AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
FY19 Maintenance Dredging Grand Haven Inner Harbor, Michigan.
This amendment is issued to:
(1) Remove language "December 1, 2019" from the Scope of Work Exercising of Options.
(2) Revise Clause 52.211-10 Commencement, Prosecution and Completion of Work alternate I. The notice to proceed date has change from June 20, 2019 to July 31, 2019.
(3) Remove 401 Water Quality Certif ication dated November 14, 2014 and Replace w ith new 401 Water Quality Certification dated April 26, 2019. Specification Section 01 99 90 - Listing of Enclosed Documents, Exhibits and Other Attachments.
Reference changes on the follow ing pages. All other terms and conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 5
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 23-May-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W911XK19B0006
X 9B. DATED (SEE ITEM 11)
08-May-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
23-May-2019
CODE
U.S.ARMY ENGINEER DISTRICT, DETROIT
477 MICHIGAN AVENUE, 7TH FLOOR
DETROIT MI 48226-4523
W911XK 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W911XK19B0006
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0001
1. CHANGES TO THE SPECIFICATIONS
A. REPLACE: Replace the 401 Water Quality Certification dated 14 November, 2014 attached to 01 99 90 “Listing of Enclosed Documents, Exhibits and Other Attachments” with the new certification dated 26 April, 2019 attached to the end of this amendment.
2. CHANGES TO SOLICITATION
A. REMOVE: Remove the following language from Section 00 10 00 – Solicitation, Exercising of Options
“If Options(s) are exercised before December 1, 2019”
B. REVISE: Revise clause 52.211-10 Commencement, Prosecution, and
Completion of Work Alternate I. The notice to proceed date has changed from June 20, 2019 to July 31, 2019
SECTION 00 10 00 - SOLICITATION
The following have been modified:
SCOPE OF WORK
Provide all necessary equipment, materials, labor, supervision, and administration as necessary to perform the work and meet the requirements indicated on the project drawings and specifications. Specific work items include:
1. Mobilize to the project work area at Grand Haven Harbor in Ottawa County, Michigan.
2. Excavate previously dredged material from the North Cell of the Verplank upland placement site, and transport the material to the placement area indicated on the drawings.
3. Clear vegetation from the South Cell of the Verplank upland placement site, and legally dispose of removed vegetation off-site.
4. Dredge Grand Haven Harbor between the upstream and downstream limits indicated on the drawings.
Dredging may be accomplished by hydraulic or mechanical means.
5. Place dredged material in the North Cell of the Verplank upland placement site. Materials placed in the upland site may only be placed hydraulically.
6. Clean up and de-mobilize from the project work area.
Exercising of Options:
1. Excavate dredged material as indicated for option work on the drawings from the South Cell of the Verplank upland placement site.
2. Transport the excavated material to the placement area as indicated on the drawings.
3. Dredge Grand Haven Harbor between the upstream and downstream limits indicated for option work on the drawings. Dredging may be accomplished by hydraulic or mechanical means.
4. Place dredged material in the North Cell of the Verplank upland placement site. Materials placed in the upland site may only be placed hydraulically.
SECURITY REQUIREMENT
1. All personnel employed by the contractor in the performance of the services specified in this contract or any representative of the contractor entering the operational area shall conform and comply with all applicable Federal/State of Michigan local laws, rules, regulations or policies. It is the contractor’s responsibility to be aware of the prevailing laws, rules, regulations or policies of the local area.
2. E-verify Program-When servicing on federal grounds, the contractor must pre-screen candidates using the E-verify Program (https://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that all contractors working on this contract have two valid forms of Government issued identification prior to entering the information in E-Verify. The vendor must ensure the correct information is entered into the E-verify system. An E-Verify verification sheet for each verified/eligible contractor candidate, working on this contract, must be provided to the Contracting Officer Representative (COR) no later than 3 business days after the initial contract award. (The purpose of using E-Verify is to ensure all contractors are U.S.
citizens or documented foreign citizens with authority to work in the United States of America). The COR will forward the verification sheets to the USACE, Detroit District Security Office for validation.
3. Security Checks-All contract employees must carry pictured identification at all times. They must show I.D. upon request by City/State/Government personnel. The Contractor's employee must carry a copy of the contract requirements with them during the implementation of this contract.
UAI 5152.211-9001 Variations in Estimated Quantities – Subdivided Items.
VARIATIONS IN ESTIMATED QUANTITIES — SUBDIVIDED ITEMS (MAR 1995)
This variation in estimated quantities clause is applicable only to item Nos. 0004, 0005, 0006, and, 0008.
(a) Variation from the estimated quantity in the actual work performed under any second or subsequent sub-item or elimination of all work under such a second or subsequent sub-item will not be the basis for an adjustment in contract unit price.
(b) Where the actual quantity of work performed for item Nos. is less than 85% of the quantity of the first sub-item listed under such item, the contractor will be paid at the contract unit price for that sub-item for the actual quantity of work performed and, in addition, an equitable adjustment shall be made in accordance with the clause Federal Acquisition Regulation (FAR) 52.211-18, Variation in Estimated Quantities.
(c) If the actual quantity of work performed under item Nos. 0004, 0005, 0006, and 0008 exceeds 115% or is less than 85% of the total estimated quantity of the sub-item under that item and/or if the quantity of the work performed under the second sub-item or any subsequent sub-item under item Nos.0004, 0005, 0006, and, 0008 exceeds 115% or is less than 85% of the estimated quantity of any such sub-item, and if such variation causes an increase or a decrease in the time required for performance of this contract the contract completion time will be adjusted in accordance with the clause FAR 52.211-18, Variation in Estimated Quantities.
(End of clause)
UAI 5152.211-9000 Evaluation of Subdivided Items.
As prescribed in 5111.703(d), insert the following provision:
EVALUATION OF SUBDIVIDED ITEMS (MAR 1995)
Item Nos.0004, 0005, 0006, and 0008 are subdivided into two or more estimated quantities and are to be separately priced. The Government will evaluate each of these items on the basis of total price of its subitems.
(End of clause)
UAI 5122.1302-100 Scope of Subpart.
Veterans Employment Emphasis for U.S. Army Corps of Engineers Contracts In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS
222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract.
While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:
U.S. Department of Labor Veterans employment: www.vets.gov/ Federal veteran employment information: www.fedshirevets.gov/index.aspx Veterans’ Employment and Training Service (VETS): http://www.dol.gov/vets/ Veterans Opportunity to Work (VOW) Program: http://benefits.va.gov/vow/ U.S. Army Warrior Transition Command Employment Index:
wtc.army.mil/modules/employers/index.html Hiring Our Heroes initiative: www.uschamberfoundation.org/hiring-our-heroes Guide to Hiring Veterans:
www.whitehouse.gov/sites/default/files/docs/white_house_business_counc il_-_guide_to_hiring_veterans_0.pdf
SECTION 00 70 00 - CONDITIONS OF THE CONTRACT
The following have been modified:
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) -
ALTERNATE I (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use including all exercised options not later than November 1, 2019. The time stated for completion shall include final cleanup of the premises.
The completion date is based on the assumption that the successful offeror will receive the notice to proceed by July 31, 2019. The completion date will be extended by the number of calendar days after the above date that the Contractor receives the notice to proceed, except to the extent that the delay in issuance of the notice to proceed results from the failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.
(End of clause)
(End of Summary of Changes)