AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
PROJECT TITLE: John Day Avian Array Improvements Phase II
The purpose of this modification is to:
1. Technical specification section 01 11 00.00 25 Paragraph 1.6 has been updated.
2. All other terms and conditions remain unchanged.
POC: Brandon Lasich Email: brandon.m.lasich@usace.army.mil
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 18-Aug-2017
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9127N-17-R-0066
X 9B. DATED (SEE ITEM 11)
28-Jul-2017
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
18-Aug-2017
CODE
USACE PORTLAND DISTRICT
333 SW 1ST AVE
PORTLAND OR 97204-3440
W9127N 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W9127N-17-R-0066
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
(End of Summary of Changes)
John Day Avian Array Improvements - Phase II
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 10 00.00 25 CONTRACT ADMINISTRATION DATA
01 10 10.00 25 CONTRACTOR'S OPERATIONS AND REQUIREMENTS
01 11 00.00 25 SUMMARY OF WORK
01 22 00.00 25 MEASUREMENT AND PAYMENT
01 32 01.00 25 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 26.00 25 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 25 QUALITY CONTROL
01 45 00.15 25 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 57 19.00 25 TEMPORARY ENVIRONMENTAL CONTROLS
01 78 23.00 25 OPERATION AND MAINTENANCE DATA
01 78 39.00 25 PROJECT RECORD DOCUMENTS
DIVISION 05 - METALS
05 50 14.00 25 STRUCTURAL METAL FABRICATIONS
DIVISION 13 - SPECIAL CONSTRUCTION
13 10 11.00 25 SYNTHETIC AVIAN LINE AND RIGGING COMPONENTS
DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT
41 22 23.00 25 WINCH AND SHEAVE ASSEMBLY
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00.00 25
SUMMARY OF WORK
PART 1 GENERAL
1.1 SUMMARY
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
1.2.2 Location
1.3 CONTRACT DRAWINGS
1.4 OCCUPANCY OF PREMISES
1.5 EXISTING WORK
1.6 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
-- End of Section Table of Contents --
SECTION 01 11 00.00 25 Page 1
SECTION 01 11 00.00 25
SUMMARY OF WORK
PART 1 GENERAL
1.1 SUMMARY
This Section provides a summary of the various Contract work elements and their relationship to each other. This summary describes work activities within interim construction completion date. This Section does not provide the technical detail for particular work activities, but describes the work as a whole, providing overall perspective to the separate tasks and their interrelationships. Use this Section in conjunction with all the Specification Sections and the Drawings to establish the total work requirements.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
The work includes modifications of the existing Avian Array at John Day Lock and Dam. Modifications include, but not limited to: replacement of avian lines along the Peninsula, Navigation Lock, Spillway, and Powerhouse, installation of winches and sheaves along the spillway, installation of wire rope slings at anchor points, and incidental related work. This effort is to include all associated works required and described within this Contract package.
1.2.2 Location
The work site is located at John Day Lock and Dam. Contractor access to the work site will be from I-84 in Rufus, Oregon.
1.3 CONTRACT DRAWINGS
a. The Drawings that accompany these Specifications are a part thereof.
b. Contract drawings, maps, and Specifications will be furnished to the Contractor without charge per Section 00700 Contract Clause 252.236-7001, CONTRACT DRAWINGS AND SPECIFICATIONS. Reference publications will not be furnished.
c. Immediately check furnished drawings, maps, and specifications and notify the Government of any discrepancies.
1.4 OCCUPANCY OF PREMISES
a.Building(s) will be occupied during performance of work under this Contract.
b. Before work is started, the Contractor must arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.
SECTION 01 11 00.00 25 Page 2
1.5 EXISTING WORK
In addition to Section 00700 Contract Clause 52.236-9, PROTECTION OF
EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS:
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portion of the existing work to remain.
b. Upon completion of the work, repair or replace portions of existing work, which have been damaged by Contractor's operations, to preconstruction conditions at the expense of the Contractor.
1.6 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT
Pursuant to Contract Clause 52.245-1, GOVERNMENT PROPERTY, the Government will furnish unspliced Vectran rope for the following lines to install by the Contractor. Refer to the drawing packet for location and termination configuration per line number:
LINE NO. ROPE DIAMETER FACTORY CUT LENGTH
4 3/16" 2800 Ft
5 3/16" 2800 ft
6 3/16" 2800 ft
7 3/16" 2800 ft
8 3/16" 2800 ft
9 3/16" 2800 ft
10 3/16" 2800 ft
11 3/16" 2800 ft
12 3/16" 2800 ft
13 3/16" 2800 ft
14 3/16" 2800 ft
15 3/16" 2800 ft
16 3/16" 2800 ft
17 3/16" 2800 ft
18 3/16" 2800 ft
19 3/16" 2800 ft
20 3/16" 2800 ft
21 3/16" 2900 ft
22 3/16" 2900 ft
SECTION 01 11 00.00 25 Page 3
LINE NO. ROPE DIAMETER FACTORY CUT LENGTH
23 3/16" 2900 ft
24 3/16" 2900 ft
25 3/16" 2900 ft
26 3/16" 2900 ft
27 3/16" 2900 ft
28 3/16" 2900 ft
29 3/16" 2900 ft
30 3/16" 2900 ft
31 3/16" 2900 ft
32 3/16" 2900 ft
33 3/16" 2900 ft
34 3/16" 2900 ft
35 3/16" 3000 ft
36 3/16" 3000 ft
37 3/16" 3000 ft
38 3/16" 3000 ft
40 3/16" 3000 ft
41 3/16" 3100 ft
42 3/16" 3100 ft
47 3/16" 3200 ft
49 3/16" 3200 ft
50 3/16" 3300 ft
51 3/16" 3300 ft
61 3/16" 3450 ft
62 3/16" 3450 ft
63 3/16" 3350 ft
64 3/16" 3350 ft
65 3/16" 3250 ft
66 3/16" 3250 ft
SECTION 01 11 00.00 25 Page 4
67 3/16" 3150 ft
68 3/16" 3150 ft
69 3/16" 3050 ft
70 3/16" 2950 ft
71 3/16" 2950 ft
72 3/16" 2850 ft
73 3/16" 2850 ft
74 3/16" 2750 ft
75 3/16" 2750 ft
76 3/16" 2750 ft
77 3/16" 2650 ft
78 3/16" 2650 ft
79 3/16" 2650 ft
80 7/64" 2500 ft
81 7/64" 2400 ft
82 7/64" 2200 ft
83 7/64" 2200 ft
84 7/64" 2200 ft
85 7/64" 2200 ft
86 7/64" 2200 ft
87 7/64" 2100 ft
88 7/64" 2100 ft
89 7/64" 2100 ft
90 7/64" 2100 ft
91 7/64" 2100 ft
92 7/64" 2000 ft
93 7/64" 2000 ft
94 7/64" 2000 ft
95 7/64" 2000 ft
SECTION 01 11 00.00 25 Page 5
96 7/64" 2000 ft
97 7/64" 2000 ft
98 7/64" 1900 ft
99 7/64" 1900 ft
100 7/64" 1900 ft
101 7/64" 1900 ft
102 7/64" 1900 ft
103 7/64" 1900 ft
104 7/64" 1900 ft
105 7/64" 1900 ft
106 7/64" 1800 ft
107 7/64" 1800 ft
108 7/64" 1800 ft
109 7/64" 1800 ft
110 7/64" 1700 ft
111 7/64" 1700 ft
112 7/64" 1700 ft
113 7/64" 1700 ft
114 7/64" 1700 ft
115 7/64" 1700 ft
116 7/64" 1700 ft
117 7/64" 1700 ft
118 7/64" 1600 ft
119 7/64" 1600 ft
120 7/64" 1600 ft
121 7/64" 1600 ft
122 7/64" 1600 ft
123 7/64" 1600 ft
124 7/64" 1700 ft
SECTION 01 11 00.00 25 Page 6
125 7/64" 1700 ft
126 7/64" 1700 ft
127 7/64" 1700 ft
128 7/64" 1700 ft
a. Quantities indicated for the above-listed items marked with an asterisk are estimates. It is the intention of the Government to furnish all quantities of the asterisk items required to complete the work as specified and the various quantities will be adjusted when necessary.
b. Quantities stated for the above items not marked with an asterisk are all that will be furnished by the Government. Contractor must furnish any additional quantities required.
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
-- End of Section --
SECTION 01 11 00.00 25 Page 7
| Technical_Sections.pdf |
| PROJECT TABLE OF CONTENTS |
| DIVISION 01 - GENERAL REQUIREMENTS |
| 01 11 00.00 25 - SUMMARY OF WORK |
| 01 11 00.00 25 - SUMMARY OF WORK |
| PART 1 GENERAL |
| 1.1 SUMMARY |
| 1.2 WORK COVERED BY CONTRACT DOCUMENTS |
| 1.2.1 Project Description |
| 1.2.2 Location |
| 1.3 CONTRACT DRAWINGS |
| 1.4 OCCUPANCY OF PREMISES |
| 1.5 EXISTING WORK |
| 1.6 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT |
| PART 2 PRODUCTS - NOT USED |
| PART 3 EXECUTION - NOT USED |
| [1]: [1] |
| Amd0001: AMD #0001 |
File details come from the government source that posted it. Updated .