W9123618B0001-0001.pdf

PDF 149 KB Posted

Attached to
WATERFIELD ROOF REPAIR
Solicitation number
W9123618B0001
Issued by

About this file

Amendment

View the file

Other files

File Type Posted
W9123618B0001_BID_ABSTRACT_SIGNED.pdf PDF
W9123618B0001-0002.pdf PDF
Waterfield_Roof_Solicitation_Package.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

WATERFIELD BUILDING EXTERNAL ROOF REPAIRS

THE PURPOSE OF THIS AMENDMENT IS TO CORRECT THE PERIOD OF PERFORMANCE FROM 90 DAYS TO 300 DAYS.

ALL OTHER TERMS AND CONDITIONS SHALL REMAIN UNCHANGED.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 5

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9123618B0001

X 9B. DATED (SEE ITEM 11)

19-Oct-2017

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

U0001

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

23-Oct-2017

CODE

USA ENGINEER DISTRICT, NORFOLK

803 FRONT STREET

NORFOLK VA 23510-1096

W91236 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9123618B0001

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 10 00 - SOLICITATION

The contractor period of performance end date has increased by 210 days from 90 days to 300 days.

SECTION 00 21 00 - INSTRUCTIONS

The following have been modified:

NOTICE TO OFFERORS

A. PROJECT OVERVIEW:

The contractor shall provide all labor, equipment, tools, materials, transportation, management, supervision and other items and services necessary for the replacement of the roof system, portions of the lightning protection system, and glazing repairs to the Waterfield Building at 803 Front St, Norfolk VA, as well as repainting of roof area steel such as solar panel structure steel supports, doors, railings and other steel and metal fabrications.. Work shall be completed in accordance with attached plans and specifications.

B. OFFEROR'S QUESTIONS AND COMMENTS

All questions and/or comments should reach the above referenced Contracting Office via ProjNet no later than 6 November 2017, in order that they may be given consideration or actions taken prior to receipt of offers.

Technical inquiries and questions relating to proposal procedures or bonds are to be submitted via Bidder Inquiry in ProjNet at http://www.projnet.org/projnet. To submit and review bid inquiry items, bidders will need to be a current registered user or self-register into system. To self-register go to web page, click BID tab select Bidder Inquiry, select agency USACE, enter Key for this solicitation listed below, and your e-mail address, click login. Fill in all required information and click create user. Verify that information on next screen is correct and click continue.

From this page you may view all bidder inquiries or add inquiry. Bidders will receive an acknowledgement of their question via email, followed by an answer to their question after it has been processed by our technical team.

The Solicitation Number is : W91236-18-B-0001 The Bidder Inquiry Key is: DA7VKT-6JIWS4

The Bidder Inquiry System will be unavailable for new inquires 14 days prior to bid opening in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary. Offerors are requested to review the specification in its entirety, review the Bidder Inquiry System for answers to questions prior enter operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.

C. BID EVALUATION AND AWARD

The Government will evaluate bids in response to this solicitation based upon the Total Evaluated Price without discussions and will award a contract to the responsible bidder whose bid, conforming to the solicitation, will be most advantageous to the Government considering only price and the price-related factors specified elsewhere in the solicitation. The Government may reject any or all bids and/or waive informalities or minor irregularities in bids received.The Government will evaluate offers for award purposes by adding the total price for all optional items to the total price for the basic requirement.

D. AWARD TO RESPONSIBLE OFFEROR

In accordance with FAR Subpart 9.1, the Contracting Officer will perform an affirmative responsibility determination to ensure that the Offeror has (a) adequate financial resources to perform; (b) ability to comply with the required performance schedule; (c) a satisfactory performance record; (d) a satisfactory record of integrity and business ethics; (e) the necessary equipment and facilities to perform or the ability to obtain them; and (f) be otherwise qualified and eligible to receive award.

E. WAGE DETERMINATION:

DOL Wage Determination VA171 dated 8 September 2017 is applicable to this solicitation.

F. CONTRACT TERM:

This contract has three (3) base CLINs and three (3) option CLINs not to exceed 300 days from issuance of the Notice to Proceed.

G.EVIDENCE OF AUTHORITY TO SIGN OFFERS

Evidence of the authority of individuals signing offers to submit firm offers on behalf of the offeror is required except where the offer is signed, and shows that it is so signed, by: the President, Vice-President, or Secretary of an incorporated offeror; a partner in the case of a partnership; or the owner in the case of a sole proprietorship. Failure to submit with the offer satisfactory evidence of the authority of all other persons may be cause for rejection of the offer as invalid or nonresponsive.

H. PREAWARD SAFETY CONFERENCE

(1) Where an apparent successful offeror, in performance of contracts during the previous three-year period, incurred one or more accidents, or where, in the opinion of the Contracting Officer, there is any question regarding this compliance with any safety or accident prevention requirement, such bidder, on request of the Contracting Officer prior to any award under this solicitation, shall attend a conference with representatives of the Contracting Officer to discuss any such accidents or non-compliance, the reason for their occurrence, and measures which will be taken to preclude any recurrence thereof.

(2) Information elicited at this conference will be used by the Contracting Officer, in conjunction with other information obtained in a preaward survey, in determining the offeror's responsibility.

(3) The items discussed, the preventive measures considered, and any conclusions reached in this conference shall be recorded in minutes of the meeting which will be provided within 10 days of the conference and shall be authenticated by the signatures of representatives of the bidder and the Contracting Officer, and any procedures noted therein as agreed upon shall become an obligation of the offeror, along with all other safety and accident prevention requirements of the contract, if award is made to him.

I. INSPECTION OF THE SITE

Prospective offerors are invited to attend a site visit 1 November 2017. Arrangements for inspection of the site shall be made in accordance with the guidance as provided in clause 52.236-27, entitled "SITE

VISIT (CONSTRUCTION)."

J. INCURRING COSTS

The Government is not liable for any costs incurred by the offeror submitting an offer in response to this solicitation.

K. AGENTS

Offers signed by an Agent must be made in the name of the Principal and must be accompanied by evidence of said Agent’s authority to act on behalf of its Principal.

L. UNAUTHORIZED INSTRUCTIONS FROM GOVERNMENT OR OTHER PERSONNEL

The contractor shall not accept instructions issued by any person, employed by the U.S. Government or otherwise, other than the Contracting Officer or the Authorized Representative of the Contracting Officer acting within the limits of his/her authority as defined in the Designation of Authority letter. A copy of the Designation of Authority letter will be furnished to the contractor at time of contract award.

SECTION 00 72 00 - GENERAL CONDITIONS

The following have been modified:

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 300 days after issuance of the Notice to Proceed. The time stated for completion shall include final cleanup of the premises.

(End of clause)

(End of Summary of Changes)