SOLICITATIONbridge.pdf
PDF 397 KB Posted
- Attached to
- IDIQ Timber Bridge
- Solicitation number
- W9124M-15-B-0001
About this file
W9124M15B0001BRIDGE
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ABSTRACTbridge.xls | XLS spreadsheet | |
| W9124M-15-B-0001_Amend_0001.pdf | ||
| DRAWINGSREV1.pdf | ||
| StatementofWorkRevised27May2015.Pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
0010606284
1. Bidders must complete and return the SF 1442 Front and Back (2 pages), Section B (Bid Price Schedule), and Section K (Reps and Certs) by date/time specified in Block 13A of the SF 1442. FAX w ill not be accepted.
2. Offeror must acknow ledge receipt of all amendments by giving number and date as required in block 19.
3. Bids and bid amendments shall be submitted in sealed envelopes or packages and show solicitation number, date, and time of closing.
Please enter your CAGE code, Tax ID (TIN) & DUNS in Block 14 of Page 2.
4. The government intends to aw ard an IDIQ Contract from this solicitation.
5. The project is set aside for 100% HUBZone.
6. A Bid guarantee is required for this solicitation.
7.The Magnitude of this project is betw een $5,000,000 and $10,000,000.
8. Hard Copy of the bid and electronic copy on CD shall be hand delivered or mailed to the address in Block 7. The envelope shall be marked IAW FAR Clause 52.214-5 and ATTN Sebrena M. Butler/Mary L. Hightow er.
9. The Statement of Work for this project is attached. Draw ings: FS-3717 and HAAF 1848 (01-22-2014)
10. Contractors must be registered in the Central Contractor Registration Database now know n as System for Aw ard Management (SAM.gov) under NAICS Code 237310. See FAR 52.204-7 and FAR 52.204-8.
X
SEBRENA BUTLER 912-767-5296
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
24-Jun-2015
(RFP)
(IFB)
CALL:
IDIQ TIMBER BRIDGE REPAIR
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________365 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________52.211-10
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________29 Jul 2015 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee X is, is not required.
C. All of fers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______60 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
MICC, FORT STEWART F10156
ATTN SEBRENA BUTLER
EMAIL: SEBRENA.M.BUTLER.CIV@MAIL.MIL
912-767-5296
FORT STEWART GA 31314
W9124M
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
02:00 PM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
WG-103-4J
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: 912-767-5296 TEL: FAX:
W9124M-15-B-0001 89
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specified below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
Section A - Solicitation/Contract Form
NOTICE TO BIDDERS
1. Bid shall be submitted in sufficient detail to allow for analysis of fairness and reasonableness. As a minimum work should be broken out into the catagories provided in Attachment A.
2. INSTALLATION ACCESS CONTROL REQUIREMENTS, the building number has changed from 253 to 226, phone number 912-767-5195 for more information.
3. COMMERCIAL VEHICLE ACCESS TO FORT STEWART AND HUNTER ARMY AIRFIELD
a. These instructions apply for vehicle access to Fort Stewart and Hunter Army Airfield (henceforth referred to as FS and HAAF). Procedures for commercial vehicle access to FS and HAAF are subject to change without prior notice.
b. Unless the contractor voluntarily participates in the RAPIDGate® Program (see the paragraph entitled Identification Of Contractor's Employees – RAPIDGate® Program), commercial vehicle access to FS -will be allowed only at a Gate 7/7C (15th Street) and HAAF – will be allowed only at Montgomery Gate (Duncan Rd) Commercial Vehicle Inspection Point (CVIP). Both of these gates are operational 24hrs, 7 days a week, 7C is operational Monday through Friday 0500 – 1700 (Closed Weekends and Federal Holidays). All gate hours are subject to change without notice because of Force Protection Conditions.
Commercial Vehicle Gates are typically closed on weekends (Saturdays and Sundays) and federal holidays. All commercial vehicles will be inspected. The contractor should anticipate delays in getting commercial vehicles on post. The contractor must also allow additional time for commercial vehicles to reach their destination by driving through FS or HAAF. If the commercial vehicle is carrying a load of cement or hot asphalt for delivery, the driver shall notify the gate guard as soon as possible and request that the vehicle be given priority for being searched; however, the Government does not guarantee that the vehicle will be given priority.
On weekends large vehicles (needing greater than 12'-5" clearance) will require a time stamped "searched" label to gain access to FS and HAAF. The driver will receive a briefing on proper procedures and a "searched" label.
The contractor shall ensure that its drivers, including drivers of subcontractors at any tier, comply with the procedures as explained to them for access to FS or HAAF.
c. If the contractor participates in the RAPIDGate® Program, contractor vehicles may enter the installation through any RAPIDGate® lane except at Force Protection Level Charlie or Delta. During Force Protection Level Charlie or Delta, all contractor vehicles must enter through a CVIP. All passengers in the contractor vehicle must have a RAPIDGate® identification card.
RAPIDGate® is valid at:
FS
Gate 1 – 24 / 7 Gate 2 – 0500 – 1730 Gate 3 – 0500 – 2100 (Sun – Sat) Gate 5 – 24 / 7 Gate 7 – 24 / 7 Gate 7C – 0500 – 1700
(M – F) Closed Weekends and Federal Holidays Gate 8 – 0500 – 2100 (Sun – Sat) Gate 9 – 24 / 7
HAAF
Montgomery Gate – 24 / 7
Wilson Gate – 0500 – 2100 (Sun – Sat)
Rio Gate – 24 / 7
d. If the RAPIDGate® Program is terminated for any reason, the contractor will be allowed access only through the 7 and 7C, FS and Montgomery Gate, HAAF.
7. IDENTIFICATION OF CONTRACTOR'S EMPLOYEES – RAPIDGATE® PROGRAM
a. These instructions apply for vehicle access to Fort Stewart and Hunter Army Airfield (henceforth referred to as FS and HAAF). Procedures for commercial vehicle access to FS and HAAF are subject to change without prior notice.
b. Each employee who requires access to FS and HAAF to perform work under any contract, at any tier, must obtain either a RAPIDGate® identification badge or a visitor’s pass to obtain access.
(1) A RAPIDGate® identification badge will only be issued to an employee, at any tier, if the employee requires access more than twice per week. A RAPIDGate® identification badge will only be issued to contractor employees if the contractor participates in the RAPIDGate® Program. The RAPIDGate® Program is a voluntary program. Companies must be listed on the Contractors Authorized List (CAL).
(2) Contractor employees, at any tier, who require access twice per week or less often or who do not participate in the RAPIDGate® Program shall obtain a visitor’s pass at a FS and HAAF at a Commercial Vehicle Inspection Point. The visitor’s pass can be issued for a maximum of 30 days at a time. Companies must be listed on the CAL and employees obtaining a pass must be sponsored.
Only those company employees listed on the CAL may sponsor other employees. Employees may also be sponsored by a military ID Cardholder associated with the contract.
c. The contractor shall provide information as required by the RAPIDGate® Program Contractor (RPC) to enable the RAPIDGate® Program contractor to conduct a criminal history background check (CHBC) on contractor employees who are to have access. The contractor is responsible for paying the RPC the fee per employee for conducting the CHBC and issuing the RAPIDGate® identification card. If the CHBC is not adverse, a RAPIDGate® identification badge will be issued by the RPC to the contractor employee. If the CHBC is adverse, the RPC is prohibited from issuing a RAPIDGate® identification badge to the contractor employee. If a RAPIDGate® identification badge is denied for any reason, the contractor employee may only enter the installation by obtaining a visitor’s pass; however, if the contractor employee does not meet the criteria for being issued a RAPIDGate® identification badge, the Government may, at its sole discretion, decide not to issue a visitor’s pass to the contractor employee.
d. If an employee no longer needs an identification badge for any reason (e.g., quits his/her job or no longer performs work under the contract), the contractor shall return the identification badge to the FS and HAAF within two (2) calendar days of such change. If the identification badge cannot be returned within the required time frame for any reason, the contractor shall immediately notify both the RPC and the Visitor Center verbally, followed up in writing the next work day. Email notification is authorized. An employee’s inability to obtain entrance to a Government installation because he/she does not have the required identification badge or visitor’s pass shall not excuse timely performance of the requirements of this contract. Badges are currently issued at the FS Registration Office, Bldg 226. The Government may change the location at which identification badges are issued or returned, with or without advance notice to the contractor. Any such changes shall not be a basis for adjusting the contract price under any clause of this contract.
e. RAPIDGate® identification badges shall not be reproduced or copied by the contractor, its subcontractors, or their employees. If an employee’s identification badge is lost, stolen, or reproduced, the contractor shall verbally report the loss, theft, or reproduction to both the RPC and the Registration Office on the day such loss, theft, or reproduction is discovered, followed by a written report of the circumstances to both the RPC and the Visitor Center within one (1) calendar day after the loss, theft, or reproduction is discovered.
f. Each contractor employee shall wear the RAPIDGate® identification badge while performing work under the contract. The identification badge shall be worn on the upper front of the outer garment unless precluded by OSHA regulation(s). The identification badge shall not be used for access to any Government installation except for performance of work under the contract for which it was issued.
g. The contractor shall, upon expiration or termination of the contract, collect all identification badges and turn them in to the COR.
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job IDIQ Bridge Contract - Base Year
FFP
IDIQ Bridge Contract - Base Year furnish all plant, labor, materials and performing all operations required in connection with Constructing and Miscellaneous Repairs to Timber and Concrete Bridges, Ft Stewart and Hunter AAF and shall be complete in strict accordance with specifications and drawings.
FOB: Destination
PROJECT: WG-103-4J/ED-36-4J
FOB: Destination
PURCHASE REQUEST NUMBER: 0010606284
NET AMT
0002 1 Job IDIQ Bridge Contract - Option Year 1
FFP
IDIQ Bridge Contract - Option Year 1 furnish all plant, labor, materials and performing all operations required in connection with Constructing and Miscellaneous Repairs to Timber and Concrete Bridges, Ft Stewart and Hunter AAF and shall be complete in strict accordance with specifications and drawings.
FOB: Destination
PROJECT: WG-103-4J/ED-36-4J
0003 1 Job IDIQ Bridge Contract - Option Year 2
FFP
IDIQ Bridge Contract - Option Year 2 furnish all plant, labor, materials and performing all operations required in connection with Constructing and Miscellaneous Repairs to Timber and Concrete Bridges, Ft Stewart and Hunter AAF and shall be complete in strict accordance with specifications and drawings.
FOB: Destination
PROJECT: WG-103-4J/ED-36-4J
BID SCHEDULE LINE ITEM
Bid Schedule Line items are based on:
a) Unit prices are for complete and in-place construction and include all labor, equipment and material required to complete the task as described in the Technical Requirements.
b) Unit Prices include delivery, unloading and storing materials, tools and equipment on site;
moving, materials, tools and equipment from storage area or truck and within 125’ to reach the site.
c) Unit prices for imported materials (aggregate, sand, soil, etc.) include delivery up to 15 miles from the closest approved source.
d) Unit prices include all fasteners such as anchor bolts, lag bolts, screws, adhesive, wedge anchors, expansion bolts, roofing clips (excluding hurricane clips) that are required.
e) Unit prices include testing, calibration, balancing and the like required to ensure proper installation, construction and performance (e.g. compaction test for backfill, hydrostatic testing, soaping of joints, others as required). Use of owner supplied materials, equipment or tying into existing equipment/piping may justify testing, balancing, etc.
f) Unit prices for demolition include all labor, equipment and material required for the complete removal of the required items; clean-up of the area; and transferring within 125' of the site into a truck or dumpster for debris or to a designated area for owner requested items.
g) The description "replace" includes the demolition of the existing item and the installation of the new item.
BID PRICE SCHEDULE
BASE YEAR
ITEM DESCRIPTION QUANTITY U/I UNIT PRICE AMOUNT
0001 Demolition of Decking, Stringers and Curbing 150 LF
0002 Demolition of Five Pile Bent 15 EA
0003 Demolition of Reinforced Concrete 50 CY
0004 Demolition of Abutement Wingwall 4 EA
0005 Demolition of Bulkhead 4 EA
0006 Construct Two-Layers of Decking, Curb and Stringers (14 foot Span)
20 EA
Stringers (14' Span)
0007 Construct Five Pile Bent and Cap, 20' Pile 5 EA
0008 Construct Five Pile Bent and Cap, 30' Pile 5 EA
0009 Construct Five Pile Bent and Cap, 40' Pile 20 EA
0010 Construct Five Pile Bent and Cap, 50' Pile 20 EA
0011 Construct Five Pile Bent and Cap, 60' Pile 5 EA
0012 Construct Bulkhead 1000 SF
0013 Construct Abutement Wall Type 1 6 EA
0014 Construct Abutement Wall Type 2 6 EA
0015 Construct Concrete Bridge Approach 4 EA
0016 Construct Bracing (Height on Bridge Under 12') 750 LF
0017 Construct Bracing (Height on Bridge Over 12') 750 LF
0018 Construct Classification Sign (Includes all Signs) 16 EA
0019 Remove and Replace Decking, Treadway and Curb (Full width - 22'-8"+ )
100 LF
Curb (Full Width - 22'-6")
0020 Remove and Replace Cap (14"x14") 5 EA
0021 Remove and Replace Stringer (10"x18") 10 EA
0022 Remove and Replace Pile 20 Foot Length 5 EA
0023 Remove and Replace Pile 30 Foot Length 5 EA
0024 Remove and Replace Pile 40 Foot Length 5 EA
0025 Remove and Replace Pile 50 Foot Length 5 EA
0026 Remove and Replace Pile 60 Foot Length 5 EA
0027 Remove and Replace Wingwall/Bulkhead Boards 500 LF
0028 Remove and Replace Curb and Blocking 250 LF
0029 Remove and Replace Damaged Treadway Spike 500 EA
0030 Inspect and Tighten Bolts (Per Span) 330 EA
0031 Remove Dirt from Bridge Treadway 4,620 LF
0032 Remove and Replace Damaged Galvanized 25 EA
Metal Pile Cap
0033 Seal Concrete Bridge Joints (Up to 2"Wide) 200 LF
0034 Provide and Install Shim for Bridge Pile/Cap 50 EA
0035 Provide and Install Pile Band 5 EA
0036 Provide and Install Rip Rap 250 Ton
0037 Remove and Replace Treadway and Deck Board 500 LF
0038 Provide and Install Nuts and Washers 10 EA
0039 Provide and Install Bolt Assembly (Includes Bolt, 10 EA
Nut and Washer)
0040 Clear 10' x 50' (Each Side of Bridge) 20 EA
0041 Select Clearing 6500 SY
0042 Provide and Install Sign 300 SF
0043 Excavation (On Site Excavation- No Haul Off) 2000 CY
0044 Excavate and Haul Soil to Site (10 Mile Radius) 2000 CY
0045 Provide and Haul Soil to Hunter AAF Project Site 1000 CY
0046 Backfilll and Compaction 2000 CY
0047 Finish Grade (Hand Work for Grassing) 1000 SY
0048 Provide and Grassing Area (Hydroseeding) 1000 SY
0049 Remove Storm Pipe Under 36" Diameter 100 LF
0050 Remove Storm Pipe Over 36" Diameter 100 LF
0051 Provide and Install 24" Diameter Storm Pipe 100 LF
0052 Provide and Install 36" Diameter Storm Pipe 100 LF
0053 Provide and Install 48" Diameter Storm Pipe 100 LF
0054 Provide and Install 60" Diameter Storm Pipe 100 LF
0055 Provide and Install 24" Diameter Storm Pipe 6 EA
Flared End Section
0056 Provide and Install 36" Diameter Storm Pipe 6 EA
Flared End Section
0057 Provide and Install 48" Diameter Storm Pipe 6 EA
Flared End Section
0058 Provide and Install 60" Diameter Storm Pipe Flared End
6 EA
Flared End Section
0059 Provide and Install Type "C" Silt Fence 500 LF
0060 Provide and Install Geotextile Material at 1000 SY
Bulkhead
0061 NON PREPRICE ITEMS 1 LS
TOTAL BASE YEAR
1st OPTION YEAR
ITEM DESCRIPTION QUANTITY U/I UNIT PRICE AMOUNT
1001 Demolition of Decking, Stringers and Curbing 150 LF
1002 Demolition of Five Pile Bent 15 EA
1003 Demolition of Reinforced Concrete 50 CY
1004 Demolition of Abutement Wingwall 4 EA
1005 Demolition of Bulkhead 4 EA
1006 Construct Two-Layers of Decking, Curb and Stringers (14 foot Span)
20 EA
Stringers (14' Span)
1007 Construct Five Pile Bent and Cap, 20' Pile 5 EA
1008 Construct Five Pile Bent and Cap, 30' Pile 5 EA
1009 Construct Five Pile Bent and Cap, 40' Pile 20 EA
1010 Construct Five Pile Bent and Cap, 50' Pile 20 EA
1011 Construct Five Pile Bent and Cap, 60' Pile 5 EA
1012 Construct Bulkhead 1000 SF
1013 Construct Abutement Wall Type 1 6 EA
1014 Construct Abutement Wall Type 2 6 EA
1015 Construct Concrete Bridge Approach 4 EA
1016 Construct Bracing (Height on Bridge Under 12') 750 LF
1017 Construct Bracing (Height on Bridge Over 12') 750 LF
1018 Construct Classification Sign (Includes all Signs) 16 EA
1019 Remove and Replace Decking, Treadway and Curb (Full width - 22'-8"+ )
100 LF
Curb (Full Width - 22'-6")
1020 Remove and Replace Cap (14"x14") 5 EA
1021 Remove and Replace Stringer (10"x18") 10 EA
1022 Remove and Replace Pile 20 Foot Length 5 EA
1023 Remove and Replace Pile 30 Foot Length 5 EA
1024 Remove and Replace Pile 40 Foot Length 5 EA
1025 Remove and Replace Pile 50 Foot Length 5 EA
1026 Remove and Replace Pile 60 Foot Length 5 EA
1027 Remove and Replace Wingwall/Bulkhead Boards 500 LF
1028 Remove and Replace Curb and Blocking 250 LF
1029 Remove and Replace Damaged Treadway Spike 500 EA
1030 Inspect and Tighten Bolts (Per Span) 330 EA
1031 Remove Dirt from Bridge Treadway 4,620 LF
1032 Remove and Replace Damaged Galvanized 25 EA
Metal Pile Cap
1033 Seal Concrete Bridge Joints (Up to 2"Wide) 200 LF
1034 Provide and Install Shim for Bridge Pile/Cap 50 EA
1035 Provide and Install Pile Band 5 EA
1036 Provide and Install Rip Rap 250 Ton
1037 Remove and Replace Treadway and Deck Board 500 LF
1038 Provide and Install Nuts and Washers 10 EA
1039 Provide and Install Bolt Assembly (Includes Bolt, 10 EA
Nut and Washer)
1040 Clear 10' x 50' (Each Side of Bridge) 20 EA
1041 Select Clearing 6500 SY
1042 Provide and Install Sign 300 SF
1043 Excavation (On Site Excavation- No Haul Off) 2000 CY
1044 Excavate and Haul Soil to Site (10 Mile Radius) 2000 CY
1045 Provide and Haul Soil to Hunter AAF Project Site 1000 CY
1046 Backfilll and Compaction 2000 CY
1047 Finish Grade (Hand Work for Grassing) 1000 SY
1048 Provide and Grassing Area (Hydroseeding) 1000 SY
1049 Remove Storm Pipe Under 36" Diameter 100 LF
1050 Remove Storm Pipe Over 36" Diameter 100 LF
1051 Provide and Install 24" Diameter Storm Pipe 100 LF
1052 Provide and Install 36" Diameter Storm Pipe 100 LF
1053 Provide and Install 48" Diameter Storm Pipe 100 LF
1054 Provide and Install 60" Diameter Storm Pipe 100 LF
1055 Provide and Install 24" Diameter Storm Pipe 6 EA
Flared End Section
1056 Provide and Install 36" Diameter Storm Pipe 6 EA
Flared End Section
1057 Provide and Install 48" Diameter Storm Pipe 6 EA
Flared End Section
1058 Provide and Install 60" Diameter Storm Pipe Flared End
6 EA
Flared End Section
1059 Provide and Install Type "C" Silt Fence 500 LF
1060 Provide and Install Geotextile Material at 1000 SY
Bulkhead
1061 NON PREPRICE ITEMS 1 LS
TOTAL 1ST OPTION YEAR
2nd OPTION YEAR
ITEM DESCRIPTION QUANTIT
Y
U/I UNIT PRICE AMOUNT
2001 Demolition of Decking, Stringers and Curbing 150 LF 2002 Demolition of Five Pile Bent 15 EA 2003 Demolition of Reinforced Concrete 50 CY 2004 Demolition of Abutement Wingwall 4 EA 2005 Demolition of Bulkhead 4 EA 2006 Construct Two-Layers of Decking, Curb and
Stringers (14 foot Span)
20 EA
Stringers (14' Span) 2007 Construct Five Pile Bent and Cap, 20' Pile 5 EA 2008 Construct Five Pile Bent and Cap, 30' Pile 5 EA 2009 Construct Five Pile Bent and Cap, 40' Pile 20 EA 2010 Construct Five Pile Bent and Cap, 50' Pile 20 EA 2011 Construct Five Pile Bent and Cap, 60' Pile 5 EA 2012 Construct Bulkhead 1000 SF 2013 Construct Abutement Wall Type 1 6 EA 2014 Construct Abutement Wall Type 2 6 EA 2015 Construct Concrete Bridge Approach 4 EA 2016 Construct Bracing (Height on Bridge Under 12') 750 LF 2017 Construct Bracing (Height on Bridge Over 12') 750 LF 2018 Construct Classification Sign (Includes all Signs) 16 EA 2019 Remove and Replace Decking, Treadway and
Curb (Full width - 22'-8"+ )
100 LF
Curb (Full Width - 22'-6") 2020 Remove and Replace Cap (14"x14") 5 EA 2021 Remove and Replace Stringer (10"x18") 10 EA 2022 Remove and Replace Pile 20 Foot Length 5 EA 2023 Remove and Replace Pile 30 Foot Length 5 EA 2024 Remove and Replace Pile 40 Foot Length 5 EA 2025 Remove and Replace Pile 50 Foot Length 5 EA 2026 Remove and Replace Pile 60 Foot Length 5 EA 2027 Remove and Replace Wingwall/Bulkhead Boards 500 LF
2028 Remove and Replace Curb and Blocking 250 LF 2029 Remove and Replace Damaged Treadway Spike 500 EA 2030 Inspect and Tighten Bolts (Per Span) 330 EA 2031 Remove Dirt from Bridge Treadway 4,620 LF 2032 Remove and Replace Damaged Galvanized 25 EA
Metal Pile Cap 2033 Seal Concrete Bridge Joints (Up to 2"Wide) 200 LF 2034 Provide and Install Shim for Bridge Pile/Cap 50 EA 2035 Provide and Install Pile Band 5 EA 2036 Provide and Install Rip Rap 250 Ton 2037 Remove and Replace Treadway and Deck Board 500 LF 2038 Provide and Install Nuts and Washers 10 EA 2039 Provide and Install Bolt Assembly (Includes Bolt, 10 EA
Nut and Washer) 2040 Clear 10' x 50' (Each Side of Bridge) 20 EA 2041 Select Clearing 6500 SY 2042 Provide and Install Sign 300 SF 2043 Excavation (On Site Excavation- No Haul Off) 2000 CY 2044 Excavate and Haul Soil to Site (10 Mile Radius) 2000 CY 2045 Provide and Haul Soil to Hunter AAF Project Site 1000 CY 2046 Backfilll and Compaction 2000 CY 2047 Finish Grade (Hand Work for Grassing) 1000 SY 2048 Provide and Grassing Area (Hydroseeding) 1000 SY 2049 Remove Storm Pipe Under 36" Diameter 100 LF 2050 Remove Storm Pipe Over 36" Diameter 100 LF 2051 Provide and Install 24" Diameter Storm Pipe 100 LF 2052 Provide and Install 36" Diameter Storm Pipe 100 LF 2053 Provide and Install 48" Diameter Storm Pipe 100 LF 2054 Provide and Install 60" Diameter Storm Pipe 100 LF 2055 Provide and Install 24" Diameter Storm Pipe 6 EA
Flared End Section 2056 Provide and Install 36" Diameter Storm Pipe 6 EA
Flared End Section 2057 Provide and Install 48" Diameter Storm Pipe 6 EA
Flared End Section 2058 Provide and Install 60" Diameter Storm Pipe
Flared End
6 EA
Flared End Section 2059 Provide and Install Type "C" Silt Fence 500 LF 2060 Provide and Install Geotextile Material at 1000 SY
Bulkhead
2061 NON PREPRICE ITEMS 1 LS
TOTAL 2ND OPTION YEAR
CLIN MAX AMOUNT
0001 $
1001 $
2001 $
TOTAL $
Section C - Descriptions and Specifications
STATEMENT OF WORK
TECHNICAL PROVISIONS
GENERAL
1. DESCRIPTION OF WORK:
1.1 Work to be Done: The work covered by this contract consists of furnishing all plant, labor, materials and performing all operations required in connection with Constructing and Miscellaneous Repairs to Timber and Concrete Bridges, Ft Stewart and Hunter AAF and shall be complete in strict accordance with specifications and drawings. The work includes, but is not necessarily restricted to, the following items.
1.1.1 After receipt of contract award and upon notification by the Contracting Officer, the Contractor shall meet Government personal for the purpose of verifying existing site conditions of each bridge. The contractor and Government will visit each bridge for the purpose of scoping the work to be done. Performance time will be sited on each delivery order in accordance with contract provision entitled, “Delivery Order Performance Time”.
1.1.2 Contractor shall demolish as issued by the delivery order existing bridge(s) which may include bulkheads, wingwalls, stringers, piles, caps, decking, and miscellaneous items.
1.1.3 Contractor shall remove all debris and demolished material to the appropriate sites. No landfill area available on Ft. Stewart or Hunter AAF.
1.1.4 Contractor shall construct new timber bridges or repair by component replacement as issued by the delivery order to include bulkheads, wingwalls, stringers, decking, piles, caps, and miscellaneous bolts, and fasteners shown on drawings. This work includes clearing brush, excavation, backfilling, compacting, and grading as necessary to complete this contract.
1.1.5 Contractor shall install storm piping in location directed. This work includes excavation, backfilling, compacting, and grading as necessary to complete this contract.
2. CLOSURE TO TRAFFIC
2.1 Contractor shall request closure of the road or bridges by written request to the Contracting Officer’s Representative at least 10 working days prior to the desired closing date for any road or bridge, or portion thereof, to traffic. The request shall also include a schedule of work for each phase of work for each bridge to be replaced. A sketch shall be provided showing locations of closure area and placement of barricades and signs for traffic control.
2.2 Before closing or removing a road or bridge, contractor shall furnish and erect approved barricades, warning lights, signals and signs to protect the public as approved by the Contracting Officer Representative. Contractor will be responsible for maintaining traffic control devices during construction at each bridge location.
3. FACTORS AFFECTING PERFORMANCE UNDER THE CONTRACT:
3.1 The contractor’s attention is directed to the fact that the work will be accomplished on tank trails located within the boundary of Ft. Stewart and Hunter AAF. The contractor shall coordinate entry through the Ft. Stewart Range Control Office, Building 8302 and the Directorate of Emergency Services at Building 283.
3.2 The contractor shall notify the Contracting Officer’s Representative 30 working days in advance to coordinate the contract performance with the Range Control Office.
3.3 Electric power will not be available for use at job site. It shall be the contractor’s responsibility to furnish all necessary electrical power, temporary wiring and safety devices necessary to comply with the applicable codes/safety requirements.
3.4 Maintenance work on bridges shall be limited to 10 bridges at one time unless approved by the COR. Total bridge replacement shall be limited to two bridges at one time unless approved by the COR.
3.5 Excavation Permits: Permits shall be issued by using the Georgia 811, Utilities Protection Center, Inc. Phone number is1-800-282-7411. Excavation of any type is prohibited after normal working hours without prior approval of the Contracting Officer.
3.6 Contractor office trailers and storage yard will be in accordance with “US Army Garrison, Ft. Stewart and Hunter AAF Policy memorandum #10-Design and Maintenance of Contractor Storage “dated 25 January 2013.
3.7 Electrical power for temporary construction office during contract will be accomplished through coordination and paid to Canoochee EMC.
SECTION 02 41 00
DEMOLITION
1. SUBMITTALS: The procedures proposed for the accomplishment of salvage and demolition work shall be submitted for approval. The procedures shall provide for safe conduct of the work, careful removal and disposition of materials specified to be salvaged, protection of property which is to remain undisturbed, coordination with other work in progress, and timely disconnection of utility services. The procedures shall include a detailed description of the methods and equipment to be used for each operation, and the sequence of operations.
2. GENERAL REQUIREMENTS: The work includes demolition or removal of all construction indicated or specified. All materials resulting from demolition work, except as indicated or specified otherwise, shall become the property of the Contractor and shall be removed from the limits of Government property. Rubbish and debris shall be removed from Government property daily unless otherwise directed so as to not allow accumulation. Materials that cannot be removed daily shall be stored in areas specified by the Contracting Officer.
3. PROTECTION:
3.1 Protection of Existing Work: Before beginning any cutting or demolition work, the Contractor shall carefully survey the existing work and examine the drawings and specifications to determine the extent of the work. The Contractor shall take all necessary precautions to insure against damage to existing work to remain in place, to be reused, or to remain the property of the Government, and any damage to such work shall be repaired or replaced as approved by the Contracting Officer at no additional cost to the Government. The Contractor shall carefully coordinate the work of this section with all other work and construct and maintain shoring, bracing and supports, as required. The Contractor shall insure that structural elements are not overloaded and be responsible for increasing structural supports or adding new supports as may be required as a result of any cutting, removal, or demolition work performed under any part of this Contract. Trees within project site shall be protected from damage.
4. BURNING the use of burning at the project site for the disposal of refuse and debris will not be permitted.
5. USE OF EXPLOSIVES: Use of explosives will not be permitted.
6. EXISTING FACILITIES:
6.1 Structures or Concrete: Existing structure and material shall be removed in their entirety.
6.2 Utilities:
6.2.1. Removal of Utilities: Existing utilities shall be removed as required. When utilities lines are encountered that are not on the drawings the COR shall be notified.
7. DISPOSTION OF MATERIAL:
7.1 Title to Materials: Title to all materials and equipment to be demolished is vested in the Contractor upon receipt of notice to proceed. The Government will not be responsible for the condition, loss or damage to such property after notice to proceed.
7.2 Material for Contractor Salvage: Material for salvage shall be stored as approved by the Contracting Officer. Salvage materials shall be removed from Government property before completion of the Contract. Material for salvage shall not be sold on the site.
7.2.1 Damaged Items: Items damaged during removal or storage shall be repaired or replaced to match existing.
8. CLEAN-UP:
8.1 Debris and Rubbish: Debris and rubbish shall be removed from job site daily.
8.2 Debris Control: Debris shall be removed and transported in a manner as to prevent spillage on streets or adjacent areas.
8.3 Regulations: Local regulations regarding hauling and disposal apply.
SECTION 03 30 00.00.20
CONCRETE FOR BUILDING CONSTRUCTION
(MINOR REQUIREMENTS)
PART 1 - GENERAL
1. APPLICABLE PUBLICATIONS: The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
1.1 American Concrete Institute (ACI) Standard:
ACI 318 (2011; Errata 1 2011, Errata 2 2012; Errata 3-4 2013) Building Code Requirements for Reinforced Concrete
1.2 American Society for Testing and Materials (ASTM) Publication:
ASTM C 94 (2013A) Ready-Mixed Concrete
2. GENERAL REQUIREMENT: The work shall be in conformance with ACI 318, part entitled "Construction Requirements," except as specified herein.
2.1 Compressive Strength: Concrete mixes shall be proportioned to obtain compressive strength in 28 days of 750 Flex. The compressive strengths shall be reached in 7 days when high- early-strength cement is used.
2.2 Air Content: Total air content of exterior concrete shall be maintained at 5 to 7 percent by volume of concrete.
2.3 Slump: Maximum slump shall be 3 inches.
2.4 Fiber Reinforcement: Concrete shall be nylon or polypropylene fiber reinforced concrete.
3. STORAGE: Materials shall be stored so as not to deteriorate or become contaminated.
PART 2 - PRODUCTS
4. MATERIALS shall conform to the following:
4.1 Abrasive Aggregate: Aluminum oxide, emery, or silicon-carbide abrasive.
4.2 Anchorage Items: Standard manufactured item of the types indicated or required for the application.
4.3 Concrete Materials: ASTM C 94, cement type optional. Only one brand of any one type of cement shall be used for exposed concrete surfaces of any individual structure.
4.4 Curing Materials: Impervious sheet or membrane-forming curing compound.
Impervious sheet shall be white opaque polyethylene 4 mil thick, waterproof kraft paper, or polyethylene-coated burlap. Membrane-forming curing compound shall be of commercial formulation, sprayable, nontoxic, and of the type that will dry within 4 hours and form a film highly resistant to moisture loss from concrete while curing. Compound shall be clear with fugitive dye, resin-base or chlorinated-rubber-base-type.
4.5 Form Coating: Nonstaining form oil or form release agent that will not deleteriously affect concrete surfaces nor impair subsequent applications.
4.6 Form Materials: Plywood or hardboard especially made for concrete form use or other materials that will produce the specified finish without adversely affecting the concrete surfaces.
4.7 Reinforcement: Deformed, Grade 60-billet steel. Mesh shall be welded steel wire fabric with wires at right angles to each other.
4.8 Dowels: Plain carbon steel bars, minimum yield point of 40,000 psi for use in slabs on grade.
4.9 Expansion Joint Filler Strip: Premolded nonextruding, resilient bituminous or nonbituminous type for use in concrete paving or construction.
4.10 Fiber: Fiber shall be nylon or polypropylene .015 inch in diameter and be at 1% content by volume or 3 pounds per cubic yard.
PART 3 - EXECUTION
5. FORMWORK shall be made mortar tight, properly aligned and adequately supported to produce concrete conforming accurately to the indicated shapes, lines, dimensions, and with surfaces free of offsets, waviness, or bulges. Where surfaces are to be exposed or painted, panels shall be manufacturer's stock size material, using smaller panels cut to required dimensions only where required by openings and joints. Panel joints in exposed or painted work shall occur at control joints, including alignment with masonry control joints and construction joints. Unless otherwise shown, exposed external corners shall be chamfered, beveled, or rounded by moldings placed in the forms. Surfaces shall be thoroughly cleaned and coated before each use. Forms shall be removed at a time and in a manner that will not injure the concrete.
6. REINFORCEMENT: Reinforcement shall be fabricated to the shapes required.
Wire-mesh reinforcement shall be continuous between joints in slabs on grade. Laps shall be at least one full mesh plus 2 inches; staggered to avoid continuous lap in either direction; and securely wired or clipped with the standard clips. Mesh shall be supported on precast concrete units or specifically designed wire-fabric supports fabricated of plastic in a manner that will support the mesh at the minimum height indicated.
7. INSTALLATION OF ANCHORAGE ITEMS shall be as indicated or required to insure sufficient anchorage for purpose intended.
8. JOINTS:
8.1 Expansion Joint: Expansion joint filler shall be as shown on drawings.
9. PLACING: Concrete footings and slabs shall be placed upon clean undisturbed surfaces free from frost, ice, and water. Dry or pervious surfaces receiving concrete shall be covered with impervious sheet materials. Concrete may be placed directly on impervious surfaces that are thoroughly moistened but not muddy. During cold weather, in-place concrete shall be protected from freezing throughout the curing period.
Concrete to receive other construction shall be screeded to the proper level.
10. CONSOLIDATION OF CONCRETE: Each layer of concrete shall be consolidated with internal concrete vibrators supplemented by hand spading, rodding, and tamping.
Vibrating equipment shall be adequate to thoroughly consolidate the concrete.
11. FINISHING CONCRETE:
11.1 Formed Surfaces: Fins and loose material shall be removed. Unsound concrete, voids over 1/2 inch in diameter, and tie-rod and bolt holes shall be cut back to solid concrete, reamed, brush-coated with cement grout, and filled solid with a stiff portland-cement-sand mortar mix. Patchwork shall finish flush with adjoining concrete surfaces and, where exposed, shall match adjoining surfaces in texture and color.
Patchwork shall be cured for 72 hours. White portland cement shall be used as needed to attain color match.
11.2 Unformed Surfaces: Surfaces shall be finished to a true plane with no deviation exceeding 5/16 inch when tested with a 10-foot straightedge. Surfaces shall be pitched to drains. Surfaces shall be screeded and floated to the required finish level with no coarse aggregate visible before finishing as specified below.
11.2.1 Nonstop Finish: The concrete shall receive a nonslip finish so indicated by brooming with a fiber-bristle brush in a direction transverse to that of main traffic. Do not use a burlap drag on fiber reinforced concrete.
12. CURING shall start as soon as free water has disappeared from concrete surfaces after placing and finishing. Curing materials shall be applied and maintained so as to protect the concrete from moisture loss for 7 days. Curing shall be accomplished by impervious sheet or membrane-forming curing compound. Concrete surfaces shall be thoroughly wetted before covering with impervious-sheet materials. Membrane-forming curing compound shall be applied with mechanical spraying equipment at a coverage of not more than 300 square feet per gallon. Surfaces of compound damaged during curing shall be resprayed. The compound shall not be used on surfaces to receive floor hardener or receiving applications depending on adhesion or bonding, except that resin-base or chlorinated- rubber-base compounds may be used on floors receiving resilient flooring; surfaces to be painted; and surfaces to receive bituminous roofing or waterproofing.
13. TESTING: Contractor is responsible for testing concrete to determine concrete strength. Each test shall comprise of taking three (3) test cylinders to determine 7, 14 and 28-day strengths of the new concrete. A minimum of one test each day that concrete is placed is required and a minimum of one test for each 50 cubic yards of concrete placed in one day is required.
SECTION 06 13 33
TIMBERWORK AND MISCELLANEOUS WORK
PART 1 - GENERAL
1.1 APPLICABLE PUBLICATIONS:
1.1.1 U.S. DEPARTMENT OF DEFENSE (DOD.):
MIL-P-21035 (1991; Rev B; Notice 2 2003) Paint, High Zinc Dust Content, Galvanizing Repair
MIL-S-46163A Sealing, Lubricating and Wicking Compound:
Thread-Locking, Anaerobic Single Component
1.1.2 American Society for Testing and Materials (ASTM) Publications:
ASTM A 123 (2012) Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products
ASTM A 153 (2009) Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel Wire
ASTM A 307 (2012) Standard Specification for Carbon Steel Externally Threaded Standard Fasteners
ASTM F 1667 (2011) Standard Specification for Driven Fasteners: Nails, Spikes and Staples
1.1.3 American Wood Preservers' Association (AWPA) Standards:
AWPA C1 (2003) All Timber Products – Preservation Treatment by Pressure Processes
AWPA C2 (2003) Lumber, Timber, Bridge Ties and Mine Ties - Preservative Treatment by Pressure Process
AWPA M2 (2001) Standard for Inspection of Treated Timber Products
AWPA M4 (2002) Care of Preservative-Treated Wood Products
AWPA M6 (1996) Brands Used on Forest Products
AWPA P5 (2007) Standard for Waterborne Preservatives
AWPA U1 (2013) Use Category System: User Specification for Treated Wood
1.2 SUBMITTALS:
1.2.1 Certified Test Reports:
Submit the inspection report of an independent inspection agency, for information only, offered products complying with applicable AWPA Standards. Identify treatment on each piece by the quality mark of an agency accredited by the Board of Review of the American Lumber Standard Committee. The AWPB Quality Mark on each piece will be accepted, in lieu of inspection reports, as evidence of compliance with applicable AWPA treatment standards.
1.2.2 Delivery Inspection List
Contractor shall field verify and submit a verification list of each treated timber member and each strapped bundle of treated lumber indicating the wording and lettering of the quality control marking, the species and condition of the wood. Do not incorporate materials damaged in transportation from the plant to site. Inspect all preservation-treated wood, visually to ensure there are no excessive residual materials or preservation deposits. Material shall be clean and dry or it will be rejected due to environmental concerns.
1.3 DELIVERY AND STORAGE: Material shall be delivered to the site in undamaged condition, stored in fully covered, well ventilated areas, and protected from extreme changes in temperature and humidity. Handle treated timber with ropes or chain slings without dropping, breaking outer fibers, bruising, or penetrating surfaces with tools. Do not use cant dogs, peaveys, hooks or pike poles. Protect timber and hardware from damage.
PART 2 - PRODUCTS
2.1 MATERIALS:
2.1.1 Lumber and Timbers: All wood used shall be as specified on drawings and identified by the grade mark of a recognized association or independent inspection agency using the specific grading requirements of an association recognized as covering the species used. The association or independent inspection agency shall be certified by the Board of Review, American Lumber Standards Committee, to grade the species used.
2.1.1.2 Preservative Treatment: All wood shall be treated with retention asset of 0.80 pound per cubic foot. Each piece of treated lumber shall be branded, by the producer, in accordance with AWPA M6. For wood not in contact with salt water or salt splash, treatment in accordance with AWPA U1 preservative AWPA P5 except that chromated zinc chlorides, pentachlorophenol-ammoniacal systems, creosote, and alkyl ammonium compounds will not be allowed. The contractor shall be responsible for the quality of treated wood products. Treatment used shall be approved for Soil Contact and Fresh Water Exposure.
2.1.2 Hardware: Nails, screws, spikes, and other fastenings shall meet the requirements of ASTM F 1667. Bolts and nuts shall conform to ASTM A 307. Provide washers, cast-iron ogee, where indicated. Provide bolts with washers under nut and head. Hot dip-galvanize all hardware. All bolt and nut connections shall have a thread-locking compound applied before tightening. Compound shall conform to Mil. Spec-S-46163A Type II, Grade G. Deck spikes shall be shall be 3/8” square x 8” long galvanized.
2.1.2.1 Zinc-Coating: Galvanize steel specified or indicated by the hot-dip process in accordance with ASTM A 123 and ASTM A 153, as applicable.
2.2 FIELD TREATMENT:
2.2.1 Timberwork: Field treat all cuts, drilled holes, bevels, notches, refacing and abrasions made in the field in treated piles or timbers in accordance with AWPA M4, MSDS, and CIS. Trim all cuts and abrasions before field treatment. Paint all depressions or openings around bolt holds, joints, or gaps including recesses formed by counterboring, with preservative treatment used for piles or timbers; and after bolt or screw is in place, fill with hot pitch or a bitumastic compound.
2.2.2 Piling Protection: In accordance with AWPA M4, immediately after pile tops are cut off and prior to placement of decking, protect pile top with several heavy applications of the same preservative used to treat the pile or post, or else copper napthenate solutions containing a minimum of 2 percent copper metal may be used with all treated products. Seal ends shall be sealed with a heavy application of coal-tar pitch or other appropriate sealer.
2.2.3 Galvanized Surfaces: Repair and recoat zinc coating which has been field or shop cut, burned by welding, abraded, or otherwise damaged to such an extent as to expose the base metal. Thoroughly clean the damaged area by wire brushing and remove all traces of welding flux and loose or cracked zinc coating prior to painting. Paint cleaned area with two coats of zinc oxide-zinc dust paint conforming to Mil. Spec.
DOD-P-21035. Compound paint with a suitable vehicle in a ratio of one part zinc oxide to four parts zinc dust by weight.
PART 3 - EXECUTION
3.1 CONSTRUCTION: Provide personal protective equipment for all persons fabricating, field treating, or handling materials treated with water-borne salts.
3.1.1 Cut and frame all lumber and timber so that joints will fit over contact surface.
Secure timbers and piles in alignment. Open joints are unacceptable. Shimming is not allowed on new work.
3.1.2 Temporary Attachments: Temporary braces may be attached to treated timber with nails or spikes only when approved by the Contracting Officer. Upon their removal, the holes shall be filled by driving galvanized nails or spikes flush with the surface.
3.1.3 Bracing: Align piles before bracing is placed. Provide bracing of sufficient length to provide a minimum distance of 8 inches between outside bolt and the end of brace.
Bracing and girts shall bear firmly against piles or timber to which secured. Place fillers to avoid bending the bracing more than one inch out of line when bracing bolts or other fastenings are drawn up tight. Built-up fillers will not be permitted. Make filler a single piece of the same treated lumber as that in the brace, with a width of not less than 6 inches and a length of not less than 12 inches. Bolt end of bracing through pile, with a bolt of not less than the indicated diameter. Bolt or boat spike intermediate intersections as indicated.
3.1.4 Caps: Prior to placing cap, prepare tops of piles according to paragraph entitled “Field Treatment”. Place timber caps to insure bearing over tops of supporting piles and to secure even alignment of their ends. Secure caps by drift bolts as shown. Place drift bolt in the center of the pile.
3.1.5 Stringers: Place crown up and, if possible, the better edge of deck stringers down.
Tops of stringers shall not vary from a plane more than will permit bearing of the floor on all stringers.