Traffic Control Coordination
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| ABSTRACT_OF_OFFERS_-_W911SG-18-B-0022.pdf | ||
| SOLICITATION_AMENDMENT_1_-W911SG-18-B-0022.pdf | ||
| iWATCH_Trng_for_Contractors_20151028.pdf | ||
| Solid_Waste_C&D_Diversion_Guidance_2015.pdf | ||
| SOLICITATION_1-_W911SG-18-B-0022.pdf | ||
| Recycling_Policy_2015.pdf | ||
| As-Built_Requirements.pdf | ||
| Drawings_New_Storm__Drain_Project_001.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ROAD CLOSURE – TRAFFIC CONTROL COORDINATION REQUIREMENTS
• 1. Project proponent (DPW engineer, BBC, COE, UPs, TXDOT, City, etc) must
• conduct all the preliminary coordination with DES, DPTMS, BBC, impacted
• facilities and (City/TXDOT when applicable).
• 2. The proponent will generate power point slides providing the pertinent
• details for the closure. See attached sample.
• ‐ Name of impacted road(s)
• ‐ Name and phone number of POC (For DPW projects managed by DPW, list the
• DPW POC)
• ‐ Beginning and end dates and times
• ‐ Brief description of the work taking place
• ‐ Map showing impacted road sections, but the area shown must be large
• enough for someone not familiar with the project to recognize where the
• project is taking place.
• ‐ Detail map showing the impacted road(s) and the traffic control plan (i.e.
• detours, one‐ways, etc)
• ‐traffic control plan to comply with TX MUTCD
• 3. Email the power point slides to the DPW Director and Deputy at least two
• weeks before the scheduled closure and concurrently provide them to DES,
• BBC, PAO and TBOC. The DPW Director or Deputy will email the info to the
• installation leadership for their awareness and approval.
• 4. If the installation leadership desires changes, the proponent will make
• the necessary changes and will provide the revised power point slides to
• DES, BBC, PAO and TBOC.
Road Closure West of Pershing Gate Start Date: 5 Jan 13/0800 End Date: 15 Apr 13/1300
Point of Contact: Mr. John Doe, 568-0000
8/10/2018 2
The heading should change to the appropriate entity if not executed by DPW
PROJECT DETAILS
• Failing road is being replaced with new asphalt pavement and pavement markings
• New sidewalk and vehicle guardrail will be installed on south side of Pershing Rd to address safety deficiencies
• New Right turn lane will be constructed on Pershing to Radford St
• Phase 1 will last approximately 60 days
• Phase 2 will last approximately 45 days
• Project has been phased to allow the gate to remain open during the two phases for inbound traffic only
8/10/2018 3
8/10/2018 4
Ft. Bliss Property Limit
Hwy 54
Construction Area ( yellow)
Pershing Gate
Pershing Gate
Hwy 54
Phase 1 Inbound Traffic Only Through Gate
Duration 60 days
Pershing Gate
Hwy 54
Phase 2 Inbound Traffic Only Through Gate
Duration 45 days