Revised Section 31 11 00 Clearing Grubbing for Amendment 0001
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FY15 MD Detroit River_Amendment 0001 FY15MDDETROITRIV
SECTION TABLE OF CONTENTS
DIVISION 31 - EARTHWORK
SECTION 31 11 00
CLEARING & GRUBBING
08/08
PART 1 GENERAL
1.1 SUBMITTALS
1.2 DELIVERY, STORAGE, AND HANDLING
PART 2 PRODUCTS - Not Used
PART 3 EXECUTION
3.1 PROTECTION
3.1.1 Roads and Walks
3.2 CLEARING AND GRUBBING
3.2.1 VEGETATION REMOVAL
3.2.2 APPLICATION OF HERBICIDE
3.3 DISPOSAL OF MATERIALS
-- End of Section Table of Contents --
SECTION 31 11 00 Page 1
SECTION 31 11 00
CLEARING & GRUBBING
08/08
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
Herbicide and tracing agent; G, AO
The Material Safety Data Sheet (MSDS); G, AO
Herbicide(s), tracing agent and the Material Safety Data Sheet (MSDS) for the used herbicide(s) must be submitted to the COR and approved prior to application.
1.2 DELIVERY, STORAGE, AND HANDLING
Deliver materials to store at the site, and handle in a manner which will maintain the materials in their original manufactured or fabricated condition until ready for use.
PART 2 PRODUCTS - Not Used
PART 3 EXECUTION
3.1 PROTECTION
3.1.1 Roads and Walks
Keep roads and walks free of dirt and debris at all times.
3.2 CLEARING AND GRUBBING
3.2.1 VEGETATION REMOVAL
Vegetation, consisting of trees, brush, and weeds, shall be cut to a maximum height of 6 inches above stone or earthen surface and debris placed as specified in paragraph DISPOSAL OF MATERIALS. All stumps and remaining vegetation must be sprayed as specified in paragraph APPLICATION OF HERBICIDE.
3.2.2 APPLICATION OF HERBICIDE
All stumps from cleared trees, brush and other vegetation shall be sprayed with an appropriate herbicide(s) approved by the Michigan Department of Environmental Quality (DEQ) listed on http://www.michigan.gov/documents/deq/wrd-anc-approvedherbicides_445623_7.pdf.
Herbicide (s) shall have a tracing agent mixed in to clearly show treated areas. Herbicide(s), tracing agent and the Material Safety Data Sheet
SECTION 31 11 00 Page 2
(MSDS) for the selected herbicide(s) must be submitted to the COR and approved prior to application.
3.3 DISPOSAL OF MATERIALS
All debris from the vegetation removal operations shall be disposed of inside the limits of the Pte. Mouillee Confined Disposal Facility in a location within cell #1 as shown on the plans and designated by the COR.
-- End of Section --
SECTION 31 11 00 Page 3
| 31 11 00 - CLEARING & GRUBBING |
| 31 11 00 - CLEARING & GRUBBING |
| PART 1 GENERAL |
| 1.1 SUBMITTALS |
| 1.2 DELIVERY, STORAGE, AND HANDLING |
| PART 2 PRODUCTS - Not Used |
| PART 3 EXECUTION |
| 3.1 PROTECTION |
| 3.1.1 Roads and Walks |
| 3.2 CLEARING AND GRUBBING |
| 3.2.1 VEGETATION REMOVAL |
| 3.2.2 APPLICATION OF HERBICIDE |
3.3 DISPOSAL OF MATERIALS