QUESTION_ANSWER.pdf
PDF 81 KB Posted
- Attached to
- Packing and Crating Local moves
- Solicitation number
- W91248-17-R-0005
About this file
QUESTIONS AND ANSWERS
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W91248-17-R-0005-0003.pdf | ||
| W91248-17-R-0005-0002.pdf | ||
| W91248-17-R-0005-0002_Conform.pdf | ||
| W91248-17-R-0005-0001.pdf | ||
| W91248-17-R-0005.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question 1: Is first year to be pro‐rated for 10 months?
Answer 1: No
Question 2: Is Section B – Supplies or Services and Prices to be considered a summary of each area bid?
Answer 2: Yes
Question 3: Does original contract come to your office or to Brenda Francis (as listed in Form 1499 Block 15)?
Answer 3: Address provided below.
Mission Installation Contracting Command ‐ Fort Campbell ATTN: Tawanna Davis Bldg 6923, 38th & Desert Storm Fort Campbell, Kentucky 42223
Question 4: Is amount on Form 1499, block 24 total for 3 years?
Answer 4: 36 months Base year‐12 months Option Year 1‐ 12 months Option Year 2‐12 months
Question 5: on pages 3, 7, and 10 the line item for bid for supplies and services does not exist. There is not a particular part of the contract to give a price for here. There should be KY to KY, TN to TN, TN/ KY or KY/ TN and Manpower reporting costs. It is listed as 0001. on page 3/ 1001 on page 7 and 2001 on page 10.
Answer 5: Provide cost on which area you will be bidding. Contractor Manpower Reporting may be a priced item.
Question 6: Also on page 61 the dates are incorrect they should now read 1 March 2017 to December 31 2017 Answer 6: Dates amended and updated.
Question 7: Also this has always been a sealed bid in the past. On line H in the instructions it requires you to send a digital copy. How can it be a sealed bid if the only copies aren't the ones in the sealed envelopes?
Answer 7: This requirement is NOT being procured through sealed bidding.
Question 8: Also on the bid schedule that was amended there are no pages for option years 1 or 2 on all three CLIN’s with quantities to bid on. They can be different prices and there could be different estimated annual quantities.
Answer 8: Bid schedule updated.
Question 9: W91248‐17‐R‐0005‐0002_Conform.pdf < Caution‐ https://www.fbo.gov/utils/view?id=db3d150636bf6ce3928350c0c0e521dc > W91248‐17‐R‐0005 (Conform with Amendment 0002) Answer 9: The documents are the same. The W91248‐17‐R‐0005‐0002_Conform is the actual solicitation with the changes incorporated. W91248‐17‐R‐0005‐0002 is just stating only the items that were amended in the solicitation.
Question 10: What does redacted mean?
Answer 10: A proposal that does not include your companies name or symbols.