Sheet1
| ITEM NO. | SUPPLIES/SERVICES | QUANTITY | UNIT | UNIT PRICE | AMOUNT | |
| BASE BID | ||||||
| 0001 | Reimbursement For Actual Performance And Payment Bond Premiums | 1 | JOB | XXXXXXXX | $ | |
| 0002 | Digital Progress Images | 12 | EA | __________ | $ | |
| Land Wall Vertical Concrete Resurfacing - STA. 0+63.95B to STA. 0+94.02B and STA. 4+03.79B to STA. 4+27.77B (CLINS 0003 through 0010) | ||||||
| 0003 | Kevel Rail Concrete Removal | 67 | SF | __________ | $ | |
| 0004 | Shotcrete Concrete Removal | 507 | SF | __________ | $ | |
| 0005 | Concrete Anchors | 244 | EA | __________ | $ | |
| 0006 | Concrete Reinforcement, Steel Bars | 137 | LB | __________ | $ | |
| 0007 | Concrete Reinforcement, Welded Wire Fabric | 306 | SF | __________ | $ | |
| 0008 | Concrete Placement | 5 | CY | __________ | $ | |
| 0009 | Shotcrete | 11 | CY | __________ | $ | |
| 0010 | Armor | 1,180 | LB | __________ | $ | |
| Land Wall Vertical Concrete Resurfacing - STA. 0+94.02B to STA. 4+03.79B (CLINS 0011 through 0028) | ||||||
| 0011 | Shoring and Bracing of Gallery | 1 | JOB | XXXXXXXX | $ | |
| 0012 | Protection of Existing Hydraulic Pipe Trench | 1 | JOB | XXXXXXXX | $ | |
| 0013 | Kevel Rail Concrete Removal | 797 | SF | __________ | $ | |
| 0014 | Precast Wall Unit Concrete Removal | 5,729 | SF | __________ | $ | |
| 0015 | Precast Mooring Hook and Ladder Unit Concrete Removal | 272 | SF | __________ | $ | |
| 0016 | Checkposts Concrete Removal | 102 | SF | __________ | $ | |
| 0017 | Concrete Anchors | 1,250 | EA | __________ | $ | |
| 0018 | Concrete Reinforcement, Steel Bars | 4,208 | LB | __________ | $ | |
| 0019 | Precast Wall Units | 1 | JOB | XXXXXXXX | $ | |
| 0020 | Precast Line Hook Unit | 1 | EA | __________ | $ | |
| 0021 | Precast Ladder Unit | 1 | EA | __________ | $ | |
| 0022 | Infill Concrete | 225 | CY | __________ | $ | |
| 0023 | Checkposts | 4 | EA | __________ | $ | |
| 0024 | Concrete Placement | 93 | CY | __________ | $ | |
| 0025 | Armor | 15,229 | LB | __________ | $ | |
| 0026 | Remove and Reinstall Subbase Material | 1 | JOB | XXXXXXXX | $ | |
| 0027 | Concrete Slab Replacement | 1 | JOB | XXXXXXXX | $ | |
| 0028 | Non-Shrink Grout | 31 | CF | __________ | $ | |
| Land Wall Vertical Resurfacing - STA. 4+47.84B to STA. 4+61.42B (CLINS 0029 to 0034) | ||||||
| 0029 | Remove and Reinstall Air Piping | 1 | JOB | XXXXXXXX | $ | |
| 0030 | Protection of Existing Hydraulic / Air Piping | 1 | JOB | XXXXXXXX | $ | |
| 0031 | Vertical Concrete Removal | 784 | SF | __________ | $ | |
| 0032 | Concrete Anchors | 235 | EA | __________ | $ | |
| 0033 | Concrete Reinforcement, Steel Bars | 1,163 | LB | __________ | $ | |
| 0034 | Concrete Placement | 30 | CY | __________ | $ | |
| 0035 | Handrail | 250 | LF | __________ | $ | |
| 0036 | Footbridge Repair | 1 | JOB | XXXXXXXX | $ | |
| TOTAL OF ESTIMATED AMOUNTS OF BASE BID | ||||||
| (ITEM NOS. 0001 THROUGH 0036, INCL.) | $ | |||||
| OPTION A | ||||||
| 1001 | Reimbursement For Actual Performance And Payment Bond Premiums | 1 | JOB | XXXXXXXX | $ | |
| Concrete Resurfacing Around Lockwall Recesses - Land Wall | ||||||
| 1002 | Vertical Concrete Removal | 1,242 | SF | __________ | $ | |
| 1003 | Concrete Anchors | 900 | EA | __________ | $ | |
| 1004 | Concrete Reinforcement, Steel Bars | 1,734 | LB | __________ | $ | |
| 1005 | Metals | 1,014 | LB | __________ | $ | |
| 1006 | Concrete Placement | 46 | CY | __________ | $ | |
| 1007 | Grating | 550 | SF | __________ | $ | |
| TOTAL OF ESTIMATED AMOUNTS OF OPTION A | ||||||
| (ITEM NOS. 1001 THROUGH 1007, INCL.) | $ | |||||
| TOTAL OF ESTIMATED AMOUNTS OF BASE BID AND OPTION A | ||||||
| (ITEM NOS. 0001 THROUGH 1007, INCL.) | $ |
| CF = CUBIC FOOT CY = CUBIC YARD EA = EACH JOB = LUMP SUM |
| LB = POUND LF = LINEAR FOOT SF = SQUARE FOOT |
| PLEASE ENSURE THAT UNIT PRICE AND AMOUNT LINES FOR ALL ITEMS |
| HAVE BEEN COMPLETED. |
| The offeror is responsible for verifying all calculations. |