Solicitation Amendment 0002 addressing questions resulting from the Site Visit on August 11, 2017.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
0011042923-0001 2U-4-3J
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of Amendment 0002 is to provide responses to offeror questions follow ing the site visit on August 11, 2017. The deadline for submitting questions, August 16, 2017, has expired. The deadline for the submission of proposals remains the same: September 5, 2017 @
2:00 p.m. EST.
a.) All other terms and conditions of this solicitation remain the same.
BASIS: This amendment is deemed necessary and in the best interest of the Government.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 24-Aug-2017
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9124M-17-B-0004
X 9B. DATED (SEE ITEM 11)
03-Aug-2017
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
24-Aug-2017
CODE
MICC - FORT STEWART
976 WILLIAM H. WILSON AVE SUITE 100
FORT STEWART GA 31314
W9124M 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W9124M-17-B-0004
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION C - DESCRIPTIONS AND SPECIFICATIONS
The following have been added by full text:
QUESTIONS
Questions pertaining to the Repair Taxiway and Aprons, WAAF
Site Visit – August 11, 2017
1.) Will the contractor be allowed to install a construction trailer near the laydown yard within the the fenced in area?
Answer: As depicted on page GI-101 of the contract drawings, the contractor staging area is on the flightline side near Hangar 7733 within the contonment fencing area.
2.) Are there any adverse weather (rain, extreme cold, etc.) delay days included in the performance period of the contract?
Answer: Please refer to the following clause: FAR 52.249-10 Default (Fixed-Price
Construction.) This clause can be found at http://farsite.hill.af.mil/
3.) Will a vacuum truck be required for cleaning the site each day?
Answer: As per specifications on drawing page GI-002 6. Debris, the contractor shall have a sweeping machine and operator on site and ready at all times during construction activity where travel on or across runways, ramp areas, taxiways, or aircraft aprons is required.
4.) The phase durations listed in the phasing plan seem short given the quantity of work to be performed. This accelerated schedule may require weekend and/or night work, which would increase the project cost. May the project phase durations be extended?
Answer: The contract duration in the information document is 365 calendar days.
However, the actual listed durations is 284 calendar days providing a built in buffer of 81 calendar days.
5.) Will you please make available the sign in sheet?
Answer: The sign-in sheet for the Site Visit Conducted on August 11, 2017 will be a separate attachment on www.fbo.gov under Solicitation W9124M-17-B-0004.
(End of Summary of Changes) http://farsite.hill.af.mil/ http://www.fbo.gov/