09B0015.pdf

PDF 711 KB Posted

Attached to
Port Austin Harbor Walkway, Michigan
Solicitation number
W911XK-09-B-0015
Issued by

About this file

W911XK-09-B-0015 Specifications

View the file

Other files

File Type Posted
Plans.zip ZIP file
Amend 0001 - W911XK-09-B-0015.pdf PDF
FY09 Port Austin Harbor Walkway Repair Sec D MI.zip ZIP file
W911XK-09-B-0015 Port Austin.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Port Austin PTAUST09

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 10 10 REAL ESTATE

01 22 00.00 10 MEASUREMENT AND PAYMENT

01 33 00 SUBMITTAL PROCEDURES

01 35 13.10 SPECIAL PROJECT PROCEDURES

01 35 29 SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 02.00 10 QUALITY CONTROL SYSTEM (QCS)

01 45 04.00 10 CONTRACTOR QUALITY CONTROL

01 57 20.00 20 ENVIRONMENTAL PROTECTION

DIVISION 02 - EXISTING CONDITIONS

02 13 90 SITE PREPARATION

DIVISION 03 - CONCRETE

03 31 01.00 10 CAST-IN-PLACE STRUCTURAL CONCRETE FOR CIVIL WORKS

DIVISION 05 - METALS

05 50 00 HANDRAILS

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 12 17 HOT MIX BITUMINOUS PAVEMENT

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION [01 10 10]

REAL ESTATE

03/01

PART 1 GENERAL

1.1 SUBMITTALS

1.2 REGULATORY REQUIREMENTS

1.2.1 Real Estate Rights

1.2.2 Additional Real Estate Rights

1.3 PROJECT/SITE CONDITIONS

1.3.1 Location and Verification

1.3.2 Survey Markers

1.3.2.1 Semipermanent Markers

1.3.2.2 Temporary Markers

PART 2 PRODUCTS (NOT APPLICABLE)

PART 3 EXECUTION (NOT APPLICABLE)

-- End of Section Table of Contents --

SECTION 01 10 10 Page 1

SECTION [01 10 10]

REAL ESTATE

03/01

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only or as otherwise designated. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section

01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Additional Property Agreements; G-RED.

Copies of any agreements for Contractor-acquired real estate rights for this project shall be furnished before entering thereon.

Certified Survey Results

Furnish a copy of certified results of surveys which verify areas and limits of Contractor-acquired real estate rights.

1.2 REGULATORY REQUIREMENTS

1.2.1 Real Estate Rights

Rights for the use of the Government-furnished property is available, and the general limits of the areas are shown on the drawings. Temporary work and storage area shall be below the Ordinary High Water Mark. Copies of instruments conveying rights are available for inspection in the Engineering, Design & Construction Division, U.S. Army Corps of Engineers, Detroit District, 477 Michigan Avenue, McNamara Building, Detroit, Michigan. Conformance to all applicable requirements of the instruments conveying rights is required. Two (2) copies of each instrument will be furnished to the Contractor. All real estate lakeward of the Ordinary High Water Mark is under Federal jurisdiction and no permit or agreements are necessary for work therein except as specified in SECTION 01 35 13.10, "SPECIAL PROJECT PROCEDURES", Paragraph, "Additional Work Proposed and Not Authorized". No other real estate rights have been obtained by the Government for this project.

SECTION 01 10 10 Page 2

1.2.2 Additional Real Estate Rights

Any additional property agreements and/or real estate rights desired by the Contractor shall be obtained by the Contractor at its own expense. Such agreements shall clearly relieve the Government of any responsibility for damages or liability resulting from the Contractor's use of such grounds.

1.3 PROJECT/SITE CONDITIONS

1.3.1 Location and Verification

It shall be the Contractor's responsibility to accurately locate the limits of all lands utilized under the contract and have said limits verified by a registered surveyor. The certified survey results shall be submitted. The corner and angle points of each area for which rights have been obtained shall be marked with semipermanent markers except where there is an approved existing property marker. Temporary markers shall be placed at points on alignment. The points on alignment shall be marked at stations so that intervals between points do not exceed 200 feet.

1.3.2 Survey Markers

All markers shall be installed in an area prior to its use and they shall be available for reference during and upon completion of use of the area.

Where approved existing property markers are found, a witness stake, as specified in Subparagraph, "Semipermanent Markers" below, shall be provided. If the types of markers specified hereinafter cannot be used, other types, as approved by the Contracting Officer, shall be provided.

1.3.2.1 Semipermanent Markers

The markers shall be a steel rod one-half inch in diameter and four (4) feet long. The steel rod shall be driven vertically into the ground so that the top is flush with the finished ground surface. Each marker shall be witnessed by a 2" x 2" yellow stake extending two (2) feet above the ground surface and driven into the ground until stable, with not less than one (1) foot penetration.

1.3.2.2 Temporary Markers

Markers shall be 2" x 2", red-colored, wood hub stakes driven into the ground until stable (not less than one (1) foot penetration) with two (2) feet projecting above the ground surface. If the period in which temporary markers are to be in place exceeds one (1) construction season, a more permanent type of marker, as approved, shall be provided.

PART 2 PRODUCTS (NOT APPLICABLE)

PART 3 EXECUTION (NOT APPLICABLE)

-- End of Section --

SECTION 01 10 10 Page 3

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00.00 10

MEASUREMENT AND PAYMENT

04/06

PART 1 GENERAL

1.1 SUBMITTALS

1.2 LUMP SUM PAYMENT ITEMS

1.3 UNIT PRICE PAYMENT ITEMS

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

SECTION 01 22 00.00 10 Page 1

SECTION 01 22 00.00 10

MEASUREMENT AND PAYMENT

04/06

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-03 Product Data

Weight Certificates

Submit certified weight certificates for R 200 fill stone.

1.2 LUMP SUM PAYMENT ITEMS

Payment items for the work of this contract for which contract lump sum payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular lump sum or unit price payment item, shall be included in the listed lump sum item most closely associated with the work involved. The lump sum price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

a. "Mobilization and Demobilization" (Item No. 0001)

(1) Payment will be made for costs associated with mobilization and demobilization, as defined in Special Clause PAYMENT FOR

MOBILIZATION AND DEMOBILIZATION.

(2) Unit of measure: lump sum.

b. "Site Preparation" (Item No. 0002)

(1) Payment will be made for costs associated with site preparation, as defined in SECTIONS 02 13 90 SITE PREPARATION and

03 31 01.00 10 CAST-IN-PLACE STRUCTURAL CONCRETE FOR CIVIL WORKS.

(2) Unit of measure: lump sum.

c. "Option-1 Site Preparation" (Item No. 0006)

(1) Payment will be made for costs associated with site preparation, as defined in SECTIONS 02 13 90 SITE PREPARATION and

03 31 01.00 10 CAST-IN-PLACE STRUCTURAL CONCRETE FOR CIVIL WORKS.

SECTION 01 22 00.00 10 Page 2

(2) Unit of measure: lump sum.

1.3 UNIT PRICE PAYMENT ITEMS

Payment items for the work of this contract on which the contract unit price payments will be made are listed in the BIDDING SCHEDULE and described below. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.

d. "Bituminous Surface": First 43 Tons and Over 43 Tons (Item No.

0003)

(1) Payment shall constitute full compensation for the costs associated with the placement of the bituminous surface. All work shall be in accordance with Section 32 12 17 HOT MIX BITUMINOUS

PAVEMENT.

(2) Unit of measure: Tons.

e. "Fill Stone": First 37 Tons and Over 37 Tons (Item No. 0004)

(1) Payment will be made for costs associated with the placement of fill stone under the bituminous surface. All work shall be in accordance with Section 02 13 90 SITE PREPARATION.

(2) Unit of measure: Ton.

f. "Handrail" (Item No. 0005)

(1) Payment shall constitute full compensation for the costs associated with the placement of 390 lineal feet of handrail along bituminous walkway. All work shall be in accordance with SECTIONS 05 50 00, HANDRAILS and 03 31 01.00 10 CAST-IN-PLACE STRUCTURAL

CONCRETE FOR CIVIL WORKS.

(2) Unit of measure: Lineal foot.

g. "Option-1 Bituminous Surface": First 52 Tons and Over 52 Tons (Item No. 0007)

(1) Payment shall constitute full compensation for the costs associated with the placement of the bituminous surface. All work shall be in accordance with Section 32 12 17 HOT MIX BITUMINOUS

PAVEMENT.

(2) Unit of measure: Tons.

h. "Option-1 Fill Stone": First 44 Tons and Over 44 Tons (Item No.

0008)

(1) Payment will be made for costs associated with the placement of fill stone under the bituminous surface. All work shall be in accordance with Section 02 13 90 SITE PREPARATION.

SECTION 01 22 00.00 10 Page 3

(2) Unit of measure: Ton.

i. "Option-1 Handrail" (Item No. 0009)

(1) Payment shall constitute full compensation for the costs associated with the placement of 470 lineal feet of handrail along bituminous walkway. All work shall be in accordance with SECTIONS 05 50 00, HANDRAILS and 03 31 01.00 10 CAST-IN-PLACE STRUCTURAL

CONCRETE FOR CIVIL WORKS.

(2) Unit of measure: Lineal foot.

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

SECTION 01 22 00.00 10 Page 4

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 33 00

SUBMITTAL PROCEDURES

04/06

PART 1 GENERAL

1.1 DEFINITIONS

1.1.1 Submittal

1.1.2 Submittal Descriptions (SD)

1.1.3 Approving Authority

1.1.4 Work

1.2 SUBMITTALS

1.3 SUBMITTAL CLASSIFICATION

1.4 SUBMITTAL REGISTER

1.5 SCHEDULING

1.6 TRANSMITTAL FORM (ENG FORM 4025)

1.7 SUBMITTAL PROCEDURES

1.7.1 Procedures

1.7.2 Deviations

1.8 CONTROL OF SUBMITTALS

1.9 GOVERNMENT APPROVED SUBMITTALS

1.10 INFORMATION ONLY SUBMITTALS

1.11 STAMPS

PART 2 PRODUCTS

PART 3 EXECUTION

SECTION 01 33 00 Page 1

SECTION 01 33 00

SUBMITTAL PROCEDURES

04/06

PART 1 GENERAL

1.1 DEFINITIONS

1.1.1 Submittal

Contract Clauses "FAR 52.236-5, Material and Workmanship," paragraph (b) and "FAR 52.236-21, Specifications and Drawings for Construction," paragraphs (d), (e), and (f) apply to all "submittals."

1.1.2 Submittal Descriptions (SD)

Submittals requirements are specified in the technical sections.

Submittals are identified by SD numbers and titles as follows.

SD-01 Preconstruction Submittals

Certificates of insurance.

Surety bonds.

List of proposed subcontractors.

List of proposed products.

Construction Progress Schedule.

Submittal register.

Schedule of prices.

Health and safety plan.

Work plan.

Quality control plan.

Environmental protection plan.

SD-03 Product Data

Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.

Samples of warranty language when the contract requires extended product warranties.

SD-04 Samples

Fabricated or unfabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.

Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.

Field samples and mock-ups constructed on the project site establish standards by which the ensuring work can be judged. Includes

SECTION 01 33 00 Page 2 assemblies or portions of assemblies which are to be incorporated into the project and those which will be removed at conclusion of the work.

SD-05 Design Data

Design calculations, mix designs, analyses or other data pertaining to a part of work.

SD-06 Test Reports

Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. (Testing must have been within three years of date of contract award for the project.)

Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.

Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.

Investigation reports.

Daily logs and checklists.

Final acceptance test and operational test procedure.

SD-07 Certificates

Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that product, system or material meets specification requirements. Must be dated after award of project contract and clearly name the project.

Document required of Contractor, or of a manufacturer, supplier, installer or subcontractor through Contractor, the purpose of which is to further quality of orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.

Confined space entry permits.

Text of posted operating instructions.

1.1.3 Approving Authority

Office authorized to approve submittal; such as

Area Office Field (AOF) Real Estate Office (REO) Engineering, Design and Construction Office (EDC) Detroit District (LRE)

SECTION 01 33 00 Page 3

1.1.4 Work

As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce submittals, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only or as otherwise designated. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section

01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Submittal register; G AOF

1.3 SUBMITTAL CLASSIFICATION

Submittals are classified as follows:

1.4 SUBMITTAL REGISTER

A submittal register showing items of equipment and materials for which submittals are required by the specifications is included at the end of this section; this list may not be all inclusive and additional submittals may be required. The Contractor shall maintain a submittal register for the project in accordance with Section 01 45 02.00 10 QUALITY CONTROL SYSTEM (QCS). The Government will provide the initial submittal register in electronic format. Thereafter, the Contractor shall maintain a complete list of all submittals, including completion of all data columns. Dates on which submittals are received and returned by the Government will be included in its export file to the Contractor. The Contractor shall track all submittals.

1.5 SCHEDULING

Submittals covering component items forming a system or items that are interrelated shall be scheduled to be coordinated and submitted concurrently. Certifications to be submitted with the pertinent drawings shall be so scheduled. Adequate time (a minimum of ten (10) calendar days exclusive of mailing time) shall be allowed and shown on the register for review and approval. No delay damages or time extensions will be allowed for time lost in late submittals.

1.6 TRANSMITTAL FORM (ENG FORM 4025)

The sample transmittal form (ENG Form 4025) attached to this section shall be used for submitting both Government approved and information only submittals in accordance with the instructions on the reverse side of the form. These forms will be furnished to the Contractor. This form shall be properly completed by filling out all the heading blank spaces and identifying each item submitted. Special care shall be exercised to ensure proper listing of the specification paragraph and/or sheet number of the contract drawings pertinent to the data submitted for each item.

SECTION 01 33 00 Page 4

1.7 SUBMITTAL PROCEDURES

Submittals shall be made as follows:

1.7.1 Procedures

The Government will further discuss detailed submittal procedures with the Contractor at the Preconstruction Conference.

1.7.2 Deviations

For submittals which include proposed deviations requested by the Contractor, the column "variation" of ENG Form 4025 shall be checked. The Contractor shall set forth in writing the reason for any deviations and annotate such deviations on the submittal. The Government reserves the right to rescind inadvertent approval of submittals containing unnoted deviations.

1.8 CONTROL OF SUBMITTALS

The Contractor shall carefully control his procurement operations to ensure that each individual submittal is made on or before the Contractor scheduled submittal date shown on the approved "Submittal Register."

1.9 GOVERNMENT APPROVED SUBMITTALS

Upon completion of review of submittals requiring Government approval, the submittals will be identified as having received approval by being so stamped and dated. One (1) copy of the submittal will be retained by the Contracting Officer and one (1) copy of the submittal will be returned to the Contractor.

1.10 INFORMATION ONLY SUBMITTALS

Normally submittals for information only will not be returned. Approval of the Contracting Officer is not required on information only submittals.

The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work;

and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.

1.11 STAMPS

Stamps used by the Contractor on the submittal data to certify that the submittal meets contract requirements shall be similar to the following:

SECTION 01 33 00 Page 5

| CONTRACTOR |

| (Firm Name) | | _____ Approved | | _____ Approved with corrections as noted on submittal data and/or | | attached sheets(s). |

| SIGNATURE: __________________________________________________________ |

| TITLE: ______________________________________________________________ |

| DATE: _______________________________________________________________ |

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 33 00 Page 6

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 1 OF 3 PAGES

Port Austin

01 10 10 SD-01 Preconstruction Submittals

1.2.2 G REDAdditional Property Agreements

1.3.1Certified Survey Results

01 22 00.00 10 SD-03 Product Data Weight Certificates

01 33 00 SD-01 Preconstruction Submittals G AOFSubmittal register

01 35 13.10 SD-01 Preconstruction Submittals

1.7.1 G AOFAccident Prevention Plan

1.7.2Payrolls and Basic Records

1.7.3 G AOFProgress Chart

1.4.2Notice to Mariners 1.4.3utility locating plan 1.4.3utility location findings 1.4.9Traffic Control Plan 1.4.12.2Survey Note Format 1.4.11.1Buoy Relocation Position 1.4.12.2Survey Information

01 35 29 SD-01 Preconstruction Submittals

1.6 G AOFAccident Prevention Plan (APP)

1.7 G AOFActivity Hazard Analysis (AHA)

1.6.1 G AOFCrane Critical Lift Plan

1.5.1.3 G AOFCrane Operators

SD-06 Test Reports 1.11Reports 1.11.1Accident Reports

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P H

C L A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 2 OF 3 PAGES

01 35 29 1.11.3Monthly Exposure Reports 1.11.4Crane Reports

Regulatory Citations and Violations

SD-07 Certificates 1.8Confined Space Entry Permit 1.8Hot work permit

G AOFContractor Safety Self-Evaluation Checklist

1.11.5Certificate of Compliance 01 45 04.00 10 SD-01 Preconstruction Submittals

G AOFContractor Quality Control Plan 01 57 20.00 20 SD-01 Preconstruction Submittals

1.5 G AOFEnvironmental Protection Plan

02 13 90 SD-01 Preconstruction Submittals

Construction Equipment Check Survey Records

03 31 01.00 10 SD-01 Preconstruction Submittals Batching and Mixing Equipment Conveying and Placement Equipment

SD-06 Test Reports G AOFConcrete Mixture Proportions

SD-07 Certificates G AOFCementitious Material G AOFAggregates

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 3 OF 3 PAGES

03 31 01.00 10 G AOFManufacturer's Literature 05 50 00 SD-04 Samples

G AOFHandrails SD-07 Certificates

G AOFMill Reports Welders

32 12 17 SD-04 Samples Bituminous pavement

SD-05 Design Data

2.2ASPHALT CEMENT BINDER

2.2ASPHALT CEMENT BINDER

2.4MIX DESIGN

2.4MIX DESIGN

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 35 13.10

SPECIAL PROJECT PROCEDURES

03/01

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 REGULATORY REQUIREMENTS

1.3.1 Additional Work Proposed and Not Authorized

1.3.1.1 Work Subject to 33 CFR 320-330

1.3.1.2 Work Subject to 40 CFR 233

1.4 PROJECT/SITE CONDITIONS

1.4.1 Condition and Use of Project Site

1.4.1.1 Physical Conditions

1.4.2 Waterways Navigation and Traffic

1.4.2.1 Navigation

1.4.2.2 Traffic

1.4.3 Existing Vegetation, Structures, Equipment, Utilities &

Improvements

1.4.4 Vehicular Access

1.4.5 Utility Services

1.4.5.1 Contractor-Furnished Utility Services

1.4.6 Identification of Employees

1.4.7 Security Requirements and Clearance of Personnel

1.4.7.1 Security Regulations

1.4.7.2 Security Checks

1.4.7.3 Loitering

1.4.8 Contract Supervision and Representation

1.4.9 Traffic Control Plan

1.4.10 Temporary Lights, Signals and Buoys Required by Coast Guard

1.4.11 Navigation Buoys

1.4.11.1 Relocation of Existing Buoys

1.4.11.2 Temporary Dredging and Construction Buoys

1.4.11.3 Buoy Markings

1.4.12 Layout of Work and Surveys

1.4.12.1 Layout of Work

1.4.12.2 Surveyor Requirements

1.4.12.3 Suspension

1.4.12.4 Verification

1.5 SEQUENCING AND SCHEDULING

1.5.1 Exclusion of Period in Computing Completion Schedules

1.5.2 Sunday, Holiday And Night Operations

1.5.3 Work Period Restrictions

1.5.4 Start Work

1.6 PRESERVATION OF HISTORICAL, ARCHAEOLOGICAL AND CULTURAL RESOURCES

1.7 REPORT REQUIREMENTS

1.7.1 Accident Prevention Plan

1.7.2 Payrolls and Basic Records

1.7.3 Progress Chart

PART 2 PRODUCTS (NOT APPLICABLE)

SECTION 01 35 13.10 Page 1

PART 3 EXECUTION (NOT APPLICABLE)

SECTION 01 35 13.10 Page 2

SECTION 01 35 13.10

SPECIAL PROJECT PROCEDURES

03/01

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. GOVERNMENT CODE OF FEDERAL REGULATIONS (CFR)

33 CFR 320-330 General Regulatory Policies, Permits, Enforcement and Definitions

40 CFR 233 State Program Regulations

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only or as otherwise designated. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section

01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Accident Prevention Plan; G-AOF

Contractor shall provide an accident prevention plan including an activity hazard analysis to the Contracting Officer within 15 calendar days after receipt of award. Safety Management System information can be submitted in lieu of the Accident Prevention Plan in accordance with the Contract Clause for Dredging and Dredge Related Marine Work.

Payrolls and Basic Records

Contractor shall submit payrolls and basic records in accordance with the CLAUSE entitled "PAYROLLS AND BASIC RECORDS (FEB 1988)".

Progress Chart; G-AOF

Contractor shall submit progress chart in accordance with the Contract clause entitled "SCHEDULE FOR CONSTRUCTION CONTRACTS (APR 1984)".

Notice to Mariners

A copy of the completed "NOTICE TO MARINERS" form shall be provided prior to the commencement of work.

SECTION 01 35 13.10 Page 3 utility locating plan utility location findings

Submit a plan of the proposed procedure for locating existing utilities prior to commencing work at the project site. Also submit a copy of the utility location findings prior to commencing work on the site.

Traffic Control Plan

At least fifteen (15) calendar days prior to commencing work at the site, submit a detailed, site specific plan for the control of traffic on the public roadways adjacent to the work area. Coordination of construction traffic with public use of the roadways shall be fully described, including all safety related characteristics.

Survey Note Format

Submit the proposed survey note format prior to performing any survey work at the work site.

Buoy Relocation Position

Immediately upon relocating any U.S. Coast Guard buoys the Contractor shall report their position by latitude and longitude in writing.

Survey Information

Upon completion of the contract work, the originals of all field notes, sketches, recordings and computations made by the Contractor in performing the layout work shall be submitted in ring binders.

1.3 REGULATORY REQUIREMENTS

1.3.1 Additional Work Proposed and Not Authorized

1.3.1.1 Work Subject to 33 CFR 320-330

Any additional work (not specifically shown on the plans or delineated in the specifications) proposed by the Contractor in or affecting navigable waters, including wetlands (as defined in 33 CFR 320-330, published in the Federal Register Vol.51, No. 219, Thursday, November 13, 1986) shall not be performed without a Department of the Army Permit. This requirement shall be applicable to all work, permanent or temporary, and/or fill(s).

The Department of the Army Permit shall be approved by the District Engineer or Deputy District Engineer in accordance with the laws of the United States and the regulations promulgated thereunder, including, but not limited to, the River and Harbor Act of 1899, the Clean Water Act and the National Environmental Policy Act of 1969, as amended. Corps employees (Contracting Officer's Representatives (COR) or inspectors) are not delegated authority to authorize such work. Information on making application for such permit(s) may be obtained by contacting one of the offices as listed hereinafter. When applying for information or a permit, a copy of any correspondence should be directed to the Contracting Officer of this contract. If a permit is not obtained, the additional work cannot be accomplished. Any delay in processing the permit will not constitute the basis of a claim under this contract. The fact that the Contractor is performing work under a Department of the Army Contract will give the

SECTION 01 35 13.10 Page 4

Contractor no greater rights than any other applicant for a Department of the Army Permit.

MICHIGAN-INDIANA

Regulatory Branch Engineering and Technical Services Division U.S. Army Engineer District, Detroit P. O. Box 1027 Detroit, MI 48231 Telephone: 313-226-6813

1.3.1.2 Work Subject to 40 CFR 233

Any additional work (not specifically shown on the plans or included in the specifications), proposed by the Contractor, in or affecting waters of the United States, including wetlands, in the State of Michigan (as defined in 40 CFR 233, published in the Federal Register, Vol. 49 No. 192, Tuesday October 2, 1984) shall not be performed without a State of Michigan regulatory permit. Information on making an application for such permit may be obtained by contacting the office listed hereinafter. When applying for a permit or for information, a copy of any correspondence shall be furnished to the Contracting Officer. If a permit is not obtained, the additional work shall not be performed. Any delay in obtaining or processing the permit will not constitute a basis for a claim under this contract.

STATE OF MICHIGAN

Department of Environmental Quality Land & Water Management Division P.O. Box 30458 Constitution Hall Lansing, MI 48909 Telephone: 517-373-1170

1.4 PROJECT/SITE CONDITIONS

1.4.1 Condition and Use of Project Site

The Contractor shall be responsible for damages that may be suffered due to its operations. The Contractor shall note CLAUSE titled "PROTECTION OF

EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS."

1.4.1.1 Physical Conditions

The physical conditions shown on the drawings are indicative of those that prevailed at the time of the site investigations and may be different than those at the time of construction. Significant variations that would require changes to the plans or specification shall be reported to the Contracting Officer immediately.

1.4.2 Waterways Navigation and Traffic

The Contractor shall acquaint itself with all information and regulations pertaining to navigation and vessel traffic within the waterways at the project site. The Contractor shall coordinate with the U.S. Coast Guard to assure that a "NOTICE TO MARINERS" is issued prior to its work activity at the project site. The completed form shall be sent to the address stated

SECTION 01 35 13.10 Page 5 in the Subparagraph entitled "Temporary Lights, Signals and Buoys Required by U.S. Coast Guard". The Government will not undertake to keep the waterways free from vessels or other obstructions, except to the extent of such regulations, if any, as may be prescribed by the Secretary of the Army, in accordance with the provisions of Section 7 of the River and Harbor Act approved 8 August 1917 (see Title 33, U.S.C.A. Sec. 1). The Contractor is required to conduct its work in such manner as to obstruct navigation as little as possible and, in case the Contractor's plant so obstructs a channel as to make difficult or endanger the passage of vessels, said plant shall be promptly moved on the approach of any vessel to such an extent as may be necessary to afford a practicable passage.

Upon completion of the work, the Contractor shall promptly remove its plant, including ranges, buoys, piles, and other marks placed by it under the contract in navigable waters or on shore.

1.4.2.1 Navigation

Information and regulations pertaining to navigation may be obtained from the current issue of the "UNITED STATES COAST PILOT 6," issued annually by the Department of Commerce, National Oceanic and Atmospheric Administration (NOAA). The "UNITED STATES COAST PILOT" may be obtained from National Ocean Survey, NOAA, Distribution Division-C44, Riverdale, Maryland 20840.

1.4.2.2 Traffic

Vessels that may use the waterways at the project site consist of recreational craft and commercial vessels. This traffic may interfere with contract operations and the Contractor shall conduct its work with due regard to and in coordination with the requirements of all navigation.

Information regarding the types and amount of passages made by commercial vessels that may use the waterways at the project site may be obtained from the current issue of the "Waterborne Commerce of the United States, Part 3, Waterways and Harbors, Great Lakes," published by the Department of Army, Corps of Engineers. The Department of the Army publication may be obtained at no charge from the following:

District Engineer, U.S. Army Engineer District, New Orleans, Waterborne Commerce Section, P.O. Box 60267, New Orleans, Louisiana 70160. Phone

504-862-1425, FAX 504-862-1091.

1.4.3 Existing Vegetation, Structures, Equipment, Utilities & Improvements

General locations of applicable existing utilities, vegetation, structures, equipment and improvements, based upon latest information available to the Government have been shown on the drawings. However, it is the Contractor's obligation to establish the exact horizontal and vertical location and size of all existing utility lines which are located within the required work area. The Contractor shall submit a utility locating plan for locating existing utilities and a copy of its utility location findings prior to commencing work on the site. Any utility lines which are not found by the Contractor, but which are known to exist at the project site, shall be reported to the Contracting Officer immediately. The Contracting Officer will have the option of directing commencement of work at the site or requiring the Contractor to submit further plans for locating the

SECTION 01 35 13.10 Page 6 utility lines. Once the utilities have been located and marked, the Contractor shall be deemed to have the location made known to it pursuant to CLAUSE titled "PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS." If the Contractor damages any existing utility line, vegetation, structure, equipment or improvement, a report thereof shall be made immediately to the Contracting Officer. In any event, existing utility lines, vegetation, structures, equipment or improvements shall be protected from damage, and if damaged, shall be repaired by the Contractor at its own expense.

1.4.4 Vehicular Access

Throughout the period of work on this contract, the Contractor shall maintain an all-weather roadway through or around its work area when work therein would otherwise block an existing roadway. Such permanent or temporary roadways shall be kept open for use by emergency vehicles, as well as residential and commercial traffic at all times.

1.4.5 Utility Services

1.4.5.1 Contractor-Furnished Utility Services

The Contractor shall furnish, all water, electric current and other utilities required for its use.

1.4.6 Identification of Employees

The Contractor shall be responsible for requiring each employee engaged on the work to wear a hardhat with labeling as required to identify that the person is an employee of the Contractor or to display other identification as may be approved.

1.4.7 Security Requirements and Clearance of Personnel

1.4.7.1 Security Regulations

The Contractor shall acquaint itself with the prevailing security rules and regulations and comply therewith in conducting its operations.

1.4.7.2 Security Checks

All personnel employed by the Contractor in the performance of the services specified in this contract or any representative of the Contractor entering the work area shall conform to all security regulations and rules which may be in effect during the contract period and will be subject to such checks as may be deemed necessary to ensure that no violations occur. The Contractor shall furnish a list of all employees who will be on the site and their work hours. The Contractor shall keep this list current.

Employees not on the list may be denied access to the facility.

1.4.7.3 Loitering

Contractor personnel shall not loiter in or around the place of duty during

SECTION 01 35 13.10 Page 7 off-duty hours. Upon completion of assigned duty, employees shall depart the grounds.

1.4.8 Contract Supervision and Representation

The Contractor's local representative shall be available to Government representatives during duty hours, 8 a.m. to 4:30 p.m., on normal working days and shall be available by telephone at other times. The name of the Contractor's representative and the contact telephone number shall be furnished to the Government.

1.4.9 Traffic Control Plan

The Contractor shall control traffic in accordance with its approved plan.

1.4.10 Temporary Lights, Signals and Buoys Required by Coast Guard

All temporary lights, signals and buoys required by the U.S. Coast Guard must be displayed during the required work. Information regarding required signals, lights, buoys and other requirements may be obtained from the Commander (oan), Ninth Coast Guard District, 1240 East Ninth Street, Cleveland, Ohio 44199-2060, Telephone (216) 522-3990.

1.4.11 Navigation Buoys

1.4.11.1 Relocation of Existing Buoys

If the relocation of existing navigation buoys is required to perform the contract work, the Contractor shall request permission for their relocation from the U.S. Coast Guard through the Contracting Officer. Once relocated, a record shall be maintained of the buoy relocation position(s). The request shall be provided to the Contracting Officer not less than three

(3) weeks prior to need of the buoy relocation. The Contractor shall be responsible for performing the relocation work, which shall be in accordance with U.S. Coast Guard requirements.

1.4.11.2 Temporary Dredging and Construction Buoys

In order to distinguish temporary buoys placed and maintained by the Contractor for dredging or construction purposes from aids to navigation placed by the U.S. Coast Guard, the Contractor's buoys shall be white and the top two (2) feet shall be light green in color. The Contractor shall remove its temporary buoys at the completion of the work.

1.4.11.3 Buoy Markings

If buoys with special markings are needed to indicate the different sides of the navigable channel, prior arrangements shall be made with the U.S.

Coast Guard, through the Contracting Officer.

1.4.12 Layout of Work and Surveys

1.4.12.1 Layout of Work

The following requirements are in addition to the requirements of CLAUSE titled "LAYOUT OF WORK, (IGLD 1985)." The Government has established bench marks and horizontal control points at the site of the work. Horizontal

SECTION 01 35 13.10 Page 8 control points and descriptions of bench marks are shown on the drawings.

The elevations of bench marks are referred to mean water level (IGLD 1955).

1.4.12.2 Surveyor Requirements

From these control points and bench marks, the Contractor shall lay out the work by establishing all lines, grades, range markers and gauges at the site as necessary to control the work. All survey information shall be recorded in accordance with standard and approved methods and in the survey note format approved by the Contracting Officer. All field notes, sketches, recordings and computations made by the Contractor in performing the layout work shall be available at all times during the progress of the work for ready examination by the Contracting Officer or his or her duly authorized representative and upon completion of the contract work the originals shall be turned over to the Contracting Officer in ring binders.

1.4.12.3 Suspension

The Contracting Officer may require that work be suspended at any time when location and limit marks established by the Contractor are not reasonably adequate to permit checking the work. Such suspension will be withdrawn upon satisfactory replacement of location and limit marks. Such suspension shall be at no additional cost to the Government and shall not entitle the Contractor to an extension of time for completing the work.

1.4.12.4 Verification

The Government may make checks as the work progresses to verify lines and grades established by the Contractor and to determine the conformance of the completed work as it progresses with the requirements of contract specifications and drawings. Such checking by the Contracting Officer or his or her representative shall not relieve the Contractor of its responsibility to perform all work in accordance with the contract drawings and specifications and the lines and grades given therein.

1.5 SEQUENCING AND SCHEDULING

1.5.1 Exclusion of Period in Computing Completion Schedules

No work will be required during the period between 01 December and 01 April inclusive and the days in this period will not be counted when computing the required completion date. The Contractor may perform work, unless otherwise prohibited, during all or any part of this period upon giving prior written notice to the Contracting Officer.

1.5.2 Sunday, Holiday And Night Operations

When the Contractor elects to work more than 8 hours per day, Monday through Friday and Saturdays, Sundays, holidays or nights when not prohibited herein, notice of its intention to do so shall be given to the Contracting Officer not less than forty-eight (48) hours in advance thereof. Adequate lighting for thorough inspection of night operations shall be provided by the Contractor at its expense.

SECTION 01 35 13.10 Page 9

1.5.3 Work Period Restrictions

No work is allowed at the project sites during the following periods:

c. Holiday periods as follows:

(1) 6 p.m. 22 May to 6 a.m. 26 May 2009

(2) 6 p.m. 2 July to 6 a.m. 6 July 2009

(3) 6 p.m. 4 September to 6 a.m. 8 September 2009

(4) 6 p.m. 25 November to 6 a.m. 30 November 2009

(5) 6 p.m. 23 December to 6 a.m. 02 January 2010

The above-stated no-work periods, as applicable, are included in the number of calendar days within which the Contractor is required to complete the work as established in CLAUSE titled "COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK" and therefore the above-stated no-work periods will not entitle the Contractor to additional time for completing the work.

1.5.4 Start Work

Evidence that the Contractor has started mobilization and preparation of submittal register, and other preparatory work will satisfy the requirement that work commence within ten (10) calendar days after receipt of Notice to Proceed. (See Clause titled COMMENCEMENT, PROSECUTION, AND COMPLETION OF

WORK, FAR 52.212-0003.)

1.6 PRESERVATION OF HISTORICAL, ARCHAEOLOGICAL AND CULTURAL RESOURCES

If, during construction activities, the Contractor observes items that may have archaeological, historical or cultural value, such observations shall be reported immediately to the Contracting Officer so that the appropriate authorities may be notified and a determination can be made as to their significance and what, if any, special disposition of the funds should be made. The Contractor shall cease all activities that may result in the destruction of these resources and shall prevent its employees from trespassing on, removing, or otherwise damaging such resources.

1.7 REPORT REQUIREMENTS

1.7.1 Accident Prevention Plan

Contractor shall provide an accident prevention plan including an activity hazard analysis to the Contracting Officer within 15 calendar days after receipt of award. Plan shall be in accordance with Contract Clause entitled "ACCIDENT PREVENTION (NOV 1991) - ALTERNATE 1.

1.7.2 Payrolls and Basic Records

Contractor shall submit payrolls and basic records in accordance with the CLAUSE entitled "PAYROLLS AND BASIC RECORDS (FEB 1988)".

SECTION 01 35 13.10 Page 10

1.7.3 Progress Chart

Contractor shall submit progress chart in accordance with the Contract clause entitled "SCHEDULE FOR CONSTRUCTION CONTRACTS (APR 1984)".

PART 2 PRODUCTS (NOT APPLICABLE)

PART 3 EXECUTION (NOT APPLICABLE)

SECTION 01 35 13.10 Page 11

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 35 29

SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTS

01/07

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 DEFINITIONS

1.4 REGULATORY REQUIREMENTS

1.5 SITE QUALIFICATIONS, DUTIES AND MEETINGS

1.5.1 Personnel Qualifications

1.5.1.1 Site Safety and Health Officer (SSHO)

1.5.1.2 Competent Person for Confined Space Entry

1.5.1.3 Crane Operators

1.5.2 Personnel Duties

1.5.2.1 Site Safety and Health Officer (SSHO)/Superintendent

1.5.3 Meetings

1.5.3.1 Preconstruction Conference

1.5.3.2 Safety Meetings

1.6 ACCIDENT PREVENTION PLAN (APP)

1.6.1 EM 385-1-1 Contents

1.7 ACTIVITY HAZARD ANALYSIS (AHA)

1.8 DISPLAY OF SAFETY INFORMATION

1.9 SITE SAFETY REFERENCE MATERIALS

1.10 EMERGENCY MEDICAL TREATMENT

1.11 REPORTS

1.11.1 Accident Reports

1.11.2 Accident Notification

1.11.3 Monthly Exposure Reports

1.11.4 Crane Reports

1.11.5 Certificate of Compliance

1.12 HOT WORK

PART 2 PRODUCTS

PART 3 EXECUTION

3.1 CONSTRUCTION AND/OR OTHER WORK

3.1.1 Hazardous Material Exclusions

3.1.2 Unforeseen Hazardous Material

3.2 PRE-OUTAGE COORDINATION MEETING

3.3 FALL HAZARD PROTECTION AND PREVENTION PROGRAM

3.3.1 Training

3.3.2 Fall Protection Equipment and Systems

3.3.2.1 Personal Fall Arrest Equipment

3.3.3 Fall Protection for Roofing Work

3.3.4 Existing Anchorage

3.3.5 Horizontal Lifelines

SECTION 01 35 29 Page 1

3.3.6 Guardrails and Safety Nets

3.3.7 Rescue and Evacuation Procedures

3.4 SCAFFOLDING

3.5 EQUIPMENT

3.5.1 Material Handling Equipment

3.5.2 Weight Handling Equipment

3.6 EXCAVATIONS

3.6.1 Utility Locations

3.6.2 Utility Location Verification

3.6.3 Shoring Systems

3.6.4 Trenching Machinery

3.7 UTILITIES WITHIN CONCRETE SLABS

3.8 ELECTRICAL

3.8.1 Conduct of Electrical Work

3.8.2 Portable Extension Cords

3.9 WORK IN CONFINED SPACES

SECTION 01 35 29 Page 2

SECTION 01 35 29

SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTS

01/07

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)

ANSI A10.32 Personal Fall Protection - Safety Requirements for Construction and Demolition Operations

ANSI Z359.1 (1992; R 1999) Safety Requirements for Personal Fall Arrest Systems, Subsystems and Components

ANSI/ASSE A10.34 (2001) Protection of the Public on or Adjacent to Construction Sites

ASME INTERNATIONAL (ASME)

ASME B30.22 (2005) Articulating Boom Cranes

ASME B30.3 (1996) Construction Tower Cranes

ASME B30.5 (2004) Mobile and Locomotive Cranes

ASME B30.8 (2004) Floating Cranes and Floating Derricks

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 10 (2002) Portable Fire Extinguishers

NFPA 241 (2004) Safeguarding Construction,Alteration, and Demolition Operations

NFPA 51B (2003) Fire Prevention During Welding, Cutting, and Other Hot Work

NFPA 70 (2005) National Electrical Code

NFPA 70E (2004) Electrical Safety in the Workplace

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2008) Safety -- Safety and Health Requirements

SECTION 01 35 29 Page 3

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

29 CFR 1910.146 Permit-required Confined Spaces

29 CFR 1926 Safety and Health Regulations for Construction

29 CFR 1926.500 Fall Protection

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

Government acceptance is required for submittals with a "G" designation.

SD-01 Preconstruction Submittals

Accident Prevention Plan (APP); G-AOF

Activity Hazard Analysis (AHA); G-AOF

Crane Critical Lift Plan; G-AOF

Proof of qualification for Crane Operators; G-AOF

SD-06 Test Reports

Reports

Submit reports as their incidence occurs, in accordance with the requirements of the paragraph entitled, "Reports."

Accident Reports

Monthly Exposure Reports

Crane Reports

Regulatory Citations and Violations

SD-07 Certificates

Confined Space Entry Permit

Hot work permit

Contractor Safety Self-Evaluation Checklist; G-AOF

Certificate of Compliance (Crane)

1.3 DEFINITIONS

a. Competent Person for Fall Protection. A person who is capable of identifying hazardous or dangerous conditions in the personal fall

SECTION 01 35 29 Page 4 arrest system or any component thereof, as well as their application and use with related equipment, and has the authority to take prompt corrective measures to eliminate the hazards of falling.

b. High Visibility Accident. Any mishap which may generate publicity and/or high visibility.

c. Medical Treatment. Treatment administered by a physician or by registered professional personnel under the standing orders of a physician. Medical treatment does not include first aid treatment even through provided by a physician or registered personnel.

d. Recordable Injuries or Illnesses. Any work-related injury or illness that results in:

(1) Death, regardless of the time between the injury and death, or the length of the illness;

(2) Days away from work (any time lost after day of injury/illness onset);

(3) Restricted work;

(4) Transfer to another job;

(5) Medical treatment beyond first aid;

(6) Loss of consciousness; or

(7) A significant injury or illness diagnosed by a physician or other licensed health care professional, even if it did not result in (1) through (6) above.

e. "USACE" property and equipment specified in USACE EM 385-1-1 should be interpreted as Government property and equipment.

1.4 REGULATORY REQUIREMENTS

In addition to the detailed requirements included in the provisions of…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .