Attachment-1_LOP-Specs.pdf
PDF 449 KB Posted
- Attached to
- Lookout Point Turbine Unit Brake Replacement
- Solicitation number
- W9127N-16-R-0051
About this file
Specifications for Lookout Point Turbine Unit Brake Replacement
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W9127N-16-R-0051-02.pdf | ||
| W9127N-16-R-0051-01.pdf | ||
| A-1_Attach-4_LOP_Brake_Ring_Drawing_Redacted.pdf | ||
| A-1_Attach-3_LP-4904-44.tif | TIF image | |
| W9127N-16-R-0051.pdf | ||
| Attachment-2_LOP-Brake_Drawings.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Lookout Point Turbine Unit Brake Replacement
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 13.00 25 GENERAL CONTRACT REQUIREMENTS
01 33 00 SUBMITTAL PROCEDURES
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
DIVISION 05 - METALS
05 05 23.20 26 WELDING
05 05 33.20 26 NON-DESTRUCTIVE TESTING
DIVISION 09 - FINISHES
09 97 02.00 25 PAINTING
DIVISION 22 - PLUMBING
22 00 00.00 26 MECHANICAL EQUIPMENT AND PIPING
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 13.00 25
GENERAL CONTRACT REQUIREMENTS
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 CONTRACTOR'S OPERATIONS AND REQUIREMENTS
1.3.1 Schedule for Delivery
1.4 SUMMARY OF WORK
1.4.1 Project Description
1.4.2 Location
1.5 MEASUREMENT AND PAYMENT
1.5.1 Unit Price Payment Items
1.5.2 Job Payment Items
1.5.3 Fabrication and Delivery of Brakes, CLIN 0001
1.6 GOVERNMENTAL SAFETY REQUIREMENTS
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
-- End of Section Table of Contents --
SECTION 01 11 13.00 25 Page 1
SECTION 01 11 13.00 25
GENERAL CONTRACT REQUIREMENTS
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 241 (2013) Standard for Safeguarding Construction,Alteration, and Demolition Operations
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. The following must be submitted in accordance with Section 01 33 00, SUBMITTAL
PROCEDURES:
SD-01 Pre-Work Submittals
Schedule for Delivery; G
1.3 CONTRACTOR'S OPERATIONS AND REQUIREMENTS
1.3.1 Schedule for Delivery
Submit delivery schedule for Government approval in accordance with Contract Technical Specification Reference Information: Schedule. The schedule must be consistent with the completion dates as specified in Contract Clause 52.211-8, Time of Delivery. The schedule will be used as a basis to evaluate the Contractor's progress for purposes of payment.
1.4 SUMMARY OF WORK
1.4.1 Project Description
This Section provides a summary of the various Contract work elements and their relationship to each other. This summary describes work activities within a completion date. This Section does not provide the technical detail for particular work activities, but describes the work as a whole, providing overall perspective to the separate tasks and their interrelationships. Use this Section in conjunction with all the Specification Sections and the Drawings to establish the total work requirements.
SECTION 01 11 13.00 25 Page 2
1.4.2 Location
The work shall be located at Lookout Point Dam. Contractor access to the work site will be from W Boundry Road, north of the powerhouse.
1.5 MEASUREMENT AND PAYMENT
a. In each instance, the Contract price for an item will constitute full compensation as herein specified, as shown, or as otherwise approved. The Contract price and payment will also constitute full compensation for all work incidental to completion of the item, unless such work is otherwise specifically mentioned for separate payment under another line item. In the event any work is required by the specifications Sections or by the Drawings and not specifically mentioned in the measurement and payment paragraphs, separate or direct payment will not be made and all costs thereof are incidental to the work and included in the Contract prices and payments for all Contract Line Item Numbers (CLIN) listed in the price schedule.
b. As stated in Contract Technical Specification Reference Information:
Specifications and Drawings, the word "provided" shall be understood to mean "furnished and installed" when used in this Section or elsewhere in the Specifications Sections.
1.5.1 Unit Price Payment Items
Payment items for the work of this Contract on which the Contract unit price payments will be made are listed in the PRICE SCHEDULE, and described below. The unit price and payment made for each item listed will constitute full compensation for furnishing all plant, labor, materials, and equipment; performing all associated Contractor quality control, environmental protection, commissioning, tests and reports, meeting safety requirements; and for performing all work required for each of the unit price items.
1.5.2 Job Payment Items
Payment items for the work of this Contract for which Contract job payments will be made are listed in the PRICE SCHEDULE, and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job item, must be included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed will constitute full compensation for furnishing all plant, labor, materials, and equipment; performing all associated Contractor quality control, environmental protection, commissioning, tests and reports, meeting safety requirements; and for performing all work required for which separate payment is not otherwise provided. A schedule of values for job items must be provided with each payment request.
MANDATORY ITEMS
1.5.3 Fabrication and Delivery of Brakes, CLIN 0001
a. Measurement: Measurement will be made as a job for brake delivery to the designated layout area, including all effort and cost incurred by the Contractor for fabrication, delivery to the job site, off-loading in designated area, and meeting safety requirements.
b. Payment: Payment will be made at the Contract amount under CLIN
SECTION 01 11 13.00 25 Page 3
0001 as a job. The unit price and payment made for each item listed must constitute full compensation for furnishing all plant, labor, materials and equipment, and performing any associated Contractor quality control, meeting safety requirements, and for performing all work required for each of the unit price items.
1.6 GOVERNMENTAL SAFETY REQUIREMENTS
Comply with EM 385-1-1, NFPA 241, the APP, the AHA, Federal and/or State OSHA regulations, and other related submittals and activity fire and safety regulations in accordance with to Section 01 35 25.00 25, GOVERNMENTAL SAFETY REQUIREMENTS. The most stringent standard must prevail.
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
-- End of Section --
SECTION 01 11 13.00 25 Page 4
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 GENERAL INFORMATION
1.2 SUBMITTALS
1.3 DEFINITIONS
1.3.1 Submittal Descriptions (SD)
1.3.2 Approving Authority
1.3.3 Work
1.4 SUBMITTAL DESIGNATION
1.5 SUBMITTAL REGISTER
1.5.1 Maintain Submittal Register
1.5.2 Use of Submittal Register
1.5.3 Government Approval Submittals
1.5.3.1 Quantity of Submittals
1.5.3.2 Processing of "G" Submittals.
1.5.4 Information Only Submittals
1.5.4.1 General
1.5.4.2 Processing of Information Only Submittals
1.6 SUBMITTAL COORDINATION
1.6.1 Submittal Coordination Meeting
1.6.2 Submittal Register ENG Form 4288-R
1.6.3 Submittal Register Updates
1.7 SCHEDULING
1.8 TRANSMITTAL FORM (ENG FORM 4025-R)
1.9 CROSS-REFERENCE (ENG FORM 4288-R/ENG FORM 4025-R)
1.10 SUBMITTAL PROCEDURES
1.10.1 e-Submittals
1.10.2 Approval of Submittals by the Contractor
1.10.3 Drawings
1.10.3.1 Printed Material
1.11 PURCHASE ORDERS
1.12 CERTIFICATES OF COMPLIANCE
1.13 DISAPPROVED SUBMITTALS
1.14 APPROVED SUBMITTALS
1.15 APPROVED SAMPLES
1.16 CONTRACTOR'S FILES
1.17 PAYMENT
1.18 WITHHOLDING OF PAYMENT
1.19 CONTRACTOR APPROVAL STAMP
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
SECTION 01 33 00 Page 1
SECTION 01 33 00 Page 2
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 GENERAL INFORMATION
a. Contract Technical Specification Reference Information: Materials and Workmanship, and Specifications and Drawings, apply to all submittals.
b. Make submittals as required by the Specifications. The Contracting Officer (CO) may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective Sections.
c. Use the same units of weights and measures on all submittals as those used in the Contract Drawings.
d. Each submittal must be complete and in sufficient detail to allow ready determination of compliance with Contract requirements.
e. The Contractor's Quality Control (CQC) System Manager must check and approve all items prior to submittal and stamp, sign, and date indicating action taken. Proposed deviations from the Contract requirements must be clearly identified. Submittals must include items such as: Contractor's, manufacturer's, or fabricator's drawings;
descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders;
samples; O&M manuals (including parts list); certifications;
warranties; and other such required submittals.
f. Submittals requiring Government approval must be scheduled and approved prior to the acquisition of the material or equipment covered thereby.
g. Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Safety Data Sheets (SDS) and in compliance with existing laws and regulations.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. Submit the following in accordance with this Section:
SD-01 Pre-Work Submittals
Submittal Register; G
SD-07 Certificates
Authorized Shop Drawing Approvers
SECTION 01 33 00 Page 3
1.3 DEFINITIONS
1.3.1 Submittal Descriptions (SD)
Submittal requirements are specified in the technical Sections and in the preliminary submittal register (ENG Form 4288-R, Attachment A1).
Submittals are identified by Submittal Description (SD) numbers and titles as follows:
SD-01 Pre-Work Submittals
Submittals required prior to start of work. Includes, but not limited to: schedules, tabular list of data, or tabular list including location, features, or other pertinent information regarding products, materials, equipment, or components to be used in the work.
Certificates of insurance.
Surety bonds.
List of proposed subcontractors.
List of proposed products.
Work Progress Schedule.
Submittal register.
Schedule of prices.
Health and safety plans.
Work plan.
Contractor Quality Control (CQC) plan.
Environmental Protection plan.
SD-02 Shop Drawings
Drawings, diagrams, and schedules specifically prepared to illustrate some portion of the work.
Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.
Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.
SD-03 Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance, and other characteristics of materials, systems, or equipment for some portion of the work.
Warranty language when the Contract requires extended product warranties.
SECTION 01 33 00 Page 4
SD-05 Design Data
Design calculations, mix designs, analyses, or other data pertaining to a part of work.
SD-06 Test Reports
Report signed by authorized official of testing laboratory that a material, product, or system identical to the material, product, or system to be provided has been tested in accordance with specified requirements. (Testing must have been within three years of date of Contract award for the project.)
Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.
Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
Investigation reports.
Daily logs and checklists.
Final acceptance test and operational test procedure.
Any reports required by the CO or designated representative to assure successful completion of tasks during the life of the Contract.
SD-07 Certificates
Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system, or material attesting that product, system, or material meets specification requirements. must be dated after award of project Contract and clearly name the project.
Document required of Contractor, or of a manufacturer, supplier, installer, or subcontractor through Contractor, the purpose of which is to further quality of orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.
Confined space entry permits.
Text of posted operating instructions.
SD-08 Manufacturer's Instructions
Preprinted material describing installation of a product, system, or material, including special notices and SDS concerning impedances, hazards, and safety precautions.
1.3.2 Approving Authority
Office or designated person authorized to approve submittal.
SECTION 01 33 00 Page 5
1.3.3 Work
As used in this Section, on- and off-site work required by Contract documents, including labor necessary to produce submittals (except those SD-01 Pre-Work Submittals noted above), materials, products, equipment, and systems incorporated or to be incorporated in such work.
1.4 SUBMITTAL DESIGNATION
Submittals are classified as follows:
a. Government Approved (G). Within the terms of the Contract Technical Specification Reference Information: Specifications and Drawings, they are considered to be "shop drawings."
b. Information Only. Submittals not requiring Government approval will be for information only. Within the terms of the Contract Technical Specification Reference Information: Specifications and Drawings, these submittals are not considered to be "shop drawings."
1.5 SUBMITTAL REGISTER
1.5.1 Maintain Submittal Register
a. Prepare and maintain Submittal Register, ENG Form 4288-R, , as the work progresses. Do not change data which is output in columns (c), (d), (e), and (f) as delivered by Government; retain data which is output in columns (a), (g), (h), and (i) as approved. This list may not be all inclusive and additional submittals may be required.
b. The Government will provide the preliminary submittal register in electronic format with the following fields completed, to the extent that will be required by the Government during subsequent usage.
(1) Column (c): Lists Specification Section in which submittal is required.
(2) Column (d): Lists each submittal description (SD No. and type, e.g. SD-02 Shop Drawings) required in each Specification Section.
(3) Column (e): Lists one principal paragraph in Specification Section where a material or product is specified. This listing is only to facilitate locating submitted requirements. Do not consider entries in column (e) as limiting project requirements.
c. Thereafter, track all submittals by maintaining a complete list, including completion of all data columns, including dates on which submittals are received and returned by the Government.
1.5.2 Use of Submittal Register
Submit submittal register with project schedule and QC plan. Verify that all submittals required for work are listed and add missing submittals.
Coordinate, update, and complete the fields on the submitted register with the project schedule.
SECTION 01 33 00 Page 6
1.5.3 Government Approval Submittals
1.5.3.1 Quantity of Submittals
SD-01, SD-02, SD-03, and SD-05 through SD-11 submittals: Upload submittals with corresponding ENG 4025-R transmittal forms (Attachment A2) as outlined in paragraph entitled e-Submittals. SD-04 submittals: Submit two samples of "G" submittals with two corresponding ENG 4025-R transmittal forms, unless otherwise specified. Upon completion of review, "G" submittal copies will be marked with an action code, dated, electronically signed, and electronically returned to the Contractor as specified below:
1.5.3.2 Processing of "G" Submittals.
a. Submittals will be reviewed and processed as follows:
(1) Approved as Submitted (Action Code "A"): Submittals which can be approved without correction will be stamped "Approved" and returned electronically to the Contractor.
(2) Approved, Except as Noted on Drawings (Action Code "B"):
Submittals which have only minor discrepancies will be annotated in red to indicate necessary corrections. Marked material will be stamped "Approved Except as Noted" and returned electronically to the Contractor for correction.
(3) Approved, Except as Noted on Drawings, Resubmission Required (Action Code "C"): Submittals which are incomplete or require more than minor corrections will be annotated in red to indicate necessary corrections. Marked material will be stamped "Approved Except as Noted - Resubmission Required" and returned electronically to the Contractor for correction. Resubmittal of only those items needing correction required.
(4) Will be Returned by Separate Correspondence (Action Code "D"): Submittals will be addressed by Serial Letter and the Contractor must respond according to instructions in the letter.
(5) Disapproved (Action Code "E"): Submittals which are fundamentally in error, cover wrong equipment or work, or require extensive corrections, will be returned to the Contractor stamped "Disapproved." Submittal will be returned electronicallyto the Contractor and an explanation will be furnished on the submitted material or on ENG Form 4025-R indicating reason for disapproval.
Complete resubmittal required.
(6) Receipt Acknowledged (Action Code "F"): Submittals stamped "Receipt Acknowledged" are complete and returned electronically to the Contractor.
(7) Other (Specify) (Action Code "G"): Submittals requiring other specific action will be stamped "Other (Specify)" and returned with a description in the Remarks section. Submittal will be returned electronically to the Contractor. Resubmittal of only those items needing correction required.
(8) Receipt Acknowledged, Does Not Comply (Action Code "X"):
Submittals which have been received but do not comply with Contract requirements. Submittal will be returned electronically
SECTION 01 33 00 Page 7 to the Contractor stamped "Receipt Acknowledged, Does Not Comply" and an explanation will be furnished. Corrective action and resubmittal required.
b. Resubmittal will not be required for approved submittals unless subsequent changes are made by Contractor or by Contract modification.
For submittals required to be resubmitted, make corrections required, note any changes by dating the revisions to correspond with the change request date, and promptly resubmit the corrected material.
Resubmittals must be associated with the "parent" by use of sequential numbers (for example, resubmittal of transmittal 8 will be 8.1, 8.2, etc). Government costs incurred after the first resubmittal may be charged to the Contractor.
1.5.4 Information Only Submittals
1.5.4.1 General
Upload submittal with corresponding ENG 4025 forms as outlined in paragraph entitled e-Submittals. Normally information only submittals will not be returned. Government approval is not required on information only submittals. These submittals will be used for information purposes. The Government reserves the right to require the Contractor to resubmit any item found not to comply with the Contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the CO from requiring removal and replacement of nonconforming material incorporated in the work; and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.
1.5.4.2 Processing of Information Only Submittals
Submit information only submittals electronically prior to delivery of the material or equipment to the job site. ENG Form 4025-R must be marked with the words "Contractor approved - information copy only" in the REMARKS block of the form. Submittals will be monitored and spot checks made.
When such checks indicate noncompliance, the Contractor will be notified by the same method used for Government Approval submittals. Resubmittal of nonconforming information only submittals must be reclassified Government Approval ("G") and re-submitted electronically for approval.
1.6 SUBMITTAL COORDINATION
1.6.1 Submittal Coordination Meeting
Meet with the CO, after the pre-work conference and before any submittals are sent to the CO, to further develop the preliminary submittal register (ENG Form 4288-R). During the meeting identify and group all required items into the categories as shown in paragraph entitled SUBMITTAL
DESIGNATION.
1.6.2 Submittal Register ENG Form 4288-R
Coordinate the submittal register with the progress schedule and submit within 15 days of Notice to Proceed. In preparing the final document, allow a minimum of 21 days for review and approval, and possible resubmittal of each item on the register.
SECTION 01 33 00 Page 8
1.6.3 Submittal Register Updates
The CQC System Manager must review the listing at least every 30 days and take appropriate action to maintain an effective system. Submit copies of updated or corrected listings to the CO at least every 30 days in the quantity specified.
1.7 SCHEDULING
Schedule and submit concurrently submittals covering component items forming a system or items that are interrelated. Adequate time (a minimum of 10 calendar days) must be allowed and shown on the register for Government review and approval. No delay damages or time extensions will be allowed for time lost in late submittals.
a. Coordinate scheduling, sequencing, preparing, and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow for potential resubmittal of requirements.
b. Submittals called for by the Contract documents must be listed on the register. Approval by the CO does not relieve the Contractor of supplying submittals required by the Contract documents but which have been omitted from the register.
c. Re-submit register and annotate monthly with actual submission and approval dates. When all items on the register have been fully approved, no further re-submittal is required.
d. Carefully control procurement operations to ensure that each individual submittal is made on or before the Contractor scheduled submittal date shown on the approved "Submittal Register."
1.8 TRANSMITTAL FORM (ENG FORM 4025-R)
Use the sample transmittal form (ENG Form 4025-R, Attachment A2) for submitting both Government Approval and Information Only submittals in accordance with the instructions on the reverse side of the form. These forms will be furnished to the Contractor. Fill forms in completely prior to submittal. Exercise special care to ensure proper listing of the specification paragraph number(s) and Contract Drawing sheet number(s) pertinent to the data submitted for each item. List each submittal item separately on the form, naming subcontractor, supplier, or manufacturer;
applicable specification paragraph number(s); drawing/sheet number; pay item number; and any other information needed to identify the item, define its use, and locate it in the work. One or more ENG 4025-R forms may be used per Specification Section, however, DO NOT include more than one Specification Section per transmittal.
1.9 CROSS-REFERENCE (ENG FORM 4288-R/ENG FORM 4025-R)
To provide a cross-reference between the approved submittal register and transmittal forms, the Contractor must record the "transmittal numbers" assigned when submitting items in column "Transmittal No." of the ENG Form 4288-R. The numbers in column "Transmittal No." of the submittal register must correspond to the column "Item No." on ENG Form 4025-R.
1.10 SUBMITTAL PROCEDURES
Upload submittals in accordance with subparagraphs entitled Government
SECTION 01 33 00 Page 9
Approved Submittals and Information Only Submittals, unless indicated otherwise in the technical specifications. Submit a complete collated "reviewers copy" with one ENG 4025-R form and attachments (not originals).
Submit hard copy and electronic copies of Record (as-built) Drawings and O&M Manuals in accordance with the applicable Specification Sections.
1.10.1 e-Submittals
The intent of electronic submittals is to expedite the supply process by reducing paperwork, improving information flow, and decreasing turnaround time. Transmit all submittals, including either an electronically signed or signed scanned copy of form ENG 4025, to the Government electronic (PDF) format via email. Submittals must be entered and tracked using QCS, if using this software. At completion of Contract closeout, provide a minimum of two archival discs (DVD-R) that include all documents and tracking logs. Color samples, color charts, or physical material samples must not be transmitted electronically. e-Submittals will not relieve the Contractor from following all applicable requirements within this and other Specifications Sections and Contract Clauses.
1.10.2 Approval of Submittals by the Contractor
a. Submit names and titles of Contractor Authorized Shop Drawing Approvers to the CO with the ENG Form 4288-R. Supplier or subcontractors certifications are not acceptable as meeting this requirement.
b. Before submittal to the CO, the Contractor's Authorized Shop Drawing Approvers must review and correct shop drawings prepared by subcontractors, suppliers, and itself, for completeness and compliance with Drawings and Specifications. Do not use red markings for correcting material to be submitted. Red markings are reserved for the CO's use.
c. Submittals for Government Approval must first be Contractor-approved and stamped, see paragraph entitled CONTRACTOR APPROVAL STAMP.
d. Submittals not conforming to the requirements of this Section will be returned to the Contractor for correction and resubmittal.
1.10.3 Drawings
Each drawing must be not larger than D size (22 inches high by 34 inches wide), include a title block in lower right hand corner, and a 3- by 4-inch clear area adjacent. The title block must contain vendor's name, Contract number, description of item(s), Contract line item number, and a revision block. Separate drawings are required for each Contract line item. Where drawings are submitted for assemblies of more than one piece of equipment or systems, of components dependent on each other for compatible characteristics, complete information must be submitted on all such related components at the same time. The information must be complete and the sequence of drawing submittal must be such that all information is available for reviewing each drawing. Drawings for all items and equipment, of special manufacture or fabrication, must consist of complete assembly and detail drawings. All revisions after initial submittal must be shown by number, date, and subject in revision block. Any drawing or electronic drawing file submitted, that is not of satisfactory quality, will be returned and must be corrected and re-submitted.
SECTION 01 33 00 Page 10
1.10.3.1 Printed Material
All requirements for shop drawings must apply to catalog cuts, illustrations, printed specifications, or other data submitted, except that the 3- by 4-inch clear area adjacent to the title block is not mandatory.
Mark out inapplicable portions of the documents. Applicable items such as model numbers, sizes, and accessories must be indicated by arrow or highlighted.
1.11 PURCHASE ORDERS
a. Each purchase order issued by the Contractor for materials and equipment to be incorporated into the work must:
(1) Clearly identify the applicable Contract number
(2) Carry an identifying number
(3) Be in sufficient detail to identify the material being purchased
(4) Indicate a definite delivery date.
b. Furnish copies of purchase orders to the CO when the Contractor requests assistance for expediting deliveries of equipment or materials, or when requested by the CO for the purpose of quality assurance review.
1.12 CERTIFICATES OF COMPLIANCE
Submit an electronic copy of certificates required for demonstrating proof of compliance of materials with specification requirements. Each certificate must be signed by an official authorized to certify on behalf of the manufacturing company, contain the name and address of the Contractor, the project name and location, and the quantity and date or dates of shipment or delivery to which the certificates apply. Copies of laboratory test reports submitted with certificates must contain the name and address of the testing laboratory and the date or dates of the tests to which the report applies. Certification must not be construed as relieving the Contractor from furnishing satisfactory material if, after tests are performed on selected samples, the material is found not to meet the specific requirements.
1.13 DISAPPROVED SUBMITTALS
a. Make all corrections required by the CO and promptly furnish a corrected submittal in the form specified for the initial submittal.
If the Contractor considers any correction or notation on the returned submittals to constitute a change to the Contract drawings or Specifications; notice as required under Contract Clause 52.243-1, Changes-Fixed-Price, is to be given to the CO. The Contractor must be responsible for the dimensions and design of connection details and performance of work. Failure to point out deviations may result in the Government requiring rejection and removal of such work at the Contractor's expense.
b. If changes are necessary to submittals, make such revisions and re-submit the submittals in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until
SECTION 01 33 00 Page 11 the changed submittals are approved.
1.14 APPROVED SUBMITTALS
a. The CO's approval or acceptance of submittals must not be construed as a complete check, and indicates only that .
b. Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor under the Contractor Quality Control (CQC) requirements of this Contract must be responsible for dimensions, the design of adequate connections and details, and the satisfactory performance of all work.
c. After submittals have been approved by the CO, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.
1.15 APPROVED SAMPLES
a. Approval of a sample is only for the characteristics or use named in such approval and must not be construed to change or modify any Contract requirements. Before submitting samples, ensure that the materials or equipment will be available in quantities required. No change or substitution will be permitted after a sample has been approved.
b. If requested, approved and/or disapproved samples, including those which may be damaged in testing, will be returned at the expense of the Contractor upon completion of the Contract.
c. Failure of any materials to pass the specified tests will be sufficient cause for refusal to consider, under this Contract, any further samples of the same brand or make of that material. Government reserves the right to disapprove any material or equipment which previously has proved unsatisfactory in service.
d. Samples of various materials or equipment delivered on the site or in place may be taken by the CO for testing. Samples failing to meet Contract requirements will automatically void previous approvals.
Contractor must replace such materials or equipment to meet Contract requirements.
e. Approval of the Contractor's samples by the CO does not relieve the Contractor of his responsibilities under the Contract.
1.16 CONTRACTOR'S FILES
Maintain "Approved as Accepted" and "Approved, Except as Noted on Drawings" (Action Codes "A" and "B") shop drawing files in fabrication shops and at field sites for Government use.
1.17 PAYMENT
Separate payment will not be made for submittals, and all costs associated therein must be included in the applicable unit prices or job prices contained in the Price Schedule. Payment will not be made for any material or equipment which does not comply with Contract requirements.
SECTION 01 33 00 Page 12
1.18 WITHHOLDING OF PAYMENT
No payment will be made for any materials incorporated into the work for Information Only submittals found to contain errors.
1.19 CONTRACTOR APPROVAL STAMP
Stamps used by the Contractor on the submittal data to certify that the submittal meets Contract requirements must be similar to the following:
| CONTRACTOR |
| (Firm Name) | | _____ Approved | | _____ Approved with corrections as noted on submittal data and/or | | attached sheets(s). |
| SIGNATURE: __________________________________________________________ |
| TITLE: ______________________________________________________________ |
| DATE: _______________________________________________________________ |
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
SECTION 01 33 00 Page 13
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 42 00
SOURCES FOR REFERENCE PUBLICATIONS
PART 1 GENERAL
1.1 REFERENCES
1.2 ORDERING INFORMATION
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
SECTION 01 42 00 Page 1
SECTION 01 42 00
SOURCES FOR REFERENCE PUBLICATIONS
PART 1 GENERAL
1.1 REFERENCES
Various publications are referenced in other Sections of the specifications to establish requirements for the work. These references are identified in each Section by document number, date and title. The document number used in the citation is the number assigned by the standards producing organization (e.g. ASTM B564 Standard Specification for Nickel Alloy Forgings). However, when the standards producing organization has not assigned a number to a document, an identifying number has been assigned for reference purposes.
1.2 ORDERING INFORMATION
The addresses of the standards publishing organizations whose documents are referenced in other Sections of these specifications are listed below, and if the source of the publications is different from the address of the sponsoring organization, that information is also provided. Documents listed in the specifications with numbers which were not assigned by the standards producing organization should be ordered from the source by title rather than by number.
AMERICAN SOCIETY FOR NONDESTRUCTIVE TESTING (ASNT)
P.O. Box 28518 1711 Arlingate Lane Columbus, OH 43228-0518 Ph: 800-222-2768; 614-274-6003 Fax: 614-274-6899 E-mail: tjones@asnt.org Internet: http://www.asnt.org
AMERICAN WELDING SOCIETY (AWS)
13301 NW 47 Ave Miami, FL 33054
Ph: 888-WELDING, 305-824-1177, 305-826-6192 Fax: 305-826-6195 E-mail: customer.service@awspubs.com Internet: http://www.aws.org
ASME INTERNATIONAL (ASME)
Two Park Avenue, M/S 10E New York, NY 10016-5990 Ph: 800-843-2763 Fax: 973-882-1717 E-mail: customercare@asme.org Internet: http://www.asme.org
ASTM INTERNATIONAL (ASTM)
100 Barr Harbor Drive, P.O. Box C700
SECTION 01 42 00 Page 2
West Conshohocken, PA 19428-2959 Ph: 877-909-2786 Internet: http://www.astm.org
INTERNATIONAL ORGANIZATION FOR STANDARDIZATION (ISO)
1, ch. de la Voie-Creuse Case Postale 56 CP 56 - CH-1211 Geneva 20 Switzerland Ph: 41-22-749-01-11 Fax: 41-22-733-34-30 E-mail: central@iso.ch Internet: http://www.iso.org
MASTER PAINTERS INSTITUTE (MPI)
2800 Ingleton Avenue Burnaby, BC CANADA V5C 6G7 Ph: 1-888-674-8937 Fax: 1-888-211-8708 E-mail: info@paintinfo.com or techservices@mpi.net Internet: http://www.mpi.net/
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
1 Batterymarch Park Quincy, MA 02169-7471 Ph: 617-770-3000 Fax: 617-770-0700 Internet: http://www.nfpa.org
SOCIETY FOR PROTECTIVE COATINGS (SSPC)
40 24th Street, 6th Floor Pittsburgh, PA 15222 Ph: 412-281-2331 Fax: 412-281-9992 E-mail: info@sspc.org Internet: http://www.sspc.org
SOCIETY OF AUTOMOTIVE ENGINEERS INTERNATIONAL (SAE)
400 Commonwealth Drive Warrendale, PA 15096 Ph: 724-776-4970 Fax: 877-606-7323 E-mail: customerservice@sae.org Internet: http://www.sae.org
U.S. ARMY CORPS OF ENGINEERS (USACE)
CRD-C DOCUMENTS available on Internet:
http://www.wbdg.org/ccb/browse_cat.php?c=68 Order Other Documents from:
USACE Publications Depot Attn: CEHEC-IM-PD 2803 52nd Avenue Hyattsville, MD 20781-1102 Ph: 301-394-0081 Fax: 301-394-0084 E-mail: pubs-army@usace.army.mil Internet: http://www.publications.usace.army.mil/ or http://www.hnc.usace.army.mil/Missions/Engineering/TECHINFO.aspx
SECTION 01 42 00 Page 3
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
SECTION 01 42 00 Page 4
DIVISION 05 - METALS
SECTION 05 05 23.20 26
WELDING
PART 1 GENERAL
1.1 GENERAL INFORMATION
1.2 REFERENCES
1.3 SUBMITTALS
1.4 QUALIFICATION OF WELDERS
1.5 SYMBOLS
PART 2 PRODUCTS
2.1 WELDING MATERIALS
PART 3 EXECUTION
3.1 WELDING OPERATIONS
3.1.1 Preparation for Welding
3.1.2 Welding Procedure
3.1.3 Preheat and Interpass Temperature
3.1.4 Welding
3.1.5 Stress Relieving
3.1.6 Temporary Welds
3.1.7 Tack Welds
3.2 INSPECTION
3.2.1 General
3.2.2 Contractor's Quality Control (CQC) Welding Program
3.2.2.1 General
3.2.2.2 Inspection
3.2.2.3 Inspection Agency
3.2.2.4 Inspection Procedure
3.2.2.5 Acceptability of Welds
3.2.2.6 Repairs
3.2.3 Government Quality Assurance
3.2.3.1 General
3.2.3.2 Non-Destructive Inspection
3.2.3.3 Test Coupons
3.3 PROTECTION OF FINISHED WORK
SECTION 05 05 23.20 26 Page 1
SECTION 05 05 23.20 26
WELDING
PART 1 GENERAL
1.1 GENERAL INFORMATION
This section covers welding, if applicable. Deviations from codes, procedures, and drawings from applicable codes, approved procedures, and approved detail drawings will not be permitted without prior written approval. Procedures must be developed by the Contractor for welding all metals included in the work. Welding must not be started until welding procedures, welders, and welding operators have been qualified. Weldments not governed by the Code must be governed by appropriate portions of the American Welding Society's publications.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referenced in the text by the basic designation only.
AMERICAN WELDING SOCIETY (AWS)
AWS A2.4 (2012) Standard Symbols for Welding, Brazing and Nondestructive Examination
AWS D1.1/D1.1M (2010; Errata 2011) Structural Welding Code - Steel
AWS QC1 (2007) Standard for AWS Certification of Welding Inspectors
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following must be submitted in accordance with SECTION 01 33 00, " SUBMITTAL PROCEDURES":
SD-06 Test Reports
Reports of Physical Tests of Specimens Welded in the Qualification Tests; G
Certified copy of reports of physical tests of specimens welded in the qualification tests, a minimum of 45 calendar days prior to the performance of work, para. 1.3.
Stress-Relief Time-Temperature Charts; G
Stress-relief time-temperature charts, a minimum of 45 calendar days after stress relieving parts, para 3.1.5.
SD-07 Certificates
SECTION 05 05 23.20 26 Page 2
Qualification of Welder(s); G
Qualification of welder(s), a minimum of 45 calendar days prior to their performance of work, para. 1.3.
Additional Operator Qualification Tests;
Witness additional operator qualification tests, time as specified in para. 1.4.
Certification of Welding Inspectors; G
Certification of welding inspectors and qualifications for all assistant inspectors, a minimum of 45 calendar days prior to their performance of work, para. 3.2.2.1.
SD-08 Manufacturer's Instructions
Deviations from Codes, Procedures, and Drawings; G
Deviations from codes, procedures, and drawings, a minimum of 60 calendar days prior to their use, para. 1.1.
Welding Procedure and Specification; G
Welding procedures, specifications and reports of test results, a minimum of 45 calendar days prior to the work, para. 3.1.2.
Welding Repair Procedure for Major Base Metal Repairs; G
Welding repair procedure for major base metal repairs, a minimum of 45 calendar days prior to the work, para. 3.1.4
1.4 QUALIFICATION OF WELDERS
Welding operators, welders, and tack welders, must be qualified and, as necessary, re-qualified for the particular type of work to be done.
Qualification must be in accordance with one of the following codes: (1) Section 4, Part C, of AWS D1.1/D1.1M. The record of qualification of welder(s) must be approved. The Contractor must certify by name the welders and welding operators so qualified including the date of qualification code, and the procedures under which qualified.
Certification and testing of welders and operators must be performed by an independent testing company. Prior qualification may be accepted provided the welder has performed satisfactory work within the preceding three months under the code for which qualified, and certification of prior qualification from an independent testing company is furnished. If at any time, the work of any operator appears questionable, such operator will be required to pass additional qualification tests to determine their ability to perform the type of work on which they are engaged. All such additional operator qualification tests for welding operators and the physical tests of the welded specimens must be witnessed. All test plates and all welding wire and electrodes must be submitted as required for making the qualification tests. The test plates must be of the same material as that to be used in the work. The edges must be grooved or beveled where required, and the technique of welding must be the same as to be used in the work. The welding wire and electrodes must be of the same size, type and brand as those to be used in the work. Three (3) certified copies of
SECTION 05 05 23.20 26 Page 3 reports of physical tests of specimens welded in the qualification tests report must be prepared. All expense in connection with making the qualification or re-qualification tests for welding operators must be borne by the Contractor.
1.5 SYMBOLS
Symbols must be in accordance with AWS A2.4.
PART 2 PRODUCTS
2.1 WELDING MATERIALS
Welding materials must comply with appropriate AWS specification. Welding equipment, electrodes, welding wire, and fluxes must be capable of producing satisfactory welds when used by a qualified welder or welding operator using qualified welding procedures.
PART 3 EXECUTION
3.1 WELDING OPERATIONS
3.1.1 Preparation for Welding
Members to be joined by welding must be cut accurately to size and, where required, must be rolled or pressed to the proper curvature. The edges of the members must be sheared, flame-cut, machined, chipped, plasma gouged, arc-air gouged (except for stainless steel), or ground to suit the required type of weld joint. The cut surface must expose sound metal free from lamination or carburized material, or other injurious defects. The surfaces to be welded, at the time of welding must be free from rust, oil, grease, dirt, moisture and other foreign matter for a distance of at least two-inches back from each edge of the weld. For site operations:
Previously deposited stainless steel must also be removed for a distance of at least one inch from the edge of the weld groove. To test for the presence of stainless steel and its successful removal, Copper Sulfate must be applied to the areas in question, prior to preheating. The copper sulfate must be removed and the area degreased before preheat is applied and start of welding.
3.1.2 Welding Procedure
The Contractor must prepare a welding procedures consisting of detailed procedure specifications for each part to be welded and tables or diagrams showing the procedure to be used for each required joint. Welding must not be performed without an approved welding procedure and specification. For all weld joints the qualification plates representing those joints must be tested in accordance with the test requirements in accordance with Section 4 of AWS D1.1/D1.1M. Applicable pre-qualified weld procedures in AWS publications may be submitted for approval.
3.1.3 Preheat and Interpass Temperature
Preheating must be performed as required by AWS D1.1/D1.1M, Subsection 5.6 and 5.7 or as otherwise specified except that the temperature of the base metal must be at least 70°F. The material to be preheated must be slowly and uniformly heated by approved means to the prescribed temperature, held at that temperature until the welding is completed and then permitted to cool slowly in still air.
SECTION 05 05 23.20 26 Page 4
3.1.4 Welding
All welding, unless otherwise specified, must be performed by the electric-arc method, by a process which will exclude the atmosphere from the molten metal. The design and construction of welded joints must conform to the requirements of AWS publications, or as otherwise specified or approved. Welding repair procedure for major base metal repairs must be submitted for approval. After being deposited, welds must be cleaned of slag and must show uniform sections, smoothness of weld metal, feather-edges without overlap, and freedom from porosity. Visual inspection at the edges and ends of welds must indicate good fusion with the base metal. All pinholes, cracks, blow holes and other defects must be repaired by air-arc gouging, chipping or grinding the defects to sound metal and re-welding. All undercutting of the side walls of the welding groove must be opened up by grinding before the next successive weld bead to allow good fusion at the side wall. The welding rods used for manual welding must be of the low-hydrogen type and must be suitable for the position in which the welding is performed.
3.1.5 Stress Relieving
Except for minor parts and parts specifically excepted from stress relieving, stress relieving of welded joints must conform to the applicable requirements of AWS D1.1/D1.1M, except:
a. Localized stress relieving will not be permitted for any initial stress relief, unless otherwise specified herein. Where major repairs after initial stress relief must be made by welding, an approved repair procedure is required, and unless otherwise approved, the welded joints must be stress relieved.
b. Parts fabricated by welding which are to receive machining must be stress relieved at a time prior to final machining.
c. Stress-relief time-temperature charts must be automatically recorded and a copy of each chart must be submitted with identification of each part pertaining thereto.
3.1.6 Temporary Welds
Temporary welds must be made under the controlled conditions prescribed herein for permanent work. All temporary welds must be made using low-hydrogen welding electrodes by welders qualified for permanent work as specified elsewhere in these specifications. Preheat furnished for temporary welds must be the same as for permanent welds, except that the minimum temperatures must be 70°F in any case. In making temporary welds, arcs must not be struck in other than weld locations. Each temporary weld must be removed after serving its purpose, ground flush with adjacent surfaces and the adjacent surfaces restored to their original condition.
3.1.7 Tack Welds
Tack welds that are to be incorporated into the permanent work must be subject to the same quality requirements as the permanent welds.
Preheating must be performed as specified for temporary welds above. Such tack welds must be cleaned and fused thoroughly with the permanent welds.
Multiple-pass tack welds must have cascaded ends. Defective tack welds must be removed before permanent welding.
SECTION 05 05 23.20 26 Page 5
3.2 INSPECTION
3.2.1 General
All welding must be inspected to ensure that the welds conform to the requirements of this specification, the appropriate sections AWS D1.1/D1.1M and the approved welding procedure. Inspection will be performed in two categories: (1) The CQC Welding Program must guarantee complete compliance of all welds with the contract requirements, and (2) The Government Quality Assurance Program will be utilized to verify implementation and acceptability of the CQC Welding Program.
3.2.2 Contractor's Quality Control (CQC) Welding Program
3.2.2.1 General
Inspections performed under the CQC Welding Program must be in accordance with the specifications herein, Section 6 of AWS D1.1/D1.1M, and in conjunction with the contract clause Inspection of Supplies-Fixed Price.
The Contractor's weld inspector must hold a current certification as a certified welding inspector (CWI) in accordance with AWS QC1 and AWS D1.1/D1.1M, paragraph 6.1.4 for AWS welds or as otherwise specified.
Copies of certification of welding inspectors and qualifications for all assistant inspectors must be approved.
3.2.2.2 Inspection
a. Inspection and tests must be performed as necessary prior to welding, during welding, and after welding to ensure that materials and workmanship meet the requirements specified. In addition to visual inspection, all welds must be subject to non-destructive inspection, see SECTION 05 05 33.20 26. As a minimum, the following amount of non-destructive inspection must be performed:
(1) Not used.
(2) Ten percent of the groove welds must be inspected by ultrasonic testing.
(3) Ten percent of the fillet welds must be inspected by magnetic particle testing or liquid penetrant testing.
(4) Not used
(5) The samples must be randomly selected and must be representative of the welds on that weldment.
b. Any weld that does not meet the acceptance criteria in SECTION 05 05 33.20 26 must not be counted as meeting the above inspection requirements. Rejection of any portion of a weld inspected on less than a 100 percent basis, by a method other than visual, must be 100 percent inspected by the method used in finding the defect. This inspection will not count towards meeting the above quality requirements.
3.2.2.3 Inspection Agency
Non-destructive inspection of welds and evaluation of tests or inspections
SECTION 05 05 23.20 26 Page 6 as to…