W911SA-18-B-2006_Amendment_0001.pdf

PDF 168 KB Posted

Attached to
Construct Training Ammunition Supply Point (ASP) at Fort McCoy, WI Federal contract opportunity
Solicitation number
W911SA-18-B-2006
Issued by
Department of the Army Materiel Command Mission and Installation Contracting Command Fort McCoy

About this file

Amendment 0001

View the file

Other files for this federal contract opportunity

Other files attached to Construct Training Ammunition Supply Point (ASP) at Fort McCoy, WI, newest first.
File Type Posted
W911SA-18-B-2006_Bid_Abstract.pdf PDF
W911SA-18-B-2006_Site_Visit_Sign_in_Sheet_1.24.18.pdf PDF
W911SA-18-B-2006_Attachment_1_Specifications.pdf PDF
W911SA-18-B-2006_Solicitation_(f).pdf PDF
W911SA-18-B-2006_Attachment_2_ATOPSEC.pdf PDF
W911SA-18-B-2006_Attachment_3_Drawings.pdf PDF
W911SA-18-B-2006_Attachment_4_Wage_Rate_Requirements.docx DOCX document
W911SA-18-B-2006_Attachment_5_SF24.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

0011114837

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to provide responses to questions.

POC: Melissa T. Gore, Contract Specialist, 608-388-1251, melissa.t.gore.civ@mail.mil

1. CONTRACT ID CODE PAGE OF PAGES

J 1 5

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 07-Feb-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W911SA-18-B-2006

X 9B. DATED (SEE ITEM 11)

12-Jan-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

07-Feb-2018

CODE

MICC - FT MCCOY

BLDG 1108 SOUTH R ST

FORT MCCOY WI 54656-5153

W911SA 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W911SA-18-B-2006

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00100 - BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS

The following have been modified:

SUPPLEMENTAL INFORMATION

Contract Specialist:

Melissa Gore Phone: 608-388-1251 E-mail: melissa.t.gore.civ@mail.mil

Contracting Officer:

Steve Bailey Phone: 608-388-6077 Email: steven.m.bailey2.civ@mail.mil

Include the following within the sealed bid package:

1) Completed SF1442 with acknowledgement of all amendments

2) Completed Attachment 5, SF24

3) Any additional verification documents

4) CD-ROM (CD-R) disk with an electronic copy of all submission requirements listed above.

Contractor POC E-mail

DUNS

TAXPAYER ID #

This solicitation is a 100% HUBZone Small Business Set Aside under NAICS code 238910 with a size standard of $15 Million.

This requirement has a period of performance of 120 days after notice to proceed.

Bids can be submitted in any of the following ways:

Delivered to or by Mail:

Mission & Installation Contracting Command – Fort McCoy Attn: Melissa Gore, Contract Specialist 1108 South R Street Fort McCoy, WI 54656-5153

A site visit is scheduled for January 24, 2018 at 10:00 AM Local time. Interested attendees are asked to meet in the Contracting Office located in Bldg. 1108. South R Street, Fort McCoy, Wisconsin. The POC for the project is Melissa Gore at (608) 388- 1251. See Site Visit in Section 00100. This will be the only site visit conducted, requests for additional site visits will be denied.

For Site Visit information, see Site Visit clause 52.236-27, Alternate 1 in Section 00100. Unless you already have a permanent vehicle pass, you will be required to obtain a one-day vehicle pass. You will be required to present the following information at the Visitor’s Center: (1) vehicle registration, (2) valid driver’s license,

(3) or car rental agreement (if applicable). It is highly recommended that bidders plan to arrive at the Visitor’s Center at least an hour prior to the scheduled time for the site visit. The conference will begin promptly without considerations for late or lost bidders; no subsequent site visits will be considered. Remarks, explanations and answers provided by Government representatives before, during and after the site visit shall not change or qualify any of the terms or conditions of the solicitation. The solicitation can only be changed by a formal written amendment issued by the Fort McCoy Contracting Office.

Any questions concerns, verification or clarification of information of the documents included in the solicitation package shall be submitted in writing and submitted to the Government POC identified herein no later than Noon, local time on February 2, 2018.

Include in the subject line of the email the Government’s solicitation number; failure to do so will lessen the Government’s ability to ensure all questions are considered during the bidding process. Provide your company name, POC and contact information in the body of the email.

The “Equal Employment Opportunity Is the Law” notice (poster) referenced in FAR clause 52.222-26(b) (3), Equal Opportunity, is located at http://www.dol.gov/ofccp/regs/compliance/posters/ofccpost.htm

In accordance with FAR 22.404-10, the contractor must post a copy of the wage determination and Department of Labor Form WH-1321 in a prominent place where employees working on federal construction contracts can easily see it. The applicable wage determination is incorporated into the contract at Section H. The WH-1321 poster is located at http://www.dol.gov/compliance/guide/index.htm

Contractors are referred to EPA’s list of EPA-designated products available at http://www.epa.gov providing products that contain recovered materials.

In accordance with DPAP changes to reporting requirements under FAR 52.223-2, Affirmative Procurement of Bio- based Products under Service and Construction Contracts, contractors are now required to submit annual bio-based reports to the new reporting module in the System for Award Management (SAM). SAM can be accessed at https://www.sam.gov.

SYSTEM for AWARD MANAGEMENT (SAM) REGISTRATION: SAM Registration is required of all Department of Defense contractors. SAM registration enables electronic funds transfer of contract payments. If your company is not already registered, please register in the CCR database at https://www.sam.gov/ www.sam.gov http://www.sam.gov https://www.sam.gov

a. A DUNS number is required for SAM registration. If your company does not have DUNS #, obtain one by calling 800-333-0505.

b. Whether your company is a current or new registrant in the SAM database, your registration must indicate that you are a provider of NAICS 238910 under the Goods – Services section of the registration to be eligible to receive a contract for this solicitation.

c. If the prospective awardee for this request for quotes is not registered in the SAM database by close of solicitation, including NAICS 238910 under the Goods – Services section, depending on mission requirements, the government reserves the right to proceed to award to the next otherwise successful registered offeror.

SAM REQUIREMENT: Prospective contractors who have not completed electronic annual representations and certifications at www.sam.gov in conjunction with required registration in the SYSTEM for AWARD MANAGEMENT (SAM) database, shall complete and submit 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2014) and 252.204-7007 ALTERNATE A, ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2014) in SAM to be eligible to receive an award for this solicitation.

PROJECT MAGNITUDE

The magnitude of this project is between $500,000 and $1,000,000.

EVALUATION FACTORS

The Government will evaluate bids received in response to this solicitation solely on the basis of price and price related factors. Bidders shall submit a price for each item specified in the solicitation. No bid for a quantity less than that specified in the solicitation will be accepted. Bids shall be evaluated using the quantities set forth in the solicitation. All prices bid in response to this solicitation must include all costs associated with work elements, applicable State sales taxes, permits, and licensure. And the overall project management, superintendence and quality control necessary for the planning and execution of multiple work requirements conducted simultaneously throughout the performance period.

BID GUARANTEE

A Bid Bond/Guarantee is required for this contract if it exceeds $150,000. The Bid Bond amount shall be twenty percent (20%) of the bid price or $3 Million, whichever is less.

Bidders must use the Standard Form (SF) 24 if providing a bid bond as the bid guarantee.

ATTACHMENTS

Attachment 1 Specifications Attachment 2 ATOPSEC Attachment 3 Drawings Attachment 4 Wage Rate Requirements Attachment 5 SF24

QUESTIONS

1. Is the entire site to be stripped or is ALL construction limited to only “Project 1?”

Answer: A description of work included in each project is in Spec Section 1000, C. NEW WORK.

(FYI, all site drainage is included in project 1 to meet the storm water permit for the entire build out.)

Project 1 includes rough grading of entire site, storm-water management and bio-retention devices, fine grading and placing dense aggregate in areas highlighted as “Project 1” on plan sheet C1.3. All other disturbed areas shall be restored with topsoil and seed. Erosion control shall be used on the entire site.

2. In regards to Land clearing tree removal, Per the spec it says “Land clearing activities for construction, maintenance, and repair activities should generally be scheduled outside the migratory nesting season which is generally considered to be from 1 May thru 30 August.” Has the government performed the required survey to ensure that this site does not have any naturally conflicting species?

Answer: An EA was done for this site by Fort McCoy. The contractor may proceed with construction activities within the grading limits with the requirement of maintaining BMP's and erosion control. The trees within the limits of construction were removed within the period of 1 October – 31 March, which is outside of the typical nesting season.

3. Per the Spec “In May 2015, the Northern Long-Eared Bat (NLEB) was listed as a federally endangered species. As a result of this listing, tree removal is temporarily prohibited unless a survey is conducted to determine if bats are present.” With that being in mind and the contractor understanding that we still need to comply with the Endangered Species act, for survey and inspection at time of construction. Has the Government done a prior survey on the area? Is it historically known that this site in fact does have the Long-eared-bat? The provision states that work would be suspended if the “bats are present.” Will the Government be allowing contract modification for Time and Compensation for “down time if needed for the endangered species?”

Answer: An EA was done for this site by Fort McCoy. The EA documented that there were no listed sightings of the NLEB within the project area or in the nearby vicinity, therefore this project is not anticipated to have a significant impact on this species. Contractor may proceed with construction activities within the grading limits with the requirement of maintaining BMP's and erosion control. The trees within the limits of construction were removed within the period of 1 October – 31 March, which is outside the typical nesting and roosting season.

4. With respect to the Spec reference in removal and recycling the “stumps” at the Ft McCoy recycling center, will this provision be for all Tree foliage and grub? Or is that provision just for the stumps?

Answer: The site was logged. The remainder that is not suitable should be disposed of on Fort McCoy since it could be contaminated with evasive seed. The disposal site for stumps and remaining slash from the logging harvest is known as the South Post Tree Disposal site which is located along Underpass Road, approximately 2 miles from the project site.

5. Is it the government intent to “site balance” the existing soils or haul off?

Answer: Yes. An Earthwork Summary for grading is provided on drawing sheet C1.5. Please see Note

3. This was designed to minimize soils to be hauled off the project. If the work requires soils to hauled off the project site, the material should be hauled to Fort McCoy spoil sites which are no farther than 5 miles away.

(End of Summary of Changes)