manager and alternate(s), who shall act for the IO-PM when the IO-PM is absent, shall be designated in writing to the Contracting Officer at the same time the PDT contacts are provided. The IO-PM or alternate(s) shall have full authority to act for the IO Contractor on all contract matters relating to daily operation of this contract. The alternate shall be on site and act for the IO-PM for every work day the IO-PM is not at work.

IV. TRANSITION PLANNING

The IO Contractor shall provide Initial Outfitting Transition Planning services, a Transition Plan and a Transition Planner for this project.

***NOTE: Transition plans shall utilize non-working hours (nights/weekends) space relocation and prep work.

***NOTE: Relocation of staff offices (including boxes and office supplies) is required.

Contractor shall supply boxes, labels, etc. to both locations in order for Military staff to pack/unpack other areas/items. Contractor shall provide boxes at least three (3) work days prior to move.

The Transition Planner shall begin work on the project within fourteen (14) days of contract award.

A. Transition Planning Transition Planning includes inventorying existing commodities, developing a plan for new and

W9127S-17-R-6030 reuse commodities and creating transition plans and schedules.

B. Transition Planner / Relocation Specialist

1. On Project / On Site Time Periods The Transition Planner / Relocation Specialist must be identified and begin work with DHA/USACE on the project within 14 days of contract award. The Transition Planner / Relocation Specialist shall be on site for the Kickoff meeting and User meetings. The Transition Planner / Relocation Specialist shall be onsite at WRNMMC full time two months prior to BOD through the final “Post Move Help” date. DHA will provide an office area with electrical service for the IO-PM and Transition Planner to use through this time period of the project. All other office support (phones, computers, use of printers, copiers, fax machines, projectors, paper, Wi-Fi) shall be the responsibility of the IO-Contractor, unless otherwise indicated by DHA.

2. Duties

The Transition Planner’s overall duties include, but are not limited to, those duties listed below:

1. Develop the overall Transition Plan (See Transition Timeline Restriction, NOTE 2, below.)

a. Develop an overall Master Schedule

b. Develop conceptual advance planning

c. Identify all occupancy milestones

d. Detail implementation plans and move sequencing, prepare and setup

e. Compile a manual of detailed move plans for every location

f. Create an orientation program to ensure that staff and occupants will be completely familiar with the new site

g. Establish a relocation execution plan

h. Develop a lessons learned and post-move clean-up plan

2. Support the IO-PM to ensure all the deliverables are completed and submitted appropriately as required.

NOTE 1: The IO Contractor shall plan his/her activities around the Construction Schedule, which will be provided by the DHA Project Officers. The IO Transition Planner shall ensure the key milestones and activities listed are incorporated into the project’s Master Construction Schedule and are routinely updated and distributed to all members of the PDT as things change.

3. Develop the IO Master Schedule: The Transition Planner shall develop an IO Master Schedule including, at a minimum, the Project Milestones, for the Walter Reed National Military Medical Center Temporary Building

a. General Contractor (GC) Construction Completion, including any early occupancy dates.

b. IO-T and IO-C Award Dates

c. Construction Durations

d. Outfitting Durations – For early occupancy and from Beneficial Occupancy Date

(BOD) to OFB dates

e. Final Acceptance – Government signing of DD250 (if required) after inspection of installed FF&E

4. Initial Outfitting – Transition (IO-T) Activities

a. IO-T User Interviews

b. IO-T Key Meetings (noted under Project Management section)

c. IO-T Review/Resolution Conferences

d. IO-T Submittal #1, Submittal #2 and Submittal #3 Dates

e. IO-T Review Periods

f. IO-C Negotiation Period

g. IO-C Award Date.

5. Initial Outfitting- Commodities (IO-C) Activities (for each phase).

a. Ensure the contractor maintains oversight and security of the work site until transition is complete.

b. Procurement Dates to include lead times for products and ordering dates

c. Transition periods (For new construction, the transition period is between the

Beneficial Occupancy Date (BOD) and the Open for Business (OFB) date.

d. Delivery Dates (for furnishings, equipment, etc.)

e. Dates that the IO Contractor needs to access certain locations to install existing/new items prior to BOD.

f. Move and installation date / period for existing commodities,

g. Installation date/period for new commodities, including low voltage systems

h. Move and installation date/period

i. Testing/certification dates of installed equipment

j. Last minute repair, modifications by on-site personnel to complete installation of new

/ reuse equipment

k. Acceptance dates for all furnishings and equipment.

l. Cleaning (all dates/periods for cleaning) of facility after installation of equipment and furnishings

m. O&M Manual delivery date to Walter Reed National Military Medical Center building manager through DHA.

n. Warehousing/storage period

o. IO Commodity Requirements

p. Reconfigure and reuse of existing commodities

q. Coordination for movement of items under contract by third party contractor (printers, copiers, etc.) NOTE: Reuse items with Lease and Maintenance agreement items: To prevent cancellation of warranties, IO Contractor shall not move reuse items for which a lease and maintenance agreement is in place. DHA/IO Contractor shall coordinate the move of these items with the reuse items’ lease and maintenance companies.

C. Transition Plan (by Department and Room)

The Transition Planner shall prepare a Transition Plan for the Walter Reed National Military Medical Center staff impacted by the project. This document is intended to be used primarily by the Walter Reed National Military Medical Center departments. It shall communicate key activities that will impact staff, patients and operations and shall be coordinated with the Construction Schedule for the WRNNMC Temporary building. The Transition Planner shall ensure the Transition Plan is routinely updated and distributed to the DHA Project Officers and USACE PM as things change.

The Transition Plan shall be developed for each floor of the Walter Reed National Military Medical Center affected by…