The Solicitation for Energy Aerospace Operation Facility; Lackland AFB, Texas is amended as follows. NOTE: Proposal Receipt date is 06 May 2019; at 10:00 a.m.,CST, as previously announced.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B5_19B0025_Site_Visit_Sign-In_Sheet.pdf.pdf | ||
| W9126G19B0025_Final.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04 EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The Solicitation for Energy Aerospace Operation Facility; Lackland AFB, Texas is amended as follows.
See SF30 Continuation Sheet(s)
NOTE: Proposal Receipt date is 06 May 2019; at 10:00 a.m.,CST, as previously announced.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA 15C. DATE SIGNED 15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer) (Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X 9A. AMENDMENT OF SOLICITATION NO.
W9126G19B0025
X 9B. DATED (SEE ITEM 11)
05-Apr-2019
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
23 -Apr-2019
CODE
US ARMY ENGINEER DISTRICT, FORT WORTH
ATTN: CESWF-CT
819 TAYLOR ST, ROOM 2A19
P.O. BOX 17300
FORT WORTH TX 76102-0300
W9126G 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODE CODE
EMAIL: TEL:
W9126G19B0025
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
CHANGES TO SOLICITATION W9126G19B0025
CHANGES TO THE SPECIFICATIONS
1. New Sections 01 91 00.15 TOTAL BUILDING COMMISSIONING, bearing the notation W9126G19B0025 0001.
2. Replacement Submittle Register: Replace the following section with the accompanying new section of the same number and title bearing the notation W9126G19B0025 0001.
End of Summary of Changes
Energy Aerospace Operation Facility LKEAOF
SECTION 01 91 00.15
TOTAL BUILDING COMMISSIONING
PART 1 GENERAL
1.1 SUMMARY
Commission the building systems listed herein. Employ the services of an independent Commissioning Firm. The Commissioning Firm must be a 1st tier subcontractor of the General or Prime Contractor and must be financially and corporately independent of all other subcontractors. The Commissioning Firm must employ a Lead Commissioning Specialist that coordinates all aspects of the commissioning process. Conform to the commissioning procedures outlined in this specification.
1.2 SYSTEMS TO BE COMMISSIONED
Commission the following systems:
Heating, Ventilating, Air Conditioning, and Refrigeration Systems (HVAC) Building Automation System Utility Monitoring and Control System Lighting Systems Power Distribution Systems Service Water Heating Systems Plumbing Systems Energy and Water Utility Metering Systems and Sub-Meters Fenestration Control Systems Building Envelope: include moisture, thermal integrity, and air tightness for the entire buidling envelope including systems such as walls, fenestration, and roofing.
1.3 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING
ENGINEERS (ASHRAE)
ASHRAE 180 (2012) Standard Practice for Inspection and Maintenance of Commercial Building HVAC Systems
ASHRAE 202 (2013; Addenda B 2018) Commissioning Process for Buildings and Systems
ASSOCIATED AIR BALANCE COUNCIL (AABC)
ACG Commissioning Guideline (2005) Commissioning Guideline
SECTION 01 91 00.15 Page 1
W9126G19B0025 0001
NATIONAL ENVIRONMENTAL BALANCING BUREAU (NEBB)
NEBB Commissioning Standard (2009) Procedural Standards for Whole Building Systems Commissioning of New Construction; 3rd Edition
SHEET METAL AND AIR CONDITIONING CONTRACTORS' NATIONAL ASSOCIATION
(SMACNA)
SMACNA 1429 (1994) HVAC Systems Commissioning Manual, 1st Edition
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 25-345-1 (1991) Systems Operation and Maintenance Documentation
1.4 COMMUNICATION WITH THE GOVERNMENT
The Lead Commissioning Specialist (CxC) must submit all plans, schedules, reports, and documentation directly to the Contracting Officer Representative concurrent with submission to the CQC System Manager. The Lead Commissioning Specialist must have direct communication with the Contracting Officer's Representative regarding all elements of the commissioning process; however, the Government has no direct contract authority with the Lead Commissioning Specialist.
1.5 SEQUENCING AND SCHEDULING
1.5.1 Sequencing
Complete the following prior to starting Functional Performance Tests of mechanical systems:
a. All equipment and systems have been completed, cleaned, flushed, disinfected, calibrated, tested, and operate in accordance with contract documents and construction plans and specifications.
b. Performance Verification Tests of the controls systems have been completed and the Performance Verification Test Report has been submitted and approved in accordance with Specification Section 23 09 00
INSTRUMENTATION AND CONTROL FOR HVAC.
c. Testing, Adjusting, and Balancing has been completed and the Testing, Adjusting, and Balancing Report, has been submitted and approved in accordance with Specification Section 23 05 93 TESTING, ADJUSTING, AND
BALANCING FOR HVAC.
d. The building envelope is enclosed according to contract documents with final construction completed, the Air Barrier Pressure Tests have been completed and the Air Leakage Test Reports and Diagnostic Test Reports have been submitted and approved in accordance with Specification Section 07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR
TIGHTNESS.
e. The Pre-Functional Checklists have been submitted and approved.
f. The Certificate of Readiness for mechanical systems has been submitted and approved.
SECTION 01 91 00.15 Page 2
Complete the following prior to starting Functional Performance Tests of the electrical systems:
a. All electrical, power generation, and lighting equipment and systems have been completed, calibrated, tested, and operate in accordance with contract documents and construction plans and specifications.
b. The building envelope is enclosed according to contract documents with final construction completed.
c. Ceiling tiles, floor coverings, and window coverings are in place.
d. The Certificate of Readiness for electrical systems has been submitted and approved.
e. LED light sources have completed a minimum 100 hour burn-in period as recommended by the fixture manufacturer.
f. Furniture is in place.
1.5.2 Project Schedule
Include the following tasks in the project schedule required by Section
01 32 01.00 10 PROJECT SCHEDULE 01 32 17.00 20 COST-LOADED NETWORK ANALYSIS
SCHEDULES (NAS). Ensure sufficient time is scheduled to accommodate the requirements of this specification section. The order of items listed below is not intended to imply a specified sequence:
a. Submission and approval of the Commissioning Firm and Commissioning Specialist.
b. Submission and approval of the Testing, Adjusting, and Balancing (TAB) Firm and TAB Specialist specified in Specification Section 23 05 93
TESTING, ADJUSTING, AND BALANCING FOR HVAC.
c. Submission of the Design Review Report specified herein.
d. Submission of the Design Review Report specified in Specification Section 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC.
e. Submission and approval of the Construction Phase Commissioning Plan.
f. Installation of permanent utilities (gas, water, electric).
g. Building Envelope Construction.
h. Submission and approval of the Building Envelope Inspection Checklists.
i. Air Barrier Pressure Tests specified in Specification Section 07 05 23
PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS.
j. Drainage and Vent, Building Sewers, Water Supply Systems and Backflow Prevention Assembly Tests specified in Specification Section 22 00 00
PLUMBING, GENERAL PURPOSE.
k. Factory Acceptance Testing for each of the systems to be commissioned as required by technical specifications.
SECTION 01 91 00.15 Page 3
l. Manufacturer's Equipment Start-Up for each of the systems to be commissioned.
m. Potable Water System Flushing specified in Specification Section
22 00 00 PLUMBING, GENERAL PURPOSE.
n. Operational Tests of the plumbing system specified in Specification Section 22 00 00 PLUMBING, GENERAL PURPOSE.
o. Potable Water System Disinfection specified in Specification Section
22 00 00 PLUMBING, GENERAL PURPOSE.
p. Submission and approval of the TAB Schematic Drawings, Report Forms, and Procedures specified in Specification Section 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC.
q. Submission and approval of Duct Air Leakage Test Procedures specified in Specification Section 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR
HVAC.
r. Duct Air Leakage Test Execution specified in Specification Section
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC.
s. Submission and approval of the Final Duct Air Leakage Test Report specified in Specification Section 23 05 93 TESTING, ADJUSTING, AND
BALANCING FOR HVAC.
t. Testing, Adjusting, and Balancing (TAB) Field Work required by Specification Section 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR
HVAC.
u. Submission and approval of the TAB Report specified in Specification Section 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC.
v. TAB Field Acceptance Testing required by Specification Section 23 05 93
TESTING, ADJUSTING, AND BALANCING FOR HVAC.
w. Submission and approval of the Start-Up Testing Report specified in Specification Section 23 09 23.02 INSTRUMENTATION AND CONTROL FOR HVAC.
x. Submission and approval of the Performance Verification Test Procedures specified in Specification Section 23 09 23.02 INSTRUMENTATION AND
CONTROL FOR HVAC.
y. Performance Verification Tests required by Specification Section 23 09
23.02 INSTRUMENTATION AND CONTROL FOR HVAC.
z. Performance Verification Test Report specified in Specification Section 23 09 23.02 INSTRUMENTATION AND CONTROL FOR HVAC.
aa. Pre-Functional Checklist Submittal.
bb. Functional Performance Testing for each system to be commissioned.
cc. Integrated Systems Tests.
dd. Post-Test Deficiency Correction for each system to be commissioned.
ee. Re-Testing.
SECTION 01 91 00.15 Page 4
ff. Training for each of the systems to be commissioned.
gg. Systems Manual Computerized Maintenance Management System Manual, Maintenance Plan, and Service Life Plan submission and approval.
hh. Seasonal Testing.
1.5.3 Phasing
1.6 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Commissioning Firm; G, DO
Lead Commissioning Specialist; G, DO
Technical Commissioning Specialists; G, DO
Commissioning Firm's Contract; G, DO
SD-06 Test Reports
Design Review Report; G, DO
Interim Construction Phase Commissioning Plan; G, DO
Final Construction Phase Commissioning Plan; G, DO S
Template Building Envelope Inspection Checklists; G, DO
Building Envelope Inspection Checklists; G, DO
Pre-Functional Checklists; G, DO
Issues Log
Commissioning Report; G, DO
SD-07 Certificates
Certificate of Readiness; G, DO
SD-10 Operation and Maintenance Data
Training Plan; G, RO
Training Attendance Rosters; G, RO
Systems Manual; G, DO
SECTION 01 91 00.15 Page 5
Systems Manual G, DO
Maintenance and Service Life Plans; G, DO
SD-11 Closeout Submittals
Final Commissioning Report; S, DO
1.7 COMMISSIONING FIRM
Provide a Commissioning Firm that is certified in commissioning by one of the following: the AABC Commissioning Group (ACG); the National Environmental Balancing Bureau (NEBB); the International Certification Board/Testing, Adjusting, and Balancing Bureau (ICB/TABB), the Building Commissioning Association (BCA); the Association of Energy Engineers (AEE).
The Commissioning Firm may employ a commissioning professional certified by the University of Wisconsin-Madison or the American Society of Heating, Refrigeration, and Air Conditioning Engineers (ASHRAE) as required in paragraph LEAD COMMISSIONING SPECIALIST as an alternative to certification of the Commissioning Firm. The Commissioning Firm must be certified in all systems to be commissioned to the extent such certifications are available from the certifying body. Describe any lapses in certification or disciplinary action taken by the certifying body against the proposed Commissioning Firm or Lead Commissioning Specialist in detail. Any firm or commissioning professional that has been the subject of disciplinary action by the certifying body within the five years preceding contract award is not eligible to perform any duties related to commissioning.
a. Submit the Commissioning Firm's certification of qualifications including the name of the firm and certifications no later than 60 calendar days after Notice to Proceed. Submit one hard copy and an electronic copy.
b. The Commissioning Firm's and Commissioning Specialists' certifications must be maintained for the entire duration of the duties specified herein. If, for any reason, the firm or a specialist loses a certification during this period, immediately notify the Contracting Officer's Representative and submit another Commissioning Firm or Commissioning Specialist for approval. All work specified in this specification section performed by the Commissioning Firm or associated Commissioning Specialists is invalid if the Commissioning Firm or Commissioning Specialist loses its certification prior to contract completion and must be performed by an approved successor.
c. The Commissioning Firm must oversee and assist the General or Prime Contractor with the work specified herein. Submit the Commissioning Firm's Contract including the Scope of Work associated with the paragraph POST-CONSTRUCTION SUPPORT no later than 30 calendar days after approval of the Commissioning Firm. Submit one hard copy and an electronic copy.
d. The Commissioning Firm may act as the Pressure Test Agency required by UFGS Section 07 05 23Specification Section 07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS provided that all qualification requirements of that specification section are met.
SECTION 01 91 00.15 Page 6
1.7.1 Lead Commissioning Specialist
The Commissioning Firm must provide a Lead Commissioning Specialist (CxC) that has a minimum of five years of commissioning experience, including two projects of similar size and complexity, and that is one of the following:
a NEBB qualified Systems Commissioning Administrator (SCA); ACG Certified Commissioning Authority (CxA); ICB/TABB Certified Commissioning Supervisor;
BCA Certified Commissioning Professional (CCP); AEE Certified Building Commissioning Professional (CBCP); University of Wisconsin-Madison Qualified Commissioning Process Provider (QCxP); ASHRAE Commissioning Process Management Professional (CPMP).
a. Submit the Lead Commissioning Specialist's certification of qualifications including the name of the specialist and firm;
certifications; years of experience; and a listing of representative projects of similar size and complexity no later than 30 calendar days after Notice to Proceed. Submit one hard copy and an electronic copy.
b. The Lead Commissioning Specialists certifications must be maintained for the entire duration of the duties specified herein. If, for any reason, the specialist loses a certification during this period, immediately notify the Contracting Officer's Representative and submit another Lead Commissioning Specialist for approval. All work specified in this specification section to be performed by the Lead Commissioning Specialist is invalid if the Lead Commissioning Specialist loses its certification prior to contract completion and must be performed by an approved successor.
c. The Lead Commissioning Specialist must lead and oversee the commissioning work specified herein and be the primary point of contact for the Government regarding the commissioning work. One of the Technical Commissioning Specialists may be the Lead Commissioning Specialist provided that all of the qualification requirements are met.
1.7.2 Technical Commissioning Specialists
Technical Commissioning Specialists, employed by the Commissioning Firm and that have the following qualifications, must perform the technical work specified herein associated with each system to be commissioned:
a. Mechanical Technical Commissioning Specialist: The technical work associated with mechanical systems including Heating, Ventilating, Air Conditioning, and Refrigeration Systems; Building Automation System;
Utility Monitoring and Control System; Service Water Heating Systems;
Plumbing Systems; Energy and Water Utility Metering Systems must be performed by a Commissioning Specialist certified by NEBB, ACG, ICB/TABB, or BCA in the commissioning of HVAC systems with five years of experience in the commissioning of HVAC systems.
b. Electrical Technical Commissioning Specialist: The technical work associated with electrical systems including Lighting Systems; Power Distribution Systems; Electrical Utility Metering Systems must be performed by an engineering technician certified by the InterNational Electrical Testing Association (NETA) with five years of experience inspecting, testing, and calibrating electrical distribution and generation equipment, systems, and devices.
c. Building Envelope Technical Commissioning SpecialistThe technical work associated with the Building Envelope system must be performed by a
SECTION 01 91 00.15 Page 7 registered architect with five years of building envelope design or construction experience. The Commissioning Firm team member with the required experience related to the building envelope may act as the Air Barrier Inspector required by Specification Section 07 27 10.00 10 BUILDING AIR BARRIER SYSTEM provided that all qualification requirements of that specification section are met.
d. Submit the Technical Commissioning Specialist's certification of qualifications including the name of the specialist and firm;
certifications; years of experience; and a listing of representative projects of similar size and complexity no later than 30 calendar days after Notice to Proceed. Submit one hard copy and an electronic copy.
1.7.3 Commissioning Standard
Comply with the requirements of the commissioning standard under which the Commissioning Firm and Specialists qualifications are approved. When the firm and specialists are certified by BCA, AEE, ASHRAE, or the University of Wisconsin-Madison, comply with the requirements of one of the acceptable standards unless otherwise stated herein. The acceptable standards are ACG Commissioning Guideline, NEBB Commissioning Standard, SMACNA 1429, or ASHRAE 202. Comply with applicable NETA testing standards for electrical systems.
a. Implement all recommendations and suggested practices contained in the Commissioning Standard and electrical test standards.
b. Use the Commissioning Standard for all aspects of Commissioning, including calibration of instruments.
c. Where the instrument manufacturer calibration recommendations are more stringent than those listed in the Commissioning Standard, adhere to the manufacturer calibration recommendations.
d. All quality assurance provisions of the Commissioning Standard such as performance guarantees are part of this contract.
e. The Commissioning Specialists must develop commissioning procedures for any systems or system components not covered in the Commissioning Standard.
f. Use any new requirements, recommendations, and procedures published or adopted prior to contract solicitation by the body responsible for the Commissioning Standard.
1.8 SUSTAINABILITY THIRD PARTY CERTIFICATION (TPC)
The Commissioning Specialists must execute and document the commissioning activities required of the Commissioning Authority for the purposes of complying with the Third Party Certification (TPC) requirements for the project in accordance with Section 01 33 29 SUSTAINABILITY REPORTING.
Provide all commissioning documentation required to meet the TPC requirements.
1.9 ISSUES LOG
The Lead Commissioning Specialist must develop and maintain an Issues Log for tracking and resolution of all deficiencies discovered through submittal reviews, inspection, and testing. Include the date of final
SECTION 01 91 00.15 Page 8 resolution of issues as confirmed by the Commissioning Specialist. Submit the Issues Log on a monthly basis at a minimum. At any point during construction, any commissioning team member finding deficiencies may communicate those deficiencies in writing to the Commissioning Specialist for inclusion into the Issues Log.
Track construction deficiencies identified in the Issues Log using QCS as specified in Specification Section 01 45 00.15 10 RESIDENT MANAGEMENT
SYSTEM CONTRACTOR MODE(RMS CM).
1.10 CERTIFICATE OF READINESS
Prior to scheduling Functional Performance Tests for each system, issue a Certificate of Readiness for the system certifying that the system is ready for Functional Performance Testing. The Certificate of Readiness must include, for each system to be commissioned, all equipment and system start-up reports; Performance Verification Test Reports; completed Building Envelope Inspection Checklists; completed Pre-Functional Checklists;
Testing, Adjusting, and Balancing (TAB) Report; HVAC Controls Start-Up Reports; and the Air Leakage Test Reports and Diagnostic Test Reports to the extent applicable to the system. The Contractor; the Lead Commissioning Specialist; the Contractor's Quality Control Representative;
the Mechanical, Electrical, Controls, and TAB subcontractor representatives must sign and date the Certificate of Readiness. Submit the Certificate of Readiness for each system no later than 14 calendar days prior to Functional Performance Tests of that system. Submit one hard copy and an electronic copy. Do not schedule Functional Performance Tests for a system until the Certificate of Readiness for that system receives approval by the Government.
PART 2 PRODUCTS
Not used
PART 3 EXECUTION
3.1 CONSTRUCTION PHASE
3.1.1 Construction Commissioning Coordination Meeting
The Lead Commissioning Specialist must lead a Construction Commissioning Coordination Meeting no later than 14 days after approval of the Commissioning Firm and Commissioning Specialists to discuss the commissioning process including contract requirements, lines of communication, roles and responsibilities, schedules, documentation requirements, inspection and test procedures, and logistics as specified in this specification section. The Contractor's Superintendent or Project Manager, the Contractor's Quality Control Representative, and the Government must attend this meeting. Invite the User and a Directorate of Public Works Representative or a Reserve Support Command Representativea Base Civil Engineer Office Representative, to attend this meeting.
3.1.2 Design Phase Commissioning Plan
A commissioning plan developed during design phase is provided as Appendix C for information only. The design phase commissioning plan does not form a part of this contract and is provided for commissioning review purposes only.
SECTION 01 91 00.15 Page 9
3.1.3 Construction Phase Commissioning Plan
3.1.3.1 Interim Construction Phase Commissioning Plan
The Lead Commissioning Specialist (CxC) must prepare the Interim Construction Phase Commissioning Plan. Submit the Interim Construction Phase Commissioning Plan no later than 30 calendar days after the Construction Commissioning Coordination Meeting and no later than 14 days prior to the start of construction of the building envelope. Submit one hard copy and an electronic copy.
Identify the commissioning and testing standards and outline the overall commissioning process, the commissioning schedule, the commissioning team members and responsibilities, lines of communication, documentation requirements for the construction phase of the project, and Template Building Envelope Inspection Checklists in the Interim Construction Phase Commissioning Plan.
3.1.3.1.1 Checklists
Download example Building Envelope Inspection Checklists, Pre-Functional Checklists, Integrated Systems Test Checklists, and Functional Performance Test Checklists for specification section 01 91 00.15 TOTAL BUILDING COMMISSIONING at the following location:
http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs/forms-graphics-t The checklists submitted in the Interim and Final Construction Phase Commissioning Plans must contain the same level of detail shown in the examples. The submitted checklists are not required to match the format of the examples.
3.1.3.1.2 Template Building Envelope Inspection Checklists
The Building Envelope Technical Commissioning Specialist must develop the Template Building Envelope Inspection Checklists. Include all items that verify the building materials and construction maintain the required thermal and moisture integrity and air tightness of the building envelope system in the Building Envelope Inspection Checklists.
3.1.3.2 Final Construction Phase Commissioning Plan
The Lead Commissioning Specialist (CxC) must prepare the Final Construction Phase Commissioning Plan. Submit the Final Construction Phase Commissioning Plan no later than 30 calendar days prior to the start of Pre-Functional Checks. Submit one hard copy and an electronic copy. Once approved, file the approved plan in the Sustainability eNotebook.
Include the information provided in the Interim Construction Phase Commissioning Plan. In addition, the Technical Commissioning Specialist must develop the Pre-Functional Checklists, Integrated Systems Test Checklists, and Functional Performance Test Checklists for each building, for each system required to be commissioned, and for each component for inclusion in the Final Construction Phase Commissioning Plan.
3.1.3.2.1 Pre-Functional Checklists
The Pre-Functional Checklists must include items for physical inspection or testing that demonstrate that installation and start-up of equipment and systems is complete. Refer to paragraph Pre-Functional Checks for more information.
SECTION 01 91 00.15 Page 10
3.1.3.2.2 Functional Performance Test Checklists
Functional Performance Test Checklists must include procedures that explain, step-by-step, the actions and expected results that will demonstrate that the system performs in accordance with the contract.
Refer to paragraph Functional Performance and Integrated Systems Tests for more information. Include the following sections and details appropriate to the systems being tested in the Functional Performance Test Checklists:
a. Notable system features including information about controls to facilitate understanding of system operation.
b. Conclusions and recommendations. Conclusions must clearly indicate if system does or does not perform in accordance with contract requirements. Recommendation must clearly indicate that the system should or should not be accepted by the Government.
c. Test conditions including date, beginning and ending time, and beginning and ending outdoor air conditions.
d. Attendees.
e. Identification of the equipment involved in the test.
f. Control system feature identification.
g. Point-to-point observations including demonstrating system flow meters and sensors have been calibrated and are correctly displayed on the Operator work station.
h. Actuator operation observations demonstrating actuator responses to commands from the control system.
i. As-found condition of the system operation.
j. List of test items with step numbers along with the corresponding feature or control operation, intended test procedure, expected system response, and pass/fail indication.
k. Space for comments for each test item.
3.1.3.2.3 Integrated Systems Test Checklists
Integrated Systems Test Checklists must include test procedures that explain, step-by-step, the actions and expected results that will demonstrate that the interactive operations between systems performs in accordance with the contract. Refer to paragraph Functional Performance and Integrated Systems Tests for more information. Include the following sections in the Integrated Systems Test Checklists:
a. Notable features of the interconnected systems organized by discipline including information to facilitate understanding of system operation.
b. Conclusions and recommendations. Conclusions must clearly indicate if the systems do or do not perform in accordance with contract requirements. Recommendation must clearly indicate that the systems should or should not be accepted by the Government.
SECTION 01 91 00.15 Page 11
c. Test conditions including date and beginning and ending time.
d. Attendees.
e. Identification of the equipment and systems involved in the test.
f. List of test items with step numbers along with the corresponding feature or control operation, intended test procedure, expected system response, and pass/fail indication.
g. Space for comments for each test item.
3.1.4 Design Review
The Lead Commissioning Specialist and Technical Commissioning Specialists must review the construction contract plans and specifications, and the Owner's Project Requirements Document. The Owner's Project Requirements Document is attached as Appendix A. The Owner's Project Requirements Document is not a contract document and is provided for commissioning review purposes only.
a. Advise the Contracting Officer's Representative of any discrepancies between the Design and Owner's Project Requirements, deficiencies of the design to comply with the Owner's Project Requirements, and deficiencies that would prevent the building systems and features from operating or performing effectively and from being adequately maintainable.
b. The Commissioning Specialists must provide a Design Review Report individually listing each deficiency and the corresponding proposed corrective action necessary for proper system operation or performance. Submit one hard copy and an electronic copy of the report to the Contracting Officer's Representative no later than 14 days after approval of the Commissioning Specialists.
c. The Lead Commissioning Specialist must participate in a meeting to discuss any items contained in the report no later than 14 calendar days after submission of the report.
3.1.5 Construction Submittals
Provide all submittals associated with the systems to be commissioned, including shop drawings; equipment submittals; test plans, procedures, and reports; and resubmittal's to the Commissioning Specialists. The Technical Commissioning Specialist must review the submittals to the extent necessary verify that the equipment and system installation will comply with the contract requirements and the Owner's Project Requirements Document.
3.1.6 Inspection and Testing
Demonstrate that all system components have been installed, that each control device and item of equipment operates, and that the systems operate and perform, including interactive operation between systems, in accordance with contract documents and the Owner's Project Requirements. Requirements in related specification sections are independent from the requirements of this section and do not satisfy any of the requirements specified in this specification section. Provide all materials, services, and labor required to perform the Pre-Functional Checks, Building Envelope Inspection, Integrated Systems Tests, and Functional Performance Tests.
SECTION 01 91 00.15 Page 12
3.1.6.1 Commissioning Team
Provide a commissioning representative for each sub-contractor associated with the systems to be commissioned. Each commissioning representative is responsible for coordination of their respective sub-contractor's execution of the commissioning activities and participation in the inspection and testing required by this specification section. The designers listed below are the designers of record for their respective systems. Substitutes must be approved by the Contracting Officer's Representative.
3.1.6.1.1 Building Envelope Inspections Team
The following team members must participate in building envelope inspections:
Designation Function
CxB Building Envelope Technical Commissioning Specialist
QAR Contracting Officer's Quality Assurance Representative
CQC Contractor's Quality Control Personnel
BEC Contractor's Building Envelope Commissioning Representative
AD Architectural Designer
3.1.6.1.2 Mechanical System Pre-Functional Checks Team
The following team members must participate in Pre-Functional checks of mechanical systems:
Designation Function
CxM Mechanical System Technical Commissioning Specialist
QAR Contracting Officer's Quality Assurance Representative
CQC Contractor's Quality Control Personnel
MC Contractor's Mechanical Commissioning Representative
EC Contractor's Electrical Commissioning Representative
CC Contractor's Controls Commissioning Representative
TABC Contractor's TAB Commissioning Representative
PC Contractor's Plumbing Commissioning Representative
IC Contractor's Irrigation Commissioning Representative
SECTION 01 91 00.15 Page 13
3.1.6.1.3 Electrical System Pre-Functional Checks Team
The following team members must participate in Pre-Functional checks of electrical systems:
Designation Function
CxE Electrical System Technical Commissioning Specialist
QAR Contracting Officer's Quality Assurance Representative
CQC Contractor's Quality Control Personnel
EC Contractor's Electrical Commissioning Representative
3.1.6.1.4 Mechanical Systems Test Team
The following team members must participate in Functional Performance and Integrated Systems Testing of mechanical systems:
Designation Function
CxM Mechanical System Technical Commissioning Specialist
QAR Contracting Officer's Quality Assurance Representative
CQC Contractor's Quality Control Personnel
MC Contractor's Mechanical Commissioning Representative
EC Contractor's Electrical Commissioning Representative
CC Contractor's Controls Commissioning Representative
TABC Contractor's TAB Commissioning Representative
PC Contractor's Plumbing Commissioning Representative
IC Contractor's Irrigation Commissioning Representative
MD Mechanical Designer
PD Plumbing Designer
ID Irrigation Designer
3.1.6.1.5 Electrical Systems Test Team
The following team members must participate in Functional Performance and Integrated Systems Testing of electrical systems:
SECTION 01 91 00.15 Page 14
Designation Function
CxE Electrical System Technical Commissioning Specialist
QAR Contracting Officer's Quality Assurance Representative
CQC Contractor's Quality Control Personnel
EC Contractor's Electrical Commissioning Representative
ED Electrical Designer
3.1.6.1.6 Other Pre-Functional and Functional Performance Participants
The following may participate as team members during Pre-Functional Checks and Functional Performance Testing:
Designation Function
DPW Directorate of Public Works Representative
BCE Base Civil Engineer Office Representative
RSC Reserve Support Command Representative
PWD Public Works Division Representative
User Using Agent's Representative
3.1.6.2 Building Envelope Inspection
Document building envelope inspection by the commissioning team using the approved Template Building Envelope Inspection Checklists. Indicate commissioning team member inspection and acceptance of each Building Envelope Inspection Checklist item by initials at the time they are inspected and found to be in conformance with contract requirements.
Inspect checklist items before they become hidden as construction progresses.
a. Submit the completed and initialed Building Envelope Inspection Checklists no later than 7 calendar days after completion of inspection of all checklists items. Submit one hard copy and an electronic copy.
b. The Building Envelope Technical Commissioning Specialist must make at least two site visits to the site to observe construction of the building envelope in-progress. On each visit, the Building Envelope Commissioning Specialist must review the Contractor's in-progress checklists to ensure that the commissioning team is inspecting the building envelope as required.
c. The Building Envelope Technical Commissioning Specialist must witness the building envelope pressure tests and diagnostic tests specified in Specification Section 07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS. The Building Envelope Technical Commissioning
SECTION 01 91 00.15 Page 15
Specialist must review the resulting reports and provide recommendations for correction of any deficiencies or further testing.
3.1.6.3 Pre-Functional Checks
Pre-Functional Checklists from the approved Final Construction Phase Commissioning Plan must be completed by the commissioning team. Complete one Pre-Functional Checklist for each individual item of equipment or system for each system required to be commissioned including, but not limited to, ductwork, piping, equipment, fixtures (lighting and plumbing), and controls. Indicate commissioning team member inspection and acceptance of each Pre-Functional Checklist item by initials. Acceptance of each Pre-Functional Checklist item by each team member indicates that item conforms to the construction contract requirements in their area of responsibility. Technical Commissioning Specialist acceptance of each Pre-Functional Checklist item indicates that each item has been installed correctly and in accordance with contract documents and the Owner's Project Requirements. Submit the completed and initialed Pre-Functional Checklists no later than 7 calendar days after completion of inspection of all checklists items for each system. Submit one hard copy and an electronic copy. Include manufacturer start-up checklists associated with equipment with the submission of the Pre-Functional Checklists.
3.1.6.4 Testing, Adjusting, and Balancing (TAB) Report and Field Acceptance Testing
The Mechanical System Technical Commissioning Specialist must review the pre-final TAB Report required by Specification Section 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC. Identify any deficiencies to the Contracting Officer's Representative and the Contractor's Quality Control Personnel. Resolve all deficiencies prior to TAB Field Acceptance Testing.
The Mechanical System Technical Commissioning Specialist must witness the TAB Field Acceptance Testing specified by Specification Section 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC. Include a certification by the Mechanical Technical Specialist that no outstanding deficiencies exist in the systems relative to Testing, Adjusting, and Balancing with the final TAB Report submittal.
3.1.6.5 HVAC Controls Test Reports
The Mechanical System Technical Commissioning Specialist must review the Start-Up Testing Report and the PVT Procedures and Reports required by Specification Section 23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC.
Include a certification by the Mechanical System Technical Commissioning Specialist that the submittals contain no deficiencies or that the submittals do not indicate any deficiencies in the HVAC systems or HVAC control systems with each of these submittals.
3.1.6.6 Tests
3.1.6.6.1 Functional Performance and Integrated Systems Tests
Schedule Functional Performance Tests for each system only after the Certificate of Readiness has been approved by the Government for the system. Correct all deficiencies identified through any prior review, inspection, or test activity before the start of Functional Performance Tests. Perform Integrated Systems Tests only after the Functional Performance Tests for each associated system are completed with all
SECTION 01 91 00.15 Page 16 deficiencies resolved and after the related Functional Performance Test Checklists have been signed by each commissioning team member.
a. Functional Performance Tests and Integrated Systems Tests must be performed with the Contracting Officer's Quality Assurance Representative present.
b. Abort Functional Performance Tests or Integrated Systems Tests when any system deficiency prevents the successful completion of the test.
c. Technical Commissioning Specialists must lead and document all Functional Performance Tests and Integrated Systems Tests for the systems to be commissioned with the Contractor and appropriate sub-contractors performing the Functional Performance Tests and Integrated Systems Tests. The representatives listed in the paragraph Commissioning Team must attend the tests. Abort Functional Performance Tests or Integrated Systems Tests when any required commissioning team member is not present for the test.
3.1.6.6.1.1 Checklist
Use the Functional Performance Test and Integrated Systems Test Checklists from the approved Final Construction Phase Commissioning Plan to guide the Functional Performance Tests and Integrated Systems Tests. Functional Performance Tests must be performed for each item of equipment and each system required to be commissioned and verify all sensor calibrations, control responses, safeties, interlocks, operating modes, sequences of operation, capacities, lighting levels, and all other performance requirements comply with construction contract regardless of the specific items listed within the Functional Performance Test and Integrated Systems Test Checklists provided. Testing must progress from equipment or components to subsystems to systems to interlocks and connections between systems. Integrated Systems Tests must be performed for the interactive operation between systems such as HVAC systems, fire protection systems, back-up electrical supply, energy generation systems, and other systems, and verify correct interactive operation, acceptable speed of response, and other contract requirements for both normal and failure modes. Examples of Integrated Systems Tests include the correct operation of HVAC systems during emergency system activation, correct operation of uninterruptible power supplies or energy generators and connected systems, or lighting system operation during power outage or emergency system activation. The order of components and systems to be tested must be determined by the Technical Commissioning Specialists.
3.1.6.6.1.2 Acceptance
Indicate acceptance of each item of equipment and systems tested by signature of each commissioning team member for each Functional Performance Test or Integrated Systems Test Checklist. The Contractor's Quality Control Representative and the Technical Commissioning Specialists must indicate acceptance after the equipment and systems are free of deficiencies.
3.1.6.6.2 HVAC Test Methods
Perform Functional Performance Tests in accordance with the following:
SECTION 01 91 00.15 Page 17
3.1.6.6.2.1 Prior to Testing
Prior to testing operating modes, sequences of operation, interlocks, and safeties, complete control point-to-point observations, test sensor calibrations, and test actuator commands.
3.1.6.6.2.2 Simulating Conditions
Over-writing control input values through the controls system is not acceptable, unless approved by the Contracting Officer's Representative .
Identify proposed exceptions in a protocol submitted to the Contracting Officer's Representative for approval. Before simulating conditions, overwriting values (if approved), or changing set-points, calibrate all sensors, transducers and devices. Below are several examples of exceptions that would be considered acceptable:
a. When varying static pressures inside ductwork can not be simulated within the duct, and where a sensor signals the controls system to initiate sequences at various duct static pressures, it is acceptable to simulate the various pressures with a Pneumatic Squeeze-Bulb Type Signaling Device with gauge temporarily attached to the sensing tube leading to the transmitter. It is not acceptable to reset the various set-points, nor to simulate an electric analog signal (unless approved as noted above).
b. Dirty filter pressure drops can be simulated using sheets of cardboard at filter face.
c. Freeze-stat safeties can be simulated by packing portion of sensor with ice.
d. High outside air temperatures can be simulated with a hair blower.
e. High entering cooling coil temperatures can be used to simulate entering cooling coil conditions.
f. Do not use signal generators to simulate sensor signals unless approved by the Contracting Officer's Representative, as noted above, for special cases.
g. Control set points can be altered. For example, to see the air conditioning compressor lockout work at an outside air temperature below 55 degrees F, when the outside air temperature is above 55 degrees F, temporarily change the lockout set point to be 0 degrees F above the current outside air temperature. Caution: Set points are not to be raised or lowered to a point such that damage to the components, systems, or the building structure and/or contents will occur.
h. Test duct mounted smoke detectors in accordance with the manufacturer's recommendations. Perform the tests with air system at minimum airflow condition in ductwork.
i. Test current sensing relays used for fan and pump status signals to control system to indicate unit failure and run status by resetting the set point on the relay to simulate a lost belt or unit failure while the unit is running. Confirm that the failure alarm was generated and received at the control system. After the test is conducted, return the set point to its original set-point or a set-point as indicated by the Contracting Officer's Representative.
SECTION 01 91 00.15 Page 18
3.1.6.6.2.3 Setup
Perform each test under conditions that simulate actual conditions as close as is practically possible. Provide all necessary materials and system modifications to produce the necessary flows, pressures, temperatures, and other conditions necessary to execute the test according to the specified conditions. At completion of the test, return the affected building equipment and systems to their pre-test condition.
3.1.6.6.3 Sample Strategy
Perform Functional Performance Tests using the following sample strategy.
Prepare and complete a Functional Performance Test Checklist for each item of equipment or system to be tested. For sample sizes less than 100 percent for all similar equipment, the Government will select the specific equipment or system to be tested during testing. Equipment Identifiers are as indicated on the design drawings:
Equipment Identifier Sample Size (Percent)
AHUs, DOAS, CUs' 100
VAV 100
Electrical Heating Equipment 100
EF 100
IWHs 100
Lighting Controls 100
Renewable Energy Systems/Equipment 100
Perform Integrated Systems Tests for all systems and equipment having interactive operation.
3.1.6.6.4 Seasonal Tests
3.1.6.6.4.1 Initial Functional Performance Tests
Perform Initial Functional Performance Tests as soon as all contract work is completed, regardless of the season. Develop and implement means of artificial loading to demonstrate, to a reasonable level of confidence, the ability of the HVAC systems to handle peak seasonal loads.
3.1.6.6.4.2 Full-Load Conditions
In addition to the Initial Functional Performance Tests, perform Functional Performance Tests of HVAC systems under full-load conditions during peak heating and cooling seasons during outdoor air condition design extremes.
Test cooling equipment and systems with the building fully occupied when performing the Functional Performance Tests during peak cooling season.
Schedule Seasonal Functional Performance Tests in coordination with the Government.
SECTION 01 91 00.15 Page 19
3.1.6.6.4.3 System Acceptance
Systems may be partially accepted by the Government prior to seasonal testing if they comply with all construction contract that can be tested during initial Functional Performance Tests. All Functional Performance Test procedures must be completed prior to full systems acceptance.
3.1.6.6.5 Aborted Tests and Re-Testing
Abort Functional Performance Tests, Integrated Systems Tests, or Seasonal Tests if any deficiency…