ProjNet_Q-A.pdf

PDF 89 KB Posted

Attached to
Preventative Maintenance for the 63D Army Reserve Regional Support Command Region 1
Solicitation number
W9127S-16-R-0020
Issued by

About this file

PROJNET Q A

View the file

Other files

File Type Posted
Sign-in-Sheet-R1_PM.pdf PDF
Amendment_0001.pdf PDF
63D_PM_Region_1_site_visit_slides.pptx PPTX presentation
Camp_Pike_Bldg__1_Map.pdf PDF
Wage_Determinations_-_R1_PM.pdf PDF
63RD_R1_FIS_PWS_9-MAR-2016.pdf PDF
ELINs_J-0200000-07_Region_1_-_22-FEB-2016.xlsx XLSX spreadsheet
Solicitation.pdf PDF
Map_63D_Regions_1-3.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNCLASSIFIED\\FOR OFFICIAL USE ONLY

Bid Inquiry Contractor Report All Inquiries

Project: 63rd Reserve Preventive Maintenance, Region 1 - AR/OK Review: RFP Reg 1 Prev Maintenance AR/OK (00001) (sorted by CommentID ) Displaying 6 inquiries.

Id Discipline Sheet Detail Spec 6476843 Contracting , , , Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

If these requirements are currently or have been being performed under a contract, who is the Contractor? What is the contract number? What is the value?

On: Apr 13 2016.

Government Response. . The preventive maintenance requirements are new ones to the USACE. This is a new requirement and not currently being performed under a government contract. On: Apr 14 2016 Current Request Status: Request Closed

Information for this report is procurement sensitive.

6477299 General 52.212-1 Attachment 2 - PPQ Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Will the Government accept CPARS reports for Corporate Experience projects/contracts in lieu of PPQs, IF, the project is completed

On: Apr 13 2016.

Government Response. . No the CPARS is not an acceptable replacement. On: Apr 18 2016 Current Request Status: Request Closed

Information for this report is procurement sensitive.

6477303 General 52.213-3, 52.209-7 Rep & Certs Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Where are these to be included In Price or Non Price Volume?

On: Apr 13 2016.

Government Response. . Non Price Volume On: Apr 18 2016 Current Request Status: Request Closed

Information for this report is procurement sensitive.

6477307 General Annex 0200000 Mgmt & Admin Spec Item 2.7.1 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Are the key personnel required to be on site or may they located at a regional office?

On: Apr 13 2016.

Government Response. . Key personnel may be located at a regional office. On: Apr 14 2016 Current Request Status: Request Closed

Information for this report is procurement sensitive.

6477308 General Annex 0200000 Mgmt & Admin Spec Item 2.6.1 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Is it required that Work Control be on site or may it be at an off site work order center?

On: Apr 13 2016.

Government Response. . Work Control may be located at an off-site call in center. On: Apr 14 2016 Current Request Status: Request Closed

Page 1 of 2ProjNet: Logged In User

5/6/2016https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicPublicReportAll...

Information for this report is procurement sensitive.

6477314 General 52.212-2 Factor 2 Evaluation Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Can you please elaborate the use of "each criterion...each service" on the following statement under 52.212-2 Evaluation, Section B. Evaluation Approach, Factor 2, Understanding of the work. It appears this is the only reference.

"To meet any single criterion listed for Factor 2, Offeror's must address EACH CRITERION as it pertains to EACH SERVICE (HVAC, electrical, plumbing, carpentry, painting, paving (of potholes), miscellaneous mechanical work and associated operation and maintenance activities)".

On: Apr 13 2016.

Government Response. . Each service (HVAC, electrical, plumbing, etc.) shall be reflected in the narrative minimum requirements (service calls, start up, PM program, Inspection/Testing/Certification, IDIQ and descriptions (a) through (g). On: Apr 18 2016 Current Request Status: Request Closed

Information for this report is procurement sensitive.

Report Complete

UNCLASSIFIED\\FOR OFFICIAL USE ONLY

Patent 11/892,984 ProjNet property of ERDC since 2004.

Page 2 of 2ProjNet: Logged In User

5/6/2016https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicPublicReportAll...