A.07.20_BLR_Spillway_Gate_PPP.pptx
PPTX presentation 2 MB Posted
- Attached to
- Blue River Spillway Gate Rehabilitation
- Solicitation number
- W9127N-15-R-0022
About this file
Site Visit Power Point Presentation
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W9127N-15-R-0022_Amend_0002.pdf | ||
| W9127N-15-R-0022Amd00001.pdf | ||
| A.07.20_Site_Visit_Attendee_list.pdf | ||
| CENWP-OD-SAF-385-1__HECP__28_May_2014.pdf | ||
| Attachment_A_Past_Performance_Questionnaire_(PPQ).docx | DOCX document | |
| Drawings.pdf | ||
| W9127N-R-0022_RFP.pdf | ||
| Bidder_Inquiry_Instructions.pdf | ||
| EM_385-1-1_30_Nov_2014.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation W9127N-15-R-0022 Blue River Dam Spillway Gate Rehabilitation General Scope Overview for Contractor Site Visit Michael I. Grasso, Contract Specialist Seth Stevens, Technical Lead 8 July 2015
US Army Corps of Engineers
BUILDING STRONG®
Disclaimer Everything presented here today is informal and does not constitute changes or deviations from the specifications.
Any answers given here today are not official. For official answers use the bidder inquiry procedures (Refer to Slide 9).
PORTLAND DISTRICT
Administrative Sign the Registry If you would like a copy of this presentation, include your email address
Restrooms
Designated Smoking Areas
Emergency Exits
Agenda Purpose/Ground Rules
Project Overview, Technical Overview, and Project Challenges Seth Stevens – Technical Lead
Field Tour
Purpose Exchange information regarding the scope of project, specifications, and outcomes
Overview of the job site
Establish lines of communication with Industry
All questions/comments will be submitted through the bidder inquiry system
Ground Rules Information conveyed at this site visit does not qualify as the terms and conditions of the solicitation
All communications shall be conducted through the Contract Specialist or Contracting Officer. Interested vendors should ask questions using the Bidder Inquiry system
Non-attendance at this event does not preclude an offeror from submitting a proposal in response to the RFP
Ground Rules cont.
Internal Source Selection Plans and procedures will not be discussed
If an item is not mentioned or addressed during this presentation, do not assume it is not important Utilize the Bidder Inquiry site that is included in the solicitation.
Offerors shall not engage individual government personnel in private discussions at any time
Solicitation Overview Terms and conditions have been posted formally and publicly.
Solicitation W9127N-15-R-0022 Federal Business Opportunity (FBO) Proposals due 30 July 2015 Total SB Set-Aside Solicitation Open to small businesses only No Subcontracting Plan with their proposal Best Value/Trade Off Best value is a process used in competitive negotiated contracting to select the most advantageous offer by evaluating and comparing factors in addition to cost or price Evaluation criteria is stated in Section 00100 of the solicitation
Submission of Questions Submit all questions in writing. All inquiries regarding this solicitation are to be submitted via ProjNet-Bid.
Telephone and email inquiries will not be accepted.
ProjNet-Bid can be accessed through ProjNet at https://www.projnet.org/projnet/.
The Bidder Inquiry Key is: 24J8Z8-7N56K4
Bidder Inquiry Bidder inquiry closes COB 27 July 2015.
Proposals shall not be based on informal discussions during site visit – submit questions via Bidder Inquiry.
Proposal Submission Please read the entire solicitation package and follow instructions to ensure a complete proposal is prepared and submitted to NWP.
Section 00100-4 Submission of Proposals covers what to include in the proposal Volumes I & II.
Proposals are due 30 July 2015, 4:00PM Pacific Time.
Project Overview
Technical Lead Seth Stevens
Purpose of Technical Presentation To highlight major scope items.
See plans and specs for complete information.
History and Overview Structural analysis to current criteria indicates gate design strength exceeded when operated at full pool Resulted in implementation of a gate operating restriction until all gates are repaired Upgrade to ensure safety, functionality, and reliability of spillway gate system
Schedule Proposals Due: 30 July 2015 Contract award: Approx. 30 Sept 2015 Notice To Proceed: Approx. 15 Oct 2015 On Site Work Window:
15 Sept 2016 – 15 Nov 2016 (for mandatory items) If optional gates awarded, 2nd work window is 15 Sept 2017 – 15 Nov 2017
Summary of Work Structural Add partial cover plates to strut arms Strengthen outer ribs at top and bottom girders Replace gate seals Upgrade fall protection systems New machinery platforms New cover structures for machinery Touch-up painting on gates New fencing
Summary of Work, continued
New Cover Plates (typ) New Rib Stiffeners (typ) New Machinery Platforms and Covers New Fencing (typ)
Summary of Work, continued Mechanical Replace hoist machinery, including position indication, limit switch equipment, wire ropes Retrofit existing trunnion hubs and yokes to install new trunnion bearing systems that utilize self-lubricated materials Install secondary containment around all oil and grease containing equipment
Summary of Work, continued Electrical Replacement of gate control panels and all controls associated with gates Replacement of lighting around gate machinery Replace feeders between new distribution panel and intake tower Replace power distribution system
Questions and Field Tour image7.png image1.png image2.png image3.png image4.png image5.jpeg image6.png
File details come from the government source that posted it. Updated .