Attachment_1_-_Statement_of_Work_19_Aug_2019.pdf

PDF 356 KB Posted

Attached to
Base Camera Equipment and Installation Federal contract opportunity
Solicitation number
W911YP-19-Q-2104
Issued by
Department of the Army Utah Army National Guard

About this file

Statement of Work Amendment 01

View the file

Other files for this federal contract opportunity

Other files attached to Base Camera Equipment and Installation, newest first.
File Type Posted
W911YP-19-Q-2104_Q&A.pdf PDF
Attachment_2_-_Equipment_Listing.pdf PDF
W911YP-19-Q-2104_Q&A.pdf PDF
Attachment_2_-_Equipment_Listing_19_Aug_2019.pdf PDF
B-8_Request_for_Quotations_Amendment_01;_Base_Camera_Plan.pdf PDF
Attachment_2_-_Equipment_Listing.xlsx XLSX spreadsheet
Attachment_3_-_Base_Map_Installation_Layout.pdf PDF
B-8_Request_for_Quotations;_Base_Camera_Plan.pdf PDF
Attachment_1_-_Statement_of_Work.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK AMENDMENT 01

UTAH AIR NATIONAL GUARD/151st SECURITY FORCES SQUADRON

BASE CAMERA PLAN

1.0 INTRODUCTION

1.1 Utah Air National Guard, 151 Security Forces Squadron, 765 North 2200 West, Salt Lake City, Utah 84116-

2999 has a requirement to purchase and install new CCTV camera and system infrastructure at the Roland R. Wright

Air National Guard Base.

2.0 TECHNICAL REQUIREMENTS

2.1 Scope of Work. This Statement of Work (SOW) identifies the work that shall be performed by the contractor for the installation of the purchased camera equipment. The contractor will be drilling small holes in the buildings to install the mounts for each camera and running CAT6 cabling through existing pathways.

2.2 Equipment: See equipment listing on Attachment 2 – Equipment Listing (Avigilon Compatible)

ALL SWITCHES MUST BE ON THE APPROVED PRODUCT LIST. Please use the following link to access the DISA approved product listing: https://aplits.disa.mil/processAPList.action

$87.50

3.0 DESCRIPTION OF TASKS - DELIVERABLES

3.1 Task 1 –The contractor shall install new cameras and perform labor to run new cabling for the cameras in

Bldgs: 10, 40, 210, 122, 112, 108, 401, 415, 19, 301, 303, 208, 215, and 218. The surface mounting points are a mixture of brick/metal/wood (exterior) and sheet rock/ceiling tile (interior).

3.2 Task 2- The contractor shall install the new server in building #401, a new 26 port fiber switch in the communications room 301, 10 port fiber switch in the communication room in Bldg. 122, a Ethernet extender in Bldg.

40.

3.3 Task 3 – The contractor shall function check all systems per this requriuement prior to the completion of this project.

3.0 INSPECTION AND ACCEPTANCE

3.1 The finished product will be inspected by the Contractor and Functional Area Chief (FAC for compliance with contract objectives).

4.0 WORK HOURS. The work hours for the Utah ANG are Monday – Thursday, 0600 – 1630. The contractor will be expected to perform during the normal UTANG work hours unless otherwise arranged in advance with the contracting officer and/or 151 SFS personnel.

5.0 WARRANTY. The contractor shall provide a standard commercial warranty.