This document provides responses to vendor questions regarding solicitation number W911SA23Q3089 for shower, laundry, and material handling equipment rental services. The solicitation will be issued on 18 May 2023 and seeks these services at Joint Base McGuire-Dix-Lakehurst in New Jersey from 1 July 2023 to 4 August 2023. Vendors must submit quotes by the due date and time listed in the solicitation, along with required documents including a signed SF 1449, completed supplemental information, and price schedule attachment. Written questions are due by 1 June 2023. The Department of the Army Materiel Command Mission and Installation Contracting Command at Fort McCoy is the contracting agency.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W911SA23Q3089 Solicitation Amendment 0004.pdf | ||
| W911SA23Q3089 Amendment 0003 (f).pdf | ||
| W911SA23Q3089 Attachment 2 Price Schedule 6.7.23.xlsx | XLSX spreadsheet | |
| W911SA23Q3089 Solicitation Amendment 0001 (f).pdf | ||
| W911SA23Q3089 Attachment 1 ATOPSEC.pdf | ||
| W911SA23Q3089 Attachment 2 Price Schedule.xlsx | XLSX spreadsheet | |
| W911SA23Q3089 Solicitation (f).pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
0011943543
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of amendment tw o (2) is to provide responses to vendor questions.
POC: Melissa T. Larson, Contract Specialist, 608-388-1247, melissa.t.larson.civ@army.mil
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 02-Jun-2023
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W911SA23Q3089
X 9B. DATED (SEE ITEM 11)
18-May-2023
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
02-Jun-2023
CODE
MICC - FT MCCOY
BLDG 1108 SOUTH R ST
FORT MCCOY WI 54656-5153
W911SA 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W911SA23Q3089
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 1449 - CONTINUATION SHEET
The following have been added by full text:
RESPONSES TO VENDOR QUESTIONS
1. Does the requirement include that the contractor provide power (generators) in order to power the shower and/or laundry trailers at all locations?
A: The contractor shall provide all power generating equipment for contractor provided equipment at all locations.
There is no on-site power available. The government will be responsible for refueling contractor’s generators with diesel fuel.
2. If contractor is responsible for providing power generators, is the contractor or the government responsible for fueling the generators?
A. The government will provide diesel to refuel equipment. The contractor shall provide the first tank of tank fuel for all contractor provided equipment. The contractor shall provide any required propane for water heaters.
3. With regards to the shower trailers; total requirements at each location are 20-24 heads divided half male, half female. Instead of the contractor providing two 10-12 head shower trailers with one each dedicated male/female, would it be acceptable to provide three 8 head shower trailers with half of the 24 total heads designated male/female?
A. The contractor shall provide the total numbers of needed showerheads. The government will identify the gender breakouts needed.
4. Will there be access to power on-site or will we need to provide generators? If so, are we responsible for refueling the generators?
A. The contractor shall provide power generating equipment for all shower and laundry trailers. There is no power available on-site. The contractor shall provide the first tank of fuel for all equipment. The government will refuel generators with diesel fuel. The government will not provide propane or fuel other than diesel.