SPECIFICATION Amendment 0002 SPECIAL PROJECT PROCEDURES.pdf
PDF 44 KB Posted
- Attached to
- FY21 Duluth Superior Harbor Maintenance Dredging
- Solicitation number
- W911XK21B0003
About this file
This solicitation package includes specifications for a FY21 Duluth-Superior Harbor maintenance dredging project. The contractor will be required to mobilize dredging equipment to the navigation channel and dredge to specified depths between upstream and downstream limits as shown in the contract drawings. Dredged material will be placed along Minnesota Point as beach nourishment. Additional requirements include debris management, signage and fencing installation, and pre- and post-work cleanups. The contractor must follow debris mitigation plans, monitoring and reporting procedures, and work period restrictions. Photography documentation and progress reporting are also specified. The soliciting agency is the Department of the Army Corps of Engineers Detroit District.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FY21 Duluth-Superior Maintenance Dredging FY21MDDULSUPHARB
CERTIFIED FINAL - READY TO ADVERTISE
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 35 13
SPECIAL PROJECT PROCEDURES
03/01
PART 1 GENERAL
1.1 SUBMITTALS
1.2 SEVERE WEATHER
1.3 PARTNERING
1.4 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS
CONTRACTS
1.5 PROJECT/SITE CONDITIONS
1.5.1 Condition and Use of Project Site
1.5.1.1 Physical Conditions
1.5.1.2 Work and Storage Areas
1.5.2 Waterways Navigation and Traffic
1.5.2.1 Navigation
1.5.2.2 Traffic
1.5.3 Existing Vegetation, Structures, Equipment, Utilities &
Improvements
1.5.4 Protection and Maintenance of Traffic
1.5.4.1 Haul Roads
1.5.4.2 Barricades
1.5.4.3 Signage and Fencing Placement Plan
1.5.5 Contract Supervision and Representation
1.5.6 Coordination with Others
1.5.7 Traffic Control Plan
1.5.8 Temporary Lights, Signals and Buoys Required by Coast Guard
1.5.9 Navigation Buoys
1.5.9.1 Relocation of Existing Buoys
1.5.9.2 Temporary Dredging and Construction Buoys
1.5.9.3 Buoy Markings
1.5.10 Layout of Work and Surveys
1.5.10.1 Layout of Work
1.5.10.2 Surveyor Requirements
1.5.10.3 Suspension
1.5.10.4 Verification
1.6 SEQUENCING AND SCHEDULING
1.6.1 Exclusion of Period in Computing Completion Schedules
1.6.2 Dredging Period Restriction
1.6.3 Weekend, Holiday And Night Operations
1.6.4 Work Period Restrictions
1.6.5 Start Work
1.7 POST-CONSTRUCTION DEBRIS MONITORING
1.8 FULL DEPTH CLEAN-UP
1.9 OPTIONAL SURFACE CLEAN-UP
1.10 CLEAN-UP REPORT
1.11 DEBRIS MANAGEMENT
1.11.1 Debris Management Plan
1.11.1.1 Mechanical Placement
1.11.1.2 Hydraulic Placement
1.12 PROGRESS PHOTOGRAPHS
SECTION 01 35 13 Page 1
1.12.1 Photographs
1.12.2 Prework Photographs
1.12.3 Construction Photographs
1.12.4 Completion Photograph
1.12.5 Photograph File, Format and Naming
1.12.6 Photograph Quantity
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION (NOT APPLICABLE)
-- End of Section Table of Contents --
SECTION 01 35 13 Page 2
SECTION 01 35 13
SPECIAL PROJECT PROCEDURES
03/01
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Payrolls and Basic Records;
Contractor shall submit payrolls and basic records in accordance with the CLAUSE 52.222-8 "PAYROLLS AND BASIC RECORDS."
Gantt Chart Schedule; G-AOF.
Contractor shall submit progress chart in accordance with the Contract clause 52.236-15 "SCHEDULE FOR CONSTRUCTION CONTRACTS."
Utility Location Plan and Findings Submit a copy of the utility location plan and findings in accordance with the paragraph entitled "Existing Vegetation, Structures, Equipment, Utilities & Improvements" prior to commencing work on the site.
Notice to Mariners See paragraph entitled "Waterways Navigation and Traffic." Submit the Notice as published.
Signage and Fencing Placement Plan; G, AOF Contractor shall submit a Signage and Fencing Placement Plan for the required temporary signage and fencing.
Debris Management Plan; G, AOF Contractor shall submit a Debris Management Plan for the required man-made debris placement mitigation.
SD-06 Test Reports
Clean-Up Report; G, AOF
SD-07 Certificates
Survey Technician's Qualifications Submit the identity and qualifications of the persons assigned to conduct surveys at least ten (10) calendar days in advance of conducting any surveys.
SD-08 Manufacturer's Instructions
SECTION 01 35 13 Page 3
Full Depth Clean-Up Equipment And Performance Data; G, AOF
Surface Clean-Up Equipment And Performance Data; G, AOF
1.2 SEVERE WEATHER
The table below provides monthly minimum anticipated adverse weather for the project region, scope of work, and anticipated equipment. It is based on National Oceanic and Atmospheric Administration (NOAA) or similar historical data for the region. The anticipated adverse weather is normal for the region and must be anticipated in the project schedule.
MONTHLY ANTICIPATED ADVERSE WEATHER DELAY
WORK DAYS FOR *LAKE SUPERIOR* BASED ON 7 DAY WORK WEEK *
JAN FEB MAR APR APR MAY JUN
1-15 16-30
(31) (29) (31) (15) (5) (7) (1)
JUL AUG SEP OCT NOV NOV DEC
1-15 16-30
(1) (1) (6) (8) (5) (15) (31)*
At a minimum, the contractor's schedule must incorporate these anticipated adverse weather delays in all on-site, weather-dependent activities. For off-site work, or if the contractor's equipment or methods dictate, the schedule should incorporate anticipated adverse weather for the historically prevalent weather conditions in that region given the equipment being used and work being performed.
Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work.
Any claim for delay due to unusually severe weather must be submitted in accordance with FAR Clause 52.249-10 Default (Fixed-Price Construction).
Include sufficient documentation to facilitate review by the Contracting Officer.
1.3 PARTNERING
In order to most effectively accomplish this contract, the Government proposes to form a partnership with the Contractor to develop a cohesive building team. It is anticipated that this partnership would involve the Contractor, primary subcontractors and designers, and the Corps of Engineers. This partnership would strive to develop a cooperative management team drawing on the strengths of each team member in an effort to achieve a quality project within budget and on schedule. This parntership would be bilateral in membership and participation will be completely voluntary. The partnering meeting shall be held at agreed upon dates/times of all involved parties. The meeting will be an informal, non-facilitated meeting and can be combined with the preconstruction conference.
SECTION 01 35 13 Page 4
1.4 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS CONTRACTS
In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS
222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:
- U.S. Department of Labor Veterans’ Employment and Training Service (VETS): https://www.dol.gov/vets/
- Federal Veteran Employment Information: https://www.fedshirevets.gov/
- Veterans Opportunity to Work (VOW) Program:
https://www.benefits.va.gov/vow/
- U.S. Army Warrior Transition Command Employment Index:
https://wct.army.mil/modules/employers/index.html
- Hiring Our Heroes: https://www.uschamberfoundation.org/hiring-our-heroes
1.5 PROJECT/SITE CONDITIONS
1.5.1 Condition and Use of Project Site
The drawings indicate soundings and elevations at the dredging and disposal sites as found in condition surveys made as stated on the contract drawings. A notification of at least five (5) calendar days shall be given to the Contracting Officer prior to bringing any construction equipment or material upon the work site. The Contractor shall be responsible for damages that may be suffered due to its operations. The Contractor shall note CLAUSE 52.236-9 "PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS."
1.5.1.1 Physical Conditions
The physical conditions shown on the drawings are indicative of those that prevailed at the time of the site investigations and may be different than those at the time of construction. Significant variations that would require changes to the plans or specification shall be reported to the Contracting Officer immediately.
1.5.1.2 Work and Storage Areas
Work and storage areas will be provided at the site and will be as designated on the contract drawings and/or approved by the Contracting Officer. All fuel storage and fueling operations shall remain within the work and storage area, unless otherwise approved by the COR. Areas made available to the Contractor will be selected to minimize interference with Government operations and other contractors.
1.5.2 Waterways Navigation and Traffic
The Contractor shall acquaint itself with all information and regulations pertaining to navigation and vessel traffic within the waterways at the project site. The Contractor shall coordinate with the U.S. Coast Guard to assure that a "NOTICE TO MARINERS" is issued prior to its work activity at
SECTION 01 35 13 Page 5 the project site. The completed form shall be sent to the address stated in the Subparagraph entitled "Temporary Lights, Signals and Buoys Required by U.S. Coast Guard". The Government will not undertake to keep the waterways free from vessels or other obstructions, except to the extent of such regulations, if any, as may be prescribed by the Secretary of the Army, in accordance with the provisions of Section 7 of the River and Harbor Act approved 8 August 1917 (see Title 33, U.S.C.A. Sec. 1). The Contractor is required to conduct its work in such manner as to obstruct navigation as little as possible and, in case the Contractor's plant so obstructs a channel as to make difficult or endanger the passage of vessels, said plant shall be promptly moved on the approach of any vessel to such an extent as may be necessary to afford a practicable passage.
Upon completion of the work, the Contractor shall promptly remove its plant, including ranges, buoys, piles, and other marks placed by it under the contract in navigable waters or on shore.
1.5.2.1 Navigation
Information and regulations pertaining to navigation may be obtained from the current issue of the "UNITED STATES COAST PILOT 6," issued annually by the Department of Commerce, National Oceanic and Atmospheric Administration (NOAA). The "UNITED STATES COAST PILOT" may be obtained from National Ocean Survey, NOAA, Distribution Division-C44, Riverdale, Maryland 20840.
1.5.2.2 Traffic
Vessels that may use the waterways at the project site consist of recreational craft and commercial vessels. This traffic may interfere with contract operations and the Contractor shall conduct its work with due regard to and in coordination with the requirements of all navigation.
Information regarding the types and amount of passages made by commercial vessels that may use the waterways at the project site may be obtained from the current issue of the "Waterborne Commerce of the United States, Part 3, Waterways and Harbors, Great Lakes," published by the Department of Army, Corps of Engineers. The Department of the Army publication may be obtained at no charge from the following:
District Engineer, U.S. Army Engineer District, New Orleans, Waterborne Commerce Section, P.O. Box 60267, New Orleans, Louisiana 70160. Phone
504-862-1425, FAX 504-862-1091.
1.5.3 Existing Vegetation, Structures, Equipment, Utilities & Improvements
General locations of applicable existing utilities, vegetation, structures, equipment and improvements, based upon latest information available to the Government have been shown on the drawings. However, it is the Contractor's obligation to establish the exact horizontal and vertical location and size of all existing utility lines which are located within the required work area. The Contractor shall submit a utility locating plan for locating existing utilities and a copy of its utility location findings prior to commencing work on the site. Any utility lines which are not found by the Contractor, but which are known to exist at the project site, shall be reported to the Contracting Officer immediately. The Contracting Officer will have the option of directing commencement of work at the site or requiring the Contractor to submit further plans for locating the utility lines. Once the utilities have been located and marked, the Contractor shall be deemed to have the location made known to it pursuant to CLAUSE 52.236-9 "PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS." If the Contractor damages any
SECTION 01 35 13 Page 6 existing utility line, vegetation, structure, equipment or improvement, a report thereof shall be made immediately to the Contracting Officer. In any event, existing utility lines, vegetation, structures, equipment or improvements shall be protected from damage, and if damaged, shall be repaired by the Contractor at its own expense.
1.5.4 Protection and Maintenance of Traffic
1.5.4.1 Haul Roads
The Contractor shall, at its own expense, construct access and haul roads necessary for proper prosecution of the work under this contract. Haul roads shall be constructed with suitable grades and widths; sharp curves, blind corners, and dangerous cross traffic shall be avoided. The Contractor shall provide necessary lighting, signs, barricades, and distinctive markings for safe movement of traffic. The method of dust control shall be adequate to ensure safe operation at all times. Location, grade, width, and alignment of construction and hauling roads shall be subject to approval by the Contracting Officer. Lighting shall be adequate to assure full and clear visibility for full width of haul road and work areas during any night work operations. Upon completion of the work, haul roads shall be removed unless otherwise approved by the Contracting Officer. Any dirt or mud which is tracked onto paved or surfaced roadways shall be promptly cleaned away.
1.5.4.2 Barricades
The Contractor shall erect and maintain temporary barricades to limit public access to hazardous areas. Such barricades shall be required whenever safe and public access to paved areas such as roads, parking areas or sidewalks is prevented by construction activities or as otherwise necessary to ensure the safety of both pedestrian and vehicular traffic.
Barricades shall be securely placed, clearly visible with adequate illumination to provide sufficient visual warning of the hazard during both day and night.
1.5.4.3 Signage and Fencing Placement Plan
Contractor shall supply adequate temporary signage and chain-link fence panels at the placement site during placement, required full depth clean-up and, if awarded, optional surface clean-up operations for the safety of the public. Signage and fencing shall be placed at the edge of the work area/placement limits. Signage and fencing locations shall be coordinated with the Contracting Officer's Representative (COR).
1.5.5 Contract Supervision and Representation
The Contractor's local representative shall be available to Government representatives during duty hours, 8 a.m. to 4:30 p.m., on normal working days and shall be available by telephone at other times. The name of the Contractor's representative and the contact telephone number shall be furnished to the Government.
1.5.6 Coordination with Others
The Contractor is informed that the Government may have other Contractors engaged in the area. Reference Clause 52.236-8, "OTHER CONTRACTS".
SECTION 01 35 13 Page 7
1.5.7 Traffic Control Plan
The Contractor shall control traffic in accordance with its approved plan.
1.5.8 Temporary Lights, Signals and Buoys Required by Coast Guard
All temporary lights, signals and buoys required by the U.S. Coast Guard must be displayed during the required work. Information regarding required signals, lights, buoys and other requirements may be obtained from the Commander (oan), Ninth Coast Guard District, 1240 East Ninth Street, Cleveland, Ohio 44199-2060, Telephone (216) 522-3990.
1.5.9 Navigation Buoys
1.5.9.1 Relocation of Existing Buoys
If the relocation of existing navigation buoys is required to perform the contract work, the Contractor shall request permission for their relocation from the U.S. Coast Guard through the Contracting Officer. Once relocated, a record shall be maintained of the buoy relocation position(s). The request shall be provided to the Contracting Officer not less than three
(3) weeks prior to need of the buoy relocation. The Contractor shall be responsible for performing the relocation work, which shall be in accordance with U.S. Coast Guard requirements.
1.5.9.2 Temporary Dredging and Construction Buoys
In order to distinguish temporary buoys placed and maintained by the Contractor for dredging or construction purposes from aids to navigation placed by the U.S. Coast Guard, the Contractor's buoys shall be white and the top two (2) feet shall be light green in color. The Contractor shall remove its temporary buoys at the completion of the work.
1.5.9.3 Buoy Markings
If buoys with special markings are needed to indicate the different sides of the navigable channel, prior arrangements shall be made with the U.S.
Coast Guard, through the Contracting Officer.
1.5.10 Layout of Work and Surveys
1.5.10.1 Layout of Work
The following requirements are in addition to the requirements of CLAUSE 52.236-17 "LAYOUT OF WORK, (IGLD 1985)." The Government has established bench marks and horizontal control points at the site of the work.
Horizontal control points and descriptions of bench marks are shown on the drawings or supplied by the Contracting Officer Representative (COR).
1.5.10.2 Surveyor Requirements
From these control points and bench marks, the Contractor shall lay out the work by establishing all lines, grades, range markers and gauges at the site as necessary to control the work. All survey information shall be recorded in accordance with standard and approved methods and in the survey note format approved by the Contracting Officer. All field notes, sketches, recordings and computations made by the Contractor in performing the layout work shall be available at all times during the progress of the work for ready examination by the Contracting Officer or his or her duly
SECTION 01 35 13 Page 8 authorized representative and upon completion of the contract work the originals shall be turned over to the Contracting Officer in ring binders.
1.5.10.3 Suspension
The Contracting Officer may require that work be suspended at any time when location and limit marks established by the Contractor are not reasonably adequate to permit checking the work. Such suspension will be withdrawn upon satisfactory replacement of location and limit marks. Such suspension shall be at no additional cost to the Government and shall not entitle the Contractor to an extension of time for completing the work.
1.5.10.4 Verification
The Government may make checks as the work progresses to verify lines and grades established by the Contractor and to determine the conformance of the completed work as it progresses with the requirements of contract specifications and drawings. Such checking by the Contracting Officer or his or her representative shall not relieve the Contractor of its responsibility to perform all work in accordance with the contract drawings and specifications and the lines and grades given therein.
1.6 SEQUENCING AND SCHEDULING
1.6.1 Exclusion of Period in Computing Completion Schedules
No work will be required during the period between 1 December and 31 March inclusive and the days in this period will not be counted when computing the required completion date. The Contractor may perform work, unless otherwise prohibited, during all or any part of this period upon giving prior written notice to the Contracting Officer.
1.6.2 Dredging Period Restriction
The Contractor's attention is directed to the allowed and prohibited dredging periods as established by the State of Wisconsin and Minnesota for this project as specified in SECTION 01 57 19, paragraph "Allowed and Prohibited Dredging Periods". The number of calendar days within which the Contractor is required to complete the work under this contract, as established in Clause 52.211-10 Alt I. titled "COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK", is exclusive of the above referenced periods during which dredging is prohibited and the days in these periods will not be counted when computing the required completion date.
1.6.3 Weekend, Holiday And Night Operations
When the Contractor elects to work on Saturdays, Sundays, holidays or nights when not prohibited herein, notice of its intention to do so shall be given to the Contracting Officer not less than forty-eight (48) hours in advance thereof. Adequate lighting for thorough inspection of night operations shall be provided by the Contractor at its expense.
1.6.4 Work Period Restrictions:
a. Fueling of equipment at Minnesota Point is limited to weekdays between 10 a.m. and 4 p.m., or as directed by the COR.
b. Installation of a material transfer box and mobilization and demobilization of equipment to the placement area is limited to
SECTION 01 35 13 Page 9 weekdays between 9 a.m. and 5 p.m., or as directed by the COR.
c. Placement of material at Minnesota Point North Placement Area is prohibited from 4 p.m. on 2 July 2021 to 8 a.m. on 6 July 2021 (Independence Day Weekend). This restriction does not apply to optional surface clean-up, if awarded.
d. Placement of material at Minnesota Point North Placement Area is prohibited from 4 p.m. on 3 September 2021 to 8 a.m. on 7 September 2021 (Labor Day Weekend).
e. Required full depth clean-up and, if awarded, optional surface clean-up operations are limited to daily hours from 6 a.m. to 6 p.m.
1.6.5 Start Work
Evidence that the Contractor has started mobilization and preparation of submittal register, and other preparatory work will satisfy the requirement that work commence within 10 calendar days after receipt of Notice to Proceed. (See FAR Clause 52.211-10 Alt I. COMMENCEMENT, PROSECUTION, AND
COMPLETION OF WORK).1.7 POST-CONSTRUCTION DEBRIS MONITORING
Upon completion of all dredging and placement operations or 1 October 2021, whichever is sooner, the Contractor shall continue to closely monitor the placement area for man-made debris. Monitoring efforts must be conducted a minimum of once per week up to the contract completion date or six total weeks of debris monitoring, whichever is sooner. Debris monitoring must be full-scale, detailed inspections of the landward portion of the placement area to collect any observable debris. Any observed debris shall be collected and appropriately discarded off site.
1.8 FULL DEPTH CLEAN-UP
The contractor shall perform a clean-up of the identified locations to the respective depths indicated on the contract drawings. The clean-up shall utilize screening methods capable of capturing debris at least as small as 1/4" in average size. All screened material must be placed and graded back in the general location it was found, maintain positive drainage toward Lake Superior. All debris captured during the screening process shall be properly handled and appropriately discarded off site. If man-made debris is observed below the required depth for full depth clean-up areas, the Contractor shall immediately notify the COR. For order of work requirements relating to optional clean-up, see SECTION 35 20 23 paragraph titled "Order of Work." For signage and fencing requirements, see paragraph titled "Signage and Fencing Placement Plan" herein. For turbidity control requirements, see SECTION 01 57 24 paragraph titled "BEST MANAGEMENT
PRACTICES FOR REQUIRED AND OPTIONAL CLEAN-UP."
Submit Full Depth Clean-up Equipment and Performance Data for proposed equipment to be utilized during full depth clean-up operations. The data must provide complete descriptions of equipment including excavation, screening, and grading prior to commencement of work. Descriptive information includes manufacturer's name, model numbers, operator manuals, and performance specifications.
1.9 OPTIONAL SURFACE CLEAN-UP
If optional surface clean-up is awarded, the Contractor shall perform a clean-up of the top 6 inches of material within the entire area identified
SECTION 01 35 13 Page 10 within the contract drawings. The contractor shall perform this clean-up twice. The first clean-up shall take place prior to placing material. The second clean-up shall take place once placement and grading of all dredged material has been completed. At the time of each clean-up, the exact limits will be defined by the COR as specified in the contract drawings. The clean-up operations utilized must be capable of capturing debris at least as small as 1/4" in average size and separating the cleaned material to be kept within the identified clean-up area in the general condition it was found prior to clean-up operations. If the Contractor's elected methods for clean-up require regrading of material, the graded material must maintain positive drainage toward Lake Superior. All debris captured during the clean-up operations shall be properly handled and appropriately discarded off site. If man-made debris is observed below the top 6 inches of material, the Contractor shall immediately notify the COR. For more in depth order of work requirements relating to optional clean-up, see SECTION 35 20 23 paragraph titled "Order of Work." For signage and fencing requirements, see paragraph titled "Signage and Fencing Placement Plan" herein. For turbidity control requirements, see SECTION 01 57 24 paragraph titled "BEST MANAGEMENT PRACTICES FOR REQUIRED AND OPTIONAL CLEAN-UP."
If optional surface clean-up is awarded, submit Surface Clean-up Equipment and Performance Data for proposed equipment to be utilized during surface clean-up operations. The data must provide complete descriptions of equipment including material collection, screening, and grading prior to commencement of work. Descriptive information includes manufacturer's name, model numbers, operator manuals, and performance specifications.
1.10 CLEAN-UP REPORT
For full depth clean-up and (if awarded) optional surface clean-up, the Contractor shall provide a detailed report of debris that was collected as a result of each clean-up operation and the date debris was collected on.
This report shall included descriptions of the type of debris found, the volume of debris collected, pictures of the debris, approximate location debris was collected at, and how/where the debris was appropriately discarded.
1.11 DEBRIS MANAGEMENT
The Contractor shall employ necessary measures to mitigate the placement of man-made debris within the placement area indicated on the contract drawings.
1.11.1 Debris Management Plan
The Contractor shall submit a detailed plan indicating the actions that will be taken to mitigate man-made debris from reaching final placement at the specified placement area. The plan shall include that documentation of all site conditions/findings and actions taken to mitigate placement of man-made debris be entered in the daily quality control reports in RMS. The Contractor shall ensure that dredged material is free of metal prior to completion or allowing the public to access the placement area, whichever is sooner.
1.11.1.1 Mechanical Placement
If the Contractor elects to utilize mechanical equipment as means to place dredged material, the Contractor shall at a minimum utilize the following practices for minimizing placement of man-made debris, unless otherwise
SECTION 01 35 13 Page 11 approved by the COR.
a. During the dredging and placement operations, the Contractor shall continuously and closely monitor the material being collected from the dredge areas and placed in the identified placement area for man-made debris. The contractor must routinely utilize metal detecting equipment to monitor placed material for man-made debris. Any man-made debris observed within the dredged material shall be immediately removed either from the scow/material transport vessel or immediately after placement and appropriately discarded off site at no additional cost to the Government.
b. All material shall be screened prior to placement to effectively capture man-made debris prior to material being placed at the Minnesota Point North Placement Area. The screening process shall contain maximum 2 inch by 2 inch grid openings.
c. During placement operations and final grading of material at the specified placement area, the Contractor shall continuously and closely monitor the material being graded for man-made debris. Any man-made debris observed within the placement area shall be picked up and appropriately discarded off site at no additional cost to the Government.
d. If man-made debris is encountered, the Contractor shall immediately notify the COR and cease operations. Operations shall only proceed upon receiving approval through the COR. The Government reserves the right to enforce additional debris management requirements if current requirements are deemed by the Government to be insufficient.
1.11.1.2 Hydraulic Placement
If the Contractor elects to utilize hydraulic equipment as means to place dredged material, the Contractor shall at a minimum utilize the following practices for minimizing placement of man-made debris, unless otherwise approved by the COR.
a. During the dredging and placement operations, the Contractor shall continuously and closely monitor the material being collected from the dredge areas for man-made debris. The contractor must routinely utilize metal detecting equipment to monitor placed material for man-made debris. Metal detection monitoring must be focused within the vicinity of the point of discharge. Any man-made debris observed within the dredged material shall be immediately removed from the scow/material transport vessel and appropriately discarded off site at no additional cost to the Government.
b. Use of hydraulic conveyance methods for material transport shall incorporate a screening process with maximum grid openings of 2 inch by 2 inch capable of effectively capturing man-made debris prior to material being placed at the Minnesota Point North Placement Area. The Contractor shall regularly check for and remove debris that has been restrained from reaching the placement area. Any man-made or natural debris captured by the required screening process shall be removed and appropriately discarded at no additional cost to the Government.
c. If man-made debris is encountered, the Contractor shall immediately notify the COR and cease operations. Operations shall only proceed upon receiving approval through the COR. The Government reserves the right
SECTION 01 35 13 Page 12 to enforce additional debris management requirements if current requirements are deemed by the Government to be insufficient.
1.12 PROGRESS PHOTOGRAPHS
1.12.1 Photographs
Color photographs will be taken with ordinary digital cameras at high resolutions (minimum five (5) megapixel) and submitted as JPG files. The JPG files shall be submitted on DVD/CD's or electronically as email attachments and uploaded to RMS, as directed by the COR. The Contractor is responsible for selecting formats and media compatible with Government equipment. The Government utilizes ordinary office software and hardware with Windows based products.
1.12.2 Prework Photographs
Before work begins, the Contractor shall photograph salient site features and conditions with particular attention to the existing transformer and its installation details. Images shall be chosen so that a comparison with final photographs will provide a comprehensive record of the work accomplished under this contract.
1.12.3 Construction Photographs
During construction, the Contractor shall photograph every activity, every crew and every major piece of construction equipment. The Contractor will take special care to photograph activities resulting from each contract modifications.
1.12.4 Completion Photograph
At completion, the Contractor shall photograph salient site features and conditions with particular attention to the placement areas and, if applicable, the hydraulic pumpout and its installation details. Images shall be chosen so that a comparison with pre-work photographs will provide a comprehensive record of the work accomplished under this contract.
1.12.5 Photograph File, Format and Naming
The Contractor shall compile a simple database for every photograph provided using common office software. Microsoft Access and Excel are examples of acceptable source software. The database may be submitted on a CD. The Contractor is responsible for selecting formats and media compatible with Government equipment. The Government utilizes ordinary office software and hardware with Windows based products. The Contractor shall prepare a single database where each and every submitted photograph submitted under this section is represented by a single record. At a minimum, each photograph shall include descriptive title and date taken.
1.12.6 Photograph Quantity
The final submittal of prework, construction and completion photographs shall be edited to select only the best and most illustrative of the photos to document the progress of the work. A minimum of five (5) and a maximum of twenty (20) photos shall be included for each feature of work, unless otherwise directed by the COR.
SECTION 01 35 13 Page 13
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION (NOT APPLICABLE)
-- End of Section --