AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

As an amendment to the solicitation, the follow ing changes are made:

1. Section 01 22 00.00 82 Measurement and Payment 3.3.2 b (NOTE) is updated. The attached revised specification is incorporated in full and replaces the previous version in its entirety.

1. CONTRACT ID CODE PAGE OF PAGES

1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 11-Sep-2017

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9127N17B0021

X 9B. DATED (SEE ITEM 11)

05-Sep-2017

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

11-Sep-2017

CODE

USACE PORTLAND DISTRICT

333 SW 1ST AVE

PORTLAND OR 97204-3440

W9127N 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9127N17B0021

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

(End of Summary of Changes)

Columbia River Side Channels Clamshell Dredging 2018

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 10 00.00 82 CONTRACT ADMINISTRATION DATA (DREDGING)

01 10 10.00 82 CONTRACTOR'S OPERATIONS AND REQUIREMENTS (DREDGING)

01 22 00.00 82 MEASUREMENT AND PAYMENT

01 35 26.00 82 GOVERNMENTAL SAFETY REQUIREMENTS (DREDGING)

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 82 QUALITY CONTROL (DREDGING)

01 45 00.15 25 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 57 20.00 82 ENVIRONMENTAL PROTECTION (DREDGING)

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION

35 20 23.00 82 DREDGING AND CHANNEL CLEARING

35 20 23.13 82 NATIONAL DREDGING QUALITY MANAGEMENT PROGRAM SCOW -

MONITORING PROFILE

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00.00 82

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 REFERENCES

1.2 GENERAL INFORMATION

1.3 UNIT PRICE PAYMENT ITEMS

1.4 JOB PAYMENT ITEMS

1.5 APPLICABLE REGULATIONS

1.5.1 Variations In Estimated Quantities - SUBDIVIDED ITEMS

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.1 MEASUREMENT AND PAYMENT

3.1.1 Mobilization and Demobilization, CLIN 0001

3.1.2 Dredging and Placement of Materials; Wahkiakum Ferry Crossing, CLIN 0002

3.1.3 Incremental Mobilization to Longview Turning Basin, (Option)

CLIN 0003

3.1.4 Dredging and Placement of Materials; Longview Turning Basin, (Option) CLIN 0004

3.2 SUBMISSION OF INVOICES FOR PAYMENT

3.3 PAYMENT METHOD

3.3.1 Pre/Post Dredge Survey

3.3.2 Quantity Surveys

-- End of Section Table of Contents --

SECTION 01 22 00.00 82 Page 1 limits are equal to or deeper than the required channel depth.

3.3.2 Quantity Surveys

a. Wahkiakum Ferry Crossing: The Government will determine cubic yard quantities for payment and acceptance by utilizing electronic depth sounding and horizontal positioning equipment. Sounding depths used for determination of pay quantity volumes will generally be derived from surveys utilizing 208 kHz single-beam acoustic methods. For computations of pay volumes, survey lines will be run cross channel every thirty feet. Volumes will be calculated using the all file.

b. Longview Turning Basin: The Government will determine cubic yard quantities for payment and acceptance by utilizing electronic depth sounding and horizontal positioning equipment. Sounding depths used for determination of pay quantity volumes will be derived from surveys utilizing multi-beam methods with HYPACK's Advanced Channel Design for volume calculations. For computations of pay volumes, multi-beam survey data will be processed using a median depth sort with a 5 by 5 foot Matrix.

NOTE: Due to unexpected ship traffic at the dock in the Longview Turning Basin work area the Government may be required to run multiple surveys in order to gather all needed data for pre-dredge and post-dredge surveys of the area. Once all data has been collected the survey data will be compiled into one data set. The data sets will be compared before compiling and overlapping validated data would be edited to bias towards the sounding that would result in the calculated volume computations to be the greatest possible value (Ex: default to a shallower sounding on the compiled pre-dredge survey and default to a deeper sounding on the post-dredge survey.)

c. As required, data from land surveys will be obtained and incorporated into the volume computation.

d. The dredging pay area is defined by intersection of the maximum dredging pay depth and the dredging pay slope. The number of cubic yards calculated as being payable will be the difference between the most recent pre-dredge and post-dredge surveys of the dredging pay area or applicable acceptance area. Any material removed from outside the maximum dredging prism will not be considered for payment.

e. Accuracy(ies) will be in accordance with stated quality control values in EM-1110-2-1003. Upon request, the Government will provide the survey line files by which surveys are run.

f. Government Equipment: The following survey equipment will be used by the Government Survey Crew during the collection of sounding data and will be considered the standard for which data is obtained:

Positioning: Applanix Wavemaster or Applanix POS MV 4 Multibeam: RESON T-50 MB Singlebeam: ODOM CV100 ECHOSOUNDER with an 3 degree 200khz transducer AML Velocity Probe AML Sound Velocity Profiler

Note: The Government will be available by request to run check

SECTION 01 22 00.00 82 Page 5

RELEASED 17B0021 Amd 0001
Technical_Sections
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 22 00.00 82 - MEASUREMENT AND PAYMENT
01 22 00.00 82 - MEASUREMENT AND PAYMENT
PART 3 EXECUTION
3.3 PAYMENT METHOD
3.3.2 Quantity Surveys