AMENDMENT 04- Conform copy.pdf

PDF 883 KB Posted

Attached to
Construct Canopy Federal contract opportunity
Solicitation number
W9124M20B0016
Issued by
Department of the Army Materiel Command Mission and Installation Contracting Command

About this file

This is a solicitation for the construction of a canopy at an Ammunition Supply Point located at Fort Stewart, Georgia. The scope of work includes design, fabrication, and installation of a pre-engineered metal building system and foundation; site work such as demolition, fencing replacement, and drainage work; and electrical work including power, lighting, and a lightning protection system. The pre-engineered metal building is specified to be approximately 90 feet wide and 110 feet long with a 16-foot clear height inside. Questions are due by August 24th, bids are due on September 15th, and work shall be completed within 180 days of award. The NAICS code for the work is 238390 and the size standard is $16.5 million.

View the file

Other files for this federal contract opportunity

Other files attached to Construct Canopy, newest first.
File Type Posted
ABSTRACT OF OFFERS- 20-B-0016- Construct Canopy at ASP.xls XLS spreadsheet
AMENDMENT 04.pdf PDF
AMENDMENT 04.pdf PDF
AMENDEMTENT 03.pdf PDF
AMENDMENT 02.pdf PDF
AMENDMENT 01 - Construct Canopy at ASP.pdf PDF
Drawings-4071 Combined 6-8-2020.pdf PDF
Solicitation- 20-B-0016- Construct Canopy ASP.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W9124M20B0016

0011512524

PROJECT NO: S6S-018-8J

PROJECT TITLE : Construct Canopy for Ammunition Supply Point

PROJECT LOCATION : Ammunition Supply Point, Fort Stew art, Georgia

SET ASIDE: 100% HUBZone

NAICS CODE : 238390 -Other Building Finishing Contractors SIZE STANDARD : 16,500,000.00

MAGNITUDE OF CONSTRUCTION PROJECT : Betw een $ 500,000 and a $ 1,000,000.00

All w ork shall be completed per Scope of Work, Terms, Conditions, Provisions, Clauses ,Draw ings, and Specif ications.

BONDS : Bid Bonds and Performance Bonds w ill be required.

SITE VISIT: Wednesday, 19 August 2020 at 9:00 a.m.

DUE DATE FOR ALL QUESTIONS : Monday, 24 August 2020 BID OPENING: Tuesday, 15 September 2020 @ 3:00 p.m at the Parking lot of Paul R.. Smith Education Center , 100 Know ledge Drive, Fort Stew art, GA 31314

X

TATJANA M. FISHER 912-767-3747

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

12-Aug-2020

(RFP)

(IFB)

CALL:

Construct Canopy ASP,FS

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________180 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________FAR 52.211-10

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________15 Sep 2020 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee X is, is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______60 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

MICC - FORT STEWART

976 WILLIAM H. WILSON AVE SUITE 100

FORT STEWART GA 31314

W9124M

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

03:00 PM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

S6S-018-8J

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX:TEL: (912)767-8420 TEL: FAX:

W9124M20B0016 119

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

Section SF 30 - BLOCK 14 CONTINUATION PAGE

ANSWERS TO FINAL QUESTIONS

CONSTRUCT CANOPY AT AMMUNITION SUPPLY POINT

W9124M20-B-0016

FS 4071

QUESTIONS/ ANSWERS

QUESTION 1:

Refer to Section C – Descriptions and Specifications / Technical Provisions General. Item 1.1.1 states to “Provide complete design,…..”. Define ‘complete design’. What level of design and design documents are required? Full blown engineered drawings and specifications prepared by architects and engineers? It appears that the structural concrete and electrical has already been designed. What type of specifications are required? Full specs created in SpecsIntact, or just notes on the drawings? Please provide further clarity on the level of design required as this can vary greatly in price.

RESPONSE:

TPG, Paragraph 1.1.1 speaks specifically to design, fabrication and installation of pre‐engineered metal building system, related foundation and 6” concrete slab.

Refer to Sheet 7 (A‐3) for Metal Building Design Criteria

Refer to Sheet 5 (A‐1) Foundation Notes for requirements in regard to foundation and slab.

Refer to Spec Section 13122, Meatal Building Systems, Part 1, Paragraph 1.02 Submittals for requirements.

QUESTION 2:

What is the preferred method of submitting RFIs for this solicitation?

Submit any RFI electronically to the Contract Specialist and Contracting Officer.

QUESTION 3:

a. What is the thickness of the existing concrete hardstand that is to be removed?

b. What is the thickness of the existing base and asphalt paving that is to be removed?

c. The pre‐solicitation in sam.gov contained the Technical Provisions, General (material specifications). The current solicitation in sam.gov does not now contain the Technical Provisions, General......will these Technical Provisions, General be re‐posted, or are we to use the same ones that were originally posted?

d. Are the factory‐primed ('red iron') surfaces of the pre‐engineered metal building to be finish‐painted?

e. Is the exposed conduit to be finish‐painted?

a. Variable thickness – 10” or less

b. Variable thickness – Base 6‐8” and Asphalt 3‐4”

c. MICC needs to answer. We do not have access to sam.gov

d. Refer to Sheet 7 (A‐3), Exterior Colors ‐ factory‐primed ('red iron') surfaces of Primary Columns and

Frames are to be finish painted to match exterior metal panel.

e. Exposed conduit at Primary Columns and Frames are to be finish painted to match exterior metal panel.

QUESTION 4:

a. Drawing A-3 calls for specific colors with codes. Do we need to figure custom colors for this building?

b. Drawing A-3 depicts the columns as straight. Can the columns be a tapered design (narrow at bottom, wider at top) if the 86’-4” inside clear is provided?

a. Specific color names are from specific manufacturers, matching colors from other manufacturers are acceptable. Codes / color numbers are just a generic way of specifying the particular colors that are acceptable. If a particular metal building manufacturer does not offer a matching color as standard, then they will need to provide custom color to match those specified.

b. Column shall be straight as indicated.

QUESTION 5:

a. Re: Technical Provisions 1.1.1 – Please clarify the design requirements. Is the design limited to the pre-engineered structure (by manufacturer), or are we to re-design the foundation/slab also?

b. Please clarify where material staging/laydown and temporary construction facilities can be located.

c. Is the drawing indicating an FES at each end of the 18” RCP?

d. Please provide a dimension to indicate the extent of fence removal (to be reinstalled).

e. It appears that the same designation is being used for EJ and CJ on the plan. For the intended use and building dimensions, it would be expected that no EJs would be required. Please clarify the requirement.

f. Typical Control Joint – Note indicates to “cut alternate wires at sawcut.” We do not see any practical way to accomplish this. The sawcut (1/5 SLAB DEPTH) will not cut the wire at 1/3 depth. Typically, the wire will be continuous at control joints. Please clarify the requirement.

g. Is the exposed structure to be painted or only factory primer?

h. Please clarify the required downspout locations.

a. TPG, Paragraph 1.1.1 speaks specifically to design, fabrication and installation of pre‐engineered metal building system, related foundation and 6” concrete slab.

Refer to Sheet 7 (A‐3) for Metal Building Design Criteria

Refer to Sheet 5 (A‐1) Foundation Notes for requirements in regard to foundation and slab.

Refer to Spec Section 13122, Meatal Building Systems, Part 1, Paragraph 1.02 Submittals for requirements.

b. Coordinate with CMB.

c. Correct. A flared end section is required at both ends of RCP.

d. A total of 60LF (30LF each side) was allocated for fence removal and reinstallation. It up to the contractor if they would like to remove less as they will then have tighter working conditions adjacent to the proposed building.

e. Provide Expansion Joints at the column center lines as noted.

f. Alternate wires can be cut prior to pouring the slab.

g. Refer to Sheet 7 (A‐3), Exterior Colors ‐ factory‐primed ('red iron') surfaces of Primary Columns and

Frames are to be finish painted to match exterior metal panel.

h. Provide downspouts at each side wall column line – A-1 thru 6 and D-1 thru 6.

Section A - Solicitation/Contract Form

TABLE OF CONTENTS

PART I – THE SCHEDULE

• SECTION A – Solicitation/Contract Form

• SECTION B – Supplies or Services and Prices/Costs

• SECTION C – Descriptions/Specifications/Statement of Work

• SECTION D – N/A

• SECTION E – Inspection and Acceptance

• SECTION F – Description and Performance

• SECTION G – Contract Administration Data

• SECTION H – Special Contract Requirements

PART II – CONTRACT CLAUSES

K. SECTION I – Contract Clauses

PART III – LIST OF DOCUMENTS, EXIBITS AND OTHER ATTACHMENTS

1 SECTION J – List of Exhibits, Attachments, and Appendices

PART IV – REPRESENTATIONS AND INSTRUCTIONS

2 SECTION K – Representations, Certifications and Other Statements of Offerors or

Respondents 3 SECTION L – Solicitation Provisions 4 SECTION M – Evaluation Factors for Award

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job Construct Canopy at ASP, FS

FFP

The work covered by this contract consists of furnishing all plant, labor, materials and performing all operations required in connection with Construct Ammunition Supply Point Canopy complete in strict accordance with specifications and drawings.

FOB: Destination

PURCHASE REQUEST NUMBER: 0011512524

PSC CD: Y1JZ

NET AMT

Section C - Descriptions and Specifications

TECHNICAL PROVISIONS GENERAL

TECHNICAL PROVISIONS

GENERAL

Construct Ammunition Supply Point Canopy

IJO NO S6S 018-8J

1. DESCRIPTION OF WORK:

1.1 Work to be Done: The work covered by this contract consists of furnishing all plant, labor, materials and performing all operations required in connection with Construct Ammunition Supply Point Canopy complete in strict accordance with specifications and drawings. The work includes, but is not necessarily restricted to, the following items.

1.1.1 Provide complete design, fabrication, and installation of pre-engineered metal building system, related foundation and 6’ thick concrete slab. Metal Building System shall be approximately 90’ wide, 110’ long with 16’ clear height inside of structure.

1.1.2 Site work includes removal and replacement of existing chain link fencing, demolition of existing 75’ wide x 102’ long concrete slab, removal and replacement of existing 24” corrugated metal drainage pipe and related excavating and grading work.

1.1.3 Electrical work will include all power, lighting and Lightning Protection

System.

1.2 Additives

1.2.1 N/ A

1.3 Government Furnished – Government Installed (GF-GI) Furniture and

Equipment:

1.3.1 N / A

1.4 Government Furnished – Contractor Installed (GF-CI) Furniture and

Equipment:

1.4.1 N / A

1.5 Contractor Furnished – Contractor Installed (CF-CI) Furniture and Equipment:

1.5.1 N / A

1.6 WORK BY OTHERS: The Contractor shall afford the Government and separate contractors’ reasonable opportunity for the introduction and storage of their materials and equipment and the execution of their work, and shall connect and coordinate his work with theirs as required by the Contract Documents.

1.7 DRAWINGS AND SITE VISITS

1.7.1 The drawings indicate the extent of the general location and arrangement of existing conditions. It is strongly recommended that the Contractor visit the site to determine the complexity of the work and the amount of material required to perform this project. Field measurements may be necessary to determine the size and quantity of materials. Conditions which are obvious/visible or which should be reasonably anticipated by the Contractor on inspection will not be considered under the Differing Site Conditions provision of the contract.

1.8 ENVIORNMENTAL REQUIREMENTS

1.8.1 Contractor shall comply with “Attachment A - Environmental

Requirements” for the following items:

Recycling, Salvage and Disposal of Materials Fort Stewart and Hunter Army Airfield

Electrical Meters and Instrument Transformers

Stormwater / Erosion and Sedimentation Control (E & S)

Requirements

Cultural Resource Management (CRM)

Integrated Pest Management Program

2. CONSTRUCTION CONSTRAINTS

2.1. Time of Performance

2.1.1 Access to Buildings – All work requiring access to building interiors excluding attics, crawl spaces, etc. and all other work shall be performed between 7:30 a.m. and 4:00 p.m. excluding official holidays, unless otherwise indicated or approved by the Contracting Officer. Requests to work during other than these normal hours shall be made in writing at least 36 hours in advance. For example, a request to work on a Saturday should be made no later than noon on Thursday.

2.1.2 Work Requiring Outages – Work requiring outages of utilities or building systems will be accomplished in accordance with prior approved schedules.

2.2. Outages – The contractor’s work requiring outages of utility or building systems will require 15 calendar day advance notice and will be subject to the approval of the Contracting Officer. Notice shall include type of outage, date, and time outage will commence and estimated duration of outage.

2.3. Continuity – All tools, labor, and materials required to complete any item of work within a given work area or requiring an outage of any building utility or system, shall be available at the site prior to commencement thereof.

Once work has commenced on an item of work said work shall be continuously and diligently performed to completion and acceptance.

2.4. Road and/or Railroad Closures – Road and/or railroad closures will require a 15-day advance written notice and be subject to the Contracting Officer’s approval. Notice shall state reason for closure, date and time closure will commence and estimated duration of closure. A sketch shall be provided showing location of closure area and placement of barricades and signs. Closures shall be limited to a maximum of 5 calendar days.

2.5. Entry – Entry to all areas, except the cantonment area, shall be coordinated with Range Control, Building 8302 (intersection of Highway 144 and Fort Stewart Road 47) and the Provost Marshal’s Office.

2.6. Fire Zone – The contractor is required to provide 72-hour notice to the

Contracting Officer prior to the final programming of the fire zone information at the main fire station.

3. CONSTRUCTION ACTIVITIES:

3.1 Contractor shall submit a Safety Plan and Construction Schedule to the

Contracting Officer’s Representative (COR) 10 days in advance of any construction activities to arrange specific schedule for performing work as required by this Contract.

4. FACTORS AFFECTING PERFORMANCE UNDER THIS CONTRACT:

4.1 The Contractor shall coordinate use of the site for access, staging, and parking with the COR.

4.2 Contractor shall be responsible for limiting access of it’s employees and subcontractors to the area of work defined in the Contract. Contractor shall not have access to restrooms and amenities such as vending machines unless granted permission by the Contracting Officer.

4.3 Contractor shall maintain haul routes to and from the job sites and the borrow pits, to include the borrow pit. In addition it is the contractor’s responsibility to meet all Local, State and Federal regulations for the operation of a borrow pit. Contractor shall control runoff and erosion on all excavation and backfilling operations.

5. AS-BUILT RECORD DRAWINGS:

5.1 The Contractor shall be responsible for maintaining one set of master/record construction drawing prints on the job site and keep a neat and accurate record of all deviations from the original contract documents as the work progresses. The contractor is responsible for noting all changes and correction on these master/record construction drawing prints promptly as the changes occur in red ink(redline prints) and note date when these changes occurred, but in no case less often than on a weekly basis. The master/record construction drawing prints which are maintained in red ink shall indicate all the changes and modifications incorporated into the work as well as the following:

5.1.1 Actual locations of all subsurface and concealed utility lines, type of materials used, sizes, etc. In order that the location of these lines and appurtenances may be determined in the event the surface openings or indicators become covered or obscured, the master/record construction drawings shall show by offset dimensions to two permanently fixed surface features. Valves, splices boxes and similar appurtenances shall be located by dimensions along the utility run from a reference point. The average depth below the surface of each run shall also be recorded.

5.1.2 Any shop drawings that constitute part of the design shall be included with the record drawings.

5.2 The master/record (redline construction drawings) prints with corrections, such as field changes and contract modifications, shall be certified by the Contractor as to their correctness and submitted to the COR for approval.

Once these provisional master/record (redline construction drawing) prints have been approved by the COR, the COR will obtain a compact disc (CD) of computer generated construction drawings from the DPW

Engineering Service Division, Building 1141 at Ft. Stewart or Building 1021 at Hunter AAF, as applicable. The contractor shall then transfer all corrections from redline construction drawing prints to the compact disc (CD) of computer generated construction drawings. Corrections done shall be in Micro Station “.dgn” format. The Contractor shall note on the computer generated construction drawings the words “AS-BUILT” in the revision block with the next revision number to identify any changes made.

Also, revision number identification will be placed where any changes were made. The contractor shall then submit AS-BUILT compact disc (CD) of computer generated drawing and one (1) AS-BUILT hardcopy with contractor’s redline corrections to the COR to insure accuracy that all corrections made were transferred from redline construction drawing prints to AS-BUILT hardcopy prints. Once the COR approves the AS-BUILT hardcopy prints the COR will then turn over to DPW/ ESD/ Drafting section for final approval of AS-BUILT compact disc (CD) of computer generated drawings and at this time the Contractor can receive final payment.

6. SECURITY REQUIREMENTS.

6.1 All contractor employees, to include subcontractor employees, requiring access to government installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee to the COR or the Contracting officer (if a COR has not been designated) within 30 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website:

https://jkodirect.jten.mil .

The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 30 calendar days after contract award.

The Contractor and all associated sub-contractor employees shall comply with applicable Installation, facility, and area Commander’s local access and security policies and procedures. If required by this contract, the contractor shall also provide all information for background checks to meet Installation access requirements to be accomplished by Installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy.

In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or Installation change, the Government may require changes in contractor security matters or processes.

ATTACHMENT A – ENVIRONMENTAL REQUIREMENTS

1. RECYCLING, SALVAGE, AND DISPOSAL OF MATERIALS

FORT STEWART AND HUNTER ARMY AIRFIELD

1.1 Disposal: All waste generated from construction, demolition, and renovation contracts must be disposed of off the installation in a permitted disposal facility and in accordance with all Federal, State, and Local rules and regulations unless otherwise stated in the contract. At the end of each month, the contactor will provide copies of all disposal weight/scale tickets to the Contracting Officer’s Representative (COR) showing the in, out, and tare weights of each load taken from the installation. The COR will provide copies of these tickets to the DPW Environmental Division, Solid Waste Management Section for tracking and regulatory reporting requirements.

1.2 Recycling/Salvage: Fort Stewart and Hunter Army Air Field has a mandatory recycling program. The Installation Command Policy Letter #30 and Command Recycling SOP can be accessed at http://www.stewart.army.mil/info/?id=443&p=1. All recyclable materials (listed in the recycling SOP) generated during the entire term of any construction, demolition, or renovation contract will be turned over to the Fort Stewart or HAAF Recycling Program. Contractors must contact the COR who will coordinate with the DPW Environmental Waste Management Section (912-767-2010) to arrange for turn-in of recyclable/salvageable materials. In areas where large amounts of scrap metal or cardboard will be generated, it is possible that a collection bin/container could be provided to the Contractor at no cost to deposit these materials. Salvage materials, unless otherwise specified, become the property of the contractor upon removal from the job site and should be taken into consideration in formulating bids.

1.3 Hauling/Transport Requirements: All vehicles and containers used to transport waste or recyclables on or off the Installations will meet all Federal and State DOT requirements. All waste or recyclable materials being transported will be loaded, tied, and covered in such a manner that will prevent any of the materials from leaking, spilling, falling or blowing from/off the vehicle or container. It is the contractor’s responsibility to ensure immediate pick-up/clean-up of any material that is accidentally dropped, spilled or blown from a vehicle or container while in transit on and off the Installation.

1.4 Custodial Contract: If this contract is for custodial services or will include a custodial service requirement, the Contractor shall empty or otherwise transfer the contents from the blue recycling containers located inside buildings/facilities to the nearest blue recycling dumpster located outside.

The contactor will ensure that all recycled paper products are first placed inside a clear plastic bag and the top is tied closed before it too is placed inside the nearest blue recycle dumpster.

1.5 Payment/Funding: If any of the conditions listed under the Recycling, Salvage, and Disposal section are not met, it will be considered a failure to comply with the terms of the contract as discussed in the inspection clause herein.

1.6 Guidance/Question: Anyone requiring further guidance, recycling training for contractors, or has additional questions on this section should contact the DPW Environmental Division, Solid Waste Management Section at 912-767-2010.

1.7 Chillers, pumps, HVAC units, and similar equipment must be logged on an applicable inventory/certification document prior to turn-in to recycling yard (on DD Form 1348). The form will be used to track the removal of units from facilities, refrigerant removal certification (if applicable), and a chain of custody from removal technician thru supply manager to recycling technician. The serial number and facility number will be listed on each form and one form may contain more than one like item. Recycling Yard personnel will verify document to items turned in, sign the document, and retain a file copy. Contractor shall submit this form to the KO. Additionally, damaged HVAC system may be accepted as scrap metal at the FSGA Recycling Scrap Metal Yard, Building 1143, or the HAAF Recycling Yard, Building 728, provided any and all freon has been certified as being removed from the system.

2. Toxic Substances Control Act (TSCA) Requirements

2.1 Asbestos Containing Materials (ACM)

2.1.1 If ACM will either be disturbed or removed, the contractor must perform asbestos abatement, containment, disposal and a 10-day notification to the Georgia Environmental Protection Division (GA EPD), as required by the Georgia Asbestos Safety Act, Official Code of Georgia Annotated Section 12-12-1. The disposal of ACM must be in accordance with both the GA EPD and Occupational Safety and Health Administration regulations.

2.1.2 REQUIRED SUBMITTAL ITEM: The Installation TSCA POC (Craig

Christopher at 912-767-1234 / Craig.W.Christopher.civ@mail.mil) must be provided a copy of the 10-day notification at the time the contractor informs GA EPD of their intent to properly abate the ACM. A copy of the Georgia asbestos shipment record must also be provided to the TSCA POC.

2.2 Lead-Based Paint (LBP)

2.2.1 If survey results, as reviewed by the Installation TSCA POC (Craig

Christopher at 912-767-1234 / Craig.W.Christopher.civ@mail.mil), indicate LBP removal is necessary, the contractor will be required to collect, contain, and dispose of the LBP off-Post in accordance with local, state, and Federal regulations. The contractor will be required to provide the disposal manifest to the TSCA POC.

2.2.2 REQUIRED SUBMITTAL ITEM: LBP survey must be provided to the TSCA

POC, as applicable. The LBP disposal manifest must be provided to the TSCA POC if LBP removal was determined necessary by the TSCA POC.

3 Installing Storage Tanks on Fort Stewart and Hunter Army Airfield

3.1 Underground Storage Tank Moratorium.

3.1.1 The installation of any underground storage tank and associated piping for the purpose of containing regulated and/or hazardous substances is strictly prohibited in the case where at least 10% of the total volume (tank + piping) is below the surface of the ground. Similarly, tanks in vaults for the purpose of installing tanks below grade are not acceptable.

3.2 Design Requirements for Aboveground Storage Tanks

3.2.1 Provide appropriate secondary containment (40 CFR 112.8(c)(2)). All aboveground storage tanks used for the purpose of storing regulated and/or hazardous substances must be double-walled. In order for a tank to be considered double-walled, the interstitial space between the inner and outer wall must be able to be inspected visually or the interstitial space must be equipped with a sensor capable of alarming in case of liquid in the interstice (access to the interstice must also allow for the periodic removal of liquids).

3.2.2 Provide tertiary containment (in accordance with 40 CFR 112.8(c)(3)). All aboveground storage tanks must be placed on an impervious diked concrete housekeeping pad designed to catch spills caused from transferring substance to/from the tank. This housekeeping pad must come with a valve that allows for the discharge of rainwater from the diked pad after a visual inspection has been done to determine that the water is clean.

3.2.3 Provide Instrumentation (Provide good engineering practices to avoid unwanted discharges, 40 CFR 112.8(c)(8)))

3.2.3.1 All aboveground storage tanks must come with a high liquid level alarm that emits both an audible and visual signal to alert operators that the tank must be emptied before further use.

3.2.3.2 The tank must also be equipped with a level gauge that allows for determining the level of liquid in the tank.

3.2.3.3 In the case of any tank equipped with a pump for the purpose of dispensing of a stored substance, the pump must have an automatic cutoff to prevent overfilling of a container.

3.2.4 Provide Labeling. All aboveground storage tanks should be labeled IAW all applicable local, state, federal laws, or industry standard. At a minimum, the tank should display an appropriate hazard warning, material ID, and storage capacity.

4. Removing Underground Storage Tanks (USTs) on Fort Stewart and

4.1 Tank Removal.

Note to ENGINEER - The Georgia Underground Storage Tank Management Program (GA USTMP) requires the removal of tanks after they have fulfilled their useful purpose and have been out of service for a period of twelve (12) months. Be aware that some tanks do NOT meet current tank standards but have an exemption from those standards based on their current use (e.g, heating oil tanks). If the use changes, those exemptions may no longer apply and the tank must be removed and if still needed will require replacement with an above ground tank.

4.2 Removal must follow the standards for removal and closure of registered tanks as outlined in the Georgia Underground Storage Tank Management Program (GA USTMP) guidance document (ref GA Rules 391-3-15-.11).

As a minimum oil samples must be taken and analyzed from the excavated pit’s walls and floor. A groundwater sample must be taken if a soil sample is not possible from beneath the UST. Soil and groundwater samples must be tested for benzene, toluene, ethylbenzene and xylenes (BTEX), total petroleum hydrocarbons-diesel range organics (TPH-DRO), and polynuclear aromatic hydrocarbons (PAHs). The USTs and associated piping must be removed and triple rinsed with water. Rinse water must be containerized (in drums or a tank) and analytical testing conducted by a certified Georgia laboratory, so the product can be correctly coded/classified on a Non-hazardous Manifest signed by an authorized representative from the Installation DPW Environmental Division. Disposal of materials (soil/rinseate) must be coordinated with the Installation DPW Environmental Division. See 1.0 for Recycling of cut up tank.

4.3 REQURED SUBMITTAL ITEM: Contractor shall provide (a) 24- hour notice and a POC / telephone number prior to UST removal activities to allow time for Installation DPW Environmental Division representation at the site during the time the tank(s) is being removed from the ground. Installation DPW Environmental POC: Algeana Stevenson at 912-315-5144; (b) All lab tests and manifests for disposal of any contaminated soil/rinseate (pre-coordination with Installation DPW Environmental Division is required).

Letter and photo documentation (hard copy and digital) of the UST removal process is required of the UST removal contractor; and (c) confirmation cut up tank was delivered to the Recycling Center.

5. Removing Aboveground Storage Tanks (ASTs) on Fort Stewart and

5.1 Tank Removal.

5.1.1 The AST(s) and associated piping must be removed and triple rinsed with water. Rinse water must be containerized (in drums or a tank) and analytical testing conducted by a certified Georgia laboratory, so the product can be correctly coded/classified on a Non-hazardous Manifest signed by an authorized representative from the Installation DPW Environmental Division. Disposal of materials (soil / rinseate) must be coordinated with the Installation DPW Environmental Division. See 1.0 for Recycling of cut up tank.

5.1.2 REQURED SUBMITTAL ITEM: Contractor shall provide (a) 24- hour notice

(and a POC/telephone number) prior to AST removal activities to allow time for Installation DPW Environmental Division representation at the site during the time the tank(s) is being removed. Installation DPW Environmental Division POC: Veronica Frazier at 912-767-2400; (b) All lab tests and manifests for disposal of any contaminated soil/rinseate (pre-coordination with the Installation DPW Environmental Division is required);

and (c) confirmation cut up tank was delivered to the Recycling Center.

6 Potable Water Utility Environmental Compliance Requirements

6.1 REQUIRED SUBMITTAL ITEM: Extending a water main: The contractor must submit applications for GA EPD’s approval through the Installation DPW Environmental Division POC: Stanley Thomas at 912-767-4139.-. At least 100 days prior to construction, the contractor must submit the following items to the Installation DPW Environmental Division:

6.1.1 Three copies of the design plans and specifications for the proposed water main extension.

6.1.2 Every sheet of the drawings must be stamped by a GA certified P.E.;

the cover page of the specifications must also be stamped with document.

6.1.3 Water Extension Submittal Forms will be required for any project that has more than one service connection or if the water line tapping off the main is at least 6 inches in diameter.

6.1.4 All water lines must be disinfected and sampled IAW the most current edition of AWWA’s C651.

7. Wells and Water Storage Tanks

7.1 The contractor must follow the specific guidance as stated in the GA EPD’s “Minimum Standards For Public Water Systems”. This document can be Found on the GA EPD’s web site:

http://www.gaepd.org/Files_PDF/techguide/wpb/standards.pdf .

7.2 Additional guidance can be found in the following documents:

7.2.1 Water Storage Tanks: The latest edition of the AWWA’s D102

(Coating Steel Water-Storage Tanks) and M42 (Steel Water-Storage Tanks).

7.2.2 Wells: AWWA’s C654 (Disinfections of Wells)

7.2.2.1 A well permit application must be submitted prior to constructing a well.

7.2.2.2 Well drilling logs, source sampling data, and P.E. construction certification statement must be submitted upon completion of all wells.

7.3 Lead Requirements

7.3.1 Reference the Safe Drinking Water Act (as amended 4 JAN 2014) regarding standard for the lead content in plumbing materials. Lead content in solder and flux will not exceed 0.2% and lead content in the wetted surface of pipes, pipe fittings, plumbing fittings, and fixtures used in public potable water systems will not exceed 0.25%.

7.3.2 Prior to building turnover (as a minimum this is inclusive of all youth occupied facilities-Elementary Schools, Child Development Centers, and Youth Activity Centers), the potable water system throughout the building shall be flushed IAW Technical Information Paper No. 31-010-0911, Guidance for Reducing Drinking Water Lead Levels in New Buildings.

7.4 Meters. All new water service connections must be metered.

8. Electrical Meters and Instrument Transformers

8.1 Electrical meters and instrument transformers shall meet or exceed the following minimum requirements:

8.1.1 Measure quantities. Electrical meter quantities measured are Power

(kilowatt), average demand over 15 minute intervals and Energy (kilowatt-hours).

8.1.2 System Accuracy. System accuracy for the meter product devices including instrument transformers shall not exceed 1% as calculated using the Root Sum Square (RSS) method and assuming normal distribution.

8.1.3 Meter Accuracy:

8.1.3.1 For facilities with connected 1oads equal to or greater than one (1) mega volt-ampere (MVA), meter certification shall be NEMA/ANSI C12.20, Accuracy class 0.2%.

8.1.3.2 For facilities with loads less than 1MVA, meter certification shall be

IEEE/ANSI C12.16, Accuracy class 0.5%.

8.1.4 Communication Protocol. Meters shall communicate via either Modbus

RTU or ANSI/CEA-709.1b (LonTalk) protocols or as otherwise specified.

8.1.5 Auxiliary data ports. Unless otherwise specified, electrical meters shall have a minimum of two pulse inputs for incorporation and transmission of other external meter data.

8.1.6 Surge Protection. IEEE/ANSI C37.90.1, Standard surge withstand capability (SWC) tests for relays and relay systems associated with electric power apparatus.

8.1.7 Current transformers (CTs) sized properly so that the meter secondary of the transformer shall output current to ensure at least a plus or minus 0.6% accuracy of current when measured between 10% and 90% of full amperage range.

8.1.7.1 CTs shall not exceed 5 amps on the secondary side.

8.1.7.2 Burden on CTs shall not exceed rated burden for the accuracy class.

8.1.7.3 CTs shall be provided in split core configuration. 1.7.4 CTs shall be provided in the appropriate ranges to meet the service entrance amperage requirements.

8.1.7.4 For facilities with a connected load equal to or greater than 1MVA, CT certification shall be IEC 185 or ANSI/IEEE C57.13 for 0.3% accuracy class or better.

8.1.7.5 For facilities with a connected load less than 1MVA, CTs shall revenue grade and certified per IEEE/ANSI C57.13 or IEC 185.

8.1.8 Current sensors shall be sized properly for the application and provide a voltage (normally 0-2 volts) to the meter that results in at least a plus or minus 0.6% accuracy of current when measured between 10% and 90% of full amperage range.

8.1.9 Voltage or Potential Transformers (PTs) sized properly so that the meter secondary of the transformer shall output voltage to ensure at least a plus or minus 0.6% accuracy of voltage when measured from zero to the IEEE/ANSI C57.13 or IEC 185 specified standard burden, at the specified standard burden power factor, and at any value from 90% to 110% of rated voltage.

8.1.9.1 For facilities with a connected load equal to or greater than 1MVA, PT certification shall be IEC 185 or IEEE/ANSI C57.13 for 0.3% accuracy class or better.

8.1.9.2 For facilities with a connected load less than 1MVA, PTs shall be revenue grade and certified per IEEE/ANSI C57.13 or IEC 185.

8.1.9.3 Burden on PTs shall not exceed rated burden for accuracy class.

8.1.10 Data Storage. Unless otherwise specified, the meter must be capable of providing and storing required interval data for a minimum of 30 days.

8.1.11 Environmental Tolerances of Metering Devices.

8.1.11.1 Meters shall be installed in indoors/interior locations and rated for operation and storage from 0° - 50° C or better and 5 to 90% relative humidity (non condensing). Interior meters shall be provided with or installed within a NEMA 12 enclosure.

8.2 Advanced Metering Data Management System front end computer requirements are:

8.2.1 Data encapsulation format shall be Extensible Markup Language (XML) and Simple Object Access Protocol (SOAP) for future output to a remote centralized meter data management system.

8.2.2 Storage of metered data for at least 2 years.

8.2.3 Display:

8.2.3.1 Display of data upon request and selectable from 1 minute to 15 minutes for kW.

8.2.3.2 Final install of front end equipment shall, at minimum, display accurate data readings for each meter in a text format. Customization of the user interface is not required. Two hardcopies and two electric copies (DVD or CD) of detailed instructions shall be provided for customization and integration of additional display features that are not prepared at the time of final install.

8.2.3.3 Display capability shall include multiple graphical formats such as data vs.

time (minutes, hours, days, weeks, months, and year) comparison between metered data from two or more meters and other standard meter data.

8.2.4 System expansion capability of 50 times for incremental future growth of metered data to include water, gas and steam.

8.2.5 Data Transmission Media is LAN, Radio Frequency, or Power Lines for interface of metered data to the Advanced Metering Data Management System, whichever is most economical for the site.

9 Water / Waste Water Systems

9.1 Backflow Prevention Device. REQUIRED SUBMITTAL ITEM: The

Contractor shall submit through the COR to the Installation DPW Environmental Division (a) type of backflow device with make, model, manufacturer, serial number and GPS coordinates for the installed location of the device; and (b) certifications by a certified backflow prevention installer/tester of backflow testing performed for each testable backflow device. The certified installer/tester must be certified from an EPD-approved Georgia Backflow Prevention Training Program.

9.2 Water Conservation Requirements. IAW the Georgia Water Stewardship

Act (GWSA), Section 8, water fixtures will meet the following minimum water conservation standards (note – Section 8 of the GWSA can be found on the bottom of the Georgia Environmental Protection Division’s website:

http://www.gaepd.org/Documents/outdoorwater.html

9.2.1 Toilets will not exceed 1.28 gallons per flush.

9.2.2 Showerheads will not exceed an average of 2.5 gallons of water per minute at 60 pounds per square inch of pressure.

9.2.3 Urinals will not exceed 0.5 gallons per flush.

9.2.4 Lavatory faucets will not exceed 1.5 gallons per minute flow.

9.2.5 Kitchen faucets will not exceed 2.0 gallons per minute flow.

9.3 Sanitary Inspections Prior to Government acceptance, the Contractor, through the COR, must coordinate with Installation Environmental Health,

(912) 435-5721 or (912) 257-1220, for bacteriological testing to ensure drinking water lines (e.g. Drinking fountain, utility sink, etc.) have been super-chlorinated with positive chlorine residuals and are free of any bacteria.

9.4 Outdoor Sprinkler Systems

Sprinkler systems must be isolated from potable drinking water lines (no cross-connection) to allow for easy conversion to non-potable water sources in the future. If a non-potable water source is within 200 feet of the site at the time of construction, tying into the non-potable lines is required.

If connected to a potable water source, a backflow preventer is required.

The sprinkler system must include timers and rain gauges to ensure the system is not running while there is a rainstorm.

9.5 Fire Hydrants

Hydrants shall be disinfected IAW AWWA Standard C651-5. Prior to placing into service, the Contractor, through the COR, must coordinate with Installation Environmental Health, (912) 435-5721 or (912) 257-1220, for bacteriological testing to ensure potable water lines have been super-chlorinated with positive chlorine residuals and are free of any bacteria.

9.6 Hydrant models specified should be those equipped with an anti-terrorism device. Fire hydrants should be equipped with a resilient seated check valve. Valve shall be manufactured to all testing and performance standards of AWWA C508 AND AWWA C550. Valves shall be rated for 250 psi water working pressure and tested at 500 psi hydrostatic pressure. Valve shall be a standalone unit able to be positively restrained to any mechanical joint fire hydrant shoe. Check valve shall be ductile iron ASTM Standard A536 (70-50-05), with NSF approved fusion bonded epoxy coating (interior and exterior). The valve shall incorporate a stainless steel spring that hastens positive closure and prevents water hammer. The valve shall be lead free, with no exposed lead bearing surface. The check valve shall have an unobstructed waterway. No reduction of port or redirection of flow will be allowed. Valve shall incorporate integral positive restraint connections to maintain a restrained connection between the fire hydrant and the gate valve. All fasteners to be Type 304 stainless steel.

9.7 Demolition

9.7.1 Ensure all water service connections with discontinued service due to abandonment or demolition are properly and permanently capped and sealed to prevent the escape of potable water or possible contamination.

9.7.2 Remove all asbestos lines that are abandoned as a result of a project.

9.8 Wastewater Requirements

9.8.1 REQUIRED SUBMITTAL ITEM: If a new sewer main, septic tank, and/or lift station will be installed, it is required that the contractor submit applications for GA EPD approval through the Installation DPW Environmental Division. At least 100 days prior to construction, the Contractor must submit the following through the COR to the DPW Environmental Division, Prevention and Compliance Branch to the attention of the Wastewater Program Manager (912-767-4937 or 767-2010).

9.8.1.1 The contractor must submit three copies of the sewer main extensions, septic tank, and/or lift station drawings and specifications.

9.8.1.2 All drawings and specification shall be stamped by a GA certified P.E.

9.8.1.3 Sanitary Sewer Extension Submittal Forms or Underground Injection

Control Non-Domestic Septic System Forms will be submitted for any project that extends the sanitary sewer main, includes installation of a lift station or installation of septic tank/ leach field or septic system.

9.8.2 Lift Stations. The following are required:

9.8.2.1 High level alarm (visual & audible).

9.8.2.2 Perimeter fencing.

9.8.2.3 A Supervisory Control and Data Acquisition (SCADA) System compatible with the current system used on the Installation (thermostat controlled panel heaters will need to be included on transmitter units).Emergency bypass.

9.8.2.4 Electric generator. The standby generator must be commissioned in accordance with applicable OSHA, EPA, NEC and NFPA 110 Section 16620 Sanitary Sewer Pump Station Emergency Pump Station Standards.

If diesel fuel generators are used (rather than natural gas) the fuel storage tanks must be double walled ASTs.

9.8.3 Demolition

9.8.4 Ensure all sewer service connections are properly disconnected prior to demolition. Permanently cap and seal service connections to prevent the infiltration of groundwater or surface water into the sanitary collection system.

9.8.5 The contents of septic tanks will be pumped out and properly disposed of at a wastewater treatment plant. The septic tank will be removed from its current location and the tank must be either recycled or otherwise properly disposed. After removal, backfill will be placed and compacted. The leach field soil may remain in place to naturally attenuate after abandonment of the site.

10 Stormwater / Erosion and Sedimentation Control (E&S) Requirements

10.1 Requirements for Sites with Soil Disturbance Greater Than 0.75 Acres

10.1.1 A Notice of Intent (NOI) for coverage under the Georgia National Pollution Discharge Elimination System (NPDES) Permit must be applied for through the DPW Environmental Office Stormwater POC (Russell Moncrief at 912- 767-0271). The land disturbance calculation must include project entrances /exits, material lay down areas, equipment storage areas, soil stockpile, fill, and muck out areas. The NOI package has a mandatory 14-day waiting period once mailed to the Georgia Environmental Protection Division (EPD).

Land disturbing activities cannot occur until the 14-day waiting period has ended.. The NOI package includes an Erosion & Sedimentation and Pollution Control (ESPC) Plan, fees in the amount of $80/acre, the fee form, and the NOI application. In addition to meeting those requirements under the Georgia Erosion and Sedimentation Control Act, the contractor must also follow Federal and local E&S control regulations. A summary of the applicable stormwater / E&S requirements are provided below:

10.1.1.1 E&S Control Best Management Practices (BMPs) will be identified in the

ESPC Plan and must be utilized by the contractor. The ESPC Plan will include those requirements identified in the “Green Book” (Manual for Erosion & Sedimentation Control for the State of Georgia), the Coastal Stormwater Supplement, the Energy Independence and Security Act Section 438, the US Environmental Protection Agency (EPA) Technical Guidance (EPA 841-B-09-001 December 2009), the United Facilities Criteria (UFC) Manual for Low Impact Design, and those additional applicable Federal and local requirements found at the following web…