B3_Solicitation_Amd2_051200.pdf
PDF 13 KB Posted
- Attached to
- San Luis Fence Replacement
- Solicitation number
- W9126G-15-B-0027
About this file
Amendment 2 Section 051200 change
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B3_Solicitation_Amd3_Test_Trench_Map.pdf | ||
| B3_Solicitation_Amd3_Trench_wall_3(2).jpg | JPG image | |
| B3_Solicitation_Amd3_Trench_4.jpg | JPG image | |
| B3_Solicitation_Amd3_Trench_wall_3.jpg | JPG image | |
| B3_Solicitation_Amd3_Trench_3.jpg | JPG image | |
| B3_Solicitation_Amd3_Trench_1.jpg | JPG image | |
| B3_Solicitation_Amd3.pdf | ||
| B3_Solicitation_Amd3_Trench_wall_2.jpg | JPG image | |
| B3_Solicitation_Amd3_Trench_2.JPG | JPG image | |
| B3_Solicitation_Amd2_024100.pdf | ||
| B3_Solicitation_Amd2.pdf | ||
| B3_Solicitation_Amd1.pdf | ||
| B3_Solicitation_Amd1_Exhibit_1_Topo.pdf | ||
| B3_Solicitation_Amd1_Section_015723.pdf | ||
| W9126G-15-B-0028_IFB_San_Luis.pdf |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
San Luis Primary Fence Replacement, Yuma Sector W9126G-15-B-0027
Pins and rollers
AISC Quality Certification
Welding procedures and qualifications
1.3 AISC QUALITY CERTIFICATION
Not Applicable. Work must be fabricated in an AISC Certified Fabrication Plant, Category Std. Submit AISC fabrication plant quality certification.
1.4 SEISMIC PROVISIONS
The structural steel system must be provided in accordance with AISC 341, Chapter J as amended by UFC 3-310-04.
1.5 QUALITY ASSURANCE
1.5.1 Preconstruction Submittals
1.5.2 Fabrication Drawing Requirements
Submit fabrication drawings for approval prior to fabrication. Contractor to show on drawings the layout of the fence panels and where custom panels are required for at gate, start/stop and point of intersection locations, and use of GFM. Prepare in accordance with AISC 326 and AISC 325.
Fabrication drawings must not be reproductions of contract drawings.
Include complete information for the fabrication and erection of the structure's components, including the location, type, and size of bolts, welds, member sizes and lengths, connection details, blocks, copes, and cuts. Use AWS A2.4 standard welding symbols. Shoring and temporary bracing must be designed and sealed by a registered professional engineer and submitted for record purposes, with calculations, as part of the drawings.
Any deviations from the details shown on the contract drawings must be clearly highlighted on the fabrication drawings. Explain the reasons for any deviations from the contract drawings.
1.5.3 Certifications
1.5.3.1 Welding Procedures and Qualifications
Prior to welding, submit certification for each welder stating the type of welding and positions qualified for, the code and procedure qualified under, date qualified, and the firm and individual certifying the qualification tests. If the qualification date of the welding operator is more than one-year old, the welding operator's qualification certificate must be accompanied by a current certificate by the welder attesting to the fact that he has been engaged in welding since the date of certification, with no break in welding service greater than 6 months.
Conform to all requirements specified in AWS D1.1/D1.1M and AWS D1.8/D1.8M.
PART 2 PRODUCTS
2.1 SYSTEM DESCRIPTION
Provide the structural steel system, including shop primer or galvanizing, SECTION 05 12 00 Page 3