Amendment 02.pdf

PDF 560 KB Posted

Attached to
OR/WA Clamshell Maintenance Dredging 2022
Solicitation number
W9127N22B0011
Issued by

About this file

This amendment modifies a solicitation for maintenance dredging services along the Columbia River in Oregon and Washington. The amendment updates the plans and specifications to reflect additional dredging work at the Wahkiakum Ferry Crossing. It adds line items for dredging and placement of materials at the Wahkiakum Ferry Crossing location, priced at firm fixed price. Inspection and acceptance will take place upon delivery to the destination point by the Government. The amendment also modifies the commencement, prosecution, and completion dates to require work to begin by June 1, 2022, prosecute diligently, and achieve final completion by December 15, 2022.

View the file

Other files

File Type Posted
C.04 Abstract.pdf PDF
OWCMD22_AMD.pdf PDF
OWCMD22_AMD_Plans.pdf PDF
Amendment 01.pdf PDF
Amend_001_Add_Wahkiakum_Ferry_Crossing.pdf PDF
22B0011-OR-WA_Clamshell_2022_Adv_Plans.pdf PDF
OWCMD22_ADV.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to:

Update the plans and specifications to reflect the updated dredging w ork at Wahkiakum Ferry Crossing along the Columbia River in Westport, Oregon and Cathlamet, Washington.

Point of contact for this amendment is: Kris Morrow (kristina.k.morrow @usace.army.mil)

1. CONTRACT ID CODE PAGE OF PAGES

1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 02-Jun-2022

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9127N22B0011

X 9B. DATED (SEE ITEM 11)

03-May-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

02-Jun-2022

CODE

USACE, PORTLAND DISTRICT

333 SW 1ST AVE

PORTLAND OR 97204

W9127N 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9127N22B0011

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 10 00 - SOLICITATION

CLIN 0009 is added as follows:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Dredging Wahkiakum Ferry Crossing

FFP

Dredging and Placement of Materials: Wahkiakum Ferry Crossing.

NET AMT

SUBCLIN 0009AA is added as follows:

0009AA 7,000 Cubic

Yard

First 7,000 Cubic Yards

Dredging and placement of materials: Wahkiakum Ferry Crossing, first 7,000 yards FOB: Destination

PSC CD: Y1KF

SUBCLIN 0009AB is added as follows:

0009AB 5,000 Cubic

Yard

Above 7,000 Cubic Yards

Dredging and placement of materials: Wahkiakum Ferry Crossing, above 7,000 yards FOB: Destination

PSC CD: Y1KF

SECTION 00 70 00 - CONDITIONS OF THE CONTRACT

The following Acceptance/Inspection Schedule was added for CLIN 0009:

INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

N/A N/A N/A N/A

The following Acceptance/Inspection Schedule was added for SUBCLIN 0009AA:

Destination Government Destination Government

The following Acceptance/Inspection Schedule was added for SUBCLIN 0009AB:

Destination Government Destination Government

SECTION 00 72 00 - GENERAL CONDITIONS

The following have been modified:

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to commence work under this contract as follows, after receiving Notice to Proceed:

(a) Commence work at Port Orford no earlier than 1 June 2022,

(b) prosecute the work diligently, and

(c) Complete all work ready for use prior to the FINAL CONSTRUCTION PHYSICAL COMPLETION DATE.

FINAL CONSTRUCTION PHYSICAL COMPLETION DATE: 15 December 2022 The time stated for FINAL CONSTRUCTION PHYSICAL COMPLETION includes physical completion of all site work, site cleanup, and demobilization.

CONTRACT END DATE: 90 days after FINAL CONSTRUCTION PHYSICAL COMPLETION DATE The time stated for CONTRACT END DATE includes submission and approval of all final remaining work documents.

The Government intends to issue NTP on or around 18 July 2022, or within 7 days of award and receipt of bonds.

NOTES: *Definition: Commence work means having dredge on site and ready to dredge

(End of clause)

(End of Summary of Changes)

File details come from the government source that posted it. Updated .