Attachment_1_Solictation.pdf
PDF 690 KB Posted
- Attached to
- James River Streambank Stabilization Project (JRSSP) Federal contract opportunity
- Solicitation number
- W91236-18-B-0003
About this file
Solicitation
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| BRRO-18-082_Combined_Stormwater_Management_and_Erosion_Sediment_Plan.pdf | ||
| Attachment_9_CORRECTED_Wingina_Nutrient_Bank_Sales_Quote_Letter_7.6.18.pdf | ||
| Attachment_8_References_PS_Amendment_1.pdf | ||
| Attachment_3_Bid_Schedule.pdf | ||
| Attachment_5_Wingina_Nutrient_Bank_Sales_Quote_Letter_7.6.18.pdf | ||
| Attachment_4_Wingina_Nutrient_Bank_Credit_Availability_Letter__7.6.18.pdf | ||
| Attachment_1_Solicitation_Amendment_0001.pdf | ||
| Attachment_6_Q&A.pdf | ||
| Attachment_2_Plan.pdf | ||
| Attachment_7_JRSSP_Site_Visit_Participant_List.pdf | ||
| Attachment_2b_Specifications.pdf | ||
| Attachment_3_Bid_Schedule.pdf | ||
| Attachment_2a_Final_Drawings.pdf | ||
| Attachment_2a_Final_Drawings.pdf | ||
| Attachment_2b_Specifications.pdf | ||
| Attachment_1_Solictation.pdf | ||
| Attachment_3_Bid_Schedule.pdf |
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W91236-18-B-0003 James River Streambank Stabilization Project (JRSSP) located in Amherst County, Virginia.
Period of Performance: 240 Calendar Days after Notice to Proceed
NAICS Code: 237990
Small Business Size Standard: $36,500,000.00
Magnitude of Construction: Betw een $1,000,000.00 and $5,000,000.00
This solicitation contains a Definitive Responsibility Criteria. Please see section 00 21 00
This acquisition is an unrestricted procurement using FAR Part 14
Contracting POC: Jerry W. Clark-Juneau. (757) 201.7643 Jerry.W.Clark-Juneau@usace.army.mil
X
JERRY W CLARK-JUNEAU 757-201-7643
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
19-Jun-2018
(RFP)
(IFB)
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________240 calendar days after receiving aw ard, X notice to proceed. This performance period is mandatory, negotiable. (See _________________________
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and ____1______ copies to perform the w ork required are due at the place specified in Item 8 by 12:00 PM__ local time ______________19 Jul 2018 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
USA ENGINEER DISTRICT, NORFOLK
803 FRONT STREET
NORFOLK VA 23510-1096
W91236
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
(hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
757-201-7183FAX:TEL: TEL: FAX:
W9123618B0003 32
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued)
(Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
W9123618B0003
Section 00 01 10 - Table of Contents
Exhibit/Attachment Table of Contents
DOCUMENT TYPE DESCRIPTION PAGES DATE
Attachment 2 Specifications 14-JUN-2018
Attachment 3 Drawings 14-JUN-2018
Attachment 4 Bid Schedule 14-JUN-2018
Section 00 10 00 - Solicitation
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job Mobilization and Demobilization
FFP
FOB: Destination
NET AMT
0002 1 Job Mussel survey and mussel relocation
0003 1 Job All Sitework
0004 1 Job Marine Filter Mattress
FFP
IAW the Specifications, the contractor shall provide all necessary materials, equipment, supplies and labor to complete the requirements of this task.
0005 1 Job Gabion Stone
FFP
Contractor shall be responsible for all tasks associated with placing 3,638 Tons of
Gabion stone fill material IAW the attached Specifications.
0006 1 Job VDOT Class II Armor Stone
FFP
Contractor shall be responsible for all tasks associated with placing 7,154 Tons of
VDOT Class II Armor Stone material IAW the attached Specifications.
0007 1 Job VDOT #21A Stone for construction road
FFP
Contractor shall be responsible for all tasks associated with placing 1,350 Tons
VDOT #21A Stone for construction road IAW the attached Specifications.
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 POP 16-AUG-2018 TO
13-APR-2019
N/A OPERATIONS BRANCH
KEITH LOCKWOOD
US ARMY ENGR DIST NORFOLK ATTN:
803 FRONT STREET
NORFOLK VA 23510
(757) 201-7127
W91236
0002 POP 16-AUG-2018 TO
N/A (SAME AS PREVIOUS LOCATION)
0003 POP 16-AUG-2018 TO
N/A (SAME AS PREVIOUS LOCATION)
0004 POP 16-AUG-2018 TO
N/A (SAME AS PREVIOUS LOCATION)
0005 POP 16-AUG-2018 TO
N/A (SAME AS PREVIOUS LOCATION)
0006 POP 16-AUG-2018 TO
N/A (SAME AS PREVIOUS LOCATION)
0007 POP 16-AUG-2018 TO
N/A (SAME AS PREVIOUS LOCATION)
Section 00 21 00 - Instructions
DRC INSTRUCTIONS
Section 00 21 00 - Instructions, Conditions & Notices to Offers
1. BIDDER QUESTIONS AND COMMENTS
All questions and/or comments should reach the above referenced Contracting Office via ProjNet no later than 2 July 2018, in order that they may be given consideration or actions taken prior to receipt of offers.
Technical inquiries and questions relating to proposal procedures or bonds are to be submitted via Bidder Inquiry in ProjNet at http://www.projnet.org/projnet. To submit and review bid inquiry items, bidders will need to be a current registered user or self-register into system. To self-register go to web page, click BID tab select Bidder Inquiry, select agency USACE, enter
Key for this solicitation listed below, and your email address, click login. Fill in all required information and click create user. Verify that information on next screen is correct and click continue. From this page you may view all bidder inquiries or add inquiry. Bidders will receive an acknowledgement of their question via email, followed by an answer to their question after it has been processed by our technical team.
The Solicitation Number is: W91236-18-B-0003
The Bidder Inquiry Key is: FX2YZ8-IW23A7
The Bidder Inquiry System will be unavailable for new inquires 10 days prior to bid opening in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary. Offerors are requested to review the specification in its entirety, review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry. The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.
2. RESPONSIBILITY DETERMINATION WITH DEFINITIVE RESPONSIBILITY
CRITERIA
The effort will be solicited and awarded utilizing the Sealed Bid procedures under FAR Part 14 with Definitive Responsibility Criteria. These criteria are specific and objective standards established by an agency as a pre- condition to award, designed to measure a prospective contractor's ability to perform the contract. In order to be found responsible, the apparent low bidder must demonstrate their past experience in all defined work criteria.
1) Revetment Work. Project experience comparable and consistent with the scope of work described in the drawings and specification sections contained in Division 35 - Waterway and
Marine Construction, included as part of this Solicitation.
2) Earthwork. Project experience comparable and consistent with the scope of work described in the drawings and specification sections contained in Division 31 - Earthwork, included as part of this Solicitation.
3) Mussel Relocation Requirements. The name of the approved Mussel Survey Contractor planned to be hired in support of fulfilling the requirements described in specification section 01
56 00 - Mussel Relocation Requirements, included as part of this Solicitation.
In addition to the examining criteria detailed in FAR 9.104-1 - Contractor Qualifications:
General Standards, the Contracting Officer will also examine whether the low bidder can meet the requirements of the Definitive Responsibility Criteria. In order to be found responsible, the apparent low bidder must provide documentation in the form of a written narrative, not to exceed three (3) pages for each definitive responsibility criteria listed. The documentation must demonstrate successful completion of one (1) year project experience for each of the definitive responsibility criteria listed. Project experience demonstrating successful completion of the defined work criteria must have occurred within the past five (5) years.
Bidders can use one or more projects per defined work criteria, to demonstrate past experience.
Each defined work criteria must be addressed. If a subcontractor is used to complete a work component associated with the definitive responsibility criteria, that subcontractor must demonstrate their past experience associated with the listed defined work criteria.
The Contracting Officer will verify that the submitted project experience meets the definitive responsibility criteria as part of the responsibility determination. Bidders are not required to submit additional documentation related to these defined work criteria at the time of bid. The
Government will request supporting documentation from the bidder anticipated to receive the award.
Should the apparent low bidder fail to submit sufficient documentation in accordance with the pertinent responsibility criteria, the Contracting Officer is authorized to make an affirmative responsibility determination, and the apparent low bidder may be determined ineligible for award.
3. RESPONSIVENESS OF BIDS (FAR 14.301)
a. To be considered for award, a bid must comply in all material respects with the invitation for bids. Such compliance enables bidders to stand on an equal footing and maintain the integrity of the sealed bidding system.
b. Facsimile and emailed bids shall not be considered unless permitted by the solicitation.
c. c. Bids should be filled out, executed, and submitted in accordance with the instructions in the invitation.
If a bidder uses its own bid form or a letter to submit a bid, the bid may be considered only if --
i. The bidder accepts all the terms and conditions of the invitation; and
ii. Award on the bid would result in a binding contract with terms and conditions that do not vary from the terms and conditions of the invitation
4. BID EVALUATION AND AWARD EVALUATIONS
a. The Government will evaluate bids in response to this solicitation without discussions and will award a contract to the responsible bidder whose bid, conforming to the solicitation, will be most advantageous to the Government considering only price and the price-related factors specified elsewhere in the solicitation. Price will be evaluated based upon the total evaluated price in accordance with FAR 52.217-5.
b. b. The Government may –
i. Reject any or all bids;
ii. Accept other than the lowest bid; and
iii. Waive informalities or minor irregularities in bids received.
5. INSPECTION OF THE SITE
Prospective bidders are invited to visit the site of the work in order to acquaint themselves as to site conditions and other problems incident to the prosecution of the work. Arrangements for inspection of the site shall be made through the Office the Area Engineer identified in the clause
52.236-27, entitled "SITE VISIT (CONSTRUCTION)."
6. RESTRICTIONS
The work is to be performed at James River Streambank Stabilization Project (JRSSP), Amherst
County which is a secure Government site managed by USACE. The Contractor shall perform the scheduled dike earthwork construction and all other associated work in accordance with all requirements as indicated and as specified herein. The Contractor is advised that any deviations from the construction methods and procedures indicated and as specified herein that are not prior-approved in writing by the Contracting Officer shall be cause for the Contracting Officer issuing a stop work order. Any stop work orders issued for such cause will not be subject to time extensions or cost recovery by the Contractor. Any non-compliance with or violation of the laws or regulations governing the work operations for the project may result in criminal and civil penalties against the Contractor.
a. Security and Public Safety of Work Areas Access to this Government site is limited and must be approved by USACE. The site's main entrance gate is located at the USACE office at the south-west corner of the site. A separate contractor's gate provides controlled access to the contractor's laydown area and work site. The Contractor shall be solely responsible for the protection of their workers and other contractors and USACE personnel at the site at all times for the duration of the contract and fully comply with the provisions of OSHA safe working practices and the Safety and Accident Prevention requirements of these specifications.
1. Protection of Government Property
The contractor shall keep their premises, work areas, and transit roads in good order and in a clean, safe condition by and at their expense. The contractor shall be responsible for any damage that may be caused by the contractor's activities and shall exercise due diligence in the protection of all property located at the site against fire or damage from any or all other causes. Contractor damages shall be promptly repaired or replaced at their expense to a condition satisfactory to USACE.
2. Coordination with Other Contractors
During the period of this contract, other contracts and USACE personnel may be in force for the construction of other features of work on or adjacent to the site of work being accomplished under this contract. The Contractor shall arrange his plant, and shall schedule and perform this work, so as to effectively cooperate with all other contractors and Government agencies. It shall be the responsibility of the Contractor on this contract to be fully informed of the extent of the limits of work to be performed by other contractors and USACE workers. Should there be any conflict between these limits, the Contractor shall immediately notify the Contracting Officer of the conflict, and the Contracting Officer's decision shall be final.
7. EVIDENCE OF AUTHORITY TO SIGN OFFER
Evidence of the authority of individuals signing offers to submit firm offers on behalf of the offeror is required except where the offer is signed, and shows that it is so signed, by: the
President, Vice-President, or Secretary of an incorporated offeror; a partner in the case of a partnership; or the owner in the case of a sole proprietorship. Failure to submit with the offer satisfactory evidence of the authority of all other persons may be cause for rejection of the offer as invalid or nonresponsive.
8. PREAWARD SAFETY CONFERENCE
a. Where an apparent low bidder, in performance of contracts during the previous three-year period, incurred one or more accidents, or where, in the opinion of the Contracting
Officer, there is any question regarding this compliance with any safety or accident prevention requirement, such bidder, on request of the Contracting Officer prior to any award under this solicitation, shall attend a conference with representatives of the
Contracting Officer to discuss any such accidents or non-compliance, the reason for their occurrence, and measures which will be taken to preclude any recurrence thereof.
b. Information elicited at this conference will be used by the Contracting Officer, in conjunction with other information obtained in a preaward survey, in determining the bidder's responsibility.
c. The items discussed, the preventive measures considered, and any conclusions reached in this conference shall be recorded in minutes of the meeting, which shall be authenticated by the signatures of representatives of the bidder and the Contracting
Officer, and any procedures noted therein as agreed upon shall become an obligation of the bidder, along with all other safety and accident prevention requirements of the contract, if award is made to him.
9. INCURRING COSTS
The Government is not liable for any costs incurred by the offeror submitting an offer in response to this solicitation.
10. AGENTS
Offers signed by an Agent must be made in the name of the Principal and must be accompanied by evidence of said Agent’s authority to act on behalf of its Principal.
11. UNBALANCED BIDS
Any offer which is materially unbalanced as to prices for the Base Items and the Optional Items may be rejected as non-responsive or otherwise not considered for award. An unbalanced offer is one which is based on prices significantly less than cost for some work and prices which are significantly overstated for other work.
12. UNAUTHORIZED INSTRUCTIONS FROMGOVERNMENTOR OTHER PERSONNEL
The contractor shall not accept instructions issued by any person, employed by the U.S.
Government or otherwise, other than the Contracting Officer or the Authorized Representative of the Contracting Officer acting within the Designation of Authority letter. A copy of the
Designation of Authority letter will be furnished to the contractor at time of contract award.
13. ANTITERRORISM/OPERATIONS SECURITY (AT OpSec) REQUIREMENTS
a. All contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or
Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes.
b. "The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 5 calendar days after the completion of the training.
c. The Contractor must pre-screen Candidates using the E-verify Program
(http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award.
http://www.uscis.gov/e-verify
Section 00 45 00 - Representations and Certifications
REPRESENTATION & CERTIFICATION
CLAUSES INCORPORATED BY REFERENCE
52.204-8 Annual Representation and Certifications JAN 2018
52.209-7 Information Regarding Responsibility Matters JUL 2013
52.222-56 Certification Regarding Trafficking in Persons MAR 2015
Compliance Plan.
252.247-7022 Representation Of Extent Of Transportation Of AUG 1992
Supplies By Sea
Section 00 70 00 - Conditions of the Contract
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 N/A N/A N/A Government
0002 N/A N/A N/A Government
0003 N/A N/A N/A Government
0004 N/A N/A N/A Government
0005 N/A N/A N/A Government
0006 N/A N/A N/A Government
0007 N/A N/A N/A Government
Section 00 72 00 - General Conditions
CLAUSES INCORPORATED BY REFERENCE
52.202-1 Definitions NOV 2013
52.203-3 Gratuities APR 1984
52.203-5 Covenant Against Contingent Fees MAY 2014
52.203-6 Restrictions On Subcontractor Sales To The Government SEP 2006
52.203-7 Anti-Kickback Procedures MAY 2014
52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or
Improper Activity
MAY 2014
52.203-10 Price Or Fee Adjustment For Illegal Or Improper Activity MAY 2014
52.203-12 Limitation On Payments To Influence Certain Federal
Transactions
OCT 2010
52.204-2 Security Requirements AUG 1996
52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber
Content Paper
MAY 2011
52.204-7 System for Award Management OCT 2016
52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011
52.204-10 Reporting Executive Compensation and First-Tier
Subcontract Awards
OCT 2016
52.204-13 System for Award Management Maintenance OCT 2016
52.204-16 Commercial and Government Entity Code Reporting JUL 2016
52.204-18 Commercial and Government Entity Code Maintenance JUL 2016
52.204-19 Incorporation by Reference of Representations and
Certifications.
DEC 2014
52.209-6 Protecting the Government's Interest When Subcontracting
With Contractors Debarred, Suspended, or Proposed for
Debarment
OCT 2015
52.209-7 Information Regarding Responsibility Matters JUL 2013
52.209-9 Updates of Publicly Available Information Regarding
Responsibility Matters
JUL 2013
52.209-10 Prohibition on Contracting With Inverted Domestic
Corporations
NOV 2015
52.214-3 Amendments To Invitations For Bids DEC 2016
52.214-4 False Statements In Bids APR 1984
52.214-6 Explanation To Prospective Bidders APR 1984
52.214-7 Late Submissions, Modifications, and Withdrawals of Bids NOV 1999
52.214-18 Preparation of Bids-Construction APR 1984
52.214-19 Contract Award-Sealed Bidding-Construction AUG 1996
52.214-26 Audit and Records--Sealed Bidding OCT 2010
52.214-27 Price Reduction for Defective Certified Cost or Pricing Data -
Modifications - Sealed Bidding
AUG 2011
52.214-28 Subcontracting Certified Cost Or Pricing Data--
Modifications--Sealed Bidding
OCT 2010
52.214-34 Submission Of Offers In The English Language APR 1991
52.214-35 Submission Of Offers In U.S. Currency APR 1991
52.219-6 Notice Of Total Small Business Set-Aside NOV 2011
52.219-14 Limitations On Subcontracting JAN 2017
52.219-28 Post-Award Small Business Program Rerepresentation JUL 2013
52.222-3 Convict Labor JUN 2003
52.222-4 Contract Work Hours and Safety Standards- Overtime
Compensation
MAY 2014
52.222-5 Construction Wage Rate Requirements--Secondary Site of the
Work
MAY 2014
52.222-6 Construction Wage Rate Requirements MAY 2014
52.222-7 Withholding of Funds MAY 2014
52.222-8 Payrolls and Basic Records MAY 2014
52.222-9 Apprentices and Trainees JUL 2005
52.222-10 Compliance with Copeland Act Requirements FEB 1988
52.222-11 Subcontracts (Labor Standards) MAY 2014
52.222-12 Contract Termination-Debarment MAY 2014
52.222-13 Compliance With Construction Wage Rate Requirements and
Related Regulations
MAY 2014
52.222-14 Disputes Concerning Labor Standards FEB 1988
52.222-15 Certification of Eligibility MAY 2014
52.222-21 Prohibition Of Segregated Facilities APR 2015
52.222-26 Equal Opportunity SEP 2016
52.222-27 Affirmative Action Compliance Requirements for
Construction
APR 2015
52.222-30 Construction Wage Rate Requirements--Price Adjustment
(None or Separately Specified Method)
MAY 2014
52.222-35 Equal Opportunity for Veterans OCT 2015
52.222-36 Equal Opportunity for Workers with Disabilities JUL 2014
52.222-37 Employment Reports on Veterans FEB 2016
52.222-40 Notification of Employee Rights Under the National Labor
Relations Act
DEC 2010
52.222-50 Combating Trafficking in Persons MAR 2015
52.222-54 Employment Eligibility Verification OCT 2015
52.222-55 Minimum Wages Under Executive Order 13658 DEC 2015
52.222-62 Paid Sick Leave Under Executive Order 13706 JAN 2017
52.223-3 Hazardous Material Identification And Material Safety Data JAN 1997
52.223-6 Drug-Free Workplace MAY 2001
52.223-18 Encouraging Contractor Policies To Ban Text Messaging
While Driving
AUG 2011
52.225-12 Notice of Buy American Requirement - Construction
Materials Under Trade Agreements
MAY 2014
52.225-13 Restrictions on Certain Foreign Purchases JUN 2008
52.227-1 Authorization and Consent DEC 2007
52.227-2 Notice And Assistance Regarding Patent And Copyright
Infringement
DEC 2007
52.227-4 Patent Indemnity-Construction Contracts DEC 2007
52.228-2 Additional Bond Security OCT 1997
52.228-11 Pledges Of Assets JAN 2012
52.228-12 Prospective Subcontractor Requests for Bonds MAY 2014
52.228-13 Alternative Payment Protections JUL 2000
52.228-14 Irrevocable Letter of Credit NOV 2014
52.228-15 Performance and Payment Bonds--Construction OCT 2010
52.229-3 Federal, State And Local Taxes FEB 2013
52.232-5 Payments under Fixed-Price Construction Contracts MAY 2014
52.232-17 Interest MAY 2014
52.232-23 Assignment Of Claims MAY 2014
52.232-27 Prompt Payment for Construction Contracts JAN 2017
52.232-33 Payment by Electronic Funds Transfer--System for Award
Management
JUL 2013
52.232-39 Unenforceability of Unauthorized Obligations JUN 2013
52.232-40 Providing Accelerated Payments to Small Business
Subcontractors
DEC 2013
52.233-1 Disputes MAY 2014
52.233-3 Protest After Award AUG 1996
52.233-4 Applicable Law for Breach of Contract Claim OCT 2004
52.236-2 Differing Site Conditions APR 1984
52.236-3 Site Investigation and Conditions Affecting the Work APR 1984
52.236-6 Superintendence by the Contractor APR 1984
52.236-7 Permits and Responsibilities NOV 1991
52.236-8 Other Contracts APR 1984
52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
APR 1984
52.236-10 Operations and Storage Areas APR 1984
52.236-11 Use and Possession Prior to Completion APR 1984
52.236-12 Cleaning Up APR 1984
52.236-13 Alt I Accident Prevention (Nov 1991) - Alternate I NOV 1991
52.236-14 Availability and Use of Utility Services APR 1984
52.236-15 Schedules for Construction Contracts APR 1984
52.236-16 Quantity Surveys APR 1984
52.236-17 Layout of Work APR 1984
52.236-21 Specifications and Drawings for Construction FEB 1997
52.236-26 Preconstruction Conference FEB 1995
52.242-13 Bankruptcy JUL 1995
52.242-14 Suspension of Work APR 1984
52.243-4 Changes JUN 2007
52.243-5 Changes and Changed Conditions APR 1984
52.245-9 Use And Charges APR 2012
52.246-12 Inspection of Construction AUG 1996
52.246-21 Warranty of Construction MAR 1994
52.248-3 Value Engineering-Construction OCT 2015
52.249-2 Alt I Termination for Convenience of the Government (Fixed-
Price) (Apr 2012) - Alternate I
SEP 1996
52.249-10 Default (Fixed-Price Construction) APR 1984
252.203-7001 Prohibition On Persons Convicted of Fraud or Other Defense-
Contract-Related Felonies
DEC 2008
252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013
252.206-7000 Domestic Source Restriction DEC 1991
252.215-7000 Pricing Adjustments DEC 2012
252.223-7001 Hazard Warning Labels DEC 1991
252.223-7004 Drug Free Work Force SEP 1988
252.223-7006 Prohibition On Storage, Treatment, and Disposal of Toxic or
Hazardous Materials
SEP 2014
252.227-7033 Rights in Shop Drawings APR 1966
252.231-7000 Supplemental Cost Principles DEC 1991
252.236-7000 Modification Proposals-Price Breakdown DEC 1991
252.236-7002 Obstruction of Navigable Waterways DEC 1991
252.236-7008 Contract Prices-Bidding Schedules DEC 1991
252.243-7001 Pricing Of Contract Modifications DEC 1991
252.243-7002 Requests for Equitable Adjustment DEC 2012
252.247-7023 Transportation of Supplies by Sea APR 2014
252.247-7024 Notification Of Transportation Of Supplies By Sea MAR 2000
CLAUSES INCORPORATED BY FULL TEXT
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 240 Calendar Days from Notice to Proceed * The time stated for completion shall include final cleanup of the premises.
*The Contracting Officer shall specify either a number of days after the date the contractor receives the notice to proceed, or a calendar date.
(End of clause)
52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $870.00 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
52.211-18 VARIATION IN ESTIMATED QUANTITY (APR 1984)
If the quantity of a unit-priced item in this contract is an estimated quantity and the actual quantity of the unit-priced item varies more than 15 percent above or below the estimated quantity, an equitable adjustment in the contract price shall be made upon demand of either party. The equitable adjustment shall be based upon any increase or decrease in costs due solely to the variation above 115 percent or below 85 percent of the estimated quantity. If the quantity variation is such as to cause an increase in the time necessary for completion, the Contractor may request, in writing, an extension of time, to be received by the Contracting Officer within 10 days from the beginning of the delay, or within such further period as may be granted by the Contracting Officer before the date of final settlement of the contract. Upon the receipt of a written request for an extension, the Contracting Officer shall ascertain the facts and make an adjustment for extending the completion date as, in the judgement of the Contracting Officer, is justified.
52.214-5 SUBMISSION OF BIDS (DEC 2016)
(a) Bids and bid modifications shall be submitted in sealed envelopes or packages (unless submitted by electronic means) (1) addressed to the office specified in the solicitation, and (2) showing the time and date specified for receipt, the solicitation number, and the name and address of the bidder.
(b) Bidders using commercial carrier services shall ensure that the bid is addressed and marked on the outermost envelope or wrapper as prescribed in subparagraphs (a)(1) and (2) of this provision when delivered to the office specified in the solicitation.
(c) Facsimile bids, modifications, or withdrawals, will not be considered unless authorized by the solicitation.
(d) Bids submitted by electronic commerce shall be considered only if the electronic commerce method was specifically stipulated or permitted by the solicitation.
(End of provision)
52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a FIRM FIXED PRICE contract resulting from this solicitation.
52.219-8 UTILIZATION OF SMALL BUSINESS CONCERNS (NOV 2016)
(a) Definitions. As used in this contract--
HUBZone small business concern means a small business concern, certified by the Small Business Administration, that appears on the List of Qualified HUBZone Small Business Concerns maintained by the Small Business
Administration.
Service-disabled veteran-owned small business concern--
(1) Means a small business concern--
(i) Not less than 51 percent of which is owned by one or more service-disabled veterans or, in the case of any publicly owned business, not less than 51 percent of the stock of which is owned by one or more service-disabled veterans; and
(ii) The management and daily business operations of which are controlled by one or more service-disabled veterans or, in the case of a service-disabled veteran with permanent and severe disability, the spouse or permanent caregiver of such veteran.
(2) Service-disabled veteran means a veteran, as defined in 38 U.S.C. 101(2), with a disability that is service-connected, as defined in 38 U.S.C. 101(16).
Small business concern means a small business as defined pursuant to Section 3 of the Small Business Act and relevant regulations promulgated pursuant thereto.
Small disadvantaged business concern, consistent with 13 CFR 124.1002, means a small business concern under the size standard applicable to the acquisition, that--
(1) Is at least 51 percent unconditionally and directly owned (as defined at 13 CFR 124.105) by--
(i) One or more socially disadvantaged (as defined at 13 CFR 124.103) and economically disadvantaged (as defined at 13 CFR 124.104) individuals who are citizens of the United States; and
(ii) Each individual claiming economic disadvantage has a net worth not exceeding $750,000 after taking into account the applicable exclusions set forth at 13 CFR 124.104(c)(2); and
(2) The management and daily business operations of which are controlled (as defined at 13.CFR 124.106) by individuals, who meet the criteria in paragraphs (1)(i) and (ii) of this definition.
Veteran-owned small business concern means a small business concern--
(1) Not less than 51 percent of which is owned by one or more veterans (as defined at 38 U.S.C. 101(2)) or, in the case of any publicly owned business, not less than 51 percent of the stock of which is owned by one or more veterans; and
(2) The management and daily business operations of which are controlled by one or more veterans.
Women-owned small business concern means a small business concern--
(1) That is at least 51 percent owned by one or more women, or, in the case of any publicly owned business, at least
51 percent of the stock of which is owned by one or more women; and
(2) Whose management and daily business operations are controlled by one or more women.
(b) It is the policy of the United States that small business concerns, veteran-owned small business concerns, service-disabled veteran-owned small business concerns, HUBZone small business concerns, small disadvantaged business concerns, and women-owned small business concerns shall have the maximum practicable opportunity to participate in performing contracts let by any Federal agency, including contracts and subcontracts for subsystems, assemblies, components, and related services for major systems. It is further the policy of the United States that its prime contractors establish procedures to ensure the timely payment of amounts due pursuant to the terms of their subcontracts with small business concerns, veteran-owned small business concerns, service-disabled veteran-owned small business concerns, HUBZone small business concerns, small disadvantaged business concerns, and women-owned small business concerns.
(c) The Contractor hereby agrees to carry out this policy in the awarding of subcontracts to the fullest extent consistent with efficient contract performance. The Contractor further agrees to cooperate in any studies or surveys as may be conducted by the United States Small Business Administration or the awarding agency of the United
States as may be necessary to determine the extent of the Contractor's compliance with this clause.
(d)(1) The Contractor may accept a subcontractor's written representations of its size and socioeconomic status as a small business, small disadvantaged business, veteran-owned small business, service-disabled veteran-owned small business, or a women-owned small business if the subcontractor represents that the size and socioeconomic status representations with its offer are current, accurate, and complete as of the date of the offer for the subcontract.
(2) The Contractor may accept a subcontractor's representations of its size and socioeconomic status as a small business, small disadvantaged business, veteran-owned small business, service-disabled veteran-owned small business, or a women-owned small business in the System for Award Management (SAM) if--
(i) The subcontractor is registered in SAM; and
(ii) The subcontractor represents that the size and socioeconomic status representations made in SAM are current, accurate and complete as of the date of the offer for the subcontract.
(3) The Contractor may not require the use of SAM for the purposes of representing size or socioeconomic status in connection with a subcontract.
(4) In accordance with 13 CFR 121.411, 124.1015, 125.29, 126.900, and 127.700, a contractor acting in good faith is not liable for misrepresentations made by its subcontractors regarding the subcontractor's size or socioeconomic status.
(5) The Contractor shall confirm that a subcontractor representing itself as a HUBZone small business concern is certified by SBA as a HUBZone small business concern by accessing the System for Award Management database or by contacting the SBA. Options for contacting the SBA include--
(i) HUBZone small business database search application Web page at http://dsbs.sba.gov/dsbs/search/dsp_searchhubzone.cfm; or http://www.sba.gov/hubzone;
(ii) In writing to the Director/HUB, U.S. Small Business Administration, 409 3rd Street, SW., Washington DC
20416; or
(iii) The SBA HUBZone Help Desk at hubzone@sba.gov.
52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL
EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance
Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
Goals for minority participation for each trade
Goals for female participation for each trade
26.6% 9.6%
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract
Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from
Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract
Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is James River
Streambank Stabilization Project (JRRSP) Amherst County, Virginia.
52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT--CONSTRUCTION MATERIALS (MAY 2014)
(a) Definitions. “Commercially available off-the-shelf (COTS) item,” “construction material,” “domestic construction material,” and “foreign construction material,” as used in this provision, are defined in the clause of this solicitation entitled “Buy American --Construction Materials” (Federal Acquisition Regulation (FAR) clause
52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers. (1) The Government will evaluate an offer requesting exception to the requirements of the
Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph
(b)(3)(i) of the clause at FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign construction material not listed by the Government in this solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR
52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested--
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States.
The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-
(c) The amount of the bid guarantee shall be ____20____ percent of the bid price or $_3,000,000.00_______, whichever is less.-
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
52.233-2 SERVICE OF PROTEST (SEP 2006)
(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from
USACE NAO-CT, ATTN: Danita A. Young, 803 Front Street, Norfolk Virginia 23510
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
52.236-1 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 1984)
The Contractor shall perform on the site, and with its own organization, work equivalent to at least percent of the total amount of work to be performed under the contract. This percentage may be reduced by a supplemental agreement to this contract if, during performing the work, the Contractor requests a reduction and the Contracting
Officer determines that the reduction would be to the advantage of the Government.
52.236-5 MATERIAL AND WORKMANSHIP (APR 1984)
(a) All equipment, material, and articles incorporated into the work covered by this contract shall be new and of the most suitable grade for the purpose intended, unless otherwise specifically provided in this contract. References in the specifications to equipment, material, articles, or patented processes by trade name, make, or catalog number, shall be regarded as establishing a standard of quality and shall not be construed as limiting competition. The
Contractor may, at its option, use any equipment, material, article, or process that, in the judgment of the
Contracting Officer, is equal to that named in the specifications, unless otherwise specifically provided in this contract.
(b) The Contractor shall obtain the Contracting Officer's approval of the machinery and mechanical and other equipment to be incorporated into the work. When requesting approval, the Contractor shall furnish to the
Contracting Officer the name of the manufacturer, the model number, and other information concerning the performance, capacity, nature, and rating of the machinery and mechanical and other equipment. When required by this contract or by the Contracting Officer, the Contractor shall also obtain the Contracting Officer's approval of the material or articles which the Contractor contemplates incorporating into the work. When requesting approval, the
Contractor shall provide full information concerning the material or articles. When directed to do so, the Contractor shall submit samples for approval at the Contractor's expense, with all shipping charges prepaid. Machinery, equipment, material, and articles that do not have the required approval shall be installed or used at the risk of subsequent rejection.
(c) All work under this contract shall be performed in a skillful and workmanlike manner. The Contracting Officer may require, in writing, that the Contractor remove from the work any employee the Contracting Officer deems incompetent, careless, or otherwise objectionable.
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it.