Amendment 1 (Corrected Copy) - RFI Answers, Revised SOW, RFI Suspense Date

View the file

Other files for this federal contract opportunity

Other files attached to Construct infrastructure for the fixed base weather observation systems for Bicycle Lake Army Air Field, newest first.
File Type Posted
Amendment_2_-_RFI_Answers,_15_Jun_17.pdf PDF
Amendment_1_-_RFI_Answers.pdf PDF
W9124B-17-B-0001_rel..pdf PDF
W9124B-17-B-0001_rel..pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

0010988894

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

a. Amendment 0001 is issued to provide responses for Question and Answ er.

b. Scope of Work has been revised and is incorporated by this amendment.

c. Closing date for acceptance of bids w ill be extended to 20 June 2017, at 2:00 p.m. PST.

d. The suspense for Requests For Information (RFI) is 9 June 17, at 16:00 p.m. PST. No RFIs w ill be accepted after this timeframe.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 24

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 08-Jun-2017

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9124B-17-B-0001

X 9B. DATED (SEE ITEM 11)

04-May-2017

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

08-Jun-2017

CODE

MICC-FORT IRWIN CONTRACTING COMMAND

PO BOX 105095 ISSUING OFFICE

FORT IRWIN CA 92310-5095

W9124B 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9124B-17-B-0001

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

SITE VISIT SIGN IN SHEET

SUMMARY OF CHANGES

SECTION B - SUPPLIES OR SERVICES AND PRICES

CLIN 0001

The CLIN extended description has changed from:

The contractor shall provide all necessary permits, material, labor, equipment, testing; drawings and/or, technical information in accordance with this scope of work, dated 24 March 2017, to construct for installation of infrastructure for the fixed base weather observation systems (FBWOS).

To:

The contractor shall provide all necessary permits, material, labor, equipment, testing; drawings and/or, technical information in accordance with this scope of work, dated 24 March 2017, revised 2 June 2017, to construct for installation of infrastructure for the fixed base weather observation systems (FBWOS)..

SECTION C - DESCRIPTIONS AND SPECIFICATIONS

The following have been modified:

SCOPE OF WORK

(End of Summary of Changes)

The following items are applicable to this modification:

AMENDMENT 0001

QUESTIONS AND ANSWERS

GENERAL ADDITIONAL NOTES:

1 – CONTRACTOR SHALL NOT SET ANY PULL BOX IN EITHER THE TAXI WAY OR RUNWAYS

1 – SET OF QUESTIONS:

1Q - Trench depths.

1A – TRENCH SHALL BE NO LESS THAN 36” IN DEPTH.

2Q - Overall Site Plan

2A – WILL BE PROVIDE IN THE AMENDMENT

3Q - Copy of layout of the 2 platforms

3A – WILL BE PROVIDE IN THE AMENDMENT

4Q - Update the materials list

4A - WILL BE PROVIDE IN THE AMENDMENT

5Q - What is the length of the fiber optics and excess power

5A – GFM LIST HAS BEEN UPDATE, APPROXIMATELY 11,000 LF

6Q - What is the slope of the ramp

6A – RAMP WILL BE AT 2 TO 12 SLOPE

7Q - Block sealer for Water Proofing needs to be added (unless it is in the connex at BLAAF)

7A – DUE TO DURABILITY THIS SHALL BE SUPPLIED AND INSTALLED BY THE CONTRACTOR.

8Q - Clarify the main power amperage.

8A – CONTRACTOR BE TAPPING INTO THE MAIN 600 AMP 120/208VOLT

2 – SET OF QUESTIONS:

1Q) Please clarify what is Government furnished and what is contractor furnished.

1A) GFM WILL BE UPDATE WILL BE PROVIDE IN THE AMENDMENT

2Q) Are there any know permits required for this project?

2A) THERE IS THE DIG PERMIT AND HOT WORK PERMIT.

3Q) What are the required tests for this project?

3A) COMPACTION OF FINAL LIFT AT 90% TRENCHES; CONTINUITY TESTING OF FIBER LINES; COMPACTION OF

CLASS II ROAD BASE I LIFTS OF 12” WITH A 95% DENSITY RESULT OR BETTER.

4Q) Regarding SOW Item 1.1, what drawings are necessary to be provided by the GC?

4A) SKETCHES OR WORKING DRAWINGS OF THIS PROJECT THAT WILL BE TURNED INTO THE FINAL AS-BUILT

DRAWINGS.

5Q) Regarding SOW Item 1.1, what is the technical data to be provided by the GC? Is this simply referring to required project submittals?

5A) YES

6Q) Regarding SOW Item 1.2, please provide a copy of the installation recommendations and standards.

6A) THESE ITEMS SHALL BE PROVIDED WHEN THE MATERIALS ARE TURNED OVER TO THE CONTRACTOR AFTER

AWARD.

7Q) Will a copy of the USACE EM 385–1–1 be provided for the jobsite?

7A) EM-385-1-1 IS ELECTRONICALLY AVAILABLE ON THE INTERNET http://www.usace.army.mil/Safety-and- Occupational-Health/Safety-and-Health-Requirements-Manual/

8Q) Regarding SOW Item 1.5, and the required 30 day notice on outages. This is difficult to schedule that far in advance and challenges to occur. Is the 30 day notice simply required, but the actual outage can be flexible by a predetermined acceptable period of days in case something unforeseen comes up?

8A) REGARDING POWER OUTAGES AND ROAD CLOSURES THE 30 DAY PROCESS IS PER OUR STANDARD OPERATING PROCEDURE. THE DATES ARE PRETTY FIRM ONCE THE CONTRACTOR ESTABLISH THEM, HOWEVER IF THE START OR END DATE NEEDS TO BE CHANGED THIS IS NOT HARD PROCESS, ONCE THE PLAN IS APPROVED BY

DPW.

9Q) Regarding SOW Item 1.7.1, AT Level I awareness training, is there a cost to the contractor or its subcontractors for this training?

9A) IF YOU HAVE NOT WORKED FOR THE GOVERNMENT IN THE PAST, THIS REQUIREMENT HAS ALWAYS BEEN PART OF THE CONTRACTORS REQUIREMENTS TO COMPLY WITH. THIS COST ON THIS IS HOWEVER THE CONTRACTOR CHARGE FOR REQUIRED TRAINING OF MOST GOVERNMENT CONSTRUCTION PROJECTS.

10Q) Regarding SOW Item 1.8, is the water available on station acceptable for use in the masonry mortar mix? Or is the contractor required to provide suitable water?

10A) THERE IS A FILL STATION ON THE CORNER OF BARSTOW ROAD AND WESTBROOK ROAD.

11Q) Regarding SOW Item 1.9, Utility/Facility drawings are for information only. The contractor must verify the accuracy of the information provided and indicate their findings in the design submittals. Is this project a design build project? If so what design submittals are required?

11A) ANY AND ALL MATERIALS THE CONTRACTOR SUPPLIES FOR THIS CONTRACT.

12Q) Regarding SOW Item 1.10, please provide a location for the closest approved landfill off post.

12A) I AM SORRY I CANNOT PROVIDE THIS INFORMATION, THIS IS THE RESPONSIBILITY OF THE CONTRACTOR TO

FIGURE OUT.

13Q) Please provide a list of the required submittals.

13A) CONTRACTOR SHALL PROVIDE ANY AND ALL ITEMS THAT ARE NOT SUPPLIED BY THE GOVERNMENT.

14Q) Please provide project specifications for this project.

14A) UNIFORMED FACILITY CRITERIA (UFC) ARE LOCATED AT http://www.wbdg.org/FFC/dod/unified-facilities-criteria-ufc

15Q) Regarding Item 1.11.1, Work Schedule (Utilizing Microsoft Projects Version 2003). Can the project be provided using Primavera or Phoenix software which is compatible to MS Project?

15A) YES, AS LONG THE ELECTRONIC VERSION THAT IS PROVIDED BY THE CONTRACTOR IS TRANSFERABLE TO MS

PROJECTS.

16Q) Regarding SOW Item 2.3, please provide a list of the required concrete support pads, sizes and required thicknesses. Also please provide a concrete specification.

16A) AS TO THE CONCRETE PADS REQUIRED THE ARE NOTED ON THE ADDITIONAL DRAWING THAT WILL BE

PROVIDE PER THE AMENDMENT.

17Q) Regarding SOW Item 3.1.1.1 Contractor shall install a retention block wall surrounding the Wind Sock Unit Site at note below on diagram. Note the grayed section on the diagram is the layout of the protection wall. Please provide product data requirements and designed drawing for the retaining wall.

17A) THE REVISED INFORMATION SHALL BE AS FOLLOWS: INSTALLATION OF RETENTION BLOCK WALL SHALL BE FOUR COURSES HEIGHT AT 80’-0” BY 80’-0” CENTERED AROUND THE EXISTING WIND SOCK. CONCRETE SUPPORTS SHALL BE FOR ELECTRICAL SERVICE AND COMMUNICATION SERVICE PANELS. WIND SOCK SHALL BE EXTENDED TO

NEW HEIGHT TO MEET THE NEW FINISHED GRADE LEVEL.

18Q) Regarding SOW Item 3.1.1.4 Contractor shall install a waterproof coating on the exterior and interior of the block wall before backfill material is installed. Please provide specification requirements for the waterproofing coating.

18A) CONTRACTOR SHALL PROVIDE THE MATERIALS AND INSTALLATION OF WATERPROOF MATERIALS WHICH

MEET DRY LOK EXTREME MASONRY OR APPROVED EQUAL.

19Q) Regarding SOW Item 3.1.3 Contractor shall provide a Class 2 dirt ramp from the bed level of the Bicycle Lake or Goldstone Lake to the top of the block wall for future access requirements. Ramp shall be 20’-0” wide sloped down to lake bed, height shall be determine in the field for vehicle access. For purposes of bidding please provide a not to exceed (NTE) height.

19A) RAMP SHALL MEET 2 TO 12 SLOPE AND NOT EXCEED THE HEIGHT OF THE BLOCK WALL.

20Q) Regarding SOW Item 3.3.4 Contractor shall install schedule 80 PVC conduit from Building 6212 to FOB approximately 150’southeast from building 6212. Final location will be noted during site visit. Please provide the final location. Also who is responsible for variances in excess of the 150' as noted in the SOW?

20A) FOB IS LOCATED BEHIND EXISTING BUILDING 6216 WHICH IS NO MORE THAN 150’ IN LENGTH.

21Q) Regarding SOW Item 3.4.1 All remaining items necessary to complete this project shall be the sole responsible of the contractor of this project to furnish, supply, and install. This inclusion is vague and places the burden on the contractor to bear responsibility for unknowns or expectations of the government not clearly stated. Please clarify "all remaining items".

21A) ALL MISCELLANEOUS CONNECTORS, FITTINGS, NUTS, BOLTS, SCREWS, ANCHORS, LUGS, SUPPORTING

DEVICES FOR ELECTRICAL AND COMMUNICATIONS. ETC….

22Q) Regarding SOW 3.4.2.1 Contractor shall be required to verify inventor of government furnished materials per the list above as to quantity. It is unclear who the "inventor" is and what the "list above is referencing. Please clarify.

22A) THE CONTRACTOR AND THE GOVERNMENT SHALL PERFORM A INVENTORY OF SAID GFM’S AS NOTED IN THE

GFM LIST.

23Q) Regarding SOW Item 3.4.2.3 Contractor shall be required to move materials from Miles Warehouse to working site at BLAFF approximately 2 miles. Who is responsible for travel in excess of 2 miles?

23a) THIS HAS CHANGES FROM THE MILES WAREHOUSE TO THE ON SITE LOCATION AS PER THE SITE VISIT.

24Q) Regarding SOW Item 3.4.2.3. Is a forklift available for use? Are the items organized, palletized, or packaged as to facilitate proper loading onto flatbed trucks?

24A) NO, CONTRACTOR HAS TO PROVIDE THEIR OWN MEANS TO MOVING THE MATERIALS FROM THE STORAGES

AREAS TO THE JOB SITE AS NOTED DURING THE SITE VISIT.

25Q) Regarding SOW Item 3.4.2.3. Who is responsible for verifying condition and quantity prior to contractor moving said materials?

25A) A PRE-WALK SHALL BE CONDUCTED AFTER AWARD OF SAID CONTRACT TO DETERMINED THE QUANTITIES

AND IF ANY ITEMS ARE DAMAGED.

26Q) Regarding SOW Item 3.2, are all electrical materials and components Government Furnished Contractor Installed (GFCI)?

26A) LL ITEMS SHALL MEET GROUNDING REQUIREMENTS OF NEC AND IEC.

27Q) Regarding SOW Item 3.1.2 BACKFILL, does the backfilled ramp require compaction tests from 3rd party?

27A) YES, REQUIRED TO MEET OR EXCEED 95% DENSITY TEST.

28Q) Regarding SOW Item 4.0 SUBMITTALS REQUIREMENTS: (Three (3) Electronic set PDF Format, in addition to what is list below– Contractor shall submit utilizing the ENG From 4025-R for Submittals and within 9251963.

What is the reference "9251963"?

28A) THIS IS A TYPO AND HAS BEEN REMOVED.

29Q) Regarding SOW Item 3.4.2.3, Please clarify Item 8. Is this 22,000 pieces of conduit or 22,000 lf. If it is lf, are the pieces 10' or 20' lengths?

29A) YES THE PVC CONDUIT IS LINEAR FEET (LF) AND THEY ARE 20’-0” LENGTHS.

30Q) Regarding SOW Item 3.4.2.3, Please clarify Item 10, is this 0ne spool or multiple? If multiple, how many?

30A) THAT DEPENDS ON THE SUPPLIER, THIS ITEMS HAS NOT BEEN PURCHASED AT THIS TIME. HOWEVER IT WILL

BE AT LEAST MORE THAN ONE.

31Q) Regarding SOW Item 3.4.2.3, Please clarify Items 16 and 17, please provide conduit lengths. Are these 10' or 20' lengths?

31A) YES, THE PVC CONDUIT IS LINEAR FEET (LF) AND THEY ARE 20’-0” LENGTHS.

32Q) Regarding SOW Item 3.4.2.3, Please clarify Item 21, please provide a picture of these utility boxes. We need to determine a method of handling.

32A) THIS WILL BE ADDED TO THE SOW.

33Q) Regarding SOW Item 3.4.2.3, Please clarify Items 23-27, please provide a picture showing current staging and packaging as to determine a method of handling for relocation.

33A) ALL BLOCK MATERIALS AND ASSOCIATES ITEMS ARE PALLETIZED AND ARE READY TO MOVE BY WHAT EVER

MEANS THE CONTRACTOR WANTS TO USE.

34Q) Regarding SOW Item 3.4.2.3, Please clarify Item 28, Is this rebar to be used in both the footing and the masonry wall. If so, are the j-dowels also provided?

36A) THE REBAR AS STATED IN THE SOW IS #4 IN THE FOOTS AND VERTICAL REBAR. THERE ARE NO

REQUIREMENTS FOR DOWELS CALLED OUT IN THIS PROJECT.

35Q) Regarding SOW Item 3.4.2.3, Please clarify Items 35 and 36. Please clarify what this is.

35A) THESE ARE THE PALLET THAT THE MATERIALS WERE DELIVERED ON COST.

36Q) Regarding SOW Item 3.4.2.3, Please clarify Item 37 and 38. Is the contractor expected to load and haul these materials? Who is responsible for amounts in excess of the stated quantities? What method will be used to determine the qtys stated are accurate and not estimated?

36A) FIRST PART THE CONTRACTOR IS RESPONSIBLE TO HAUL FROM THE CURRANT LOCATION AS NOTED DURING THE SITE VISIT TO THE JOB SITE. SECOND PART, EXCESS MATERIALS WILL BE LEFT FOR GOVERNMENT USES IN THE

FUTURE. FINAL PART, THE MATERIAL HAS BEEN VERIFIED PER LOAD TICKETS.

37Q) Regarding SOW Item 3.4.2.3, Please clarify Item 37, is this product to be used for the SOW requirement 3.1?

37A) YES

38Q) Please confirm that all as-builts are to be submitted in an AutoCAD version.

38A) AUTOCAD VERSION 2006 OR NEWER.

39Q) Regarding SOW Item 4.8 Final As-Built Drawings – Contractor shall be required to submit a full set of As-Built Drawings to include, but not limited to, the following (if applicable): Site Plan, Landscape Drawings; Architectural Drawings, Civil Drawings; Structural Drawings; Special Equipment Drawing; Mechanical Drawings and Electrical Drawings (Five(5) hardcopy sets and electronic submittal using AutoCAD compatible, version 2006). CONTRACTOR NOTE: all underground utilities will be noted on all as-built drawings. Where no drawings have been provided, what is the expectation of the contractor? Is the contractor to produce these drawings? Is this a Design Build project?

39A) THE CONTRACTOR IS REQUIRED IN PROVIDING QAS-BUILT DRAWING FOR THIS PROJECT. THIS IS NOT A DESIGN BUILD CONTRACT. AS NOTED ABOVE THE CONTRACTOR MAY DEVELOP SKETCHES AND WORKING

DRAWINGS WHICH CAN BE TURNED INTO FINAL AS-BUILT DRAWINGS.

40Q) Follow up question to question 39), regarding SOW Item 5.0 PERIOD of PERFORMANCE: SHALL BE COMPLETED WITHIN 120 CALENDAR FROM AWARD OF CONTRACT. If the contractor is to produce project drawings will the performance period be adjusted accordingly?

40A) UNLESS THE CONTRACTOR CAN PROVIDE INFORMATION WHY THEY NEED MORE THAN 120 CONSTRUCTION

CALENDAR DAYS – THIS PROJECT IS DEVELOPED AND SCOPED 120 CALENDAR DAYS.

41Q) Regarding page 11 of 70, was this page intentionally left blank or is data unintentionally been left out?

41A) Due to computer system glitch, page 11 was system added, there was no data lost, only an unnecessary page.

42Q) Regarding SOW Item 3.4 GOVERNMENT FURNISHED MATERIALS Items 23-27. Are these materials to be used for the SOW Item 3.1?

42A) YES

43Q) Are any special inspections required to be provided by the contractor? Do these have to be a 3rd party testing and inspection company?

43A) NO SPECIAL INSPECTIONS REQUIRED.

44Q) Please confirm that all materials provided by the government meet the "52.225-9 BUY AMERICAN— CONSTRUCTION MATERIALS (MAY 2014)" stated in the solicitation. We want to ensure the contractor will NOT be held responsible for products not compliant that are NOT provided by the contractor. If the products are not confirmed compliant who is responsible for documenting or procuring compliant materials to satisfy the SOW or contract?

44A) CONTRACTOR SHALL NOT BE HELD RESPONSIBLE FOR GFM IN SUPPLY METHODS.

45Q) Please clarify the required documents for proposal submission. We note the requirements stated in Section L - Instructions, Conditions and Notices to Bidders. Is this list complete?

45A) As stated, in Section L. Bidders are to provide: 1) Completed 1442 and acknowledgement of all amendments. 2) Completed SF 24 – Bid Bond 3) Any additional verification documents “Representations and Certifications”, Schedule B.; etc.

46Q) Is the Solicitation section 52.219-1 SMALL BUSINESS PROGRAM REPRESENTATIONS (OCT 2014) - ALTERNATE I (SEPT 2015), required to be filled out and submitted along with the SF1442?

46A) Yes, This is part of the Representation and Certifications.

47Q) Is the entire solicitation to be returned with the proposal submission?

47A) No

48Q) Please provide a blank copy of the SF24.

48A) The SF24 – Bid Bond is provided by the bonding company; or you can find it at www.gsa.gov.

49Q) Is an email proposal submission acceptable. The reason to ask is electrical subcontractor oft times do not provide their pricing until the hour prior to bid closing.

49A) No. Bids are to be hand delivered or mailed. Bids must arrive prior the bid opening date and time specified in the solicitation.

50Q) Is there an acceptable means and method to revising a proposal prior to bid closing?

50A) Bids must arrive prior the bid opening date and time specified in the solicitation.

3 – SET OF QUESTIONS:

1Q - On the Bid Form supplied for Item 8-it says to provide 22,000 each of 2” conduit. Should that be 22,000 LF?

1A – YES IT IS LINEAR FEET (LF)

2Q - What is the length of trench excavation on this project?

2A – APPROXIMATELY 11,150 LF

4 – SET OF QUESTIONS:

1Q - At the job walk it was mentioned that waterproofing will be required on the masonry. I think that that description will need to be placed on the Bid Form Items. Thanks

1A - All prices bid in response to this solicitation must include all costs associated with this project, and applicable state sales tax, permits and licenses.

All work to be performed in accordance with the statement of work, dated 24 March 2017, Revised 02 June 2017.

5 – SET OF QUESTIONS:

Q1. What is the depth of the underground conduit?

A1. MINIMUM OF 36"

Q2. Is metallic warning tape required in the trenches?

A2. YES, PROVIDE BY THE GOVERNMENT

Q3. Who is providing the fiber optic cable?

A3. GOVERNMENT

Q4. Can we stub up to the panels with PVC?

A4. NO, RIGID STEEL IS BEING PROVIDED BY GOVERNMENT.

Q5. Do you have site plans with dimensions?

A5. PROVIDED WITH AMENDMENT.

Q6. Is there any grounding required inside the raised block areas?

A6. YES, PER NEC AND IEC.

Q7. Can you provide photos of existing platforms.

A7. PROVIDED WITH AMENDMENT.

Q8. Is client providing waterproofing material for the wall?

A8. CONTRACTOR IS PROVIDING.

Q9. Will there be fiber optic test required provide specification.

A9. CONTINUITY TESTING.

Q10. Do you have a preliminary testing schedule for the client shut downs?

A10. THE ONLY TESTING , CONTINUITY, AND COMPACTION.

Q11. Please clarify if contractor is responsible for relocating the CPS?

A12. NO

Q12. The diagram of page 9 of the RFP shows a door. Is customer providing door?

A12. NO DIAGRAM IS FOR LOCATION ONLY INFORMATION.

Q13. Provide detail for the CMU walls.

A13. NO DIAGRAM STANDARD BLOCK INSTALLATION INFORMATION IN WRITE UP OF SOW.

Q14. What happens if the material on-site for civil work is not sufficient. Does the Government or contractor buy the additional materials?

A14. THE GOVERNMENT HAS PURCHASED MORE THAN THE REQUIRED ESTIMATED AMOUNTS.