Specifications_Final_-_Service_Barge_101_Drydock_and_Repairs.pdf

PDF 263 KB Posted

Attached to
Service Barge Dry Docking and Repairs
Solicitation number
W911WN-16-T-3004
Issued by

About this file

Specifications

View the file

Other files

File Type Posted
W911WN-16-T-3004_Solicitation_FINAL.pdf PDF
Drawings_1-6.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SERVICE BARGE 101

DRY DOCK AND REPAIR

SERVICE BARGE 101 DRY DOCK AND REPAIR

DRYDOCK AND REPAIR OF "SERVICE BARGE 101"

SECTION 01 30 00

GENERAL REQUIREMENTS

DRYDOCK AND REPAIR OF "SERVICE BARGE 101"

PART 1 GENERAL

This section addresses the general requirements applicable to the performance of the work under this contract. These requirements are in addition to those specified in other sections of the contract.

1. INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS

1.1. LOCATION AND DESCRIPTION OF WORK

1.1.1. Location. The SERVICE BARGE 101 is located at the U.S. Army Corps of Engineers Pittsburgh Engineer Warehouse and Repairs Shops, Neville Island, Pennsylvania, at River Mile 7.5, Main Channel, Ohio River.

1.1.2. Description of Work. The work consists of dry docking and repairing the vessel, including transporting the vessel to the Contractor's facility and returning it to the Government facility upon completion of repairs.

1.1.3. Delivery. The contractor shall begin preparatory work for the drydock within 10 days of receipt of award. The Contractor shall be required to commence the actual drydock physical work under this contract on or about 14 November 2016 and to complete the physical work in 45 days; and deliver the repaired barge to the Pittsburgh Engineer Warehouse and Repair Station.

1.2. SCOPE OF WORK

1.2.1. These specifications cover the requirements for drydock and repair of the Government owned and operated "SERVICE BARGE 101." The work to be performed under this contract consists of furnishing all plant, labor, materials, equipment and transportation thereof, and performing all operations required to make repairs to the vessel as specified herein. Work includes: sandblasting the entire barge exterior hull, repairing rusted and/or damaged metal and paint the barge as outlined in these specifications.

All work shall be in accordance with U.S. Coast Guard and American Bureau of Shipping Regulations and Standards where applicable. The Contractor shall furnish the necessary facilities for movement of the vessel. Should the removal or shifting of any parts of the barge be necessary for carrying out the repairs specified, the same shall be done by the Contractor and all such removals shall be subsequently replaced and any damage or loss resulting there from shall be restored by the Contractor at its own expense. Should any portion of the barge's structure require alteration in order to carry out the work, even though not specifically mentioned herein, the Contractor shall make such alterations. While the barge is in the Contractor's possession, the Contractor shall be responsible for any loss or damages. The Contractor shall construct temporary cover and take the necessary precautions to prevent delays resulting from weather.

1.2.2. The service barge was built by Patti Industries in 1989 and is of all steel, welded construction. The service barge is used in the maintenance and repair of hydraulic structures for the Pittsburgh District Army Corps of Engineers. Principal dimensions of the vessel are as follows:

Displacement (@ 75% tankage): 1,095 Short Tons

LOA: 150'-0"

Molded Beam: 52'-0" Depth Amidships (@ side): 9'-5"

1.2.3. Work Tasks – The repairs required on Barge #101, include the following:

1.2.3.1. Drydock (CLIN 0001) The barge shall be dry-docked at the site where repairs are to be made prior to commencement of the repair work specified in this Contract. The Contractor shall dry dock the barge in accordance with the attached drydock plan drawing 395-H110-B005 entitled DOCKING PLAN. The Contractor shall be responsible for properly positioning the supporting blocks so that the barge will not be damaged. The blocks shall be set to bear on frames or bulkheads of the hull and the barge shall be supported with the bottom of the hull high enough above the floor to allow all work to be accomplished. The dry-dock and/or other places where work under this work order is being performed shall be kept clean and free of expended blasting abrasives, scrap metal, water, scrap lumber, and other debris. All air hoses, water hoses, and electrical extension cables on or about the barge shall be kept arranged in a neat, orderly, and workman like fashion.

1.2.3.1.1. The Contractor shall remove and relocate dry

docking blocks and/or supports, or refloat and re-drydock the vessel, as needed at no additional cost to the Government in order to assure complete coverage in cleaning and painting or for any other work as specified herein. Prior to doing so, the Contractor shall notify the COR of its plan to relocate the blocks to adequately support the vessel.

1.2.3.1.2. Towing and drydock will be paid for at the JOB

contract price for "Towing and Drydock," which price shall include all costs in connection with the movement of the vessel, wharfage, tonnage, dockage, mooring lines, shore power, and similar expense. All towing and shifting at the repair facility is the Contractor’s responsibility and shall be included in this item.

1.2.3.1.3. Shore Power and Access. As part of the drydock

of the vessel, shore power shall be provided for the duration of the contract. Minimum shore power provided shall be 480 volts AC, 3 Phase, 100 amp service. A hard wired or plug and receptacle shore power connection shall be made by shipyard personnel with the assistance of members of the vessel crew such that the correct phasing is achieved.

Access to the vessel once on dock will be by conventional stairs secured at the main deck of the vessel.

1.2.3.2. Power Tool Clean (CLIN 0002 & 0003). Power Tool Clean the corroded areas of the barge hull according to Steel Structures Painting Council Standards SSPC-SP3. Remove all loose mills scale, loose rust, and other detrimental foreign matter to facilitate hull pit repairs and weld seam repairs.

NOTE: The bottom hull plating at the fuel tanks at midships, port, and starboard side; and the fuel oil day tank at bow rake knuckle, port side shall be excluded from the repair procedures listed in paragraph 1.2.3.2 (above) and paragraphs 1.2.3.3 and 1.2.3.4 (below)

1.2.3.3. Corrosion Pitting Repair (CLIN 0002). As directed by the COR, the Contractor shall repair the rust pitting in scattered locations on the hull and channel coolers. Weld fill all pits having a depth of 3/16” and greater. Since the scope of the pit repairs cannot be determined until after the vessel is drydocked, bidders shall quote a unit price per pit. Estimate up to 500 pits maximum to be welded per SECTION 05 50 14.00 08 STRUCTURAL METAL FABRICATIONS AND MISCELLANEOUS METALWORK. Once the rust pits are filled with weld, grind them smooth with the exterior of the hull.

1.2.3.4. Hull Weld Seam Repair (CLIN 0003). If directed by the COR, the Contractor shall weld seams in scattered locations on the hull. The Contractor shall vee-out (using a grinder) existing welds prior to welding seams. Since the scope of the weld seam repair, if any, cannot be determined until after the vessel is drydocked, bidders shall quote a unit price per linear foot of seam. A quantity of 100 linear feet maximum will be used for comparison of bids. For purposes of this provision a seam will be considered any line contact between two or more members. Payment for welding any seam will be on a linear foot of seam basis regardless of the number of members forming the seam or the number of passes or their locations required, as long as all welding passes affect substantially the same heat-affected zone.

Lapped seams between parallel plates shall be considered two seams if each edge of each plate is welded. Weld Repair shall be in accordance with per

SECTION 05 50 14.00 08 STRUCTURAL METAL FABRICATIONS AND MISCELLANEOUS

METALWORK.

1.2.3.5. Repair Channel Bar Coolers (CLIN 0004): The vessel is equipped with four (4) water cooled diesel engines and two (2) water cooled air compressors. Each piece of equipment is fitted with a bottom mounted channel bar keel cooler. Reference drawing 395-M510-B006 entitled CHANNEL BAR KEEL COOLERS. A past inspection of the coolers revealed pinhole leaks at six

(6) each longitudinal and transverse weld seams, in the following locations:

a. At midships, channel #9 & #12 inboard of the port side and located at the 1 ft. long channel splices. This is the #2 engine keel cooler.

b. Centered 40 ft. aft of the headlog, #6 inboard of the port side. This is engine #2 keel cooler.

c. At midships, channel #9 outboard to starboard side of the port set of coolers. This is engine #4 keel cooler.

d. Centered 40 ft. aft of the headlog, #8 & #9 outboard to the starboard side of the port coolers. This is engine #4.

Upon docking of the vessel under the terms of this contract, the coolers will be re-inspected by a representative of the Contracting Officer and a representative of the Contractor and all pinholes will be marked for repair accordingly. The Contractor shall subsequently drain the six (6) each systems completely, and pressure test to 5 psi to find all pin holes. The pinholes found shall be arced and rewelded. "Pinhole" leaks are defined as leaks small enough to wet the immediate area but not large enough to cause dripping or running of the coolant. Line item 0004 provides for the contactor to drain the affected coolers, pressure test to 5 psi and weld up to ten (10) pinhole leaks at the contract JOB price.

1.2.3.6. Disposal of Coolant and Supply of New Coolant (CLIN 0005 & CLIN 0006). Each of the three main diesel engine systems contains approximately 315 gallons of coolant. The auxiliary diesel generator engine cooling system and each of the two air compressor cooling systems contain approximately 150 gallons of coolant. It will be the responsibility of the Contractor to properly dispose of all used antifreeze. A manifest shall be provided to document disposal in accordance with the Environmental Protection Agency. The Contractor shall provide new antifreeze coolant, Texaco Extended Life Prediluted 50/50 Coolant/Antifreeze, Texaco Product Code 7998 or Shell Rotella Extended Life Prediluted 50/50 Coolant/Antifreeze. The Government will be responsible for installing the new antifreeze coolant into all engines/keel coolers. Line item 0005 provides for disposal of up to 1,395 gallons of used antifreeze drained from the coolers prior to repairs.

Disposal will be paid at the unit price for the amount actually removed.

Line items 0006 provide for supply of 1430 gallons of new antifreeze coolant.

The Contractor shall coordinate with the COR all work related to the repair of the channel coolers to ensure that the cooling system is refilled with new coolant as soon as practical after draining to prevent any rust/scale from developing.

1.2.3.7. Anodes (CLIN 0007). Remove and reinstall six (6) each anodes located on hull of barge to facilitate blasting and painting. Should new anodes be required to replace existing deteriorated anodes, they will be provided by the Government

1.2.3.8. Sea Chest (CLIN 0008). Remove sea chest grating, clean, repair, blast, and paint grating and interior of sea chest per SECTION 09965 PAINTING: HYDRAULIC STRUCTURES. Reinstall grating. Protect all pipe intakes. Use Hull Coating system. Reference drawing 395-H210-B005, titled

MISC. STRUCTURAL DETAILS.

1.2.3.9. Exterior Hull Surface Preparation (CLIN 0009). Prepare surface of all exterior hull steel, including the push knees, from the deck edge down. Preparation shall include removal of rust, oxidation, dirt, oil, and grease, and shall be in accordance with Steel Structures Painting Council Standards, SSPC-SP 10 (Near White Blast). After dry blasting, the surface profile shall be jagged, with a profile depth between 1 and 2 mils as measured by ASTM D4417, Method C. Appropriate abrasive blast media shall be used to produce the desired surface profile and to give an angular anchor tooth pattern. If recycled blast media is used, an appropriate particle size distribution shall be maintained so that the specified profile is consistently obtained. Steel shot or other abrasives that do not produce an angular profile shall not be used. Surfaces shall be dry at the time of blasting. For complete surface preparation requirements refer to SECTION

09965 PAINTING: HYDRAULIC STRUCTURES.

1.2.3.10. Exterior Hull Painting (CLIN 0009). The Hull including the push knees of SERVICE BARGE 101, from the deck edge down shall be a painted subsequent to surface preparation in accordance with paragraph 3.1 per the Paint Schedule paragraph 3.2.1.1; for the Hull Exterior. For complete painting requirements refer to SECTION 09965 PAINTING: HYDRAULIC

STRUCTURES.

1.2.3.11. Lower Exterior Deck Surface Preparation (CLIN 0010).

Prepare surfaces of Lower Exterior Deck and Fittings using Steel Structures Painting Council Standard SSPC-SP12 Low Pressure Water Cleaning (LPWC) method to remove surface contamination. Supplement SSPC-SP 12 LPWC with SSPC-SP1 Solvent Cleaning, SSPC-SP2 Hand Tool Cleaning, and SSPC-SP3 Power Tool Cleaning to clean areas of corrosion and loose or flaking paint (feather edges of sound, existing paint back to a firm edge). Sand or brush-off blast glossy surfaces and bare metal to provide profile. Spot prime clean, bare metal with Wasser primer, MC-MioZinc. Alternately, the surface preparation of Exterior Deck and Fitting Surfaces may be brush-off blast cleaned in accordance with the SSPC-SP7 (Brush-Off Blast Cleaning). Note, areas along hatch covers, manhole coamings and other areas not easily cleaned shall be hand tool cleaned in accordance with SSPC-SP2 and 3 (Hand and Power Tool Cleaning). These covers and hatches shall be opened or removed to facilitate cleaning and painting of the edges. Surfaces shall be dry at the time of blasting. For complete surface preparation requirements refer to SECTION

09965 PAINTING: HYDRAULIC STRUCTURES.

1.2.3.12. Exterior Lower Deck and Fittings Painting (CLIN 0010).

Subsequent to surface preparation in accordance with paragraph 3.1, the Exterior Lower Deck of Service Barge 101 shall be topcoated per the Paint Schedule paragraph 3.2.1.1, “Deck & Fittings.” For complete surface preparation requirements refer to SECTION 09965 PAINTING: HYDRAULIC

STRUCTURES.

1.2.3.13. Portable Toilet (CLIN 0011). The Service Barge 101 shall be provided with one (1) chemical toilet. The toilet facility shall be equipped with a toilet seat and toilet seat cover. Each toilet facility shall be equipped with a metal, plastic, or porcelain urinal trough. All shall be provided with an adequate supply of toilet paper and a holder for each seat. Provide hand sanitizer as a substitute for running water. Hand sanitizer must contain at least 60% ethyl alcohol as its active ingredient and workers shall be trained to properly use the sanitizer. Locate Portable Toilet on deck.

1.3. CONTRACT DRAWINGS, MAPS, AND SPECIFICATIONS

a. The Government will provide the Contractor, without charge, three (3) sets of large-scale contract drawings and specifications except publications incorporated into the technical provisions by reference.

b. The work shall conform to the specifications and the contract drawings identified on the following index of drawings:

Title Drawing No.

LINES & BODY PLAN 395-H100-B001

DOCKING PLAN 395-H110-B005

ARRANGEMENT OF MAIN DECK 395-H140-B001

OUTBOARD PROFILE 395-H140-B004

CHANNEL BAR KEEL COOLERS 395-M510-B006

MISC. STRUCTURAL DETAILS (SEA CHEST) 395-H210-B005

1.3.1. Contract Drawings - General

The contract drawings reflect the work to be performed under this contract.

The Contractor shall check all drawings immediately upon receipt, and verify the figures, dimensions, and representation of the work. The Contractor shall compare all drawings and verify the figures before laying out the work.

Dimensions marked on drawings shall, in general, be followed in preference to scale measurements. The Contractor shall promptly notify the Contracting Officer of any discrepancies, and shall be responsible for any errors which might have been avoided by complying with this paragraph. Any omissions from the contract drawings and specifications or incorrect description of details of the work which are manifestly necessary to carry out the intent of the contract drawings and specifications, or which are customarily performed, shall not relieve the Contractor from performing such omitted or incorrectly described details of work, but shall be performed as if fully and correctly set forth and described in the contract drawings and specifications. Unless otherwise noted, dimensions and elevations, and other features shown on contract drawings are based on site surveys and measurements, and As-Built drawings. The Government cannot guarantee the accuracy of the dimensions, elevations, and features shown on the contract drawings which are based on the reference drawings, and it shall be the responsibility of the Contractor to verify all elevations and the dimensions shown by measurements in the field, at no additional cost to the Government.

1.4. SUBMITTALS

Government approval is required for submittals with a “G” designation;

submittals having an "FIO" designation are for information only. The following shall be submitted in accordance with Section 01330 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

1.4.1. Transportation Plan; G

The Contractor shall furnish a description of the vessel it proposes to utilize for transportation of the SERVICE BARGE from and to the Government Facility. The description shall include type, size and horsepower rating of vessel, method of securing the SERVICE BARGE, and methods for protecting the finished coating from damage prior to acceptance by the Government at the destination.

1.4.2. Dry Dock Plan; G

The Contractor shall furnish a dry docking plan depicting location of dry docking blocks and supports. Refer to Service Barge 101 DOCKING PLAN DRAWING #395-H110-B005.

1.5. INSPECTIONS AND ACCEPTANCE OF WORK

Notwithstanding other provisions of this contract, all materials and work to be performed under this contract shall be inspected and accepted by the Contracting Officer or his authorized representative(s). The Contracting Officer or his authorized representative shall be the individual(s) solely authorized to reject materials, disapprove or approve any work in progress, or order or direct any revision or change to the plans and specifications as presently shown and stated.

1.6. Access to Work

The Contractor shall provide safe access to all work area for inspection by the Government.

1.7. SAFETY AND HEALTH REQUIREMENTS GENERAL

The Contractor shall perform all work in accordance with COE EM 385-1-1. The Contractor shall conform to the U.S. Coast Guard (USGC) and U.S. Occupational Safety and Health Requirements Standards (OSHA) regarding shipyard employees.

The Contractor shall provide suitable ladders, gangways, and scaffolds for access to the job. Such equipment considered unsafe or inadequate by the COR shall be removed and replaced by the Contractor with equipment that conforms to the above requirements.

1.8. INSPECTION BY PROSPECTIVE BIDDERS

Prospective bidders are advised and encouraged to inspect the vessel prior to submittal of their bid. To arrange an inspection contact Mr. Jim Williams, Operations & Readiness Division, telephone (412) 395-7605 during normal business hours.

PART 2 PRODUCTS

2. PRODUCTS AND PARTS OF STANDARD MANUFACTURE

All materials, supplies and articles furnished so as to be incorporated into the work under this contract shall be new and shall, whenever so specified and otherwise practicable, be standard products of recognized reputable manufacturers. Standard products of manufacturers other than those specified will be accepted when it is proven to the satisfaction of the Contracting Officer, that they are equal in performance, strength, durability, usefulness and convenience for the purpose intended. Any changes required in the details and dimensions shown on the drawings as a result of the substitution of standard products, other than those provided for, shall be properly made as approved by the Contracting Officer, and at the expense of the Contractor.

All products specified by "similar or equal to" a particular brand name are for descriptive purposes only and are not to imply that the product is available from only that source.

PART 3 EXECUTION

3. EXECUTION OF WORK

3.1. General

The work shall be prosecuted in such order of precedence as best suits the Contractor's fabrication and delivery schedule and the following restrictions. The Contractor shall perform the work in a diligent, effective manner, and shall schedule his operations in such a manner that the work is completed on time. In accordance with Section F DELIVERIES AND PERFORMANCE, clause "LIQUIDATED DAMAGES - SUPPLIES, SERVICES OR RESEARCH AND DEVELOPMENT", the Contractor will be assessed the daily monetary damages for failure to deliver products by the specified delivery dates.

3.2. TESTING

Where testing is specified herein to be performed by the Government, the Government will perform the testing or will have the testing performed at a commercial laboratory at the expense of the Government. Where items or additional samples from items which have been previously tested and approved at the expense of the Government are required to be retested, the Government will bear the costs of such retesting. Where retesting is required because of the failure of previously tested samples, the expenses of all such retesting shall be borne by the Contractor at no extra expense to the Government. The Contractor shall pay for all additional retesting required due to subsequent test failures. Where so required for original testing, retesting will be performed either in the Government laboratories or at such commercial laboratories as may be approved by the Contracting Officer.

3.3. RECORDS AND REPORTS

All records, test reports and similar documentation produced in connection with quality control operations shall be promptly submitted to the Contracting Officer or his authorized representative as required by the specifications.

-- End of Section --

SECTION 01330

SUBMITTAL PROCEDURES

DRYDOCK AND REPAIR OF "SERVICE BARGE 101"

PART 1 GENERAL

1. SUBMITTALS

1.1. SUBMITTAL IDENTIFICATION

Submittals are identified by Submittal Description (SD) numbers and titles as follows:

SD-01 Preconstruction Submittals

Submittals which are required prior to a notice to proceed. Submittals required prior to the start of the next major phase of the construction on a multi-phase contract. Schedules or tabular list of data or tabular list including location, features, or other pertinent information regarding products, materials, equipment, or components to be used in the work, submitted prior to commencement of construction to which the submittal applies.

Certificates of insurance Submittal register Quality control (QC) plan Transportation Plan Dry Dock Plan Residual Paint & Blast Media Management and Disposal Plan Proprietary Paint

SD-03 Product Data

Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.

SD-06 Test Reports

Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be furnished has been tested in accord with specified requirements.

(Testing must have been within three years of date of contract award for the project.)

Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.

Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.

Investigation reports.

Daily logs and checklists.

Final acceptance test and operational test procedure.

SD-07 Certificates

Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that product, system or material meets specification requirements. Must be dated after award of project contract and clearly name the project.

Document required of Contractor, or of a manufacturer, supplier, installer or subcontractor through Contractor, the purpose of which is to further quality of orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.

1.2. SUBMITTAL CLASSIFICATION

Submittals are classified as follows:

1.2.1. Government Approved

Governmental approval is required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer.

Within the terms of the Contract Clause entitled "Specifications and Drawings for Construction," they are considered to be "shop drawings."

1.2.2. Information Only

All submittals not requiring Government approval will be for information only. They are not considered to be "shop drawings" within the terms of the Contract Clause referred to above.

1.3. APPROVED SUBMITTALS

The Contracting Officer's approval of submittals shall not be construed as a complete check, but will indicate only that the general method of construction, materials, detailing and other information are satisfactory.

Approval will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor under the CQC requirements of this contract is responsible for dimensions, the design of adequate connections and details, and the satisfactory construction of all work. After submittals have been approved by the Contracting Officer, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.

1.4. DISAPPROVED SUBMITTALS

The Contractor shall make all corrections required by the Contracting Officer and promptly furnish a corrected submittal in the form and number of copies specified for the initial submittal. If the Contractor considers any correction indicated on the submittals to constitute a change to the contract, a notice in accordance with the Contract Clause "Changes" shall be given promptly to the Contracting Officer.

1.5. WITHHOLDING OF PAYMENT

Payment for materials incorporated in the work will not be made if required approvals have not been obtained.

1.6. SUBMITTALS

Government approval is required for submittals with a “G” designation;

submittals having an "FIO" designation are for information only. The following shall be submitted in accordance with the requirements of this Section:

SD-01 Preconstruction Submittals

Submittal Register; G

The Contractor shall submit the Submittal Register, ENG Form 4288, in accordance with the requirements of paragraph "SUBMITTAL REGISTER (ENG Form 4288)".

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION

3. GENERAL

The Contractor shall make submittals as required by the specifications. The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Units of weights and measures used on all submittals shall be the same as those used in the contract drawings. Each submittal shall be complete and in sufficient detail to allow ready determination of compliance with contract requirements. Prior to submittal, all items shall be checked and approved by the Contractor's Quality Control (CQC) representative and each item shall be stamped, signed, and dated by the CQC representative indicating action taken. Proposed deviations from the contract requirements shall be clearly identified. Submittals shall include items such as descriptive literature including (but not limited to) catalog cuts and diagrams; test reports; samples; certifications; warranties; and other such required submittals. Submittals requiring Government approval shall be scheduled and made prior to the acquisition of the material or equipment covered thereby. Samples remaining upon completion of the work shall be picked up and disposed of in accordance with manufacturer's Material Safety Data Sheets (MSDS) and in compliance with existing laws and regulations.

3.1. SUBMITTAL REGISTER

At the end of this section a submittal register listing items of equipment and materials for which submittals are required by the specifications; this list may not be all inclusive and additional submittals may be required.

Prepare and maintain the submittal register as the work progresses. Do not change data which is output in columns (c), (d), (e), and (f) as delivered by Government; retain data which is output in columns (a), (g), (h), and (i) as approved. A submittal register showing items of equipment and materials for which submittals are required by the specifications is provided as an attachment. This list may not be all inclusive and additional submittals may be required. Maintain a submittal register for the project in accordance with Section 01 45 01.10 USACE QUALITY CONTROL SYSTEM (QCS). The Government will provide the initial submittal register in electronic format with the following fields completed, to the extent that will be required by the Government during subsequent usage.

Column (c): Lists specification section in which submittal is required.

Column (d): Lists each submittal description (SD No. and type, e.g. SD-02 Shop Drawings) required in each specification section.

Column (e): Lists one principal paragraph in specification section where a material or product is specified. This listing is only to facilitate locating submitted requirements. Do not consider entries in column (e) as limiting project requirements

Thereafter, the Contractor is to track all submittals by maintaining a complete list, including completion of all data columns, including dates on which submittals are received and returned by the Government

3.2. SCHEDULING

Submittals covering component items forming a system or items that are interrelated shall be scheduled to be coordinated and submitted concurrently.

Certifications to be submitted with the pertinent drawings shall be so scheduled. Adequate time (a minimum of 30 calendar days exclusive of mailing time) shall be allowed and shown on the register for review and approval. No delay damages or time extensions will be allowed for time lost in late submittals. A minimum of 30 days shall be allowed for any required resubmittal.

3.3. TRANSMITTAL FORM (ENG FORM 4025)

The sample transmittal form (ENG Form 4025) attached to this section shall be used for submitting both Government approved and information only submittals in accordance with the instructions on the reverse side of the form. These forms will be furnished to the Contractor. This form shall be properly completed by filling out all the heading blank spaces and identifying each item submitted. Special care shall be exercised to ensure proper listing of the specification paragraph and/or sheet number of the contract drawings pertinent to the data submitted for each item.

3.4. SUBMITTAL PROCEDURE.

Submittals shall be made as follows:

3.4.1. Submission. Three copies of submittals shall be submitted to:

Plant Manager U.S. Army Corps of Engineers Operations & Readiness Division 3500 Grand Ave.

Neville Island, PA 15225

3.4.2. Technical Data and Manufacturer's Literature

Where materials are stocked with the manufacturer, catalog data, including specifications and full descriptive matter, may be submitted as shop drawings. When catalog data includes non-applicable data, the applicable data shall be clearly designated and identified by item number, item name, and name of manufacturer.

3.4.3. Samples

All samples of materials submitted as required by these specifications shall be properly identified and labeled for ready identification.

3.4.4. Deviations

For submittals which include proposed deviations requested by the Contractor, the column "variation" of ENG Form 4025 shall be checked. The Contractor shall set forth in writing the reason for any deviations and annotate such deviations on the submittal. The Government reserves the right to rescind inadvertent approval of submittals containing unnoted deviations.

3.5. CONTROL OF SUBMITTALS

The Contractor shall carefully control his procurement operations to ensure that each individual submittal is made on or before the Contractor scheduled submittal date shown on the approved "Submittal Register."

3.6. GOVERNMENT APPROVED SUBMITTALS

Upon completion of review of submittals requiring Government approval, the submittals will be identified as having received approval by being so stamped and dated. Two copies of the submittal will be retained by the Contracting Officer and one copy of the submittal will be returned to the Contractor.

3.7. INFORMATION ONLY SUBMITTALS

Normally submittals for information only will not be returned. Approval of the Contracting Officer is not required on information only submittals. The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications, will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work, and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.

3.8. STAMPS

Stamps used by the Contractor on the submittal data to certify that the submittal meets contract requirements shall be similar to the following:

CONTRACTOR

(Firm Name)

_____ Approved

_____ Approved with corrections as noted on submittal data and/or attached sheets(s).

SIGNATURE: __________________________________________________________

TITLE: ______________________________________________________________

DATE: _______________________________________________________________

INTENTIONALLY LEFT BLANK

SAMPLE ENG FORM 4288

INTENTIONALLY LEFT BLANK

SAMPLE ENG FORM 4025

SECTION 01 42 00

SOURCES FOR REFERENCE PUBLICATIONS

DRYDOCK AND REPAIR OF "SERVICE BARGE 101"

PART 1 GENERAL

1. REFERENCES

Various publications are referenced in other sections of the specifications to establish requirements for the work. These references are identified in each section by document number, date and title. The document number used in the citation is the number assigned by the standards producing organization, (e.g., ASTM B 564 Nickel Alloy Forgings). However, when the standards producing organization has not assigned a number to a document, an identifying number has been assigned for reference purposes.

1.1. ORDERING INFORMATION

The addresses of the standards publishing organizations whose documents are referenced in other sections of these specifications are listed below, and if the source of the publications is different from the address of the sponsoring organization, that information is also provided. Documents listed in the specifications with numbers which were not assigned by the standards producing organization should be ordered from the source by title rather than by number.

AMERICAN BUREAU OF SHIPPING (ABS)

16855 Northchase Drive Houston, TX 77060 USA Phone: 281-877-5800 Fax: 281-877-5803 E:Mail: ABS-WorldHQ@eagle.org Internet: http://www.eagle.org

AMERICAN SOCIETY FOR NONDESTRUCTIVE TESTING (ASNT)

1711 Arlingate Lane P.O. Box 28518 Columbus, OH 43228-0518 Phone: 800-222-2768; 614-274-6003 Fax: 614-274-6899 E-mail: webmaster@asnt.org Internet: http://www.asnt.org

AMERICAN SOCIETY FOR QUALITY (ASQ)

600 North Plankinton Avenue Milwaukee, WI 53203 -or- P.O. Box 3005 Milwaukee, WI 53201-3005 Phone: 800-248-1946; 414-272-8575 Fax: 414-272-1734 E-mail: cs@asq.org or help@asq.org Internet: http://www.asq.org mailto:ABS-WorldHQ@eagle.org http://www.eagle.org/ mailto:webmaster@asnt.org http://www.asnt.org/ mailto:cs@asq.org mailto:help@asq.org http://www.asq.org/

AMERICAN WELDING SOCIETY (AWS)

550 N.W. LeJeune Road Miami, FL 33126 Phone: 800-443-9353; 305-443-9353 Fax: 305-443-7559 E-mail: info@aws.org Internet: http://www.aws.org

ASME INTERNATIONAL (ASME)

Three Park Avenue, M/S 10E New York, NY 10016 Phone: 212-591-7722; 800-843-2763 Fax: 212-591-7674 E-mail: infocentral@asme.org Internet: http://www.asme.org

ASTM INTERNATIONAL (ASTM)

100 Barr Harbor Drive P.O. Box C700 West Conshohocken, PA 19428-2959 Phone: 610-832-9500 Fax: 610-832-9555 E-mail: service@astm.org Internet: http://www.astm.org

THE SOCIETY FOR PROTECTIVE COATINGS (SSPC)

40 24th Street, 6th Floor Pittsburgh, PA 15222-4656 Phone: 412-281-2331 Fax: 412-281-9992 E-mail: info@sspc.org Internet: http://www.sspc.org

NATIONAL INSTITUTE FOR OCCUPATIONAL SAFETY AND HEALTH (NIOSH)

395 E Street, S.W.

Suite 9200 Patriots Plaza Building Washington, DC 20201 Phone: 800-232-4636 Fax: 513-533-8347 E-mail: nioshdocket@cdc.gov Internet: http://www.cdc.gov/niosh/

Occupational Safety & Health Administration 200 Constitution Ave., NW Washington, DC 20210 Phone: 800-321-OSHA (6742) Fax:

E-mail:

Internet: www.OSHA.gov mailto:info@aws.org http://www.aws.org/ mailto:infocentral@asme.org http://www.asme.org/ mailto:service@astm.org http://www.astm.org/ mailto:info@sspc.org http://www.sspc.org/ http://www.cdc.gov/niosh/ https://www.osha.gov/

U.S. ARMY CORPS OF ENGINEERS (USACE)

Order CRD-C DOCUMENTS from:

U.S. Army Engineer Waterways Experiment Station ATTN: Technical Report Distribution Section, Services Branch, TIC 3909 Halls Ferry Road Vicksburg, MS 39180-6199 Phone: 601-634-2664 Fax: 601-634-2388 E-mail: mtc-info@erdc.usace.army.mil Internet: http://www.erdc.usace.army.mil/

Order Other Documents from:

USACE Publications Depot Attn: CEHEC-IM-PD 2803 52nd Avenue Hyattsville, MD 20781-1102 Phone: 301-394-0081 Fax: 301-394-0084 E-mail: pubs-army@usace.army.mil Internet: http://www.publications.usace.army.mil/

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

8601 Adelphi Road College Park, MD 20740-6001 Phone: 866-272-6272 Fax: 301-837-0483 E-mail:

Internet: http://www.archives.gov

Order documents from:

Superintendent of Documents U.S.Government Printing Office (GPO 732 North Capitol Street, NW Washington, DC 20401 Phone: 202-512-1800 Fax: 202-512-2104 E-mail: contactcenter@gpo.gov Internet: https://www.gpo.gov/fdsys/

CODE OF FEDERAL REGULATIONS (CFR)

Order from:

Government Printing Office Washington, DC 20402-9328 Phone: 202-512-1800 Fax: 202-275-7703 E-mail:

Internet: https://www.gpo.gov/ mailto:E-mail:%09mtc-info@erdc.usace.army.mil http://www.erdc.usace.army.mil/ mailto:pubs-army@usace.army.mil http://www.publications.usace.army.mil/ http://www.archives.gov/ mailto:E-mail:%09contactcenter@gpo.gov https://www.gpo.gov/fdsys/ https://www.gpo.gov/

ENVIRONMENTAL PROTECTION AGENCY (EPA)

Public Information Center 401 M St., SW Washington, DC 20460 Phone: 800-490-9198

FAX: 202-260-6257

E-mail:

Internet: http://www.epa.gov

NOTE: Some documents are available only from:

National Technical Information Services (NTIS) 5285 Port Royal Rd.

Springfield, VA 22161 Phone: 800-553-6847 Fax: 703-321-8547 E-mail:

Internet: http://www.ntis.gov/

EM 385-1-1: U.S. ARMY CORPS OF ENGINEERS (COE)

Order from:

Government Printing Office Washington, DC 20402-9328 Phone: 202-512-1800 Fax: 202-275-7703 E-mail:

Or:

U.S. Army Corps of Engineers Safety and Health Links:

http://www.usace.army.mil/Safety-and-Occupational-Health/Safety-and- HealthRequirements-Manual/ http://www.epa.gov/ http://www.ntis.gov/ http://www.usace.army.mil/Safety-and-Occupational-Health/Safety-and-HealthRequirements-Manual/ http://www.usace.army.mil/Safety-and-Occupational-Health/Safety-and-HealthRequirements-Manual/

SECTION 01451

CONTRACTOR QUALITY CONTROL

DRYDOCK AND REPAIR OF "SERVICE BARGE 101"

PART 1 GENERAL

1. SUMMARY

1.1. This section covers requirements for Contractor quality control required under this contract.

1.2. SUBMITTALS

Government approval is required for submittals with a “G” designation;

submittals having an "FIO" designation are for information only. The following shall be submitted in accordance with Section 01300 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Quality Control Plan; G

The Contractor shall submit a quality control plan for approval in accordance with paragraph "QUALITY CONTROL PLAN".

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION

3. GENERAL

3.1. The Contractor is responsible for quality control and shall establish and maintain an effective quality control system. The quality control system shall consist of plans, procedures, and organization necessary to produce an end product which complies with the contract requirements. The system shall cover all construction operations, both on-site and off-site, and shall be keyed to the proposed construction sequence.

3.2. QUALITY CONTROL PLAN

3.2.1. General

The Contractor shall furnish for review by the Government, not later than ten

(10) days after receipt of Notice to Proceed, the Contractor Quality Control (CQC) Plan proposed to implement the requirements of this Section. The plan shall identify personnel, procedures, controls, instructions, tests, records, and forms to be used. Work will be permitted to begin only after acceptance of the CQC Plan or acceptance of an interim plan applicable to the particular feature of work to be started. Work outside of the features of work included in an accepted interim plan will not be permitted to begin until acceptance of a CQC Plan or another interim plan containing the additional features of work to be started.

3.2.2. Content of the CQC Plan

3.2.2.1. The CQC plan shall include, as a minimum, the following to cover all construction operations, both on-site and off-site, including work by subcontractors, fabricators, suppliers and purchasing agents:

a. A description of the quality control organization, including a chart showing lines of authority and acknowledgment that the CQC staff shall implement the three phase control system for all aspects of the work specified.

b. The name, qualifications (in resume format), duties, responsibilities, and authorities of each person assigned a Quality Control (QC) function.

c. A copy of the letter to the Contractor's representative responsible for CQC signed by an authorized official of the firm which describes the responsibilities and delegates sufficient authorities to adequately perform the functions including authority to stop work which is not in compliance with the contract.

d. Procedures for scheduling, reviewing, certifying, and managing submittals, including those of subcontractors, off-site fabricators, suppliers and purchasing agents.

e. Control, verification and acceptance testing procedures for each specific test to include the test name, specification paragraph requiring test, feature of work to be tested, test frequency, and person responsible for each test (Laboratory facilities will be approved by the Contracting Officer).

f. Procedures for tracking preparatory, initial, and follow-up control phases and control, verification, and acceptance tests including documentation.

g. Procedures for tracking construction deficiencies from identification through acceptable corrective action. These procedures will establish verification that identified deficiencies have been corrected.

h. Reporting procedures, including proposed reporting formats, to include daily reports.

3.2.3. Acceptance of Plan

Acceptance of the Contractor's plan is required prior to the start of construction. Acceptance is conditional and will be predicated on satisfactory performance during the construction. The Government reserves the right to require the Contractor to make changes in his CQC plan and operations including removal of personnel, as necessary, to obtain the quality specified.

3.2.4. Notification of Changes

After acceptance of the QC plan, the Contractor shall notify the Contracting Officer in writing a minimum of seven calendar days prior to any proposed change. Proposed changes are subject to acceptance by the Contracting Officer.

3.3. COORDINATION MEETING

After the preconstruction Conference, before start of construction, and prior to acceptance by the Government of the Quality Control Plan, the Contractor shall meet with the Contracting Officer or Authorized Representative and discuss the Contractor's quality control system. During the meeting, a mutual understanding of the system details shall be developed, including the forms for recording the CQC operations, control activities, testing, administration of the system for both on-site and off-site work, and the interrelationship of Contractor's Management and control with the Government's Quality Assurance.

3.4. QUALITY CONTROL ORGANIZATION

The Contractor shall identify an individual within his organization at the site of the work who shall be responsible for overall management of CQC and have the authority to act in all CQC matters for the Contractor. This CQC System Manager shall be on the site at all times during construction and shall be employed by the Contractor. In addition to implementing and managing the QC program, the QC Manager may perform the duties of project superintendent.

3.4.1. CQC Organizational Staffing

The Contractor shall provide a CQC staff which shall be at the site of work at all times during progress, with complete authority to take any action necessary to ensure compliance with the contract.

3.4.2. Organizational Changes

The Contractor shall obtain Contracting Officer's acceptance before replacing any member of the CQC staff. Requests shall include the names, qualifications, duties, and responsibilities of each proposed replacement.

3.5. CONTROL

Contractor Quality Control is the means by which the Contractor ensures that the construction, to include that of subcontractors and suppliers, complies with the requirements of the contract. The controls shall be adequate to cover all construction operations, including both on-site and off-site fabrication, and will be keyed to the proposed construction sequence. A quality control plan shall be submitted by off-site fabricators covering their portion of the work under this contract.

3.6. TESTING PROCEDURE

The Contractor shall perform tests specified or required to verify that control measures are adequate to provide a product which conforms to contract requirements. Testing includes operation and/or acceptance tests when specified.

3.7. COMPLETION INSPECTION

At the completion of all work or any increment thereof established by a completion time stated in paragraph "COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK," or stated elsewhere in the specifications, the

Contractor's representative responsible for CQC shall conduct an inspection of the work and develop a "punch list" of items which do not conform to the approved plans and specifications. Such a list of deficiencies shall be included in the CQC documentation, as required by paragraph DOCUMENTATION below, and shall include the estimated date by which the deficiencies will be corrected. The Contractor's representative responsible for CQC shall make a second inspection to ascertain that all deficiencies have been corrected and so notify the Government. These inspections and any deficiency corrections required by this paragraph will be accomplished within the time stated for completion of the entire work or any particular increment thereof if the project is divided into increments by separate completion dates.

3.8. DOCUMENTATION

The Contractor shall maintain current records of quality control operations, activities, and tests performed, including the work of subcontractors and suppliers. These records shall be on an acceptable form and shall include factual evidence that required quality control activities and/or tests have been performed.

3.9. NOTIFICATION OF NONCOMPLIANCE

The Contracting Officer will notify the Contractor of any detected noncompliance with the foregoing requirements. The Contractor shall, after receipt of such notice, immediately take corrective action. Such notice, when delivered to the Contractor at the site of the work, shall be deemed sufficient for the purpose of notification. If the Contractor fails or refuses to comply promptly, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders shall be made the subject of claim for extension of time or for excess costs or damages by the Contractor.

3.10. SAMPLE FORMS

A sample form is enclosed at the end of the section.

CONTRACTOR'S NAME

(Address)

DAILY CONSTRUCTION QUALITY CONTROL REPORT

Date:_________ Report No. __________

Contract No.:_________________________

Description and Location of Work: ________________________________________

Weather: (Clear) (P. Cloudy) (Cloudy)

Temperature: ______ Min. ______ Max. Rainfall: _____________ inches

Adverse Weather Delay: Cause: ___________________ % work-day delayed_____

Contractor/Subcontractors and Area of Responsibility

a. ______________________________________________________________________

b. ______________________________________________________________________

c. ______________________________________________________________________

d. ______________________________________________________________________

1. Work Performed Today: (Indicate location and description of work performed. Refer to work performed by prime and/or subcontractors by letter in table above.)

2. Results of Surveillance: (Include satisfactory work completed, or deficiencies with action to be taken.)

3. Tests required by Plans and/or Specifications Performed and Results of Tests:

4. Verbal Instructions Received: (List any instructions given by Government personnel on construction deficiencies, retesting required, etc., with action to be taken.)

5. Remarks: (Cover any conflicts in plans, specifications, or instructions)

6. Accident Report: (Record daily accidents resulting in lost time, explain what measures will be taken to prevent further accidents of this…