Bid Schedule To Complete and Return with Bid Package
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid_Abstract.xlsx | XLSX spreadsheet | |
| Bid_Results.pdf | ||
| W911WN18B8004-0002.pdf | ||
| AO37_LCH_0-121-A.pdf | ||
| AO37_LCH_11-050-A.pdf | ||
| 01_35_00.00_08.pdf | ||
| W911WN18B8004-0001.pdf | ||
| Constracting_Discussion_and_Agenda,_Site_Visit,_7-13-18.pdf | ||
| Sign-In_Sheet,_Attendees,_Site_Visit,_7-13-18.pdf | ||
| Attachment_3,_Wage_Determination,_PA180004_06-15-2018_PA4.pdf | ||
| Attachment_2,_Drawings_Certified_Final,_April_2018.pdf | ||
| Attachment_1,_Technical_Specifications,_Certified_Final,_April_2018.pdf | ||
| W911WN18B8004.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Price Schedule
| BID SCHEDULE | |||||
| ITEM | DESCRIPTION | Quantity | Unit | Unit Price | Total |
| BASE CONTRACT | |||||
| 0001 | REIMBURSEMENT FOR ACTUAL PERFORMANCE AND PAYMENT BOND PREMIUMS, BASE CONTRACT | 1 | JOB | $________ | $________ |
| 0002 | MOBILIZATION AND DEMOBILIZATION | 1 | JOB | $________ | $________ |
| 0003 | DIGITAL PROGRESS IMAGES | 33 | SETS | $________ | $________ |
| 4 | REMOVAL AND PLACEMENT EXISTING TRAINING DIKE STONE | 14,300 | CUBIC YARDS | $________ | $________ |
| 5 | REMOVAL AND PLACEMENT OF DERRICK STONE | 11,200 | CUBIC YARDS | $________ | $________ |
| 6 | UNDERWATER ALLUVIUM EXCAVATION FOR SCOUR PROTECTION, ABUTMENT PROTECTION WALL AND ABUTMENT PROTECTION GROUT BAGS | 32,300 | CUBIC YARDS | $________ | $________ |
| 0007 | SAMPLING AND TESTING AREA "C" | 1 | JOB | $________ | $________ |
| 0008 | DREDGING, AREA "C" | 13,630 | CUBIC YARDS | $________ | $________ |
| 0009 | DREDGING, DOWNSTREAM FLOODWAY AND APPROACH | 137,830 | CUBIC YARDS | $________ | $________ |
| 0010 | DISPOSAL OF CONTAMINATED DREDGED MATERIAL | 13,630 | CUBIC YARDS | $________ | $________ |
| 0011 | ABUTMENT PROTECTION WALL DEMONSTRATION PROJECT | 1 | JOB | $________ | $________ |
| 0012 | SCOUR PROTECTION DEMONSTRATION PROJECT | 1 | JOB | $________ | $________ |
| 0013 | ABUTMENT PROTECTION WALL, 48-INCH DIAMETER BY 1/2-INCH THICK PIPE PILE | 1,140 | LINEAR FEET | $________ | $________ |
| 14 | ABUTMENT PROTECTION WALL, PZC 18 METAL SHEET PILING | 2,280 | LINEAR FEET | $________ | $________ |
| 15 | ABUTMENT PROTECTION WALL, HP12x53 END PILE | 30 | LINEAR FEET | $________ | $________ |
| 16 | ABUTMENT PROTECTION WALL, W33x291 KING PILES 1 to 21 | 21 | EACH | $________ | $________ |
| 17 | ABUTMENT PROTECTION WALL, W33x291 KING PILES 22 to 28 | 17 | EACH | $________ | $________ |
| 18 | ABUTMENT PROTECTION WALL PIPE PILE, ALLUVIUM EXCAVATION | 950 | LINEAR FEET | $________ | $________ |
| 0019 | ABUTMENT PROTECTION WALL, 42-INCH DIAMETER ROCK SOCKET | 988 | LINEAR FEET | $________ | $________ |
| 0020 | ABUTMENT PROTECTION WALL, CONCRETE FOR CAST-IN-PLACE CONCRETE PILES | 836 | CUBIC YARDS | $________ | $________ |
| 0021 | ABUTMENT PROTECTION, BEDDING MATERIAL | 170 | CUBIC YARDS | $________ | $________ |
| 0022 | ABUTMENT PROECTION, GEOGRID REINFORCEMENT | 910 | SQUARE YARDS | $________ | $________ |
| 0023 | ABUTMENT PROTECTION, FURNISH AND INSTALL GROUT BAGS WITH ACCESSORIES AND GROUT INFILL | 1,365 | CUBIC YARDS | $________ | $________ |
| 0024 | SCOUR PROTECTION, BEDDING MATERIAL | 2355 | CUBIC YARDS | $________ | $________ |
| 0025 | SCOUR PROTECTION, GEOGRID REINFORCEMENT | 4,710 | SQUARE YARDS | $________ | $________ |
| 0026 | SCOUR PROTECTION, FURNISH AND INSTALL GROUT BAGS WITH ACCESSORIES AND GROUT INFILL | 6,275 | CUBIC YARDS | $________ | $________ |
| 0027 | SCOUR PROTECTION, APRON TIE-IN ELEMENT | 302 | CUBIC YARDS | $________ | $________ |
| 0028 | SCOUR PROTECTION, TEMPORARY TERMINATION | 2 | EACH | $________ | $________ |
| 0029 | INSTRUMENTATION | 1 | JOB | $________ | $________ |
| TOTAL, BASE CONTRACT, ITEMS 0001 THROUGH 0029 | $________ | ||||
| AWARDABLE OPTION | |||||
| 1001 | REIMBURSEMENT FOR ACTUAL PERFORMANCE AND PAYMENT BOND PREMIUMS, BASE CONTRACT | 1 | JOB | $________ | $________ |
| 1002 | DREDGING, UPSTREAM FLOODWAY AND APPROACH | 81,840 | CUBIC YARDS | $________ | $________ |
| TOTAL, AWARDABLE CONTRACT, ITEMS 1001 AND 1002 | $________ |