G1_Award_19-P-0138_v1_released.pdf
PDF 912 KB Posted
- Attached to
- Hydropower Systems Testing
- Solicitation number
- W9126G19Q0042
About this file
Contract award for 19P0138
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A5.2_JA_Simplified_Acquisition_v2.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SEE ADDENDUM
(No Collect Calls)
W9126G19Q0042 24-May-2019
b. TELEPHONE NUMBER
817-886-1025
8. OFFER DUE DATE/LOCAL TIME
05:00 PM 26 Jul 2019
5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 2/2012)
Prescribed by GSA – FAR (48 CFR) 53.212
(TYPE OR PRINT)
(SIGNATURE OF CONTRACTING OFFICER)
ADDENDA ARE
X
26. TOTAL AWARD AMOUNT (For Gov t. Use Only )
23.
CODE 10. THIS ACQUISITION IS
SUCH ADDRESS IN OFFER
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT
BELOW IS CHECKED
TELEPHONE NO.(617)926-4900
W9126G9. ISSUED BY
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK
W9126G19P0138 01-Aug-2019
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME
SUPHAKIT AREEYAT
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER
(TYPE OR PRINT)
30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA
27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.
X
25. ACCOUNTING AND APPROPRIATION DATA
1. REQUISITION NUMBER
20.
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
ARE NOT ATTACHED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
LaVonne D. Lee / Contract Specialist
See Schedule $33,350.00
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS: SEE SCHEDULE
. YOUR OFFER ON SOLICITATION
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
% FOR:SET ASIDE:UNRESTRICTED ORX
SMALL BUSINESS
17a.CONTRACTOR/ CODE 94856 FACILITY
OFFEROR CODE
US ARMY CORPS OF ENGINEERS FORT WORTH
819 TAYLOR ST, CT OFC RM 2A17
FORT WORTH TX 76102-0300
DOBLE ENGINEERING COMPANY
LAWRENCE NORDT
85 WALNUT ST
WATERTOWN MA 02472-4044
USACE FINANCE CENTER MILLINGTON
ATTN: CEFC-AO-P
5722 INTEGRITY DRIVE
MILLINGTON TN 38054-5005
18a. PAYMENT WILL BE MADE BY CODE 964145
RATED ORDER UNDER
DPAS (15 CFR 700)
13a. THIS CONTRACT IS A
13b. RATING
CODE
SEE ITEM 9
15. DELIVER TO CODE 967442 16. ADMINISTERED BY
Net 30 Days
12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
14. METHOD OF SOLICITATION
RFQ IFB RFPX
WHITNEY AQUILLA LAKES
USAED, FORT WORTH
285 CR 3602
CLIFTON TX 76634
(817) 886-6403FAX:
TEL: (817) 886-1077
SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
8(A)
HUBZONE SMALL
BUSINESS
SIZE STANDARD:
NAICS:
334515
OFFER DATED
29. AWARD OF CONTRACT: REF.
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
X
EMAIL: lavonne.d.lee@usace.army.mil
817-886-1161TEL:
31c. DATE SIGNED
01-Aug-2019
SEE SCHEDULE
SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT
24.22.21.19.
WOMEN-OWNED SMALL BUSINESS (WOSB)
ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
(CONTINUED)
PAGE 2 OF46
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE
37. CHECK NUMBER
FINALPARTIALCOMPLETE
36. PAYMENT35. AMOUNT VERIFIED
CORRECT FOR
34. VOUCHER NUMBER
FINAL
33. SHIP NUMBER
PARTIAL
38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS
STANDARD FORM 1449 (REV. 2/2012) BACK
Prescribed by GSA – FAR (48 CFR) 53.212
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
SEE SCHEDULE
20.
SCHEDULE OF SUPPLIES/ SERVICES
21.
QUANTITY UNIT
22. 23.
UNIT PRICE
24.
AMOUNT
19.
ITEM NO.
W9126G19P0138
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job $33,350.00 $33,350.00
Funded Amt:
HPP SYS PWR FACTR TE EQ & SVC
Hydropwer Systems Power Factor Test Equipment and Services
The Contractor shall provide equipment repairs, software updates, power generation data analysis, maintenance comparison and report preparation services necessary to support Power Factor Testing IAW the PWS.
Period of Performance: 1 Aug 19 - 31 Jul 20
Mail Invoice To:
Beasley, Michael D CIV USARMY CESWF (US)
<Michael.D.Beasley@usace.army.mil>
285 CR 3602
Clifton TX 76634
254-622-3268
NAICS CD: 334515
, FSC CD: 6695
000101 $0.00
Funded Amt: $11,116.66
FY19 WHITNEY - POWER FACTOR TESTING
000102 $0.00
Funded Amt: $11,116.67
FY19 SAM RAYBURN - POWER FACTOR TESTING
000103 $0.00
Funded Amt: $11,116.67
FY19 RD WILLIS - POWER FACTOR TESTING
1001 1 Job $34,130.00 $34,130.00
OPTION Funded Amt:
OPT1: HPP SYS PWR FACTR TE EQ & SVC
Period of Performance: 1 Aug 20 - 31 Jul 21
<Michael.D.Beasley@usace.army.mil>
285 CR 3602
2001 1 Job $34,940.00 $34,940.00
OPTION Funded Amt:
OPT2: HPP SYS PWR FACTR TE EQ & SVC
Period of Performance: 1 Aug 21 - 31 Jul 22
<Michael.D.Beasley@usace.army.mil>
285 CR 3602
3001 1 Job $35,960.00 $35,960.00
OPTION Funded Amt:
OPT3: HPP SYS PWR FACTR TE EQ & SVC
Period of Performance: 1 Aug 22 - 31 Jul 23
<Michael.D.Beasley@usace.army.mil>
285 CR 3602
4001 1 Job $36,800.00 $36,800.00
OPTION Funded Amt:
OPT4: HPP SYS PWR FACTR TE EQ & SVC
Period of Performance: 1 Aug 23 - 31 Jul 24
Sam Rayburn/RD Willis Power Plant
7696 RR 255 West
Jasper, TX 75951-6400
(409)384-5716
Section C - Descriptions and Specifications
CONTRACTING OFFICER STATEMENT
Only a warranted Contracting Officer (either a Procuring Contracting Officer (PCO), or an
Administrative Contracting Officer (ACO)), acting within their delegated limits, has the authority to issue modifications or otherwise change the terms and conditions of this contract. If an individual other than the Contracting Officer attempts to make changes to the terms and conditions of this contract you shall not proceed with the change and shall immediately notify the Contracting Officer.
PWS
PERFORMANCE WORK STATEMENT (PWS)
HYDROPOWER SYSTEMS POWER FACTOR TEST EQUIPMENT AND SERVICES
SAM RAYBURN / WHITNEY / RD WILLIS POWER PLANTS
1. GENERAL: This is a non-personal services contract to provide power factor test equipment and services. The
Government shall not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the Contractor who, in turn is responsible to the Government.
1.1 Description of Services/Introduction: The Contractor shall provide all equipment, personnel specific to maintenance or replacement of this equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to supply all necessary power factor test equipment and support services required to complete analyzation and verification of hydropower electrical systems as defined in this Performance Work Statement. The Contractor shall perform to the standards in this contract.
1.2. Scope: The Contractor shall provide the following specific test equipment and engineering support to accomplish testing and verification of power system integrity; Services include:
Provide one each Insulation Analyzer, Safety Strobe indicating testing condition, and cable and accessory container. This equipment must be able to perform the following tests:
o Power Factor/Tangent Delta testing support services to confirm insulation integrity and quality.
o Capacitance testing to measure physical changes that may have occurred to the apparatus.
o Turns ratio testing to detect shorted turns or winding damage.
o Liquid Insulation testing to detect deterioration of insulating oils.
o Hardware:
Output current of 300mA for at least 4 minutes at 10kV output voltage using input sources of 120VAC and 20A. Test equipment should be able to perform this without external power supply.
Removable field calibration module with the ability to calibrate at a minimum of 50% of current ranges without external devices, including resonating inductors.
Automatically sense input voltage with a range from 96 VAC to 264 VAC.
Must be able to perform all tests and safety functions from a single constructed test unit.
Must use a resistive element to prevent excessive dielectric losses and moisture buildup during testing.
Must be compatible with an integrated transportation device.
Must be able to perform transformer turns ratio at a test potential of 10 kV using an external reference capacitor.
Must be able to perform test measurements above 12 kV with the use of an external voltage source and reference element.
Must have an integrated temperature and humidity sensor whereupon values are automatically uploaded by the software.
Unit must weigh less than 100 lbs.
Must be able to meet the following environmental standards when removed from shipping crates:
Drop Test: IEC 60068-2-6
Shock: IEC 60068-2-27 & ASTM D999.75
Dry Heat: IEC 60068-2-30
Cold: IEC 60068-2-1
Vibration: IEC 60068-2-6
Must have a current user list with a minimum of 100 independent companies.
Provide the most current version of software to support this analyzer, with the following capabilities:
o Collect, analyze and manage test results.
o Pictures for lead connection and test setup guidance.
o Manage data by establishing library of every result collected.
o Must provide and be compatible with a centralized database for test results that allows benchmarking with other users.
o Software must have the ability to modify and update expert system limits from a centralized database.
o Must be compatible with a software package having the ability to perform expert analysis by apparatus, type, and class where appropriate. Results must be based upon industry comparable statistics and experiences for a minimum of 50 years.
o Software must have preconfigured test forms for multiple different apparatus types and tests.
One Digital display device that enables independent control of test equipment.
o Must withstand an operation 4’ drop to concrete and operational 7’ drop to plywood.
o Fully submersible up to 30 minutes.
o Impenatrable to dust and debris.
o Operates in 20°F to 120°F temperatures.
o Sunlight readable screen.
o Full shift battery life of 8 hours.
Technical Support services:
o Must be capable of being supported by a staff of technical experts suppurted by engineers with experience in the specific power equipment and high voltage testing industry.
o Must have a dedicated technical support team with access to engineer services.
o Support must be given 365 days a year on a 24 hour basis.
o Must be able to provide 24-hour service turnaround for defective units.
o Must include annual refresher training of USACE personnel.
o Must have on-site materials laboratory to ensure seamless support between oil testing and offline power factor testing.
o Must include access to an online knowledgebase with the following information:
Library of Reference Books/Guides
Apparatus Manufacturer’s Service Advisories
Industry Trouble and Failure reports
Tutorials
SFRA Resource Center
Partial Discharge (PD) Resource Center
Insulating Materials Resource Center
Protection & Automation Resource Center
Relay Test Plan Library o Must have access to an extensive database with multiple individual data points spanning 30 years of historical test results.
The Contractor shall accomplish the following services:
The Contractor shall utilize their technical engineering staff and their historical database of related high voltage generating and switchyard equipment to provide technical recommendations for maintenance, and any indicated specific tests required for additional diagnosis, and failure mode analysis to the Corps of Engineers.
Upon analysis of periodic test data provided by the Fort Worth District’s three hydroelectric power plants, the
Contractor shall provide site specific analysis relative to the power plant submitting test data, directly to the specific power plant submitting the test data for analysis and recommendations.
All testing of government equipment shall be conducted by personnel from each power plant in accordance with recommended connections and practices per Contractor training and instruction.
It shall be the responsibility of each specific Power Plant to schedule training from the Contractor in order to assure properly trained personnel are available to conduct power factor testing on plant equipment.
The Contractor shall also make available to the staff of the power plants, training in use of the Power Factor test equipment as required for the specific type of equipment to be tested by power plant staff, not to exceed the allowable training limits provided as part of this contract, and refresher courses as requested by each power plant up to the allowable training allocation provided by the contract.
Training shall be done at the Sam Rayburn Power Plant by arrangement with the Contractor, on the same type equipment or newer model, as the test equipment provided as part of this contract.
When training is arranged to be held at the Sam Raybun Power Plant, all costs associated with travel by
Contractor personnel, per diem and lodging costs are to be borne by the Contractor.
1.3 Period of Performance: The period of performance shall be a Base Year, plus (4) 12 month Option years.
1.4 General Information
1.4.1 Quality Control: The Contractor shall develop and maintain an effective Quality Control Program to ensure services are performed in accordance with this PWS. The Contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The contractor shall provide documentation that all test equipment has been calibrated within the manufactures specified requirements. The Contractor’s quality control program is the means by which he assures himself that his work complies with the requirement of the contract. Should the Contractor have an established Quality
Control Plan, it is to be submitted at the time of the proposal. After acceptance of the quality control plan the Contractor shall receive the Contracting Officer’s acceptance in writing of any proposed change to his
QC system.
1.4.2 Quality Assurance: The Government shall evaluate the Contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan. This plan is primarily focused on what the
Government must do to ensure that the Contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the minimum acceptable defect rate(s).
1.4.3 Government Holidays: Although the Contractor’s services would not normally be required after normal duty hours or on holidays, a 365 day, 24 hour customer service line is required for critical support and power generation emergencies.
New Year’s Day Labor Day
Martin Luther King Jr.’s Birthday Columbus Day
President’s Day Veteran’s Day
Memorial Day Thanksgiving Day
Independence Day Christmas Day
1.4.4 Hours of Operation: Normal Duty hours of operation is 07:00 to 17:30 Monday through Friday.
1.4.5 Place of Performance: The work to be performed under this contract will be performed primarily at the Sam Rayburn Power Plant, Jasper TX. At times, the equipment and services will also be required at the
RD Willis Power Plant, Town Bluff, TX and the Whitney Power Plant, Clifton TX.
1.4.6 Type of Contract: The government will award a Firm Fixed performance contract. Payments shall be made based on line item pricing for the contract Base and Option Years, as submitted by the Contractor and accepted at contract award. Invoices shall be submitted to the
1.4.7 Security Requirements: All Contractor and all associated Subcontractors’ employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by the Government Representative, if required). The Contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office.
Contractor workforce must comply with all personal identity verification requirements (FAR clause
52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the
Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes. Contractor and all associated sub-contractors employees shall comply with adjudicated standards and procedures using the National Crime Information
Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSBD) (Army
Directive 2014-05 / AR 190-13), applicable installation facilities and area commanders installation /facility access and local security policies and procedures ( provided by government representive, as NCIC and
TSBD are available).
1.4.7.1 The Contractor must pre‐screen Candidates using the E‐verify Program
(http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Contractor must ensure that the Candidate has two valid forms of
Government issued identification prior to enrollement to ensure the correct information is entered into the E‐verify system. An initial list of verified/eligible Candidates must be provided to the Hydropower Business Line Manager no later than 15 business days after the initial contract award, if required. When contracts are with individuals, the individuals will be required to complete a Form I‐9, Employment Eligibility Verification. This Form shall become part of the official contract file.
1.4.7.2 All contract employees, including subcontractor employees who are not in possession of the appropriate security clearance or access privilages, will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas.
1.4.7.3 I-WATCH, Corps Watch, or See Something, Say Something program. The Contractor and all associated sub-contractors shall receive a brief/training on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the Power Plant Superintendant NLT 5 calendar days after the completion of the training. I-Watch/CORPS watch training video and literature can be found at the following web site.
http://www.swf.usace.army.mil/BusinessWithUs/Contracting.aspx.
1.4.7.4 Physical Security: The Contractor shall be responsible for safeguarding all Government equipment, information and property during the execution of this contract.
http://www.uscis.gov/e-http://www.swf.usace.army.mil/BusinessWithUs/Contracting.aspx
1.4.7.5 Key Control: No keys will be issued during the execution of this contract.
1.4.8 Special Qualifications: Must be capable of being supported by a technical staff, supported by
Electrical Engineers qualified within the power generation and analyzation industry. Support must include data storage and comparison capabilities.
1.4.9 Post Award Conference/Periodic Progress Meetings: The Contractor agrees to attend any post award conference convened by the contracting activity or contract administration office in accordance with
Federal Acquisition Regulation Subpart 42.5. The Contracting Officer, Contracting Officers Representative
(COR), and other Government personnel, as appropriate, may meet periodically with the contractor to review the Contractor's performance. At these meetings the Contracting Officer will apprise the contractor of how the Government views the Contractor's performance and the Contractor will apprise the
Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the Government.
1.4.10 Contracting Officer Representative (COR): The COR will be identified by separate letter. The
COR monitors all technical aspects of the contract and assists in contract administration The COR is authorized to perform the following functions: assure that the Contractor performs the technical requirements of the contract: perform inspections necessary in connection with contract performance:
maintain written and oral communications with the Contractor concerning technical aspects of the contract:
issue written interpretations of technical requirements, including Government drawings, designs, specifications: monitor Contractor's performance and notifies both the Contracting Officer and Contractor of any deficiencies; coordinate availability of government furnished property, and provide site entry of
Contractor personnel. A letter of designation issued to the COR, a copy of which is sent to the Contractor, states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the contract.
1.4.11 Contractor Key Personnel: The following personnel are considered key personnel by the
Government: The Contractor, Regional Service Manager, Professional Engineer shall provide a contract manager who shall be responsible for the performance of the work. The name of this person and an alternate who shall act for the Contractor when the Manager is absent shall be designated in writing to the
Contracting Officer. The contract Manager or alternate shall have full authority to act for the Contractor on all contract matters relating to daily operation of this contract.
1.4.12 Identification of Contractor Employees:
“Identification of Contractor Employees in the Federal Workplace (Aug 2008):
(a) The Contractor shall provide each of its employees who will be involved in the performance of the contract, on a Government facility, with an identification (ID) badge. The ID badge shall clearly display the Contractor’s name and the employee’s name and color photograph. The Contracting Officer or his/her designee shall approve the ID badge before the commencement of contract performance. It is the
Contractor’s responsibility to ensure that all Contractor personnel wear the ID badge at all times when performing work under this contract at a Government facility. Unless otherwise specified in the contract, each Contractor employee shall wear the ID badge in a conspicuous place on the front of their clothing and above their waist, except when safety or health reasons prohibit such placement. This requirement is in addition to any Government facility security provisions that require that a Government-issued security badge also be worn. The Contractor will be onsite a maximum of 5 work days per year. While onsite, the
Contractor shall be escorted by government personnel 100% of the time.
(b) Contractor personnel shall clearly identify themselves to all attendees as a Contractor employee before the commencement of meetings with Government or other Contractor personnel. Contractor personnel shall clearly and immediately identify themselves as a Contractor employee when placing, answering or participating in telephone/VTC conversations with Government or other Contractor personnel.
(c) When Contractor personnel send e-mail messages from or to a Government-owned computer, they shall include a signature block that includes their employer’s name and the employee’s full name and e-mail address.
(d) Each of the requirements set forth in paragraphs a-c above, must be included in all subcontracts at any tier.”
1.4.13 Contractor Travel All travel, per diem and lodging by the Contractor will be borne by the
Contractor.
1.4.14 Data Rights NOT APPLICABLE
1.4.15 Organizational Conflict of Interest: NOT APPLICABLE
1.5. GOVERNMENT FURNISHED ITEMS AND SERVICES:
1.5.1 Facilities: During training of Government employees at the Governemnt site, the Government will provide the necessary workspace for the Contractor staff to provide such training.
1.5.2 Equipment NOT APPLICABLE.
1.5.3 Materials NOT APPLICABLE.
1.6 CONTRACTOR FURNISHED ITEMS AND RESPONSIBILITIES:
1.6.1 General Support:
o Must be capable of being supported by a staff of Electrical Engineers qualified within the power generation and analyzation industry.
o Must have a dedicated Support Engineer.
o Support must be given 365 days a year on a 24 hour basis.
o Must be able to provide 24-hour service turnaround for defective units.
o Must include annual refresher training.
o The Contractor shall be responsible for all normal maintenance, normal repair and service during the contract period at no additional cost to the Government.
o The Contractor shall provide all related services for any equipment that is covered by manufacturer’s warranty.
o When equipment is out of service (not available for use) the Contractor shall repair and return the equipment to service within 72 hours after notification. If the equipment cannot be repaired within
24 hours after notification, the Contractor shall provide a replacement that meets the same specifications at no additional cost to the Government. Replacement equipment shall be on site within 48 hours of such notification to the Contractor.
o All equipment shall be in a fully operational condition at the time of delivery.
o The Contractor shall respond to calls for service and repairs within 24 hours of notification.
1.6.2 Equipment: The Contractor shall provide:
o One each- Insulation Analyzer, Safety Strobe indicating testing condition, and cable and accessory container. This equipment must be able to perform the following tests:
Power Factor/Tan Delta testing to confirm insulation integrity and quality.
Capacitance testing to measure physical changes that may have occurred to the apparatus.
Turns ratio testing to detect shorted turns or winding damage.
Liquid Insulation testing to detect deterioration of insulating oils.
Removable field calibration module with the ability to calibrate at a minimum of 50% of current ranges without external devices, including resonating inductors.
Must have an integrated temperature and humidity sensor whereupon values are automatically uploaded by the software.
o Provided with current version of software, with the following capabilities:
Collect, analyze and manage test results.
Pictures for lead connection and test setup guidance.
Manage data by establishing library of every result collected.
Must provide and be compatible with a centralized database for test results that allows benchmarking with other users.
Software must have the ability to modify and update expert system limits from a centralized database.
Must be compatible with a software package having the ability to perform expert analysis by apparatus, type, and class where appropriate. Results must be based upon industry comparable statistics and experiences for a minimum of 50 years.
Software must have preconfigured test forms for multiple different apparatus types and tests.
o One Digital display device that enables independent control of test equipment.
Must withstand an operation 4’ drop to concrete and operational 7’ drop to plywood.
Fully submersible up to 30 minutes.
Impenatrable to dust and debris.
Operates in 20°F to 120°F temperatures.
Sunlight readable screen.
Full shift battery life of 8 hours.
1.6.3. Materials:
o Must have on-site materials laboratory to ensure seamless support between oil testing and offline power factor testing o Must include access to an online knowledgebase with the following information:
Library of Reference Books/Guides
Apparatus Manufacturer’s Service Advisories
Industry Trouble and Failure reports
Tutorials
SFRA Resource Center
Partial Discharge (PD) Resource Center
Insulating Materials Resource Center
Protection & Automation Resource Center
Relay Test Plan Library
1.7 CONTRACTOR MANAGEMENT REPORTING (CMR) NOT APPLICABLE.
1.8 APPLICABLE PUBLICATIONS (CURRENT EDITIONS)
1.8.1 The Contractor must abide by all applicable regulations, publications, manuals, and local policies and procedures.
o Drop Test: IEC 60068-2-6 o Shock: IEC 60068-2-27 & ASTM D999.75 o Dry Heat: IEC 60068-2-30 o Cold: IEC 60068-2-1 o Vibration: IEC 60068-2-6
1.9 Attachment/Technical Exhibit List:
1.9.1 Attachment 1/Technical Exhibit 1 – Performance Requirements Summary
1.9.2 Attachment 2/Technical Exhibit 2 – Deliverables Schedule
TECHNICAL EXHIBIT 1
Performance Requirements Summary
The contractor service requirements are summarized into performance objectives that relate directly to mission essential items. The performance threshold briefly describes the minimum acceptable levels of service required for each requirement. These thresholds are critical to mission success.
Performance Objective
Standard
Performance
Threshold Method of
Surveillance
PRS # 1 – Power
Factor test equipment.
The Contractor shall provide Power Factor test equipment, accessories, and operating software.
The Contractor provided Power Factor test equipment, accessories, and operating software shall conform to the following standards:
Insulation Analyzer, This equipment must be able to perform the following tests:
Power Factor/Tan Delta testing.
Capacitance testing.
High Voltage Turns ratio testing.
Liquid Insulation testing.
Output current of 300mA for at least 4 minutes at 10kV.
Output voltage using input sources of 120VAC and 20A.
Test equipment should be able to perform this without external power supply. Removable field calibration module able to calibrate at a minimum of 50% of current ranges without external devices. Automatically sense input voltage ranging from 96 to 264 VAC. Must prevent excessive dielectric losses and moisture buildup during testing.
Must be able to perform transformer turns ratio at a test potential of 10 kV. Must have an integrated temperature and humidity sensor.
Unit must weigh less than 100 lbs. Must be able to meet the following environmental standards when removed from shipping crates: Drop Test: IEC 60068-2-6
Shock: IEC 60068-2-27 & ASTM D999.75
Dry Heat: IEC 60068-2-30
Cold: IEC 60068-2-1
Vibration: IEC 60068-2-6
Must be provided with current version of software, which can collect, analyze and manage test results. Manage data by establishing library of every result collected. Must provide and be compatible with a centralized database for test results that allows benchmarking with other users. Software must be able to modify and update expert system limits from a centralized database. Must be compatible with a software package having the ability to perform expert analysis by apparatus, type, and class where appropriate. Software must have preconfigured test forms for multiple different apparatus types and tests. Must have Digital display device that enables independent control of test equipment. Must withstand an operation 4’ drop to concrete and operational 7’ drop to plywood. Must be fully submersible up to 30 minutes and impenatrable to dust and debris. Must operates in 20°F to
120°F temperatures, have a sunlight readable screen and have a full shift battery life of eight (8) hours.
Zero deviation from standard.
The 100% inspection method will be used to verify proper test equipment type and serviceability though out the duration of this contract.
Verification of services will be performed by the
Designated
Government
Representative.
PRS # 2 – Technical support. The Contractor shall provide perpetual equipment operational support and serviceability including
24-hour replacements of test equipment and test cables.
Technical support here
But, reports, manuals, etc. in
DELIVERABLES
The Contractor provided support must be capable of being supported by a staff engineers with experience in the power industry. Must have a dedicated support engineer. Support must be available one full calendar year for each Base and
Option Year on a 24 hour basis. Must be able to provide 24-hour service turnaround for defective units. Must provide on-site materials laboratory to ensure seamless support between oil testing and offline power factor testing. Must include access to an online knowledge base with the following information:
Library of Reference Books/Guides
Apparatus Manufacturer’s Service Advisories
Industry Trouble and Failure reports
Tutorials
SFRA Resource Center
Partial Discharge (PD) Resource Center
Insulating Materials Resource Center
Protection & Automation Resource Center
Relay Test Plan Library
Must have access to an extensive database with multiple individual data points spanning 30 years of test data, historical results.
Zero deviation from standard.
The 100% inspection method will be used to monitor all contract services.
Verification of services will be performed by the
Designated
Government
Representative.
PRS # 3 – Training on test equipment. The
Contractor shall provide test equipment training by Contractor’s
Engineers at
Government facilities annually or as software updates require.
Training shall be provided upon notification and coordination by each specific Power Plant in order to assure personnel are properly trained to conduct power factor testing on plant equipment. The Contractor shall also make available to the staff of each power plant, training in use of the Power Factor test equipment for the specific type of equipment to be tested by power plant staff, not to exceed the allowable training limits provided as part of this contract, and refresher courses as requested by each power plant. Training shall be done at the Sam Rayburn Power Plant as requested by the Designated
Government Representative. Contractor training shall be on the same type equipment or newer model and of the same type the test equipment provided as part of this contract. When training is arranged to be held at the Sam Rayburn Power
Plant, all costs associated with travel by Contractor personnel, per diem and lodging costs shall be at no additional cost to the
Government.
Zero deviation from standard.
The 100% inspection method will be used to monitor all contract services.
Verification of services will be performed by the
Designated
Government
Representative.
PRS # 4 – Analyze and record and provide access to database of historical collected data. The Contractor shall utilize access to the power generation database to benchmark
USACE owned equipment against industry historical data.
The Contractor’s service shall include, engineering staff support to utilize the industry historical database of related high voltage generating and switchyard equipment to provide engineering recommendations for maintenance, and any indicated specific tests required for additional diagnosis, and failure mode analysis to the Corps of Engineers. Upon analysis of periodic test data collected from the Fort Worth
District’s three (3) hydroelectric power plants (Sam Rayburn, RD Willis and Whitney), the Contractor shall provide site specific analysis relative to the power plant submitting test data and directly to the specific power plant submitting the test data for analysis and recommendations.
Zero deviation from standard.
Periodic
Surveillance, as tests are done, sampling of resulting data will be verified as needed by the
Designated
TECHNICAL EXHIBIT 2
DELIVERABLES SCHEDULE
Deliverable Frequency # of Copies Medium/Format Submit To
Item a. The
Contractor shall attend a pre-work conference prior to initiation of any work under this contract and, if required, meetings to discuss safety or hazardous activities.
Conference may be in person or by teleconference, as coordinated by the
Designated
Government
Representative.
Refer to PWS paragraph 1.4.9.
Contractor shall be required to attend a meeting prior to commencement of initial work or at any time the KO or
Designated
Government
Representative determines performance does not meet the minimum standards of this contract, or issues concerning safety are present.
Attendance is required to satisfy all meeting sign in logs or identify corrective actions.
The Contractor shall submit responses by hard copy, fax or electronic, email format to resolve safety issues or performance issues.
Conference shall be held on site at the
Sam Rayburn Power
Plant or by tele-conference as selected by the
Government.
Attn: Tom Webb
7696 255 West, Jasper, TX 75951
Item b. Power
Factor Test analysis test results, maintenance recommendations and historical comparison data shall be available upon request from the USACE
Designated
Representative.
Results due within
30 calendar days of
Governement data submission.
How long does it normally take to have data or recommendations
(other needs ?)
available?
One (1) copy or available online as requested by the
The test results and analysis may be returned in paper
(hard copy), CD in
MS Word, DVD, Briefing Slides on
CD, Excel
Spreadsheet, etc.
In addition to this format, non sensitive material may be attached to an email to expedite delivery.
Sam Rayburn Power
Plant.
Attn: Tom Webb
Item c. Contractor shall provide all necessary training manuals during equipment training.
Training materials due once, at time of training.
Number of copies:
2 ea Hard Copy
2 ea CD
The Contractor shall provide hard copy
Sam Rayburn Power
Plant.
Attn: Tom Webb
Item d. Contractor shall submit a complete and accurate invoice upon completion of work. The
Contractor may submit a request partial payment upon completion of
One copy, subject to verification, review and acceptance by the Designated
Representative upon completion of work.
Resubmission may be required as needed if corrections are required.
Two copies required and subject to review and approval by the KO or
Designated
The Contractor shall submit by hard copy, fax or electronic email format. Any noted deficiencies shall be resolved prior to payment being approved and completed.
Invoice submissions shall be made to the
Whitney Project
Office, Attn: Tom Webb
Deliverable Frequency # of Copies Medium/Format Submit To
CLIN, or at completion of work for Power Plants.
Invoices shall include the contract number, the
Contractor’s name, address and contact information as registered under the
System for
Acquisition
Management (SAM) and a list of completed CLINs.
Prices shall be derived from the contract bid schedule for the appropriate Base or
Option Year pricing.
Refer to PWS paragraphs 1.3 and
1.4.6.
Section E - Inspection and Acceptance
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 N/A N/A N/A Government
000101 N/A N/A N/A N/A
000102 N/A N/A N/A N/A
000103 N/A N/A N/A N/A
1001 N/A N/A N/A Government
2001 N/A N/A N/A Government
3001 N/A N/A N/A Government
4001 N/A N/A N/A Government
Section F - Deliveries or Performance
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 POP 01-AUG-2019 TO
31-JUL-2020
N/A WHITNEY AQUILLA LAKES
USAED, FORT WORTH
285 CR 3602
CLIFTON TX 76634
254-622-3332
FOB: Destination
967442
000101 N/A N/A N/A N/A
000102 N/A N/A N/A N/A
000103 N/A N/A N/A N/A
1001 POP 01-AUG-2020 TO
31-JUL-2021
N/A WHITNEY AQUILLA LAKES
USAED, FORT WORTH
285 CR 3602
CLIFTON TX 76634
254-622-3332
2001 POP 01-AUG-2021 TO
31-JUL-2022
N/A (SAME AS PREVIOUS LOCATION)
3001 POP 01-AUG-2022 TO
31-JUL-2023
N/A (SAME AS PREVIOUS LOCATION)
4001 POP 01-AUG-2023 TO
31-JUL-2024
N/A (SAME AS PREVIOUS LOCATION)
Section G - Contract Administration Data
ACCOUNTING AND APPROPRIATION DATA
AA: 096 NA X 2019 3123 000 0000 CCS: 300 M2 2019 08 2455 019920 96412 2540 21911K NA 27B58K
AMOUNT: $11,116.66
AB: 096 NA X 2019 3123 000 0000 CCS: 300 M2 2019 08 2455 016040 96412 2540 2L49C0 NA 263JC4
AMOUNT: $11,116.67
AC: 096 NA X 2019 3123 000 0000 CCS: 300 M2 2019 08 2455 079053 96412 2540 2BHHJ5 NA 25K520
AMOUNT: $11,116.67
ACRN CLIN/SLIN CIN AMOUNT
AA 000101 W45XMA912642840001 $11,116.66
AB 000102 W45XMA912642840002 $11,116.67
AC 000103 W45XMA912642840003 $11,116.67
Section I - Contract Clauses
CLAUSES INCORPORATED BY REFERENCE
52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011
52.204-10 Reporting Executive Compensation and First-Tier
Subcontract Awards
OCT 2018
52.204-18 Commercial and Government Entity Code Maintenance JUL 2016
52.209-6 Protecting the Government's Interest When Subcontracting
With Contractors Debarred, Suspended, or Proposed for
Debarment
OCT 2015
52.209-10 Prohibition on Contracting With Inverted Domestic
Corporations
NOV 2015
52.212-4 Contract Terms and Conditions--Commercial Items OCT 2018
52.219-6 Notice Of Total Small Business Set-Aside NOV 2011
52.222-3 Convict Labor JUN 2003
52.222-19 Child Labor -- Cooperation with Authorities and Remedies JAN 2018
52.222-21 Prohibition Of Segregated Facilities APR 2015
52.222-26 Equal Opportunity SEP 2016
52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011
52.223-15 Energy Efficiency in Energy-Consuming Products DEC 2007
52.223-16 Alt I Acquisition of EPEAT - Registered Personal Computer
Products - Alternate I
JUN 2014
52.223-17 Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts
AUG 2018
52.223-18 Encouraging Contractor Policies To Ban Text Messaging
While Driving
AUG 2011
52.225-13 Restrictions on Certain Foreign Purchases JUN 2008
52.232-33 Payment by Electronic Funds Transfer--System for Award
Management
OCT 2018
52.233-3 Protest After Award AUG 1996
52.237-2 Protection Of Government Buildings, Equipment, And
Vegetation
APR 1984
52.237-3 Continuity Of Services JAN 1991
52.253-1 Computer Generated Forms JAN 1991
252.203-7000 Requirements Relating to Compensation of Former DoD
Officials
SEP 2011
252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013
252.204-7000 Disclosure Of Information OCT 2016
252.204-7003 Control Of Government Personnel Work Product APR 1992
252.223-7006 Prohibition On Storage, Treatment, and Disposal of Toxic or
Hazardous Materials
SEP 2014
252.225-7001 Buy American And Balance Of Payments Program-- Basic DEC 2017
252.225-7002 Qualifying Country Sources As Subcontractors DEC 2017
252.232-7003 Electronic Submission of Payment Requests and Receiving
Reports
DEC 2018
252.232-7010 Levies on Contract Payments DEC 2006
252.233-7001 Choice of Law (Overseas) JUN 1997
252.239-7001 Information Assurance Contractor Training and Certification JAN 2008
252.243-7001 Pricing Of Contract Modifications DEC 1991
252.246-7004 Safety of Facilities, Infrastructure, and Equipment for
Military Operations
OCT 2010
252.247-7023 Transportation of Supplies by Sea FEB 2019
CLAUSES INCORPORATED BY FULL TEXT
52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC
2014)
The Contractor's representations and certifications, including those completed electronically via the System for
Award Management (SAM), are incorporated by reference into the contract.
(End of clause)
52.212-5 CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT STATUTES OR
EXECUTIVE ORDERS—COMMERCIAL ITEMS (DEVIATION 2018-O0021) (MAY 2019)
(a) Comptroller General Examination of Record. The Contractor shall comply with the provisions of this paragraph
(a) if this contract was awarded using other than sealed bid, is in excess of the simplified acquisition threshold, and does not contain the clause at 52.215-2, Audit and Records—Negotiation.
(1) The Comptroller General of the United States, or an authorized representative of the Comptroller General, shall have access to and right to examine any of the Contractor’s directly pertinent records involving transactions related to this contract.
(2) The Contractor shall make available at its offices at all reasonable times the records, materials, and other evidence for examination, audit, or reproduction, until 3 years after final payment under this contract or for any shorter period specified in FAR Subpart 4.7, Contractor Records Retention, of the other clauses of this contract. If this contract is completely or partially terminated, the records relating to the work terminated shall be made available for 3 years after any resulting final termination settlement. Records relating to appeals under the disputes clause or to litigation or the settlement of claims arising under or relating to this contract shall be made available until such appeals, litigation, or claims are finally resolved.
(3) As used in this clause, records include books, documents, accounting procedures and practices, and other data, regardless of type and regardless of form. This does not require the Contractor to create or maintain any record that the Contractor does not maintain in the ordinary course of business or pursuant to a provision of law.
(b)(1) Notwithstanding the requirements of any other clauses of this contract, the Contractor is not required to flow down any FAR clause, other than those in this paragraph (b) (1) in a subcontract for commercial items. Unless otherwise indicated below, the extent of the flow down shall be as required by the clause—
(i) 52.203-13, Contractor Code of Business Ethics and Conduct (Oct 2015) (41 U.S.C. 3509).
(ii) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017)
(section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L.
113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).
(iii) 52.204-23, Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by
Kaspersky Lab and Other Covered Entities (Jul 2018) (Section 1634 of Pub. L. 115-91).
(iv) 52.219-8, Utilization of Small Business Concerns (Oct 2018) (15 U.S.C. 637(d)(2) and (3)), in all subcontracts that offer further subcontracting opportunities. If the subcontract (except subcontracts to small business concerns) exceeds $700,000 ($1.5 million for construction of any public facility), the subcontractor must include 52.219-8 in lower tier subcontracts that offer subcontracting opportunities.
(v) 52.222-17, Nondisplacement of Qualified Workers (MAY 2014) (E.O. 13495). Flow down required in accordance with paragraph (l) of FAR clause 52.222-17.
(vi) 52.222-21, Prohibition of Segregated Facilities (APR 2015).
(vii) 52.222-26, Equal Opportunity (Sept 2016) (E.O. 11246).
(viii) 52.222-35, Equal Opportunity for Veterans (Oct 2015) (38 U.S.C. 4212).
(ix) 52.222-36, Equal Opportunity for Workers with Disabilities (July 2014) (29 U.S.C. 793).
(x) 52.222-37, Employment Reports on Veterans (FEB 2016) (38 U.S.C. 4212).
(xi) 52.222-40, Notification of Employee Rights Under the National Labor Relations Act (Dec 2010) (E.O. 13496).
Flow down required in accordance with paragraph (f) of FAR clause 52.222-40.
(xii) 52.222-41, Service Contract Labor Standards (Aug 2018) (41 U.S.C. chapter 67).
(xiii)(A) 52.222-50, Combating Trafficking in Persons (Mar 2015) (22 U.S.C. chapter 78 and E.O. 13627).
(B) Alternate I (Mar 2015) of 52.222-50 (22 U.S.C. chapter 78 and E.O. 13627).
(xiv) 52.222-51, Exemption from Application of the Service Contract Act to Contracts for Maintenance, Calibration, or Repair of Certain Equipment-Requirements (May 2014) (41 U.S.C. chapter 67).
(xv) 52.222-53, Exemption from Application of the Service Contract Act to Contracts for Certain Services-
Requirements (May 2014) (41 U.S.C. chapter 67).
(xvi) 52.222-54, Employment Eligibility Verification (Oct 2015) (E.O. 12989).
(xvii) 52.222-55, Minimum Wages Under Executive Order 13658 (Dec 2015).
(xviii) 52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan 2017) (E.O. 13706).
(xix)(A) 52.224-3, Privacy Training (JAN 2017) (5 U.S.C. 552a).
(B) Alternate I (JAN 2017) of 52.224-3.
(xx) 52.225-26, Contractors Performing Private Security Functions Outside the United States (Oct 2016) (Section
862, as amended, of the National Defense Authorization Act for Fiscal Year 2008; 10 U.S.C. 2302 Note).
(xxi) 52.226-6, Promoting Excess Food Donation to Nonprofit Organizations (May 2014) (42 U.S.C. 1792). Flow down required in accordance with paragraph (e) of FAR clause 52.226-6.
(xxii) 52.247-64, Preference for Privately Owned U.S.-Flag Commercial Vessels (Feb 2006) (46 U.S.C. Appx.
1241(b) and 10 U.S.C. 2631). Flow down required in accordance with paragraph (d) of FAR clause 52.247-64.
(2) While not required, the contractor may include in its subcontracts for commercial items a minimal number of additional clauses necessary to satisfy its contractual obligations.
52.217-9 OPTION TO EXTEND THE TERM OF THE CONTRACT (MAR 2000)
(a) The Government may extend the term of this contract by written notice to the Contractor within 30 days before the contract expires; provided that the Government gives the Contractor a preliminary written notice of its intent to extend at least 30 days before the contract expires. The preliminary notice does not commit the Government to an extension.
(b) If the Government exercises this option, the extended contract shall be considered to include this option clause.
(c) The total duration of this contract, including the exercise of any options under this clause, shall not exceed 66 month.
52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JULY 2013)
(a) Definitions. As used in this clause--
Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.
Small business concern means a concern, including its affiliates, that is independently owned and operated,…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it.