W991S822Q0002 - 0001 (Released).pdf

PDF 332 KB Posted

Attached to
SCIF In-a-Box Concrete Pad Construction Federal contract opportunity
Solicitation number
W911S822Q0002
Issued by
Department of the Army Materiel Command Mission and Installation Contracting Command Joint Base Lewis-McChord

View the file

Other files for this federal contract opportunity

Other files attached to SCIF In-a-Box Concrete Pad Construction, newest first.
File Type Posted
Contractor QA 05 APR 2022.pdf PDF
Attachment 2 - Site Pictures_PDS.pdf PDF
Attachment 1 - Specs_Equipment Locations.pdf PDF
W991S822Q0002 (Released).pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W911S822Q0002

0011747906

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to make necessary changes to the Statement of Work and correct the NAICS code called out in Section L, as indicated in BOLD. As a result of the delays in these changes, the solicitation response date shall be extended to 15 APR 2022. All other terms and conditions remain the same.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 29

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 11-Apr-2022

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W911S822Q0002

X 9B. DATED (SEE ITEM 11)

21-Mar-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

11-Apr-2022

CODE

MICC-JB LEWIS-MCCHORD

BUILDING 2015

JOINT BASE LEWIS-MCCHORD WA 98433-9500

W911S8 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION C - DESCRIPTIONS AND SPECIFICATIONS

The following have been modified:

STATEMENT OF WORK

1. GENERAL DISCUSSION:

1.1. Project Identification

1.1.1. Project Title: SCIF-in-a-Box (SIAB) Site Prep

1.1.2. IJO Number(s): TNA210691J

1.1.3. Project Package Number(s): PS 2215

1.2. Description of Work

1.2.1. The Contractor shall supply all supervision, labor, equipment, and materials to perform all work in strict accordance with the contract, this statement of work, and identified drawings to conduct site preparations for the SIAB as discussed in this statement of work (SOW).

1.3. Area Description

1.3.1. Location

1.3.1.1. The project site is at the Intelligence Operations Facility (IOF) compound which is the fenced off area are building 9113. Building 9113 is located off Jackson Ave. at Hillside Dr. and Mil Park Ave. on JBLM Main.

1.3.2. Known Existing Site Condition

1.3.3. The site to receive the SIAB currently has concrete pads that are to be demolished and replaced as part of this contract. The area inside the fence line is primarily gravel and will be trenched as required to provide electrical and communications.

1.4. Principal Items To Be Accomplished

1.4.1. Base Item CLIN 0001: Construct New Concrete Pad, IJO# TNA210691J, BLDG# 9113, Construction

1.4.1.1. Contractor shall install a new concrete equipment pad for the new SIAB.

a. Contractor shall demo all of the existing concrete and reinforcing in the area that the new equipment pad is to be constructed (see Attachment #2).

b. Contractor shall prepare the subgrade as required to install 8” of 5/8” crushed aggregate base course below the new concrete pad. Crushed base course shall be compacted to 95% standard density with 4” lifts. Base course shall be leveled as required for the new equipment pad. Contractor to provide submittal showing compaction testing.

c. Contractor shall install a new level 6” thick, 4,000 psi Portland cement concrete pad. Pad shall have a

1” chamfer on all edges. Pad shall extend 4” above grade. Concrete pad shall be approximately 31’ by 49’ and be installed in the orientation shown in Attachment #1. The outer 30” perimeter of the concrete pad shall have a thickened edge that extends 12” below grade. Concrete pad and thickened edge shall be reinforced with #4 rebar at 12” on center each way. Contractor shall install a control joint in the middle of the slab. Contractor shall finish slab to promote drainage. See Attachment #1 for concrete pad drawing.

1. The concrete used shall meet the requirements of American Concrete Institute (ACI) 301.

Cement shall meet American Society for Testing and Materials (ASTM) C150 Type I or Type II.

Coarse and fine aggregate shall meet ASTM C33. Water used shall be clean and potable. Air entrainment shall be in accordance with (IAW) ASTM C260 and ASTM C494 (entrain 5% +/- 1.5% by volume in all concrete exposed to weather). Any water reducing admixture used shall meet ASTM C494 and shall be used IAW manufacturer instructions. Concrete slump shall not exceed 5”. The Contractor shall provide a concrete mix design submittal prior to pad construction.

d. Contractor shall provide a submittal on the 28 day compressive strength of the new concrete pad prior to new equipment install (CLIN 0003).

1.4.2. Base Item CLIN 0002: Install SIAB Electrical and Communications Ducts, IJO# TNA210691J, BLDG# 9113, Construction

1.4.2.1. Contractor shall trench and install concrete encased ducts and conductors for electrical as required to feed the new service to the SIAB. Contractor shall provide structural bedding for the new duct bank. New duct bank shall consist of two 2” Schedule 40 polyvinyl chloride (PVC) ducts spaced a minimum of 3” apart.

PVC ducts shall be installed on plastic chairs with a tie wire method of securing them. At transition areas (from underground to above ground or vice versa), Contractor shall install long radius rigid galvanized steel (RGS) elbows wrapped with corrosion proof tape 12” above (as feasible) grade and 12” below grade.

The new SIAB shall be fed from the main distribution panel (MDP) called out in Attachment #1. The new electrical shall be sized appropriately to provide a 120/208V 3-phase 60 Hz 200 amp service to the new equipment. All conductors shall be copper. All feeder conductors must be continuous runs and without splices (no exceptions). Neutral conductors shall be separate conductors. Ground conductors shall be separate conductors. All fittings shall be weatherproof.

a. Contractor to note that only one of the new conduits will be utilized. The remaining spare conduit shall be provided with pull strings. The MDP side of the conduits shall be dead-ended into the MDP/MDP vault. The equipment side of the conduits shall be stubbed-up at and secured to the edge of the new concrete pad such that the new service can be connected to the equipment once it is installed. Exact locations for stub-up to be field verified with the Government Project Manager (PM). The MDP side of the conduits shall be ran behind the MDP (see Attachment #1 for trench/duct bank route).

The MDP side of the conduits shall transition from underground to above ground and tap into the top of the MDP via LB’s or similar. The conduits entering the top of the MDP shall be properly supported with galvanized steel channel framing. The equipment side of the conduits shall be stubbed-up at and secured to the edge of the new concrete pad such that the new service can be connected to the equipment once it is installed. Exact locations for stub-up to be field verified with the Government Project Manager (PM). Conduit termination points of entry/exit shall be grouted. Contractor shall install weatherproof caps on conduit as required.

b. On the MDP side of the new electrical service the Contractor shall install a new circuit breaker in the MDP (replacing an existing unused breaker if required) for the new service and make the necessary connections to power the new equipment. On the MDP side of the new electrical service the Contractor shall install a new circuit breaker in the MDP for the new service and make the necessary connections to power the new equipment.

c. Contractor shall install steel channel framework for support as required. Channel not exposed to the weather shall be galvanized. Channel exposed to the weather shall be stainless steel.

1.4.2.2. Contractor shall trench and install concrete encased ducts as required to provide a new communications duct bank extending from building 9114 out to the new concrete pad. Contractor shall provide structural bedding for the new duct bank. New duct bank shall consist of two 4” Schedule 40 PVC ducts spaced a minimum of 4” apart. PVC ducts shall be installed on plastic chairs with a tie wire method of securing them. Contractor shall follow protected distribution system (PDS) guidelines for buried duct banks called out in Attachment #2. At transition areas (from underground to above ground or vice versa), Contractor shall install long radius rigid galvanized steel (RGS) elbows wrapped with corrosion proof tape 12” above (as feasible) grade and 12” below grade. See attachment #1 for approximate route for new communications duct bank.

a. Contractor to provide pull strings in each of the new conduits. The equipment side of the conduits shall be stubbed-up similar to the electrical conduits and be provided with weatherproof caps. The side terminated at building 9114 shall be terminated inside the building. Exact location of terminations is to be field verified with the Government PM.

b. Contractor to note that there is an existing abandoned communications duct bank that used to provide a PDS to the approximate location for the new concrete pad (red dashed line on Attachment #1). The abandoned duct terminates in the manhole shown in the attachment and a path from the manhole extends inside building 9114. The Contractor may utilize the existing abandoned pathway depending upon the route chosen. Alternatively, the Contractor may transition the duct from underground to above ground next to and within 6” of the east side of building 9114, core a hole in the wall, and install a LB to transition into the building. All connections (LB, fittings, etc.) must be permanently sealed completely around all mating surfaces (welding, epoxy, fusion, or PVC glue).

Any wall penetrations made shall be fire stopped.

1.4.2.3. Contractor shall return the site to original conditions after installation of the new duct banks to include but not limited to patching of any asphalt and/or concrete disturbed as a result of the new material install.

1.4.3. Base Item CLIN 0003: Install SIAB and Connect Power, IJO# TNA210691J, BLDG# 9113, Equipment

1.4.3.1. The SIAB will be placed on to the new equipment pad by others. Once the equipment is in place, the

Contractor shall mount the equipment to the pad IAW manufacturer guidelines (Attachment #1).

1.4.3.2. Contractor shall install and connect equipment grounding for the SIAB IAW manufacturer guidelines and National Electric Code (NEC) requirements.

1.4.3.3. Contractor shall connect the new electrical service to the equipment’s pre-wired junction box using Myers hubs or similar.

1.4.3.4. Contractor shall install steel channel framework for support as required. Channel not exposed to the weather shall be galvanized. Channel exposed to the weather shall be stainless steel.

2. PERFORMANCE AND SCHEDULING:

2.1. Performance Period Requirements

2.1.1. The Contractor is required to commence work under this Contract within five (5) calendar days after the date of issuance of the Notice to Proceed (NTP) for the Base Item(s), prosecute the work diligently, and complete all work on all Base Item(s) no later than 90 calendar days after the date of issuance of the Notice to Proceed for the Base Item(s). The time stated for completion includes final cleanup of the premises and submission of all required close-out documentation.

2.1.2. Blank copies of Government forms required by this SOW will be provided to the Contractor within 14 calendar days of award issuance. Examples of these forms include: daily reports, ENG Form 4025-R, headquarters joint base (HJB) 229, etc.

2.2. Construction Phasing Requirements

2.2.1. Contractor shall coordinate all shut downs/outages with DPW.

2.2.2. The IOF is a high security facility. The contractor should expect to sign in daily and be escorted at all times.

2.2.3. There are multiple ongoing construction projects at the IOF and surrounding area. The contractor should expect to work in a congested area with other contractors/tradesmen and maintain a flexible work schedule.

Typical work hours are from 0730-1630 M-F. The contractor will be required to attend coordination meetings with the Government and other contractors as required in order to de-conflict any work in the area.

2.2.4. The Contractor shall complete the work in CLIN 0001 as soon as feasible after contract award and prior to completing work in CLIN 0002 and CLIN 0003.

2.3. Perform other work necessary

2.3.1. The Contractor shall be responsible for providing a complete and useable product/system and shall be responsible for accomplishing all tasks incidental to the completion of the project requirements.

Requirements for a complete and useable product which are not explicitly called out in the SOW but are reasonably discernable via any other method than destructive testing shall be considered a requirement of the project/contract.

3. SUBMITTAL PROCEDURES:

3.1. Project Submittal Requirements: All submittals shall be submitted electronically (emailed) to the Government

PM in Adobe Acrobat .pdf format. An ENG Form 4025 shall accompany each submittal. These forms will be furnished to the Contractor by the PM. The submittal file name shall be in the format “Contract # – submittal #, submittal name” for example; “0020-001 RTU”. Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. Drawings if required by the SOW shall be in ACAD format and a second electronic copy in PDF format. The Government reserves the right to request submittals not listed in this SOW; any submittals not listed in this SOW but requested by the Government shall become a requirement of the project. Submittals requiring Government approval are to be scheduled and made prior to the acquisition of the material or equipment covered thereby. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements. Contractor shall check and approve all items prior to submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified.

3.1.1. The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer (KO) from requiring removal and replacement of nonconforming material incorporated in the work; and does not relieve the Contractor of the requirements to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.

3.1.2. Government Approval. Government approval is required for critical materials, deviations, equipment whose compatibility with the entire system must be checked, safety requirements, and other items as designated by the KO. Government approval is required for any deviations from the solicitation or accepted proposal and other items as designated by the KO. These deviations must contain proper documentation stating why this deviation is necessary and why it is beneficial to the Government.

3.1.3. Information Only. Submittals not requiring Government approval will be for information only. The approving authority will not provide approval of information only submittals but shall provide acknowledgement of receipt.

3.1.4. Variations. Variations from contract requirements require Government approval and will be considered where advantageous to Government and/or overall project. Discussion with KO or their representative (DPW PM, MICC CS, etc.) prior to submission will help ensure functional and quality requirements are met and minimize rejections and resubmittals. Specifically point out variations from contract requirements in transmittal letters. Failure to point out variations may result in the Government requiring rejection and removal of such work at no additional cost to the Government. When proposing a variation, deliver written request to the KO, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government. In addition to documentation required for variation, include the submittals required for the item. Clearly mark the proposed variation in all documentation. Check the column "variation" of ENG Form 4025 for submittals that include proposed variations requested by the Contractor. Set forth in writing the reason for any variations and annotate such variations on the submittal.

The Government reserves the right to rescind inadvertent approval of submittals containing unnoted variations.

3.1.5. Approval. When approving authority is KO or the designated representative, the Government will: Note date on which submittal was received. Review submittals for approval within scheduling period specified and only for conformance with project design concepts and compliance with contract documents. Identify returned submittals with one of the actions defined in paragraph entitled "Review Notations" and with markings appropriate for action indicated. Upon completion of review of submittals requiring Government approval, stamp and date approved submittals. The transmittal form (4025-R) showing approval of the submittal will be retained by the KO and one copy of the transmittal form will be returned to the Contractor electronically. The KO's approval or acceptance of submittals is not to be construed as a complete check, and indicates only that the general method of construction, materials, detailing and other information are satisfactory. Approval or acceptance will not relieve the Contractor of the responsibility for any error that may exist, as the Contractor is responsible for the satisfactory construction of all work. After submittals have been approved or accepted by the KO, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.

3.1.6. Disapproval. Contractor shall make corrections required by the KO. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications, notice as required under the clause entitled, "Changes" is to be given to the KO. Failure to point out deviations may result in the Government requiring rejection and removal of such work at the Contractor's expense. If changes to submittals are necessary, the Contractor shall make such revisions and submission of the submittals in accordance with the procedures above within 7 calendar days. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.

3.1.7. Duration for submittal review: The Government shall have up to 14 calendar days to review each submittal starting when the Government receives the electronic submission. Longer review times may be required on a case-by-case basis.

3.2. Project Schedule:

3.2.1. Prepare for approval a Project Schedule, as specified herein. Show in the schedule the sequence in which the

Contractor proposes to perform the work and dates on which the Contractor contemplates starting and completing all schedule activities. The scheduling of the entire project, including construction sequences, is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel shall actively participate in its development. Subcontractors and suppliers working on the project shall also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool.

3.2.1.1. Approved Project Schedule. Use the approved Project Schedule to measure the progress of the work and to aid in evaluating time extensions. Make the schedule cost loaded and activity coded. The schedule will provide the basis for all progress payments. If the Contractor fails to submit any schedule within the time prescribed, the KO may withhold approval of progress payments until the Contractor submits the required schedule.

3.2.1.2. Default Terms. Failure of the Contractor to comply with the requirements of the contract shall be grounds for a determination, by the KO, that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the contract. Upon making this determination, the KO may terminate the Contractor's right to proceed with the work, or any separable part of it, in accordance with the default terms of the contract.

3.2.2. BASIS FOR PAYMENT AND COST LOADING: Use the schedule as the basis for determining contract earnings during each update period and therefore the amount of each invoice payment. Lack of an approved schedule update, or qualified scheduling personnel, will result in the inability of the KO to evaluate Contractor percentage complete for the purposes of payment. Failure of the Contractor to provide all required information will result in the disapproval of the preliminary, initial, and subsequent schedule updates. In the event schedule revisions are directed by the KO and those revisions have not been included in subsequent revisions or updates, the KO may hold retainage up to the maximum allowed by contract, each payment period, until such revisions to the Project Schedule have been made. Activity cost loading shall be reasonable, as determined by the KO. The aggregate value of all activities coded to a contract line item number (CLIN) shall equal the value of the CLIN on the Project Schedule. The Government will withhold 5% of the project amount for submission and acceptance of any and all closeout documents as specified in each project and this shall be shown on the project schedule.

3.2.3. PROJECT SCHEDULE DETAILED REQUIREMENTS: The computer software system utilized to produce and update the Project Schedule shall be capable of meeting all requirements of this specification. Failure of the Contractor to meet the requirements of this specification will result in the disapproval of the schedule.

3.2.3.1. Critical Path Method. Use the Critical Path Method (CPM) of network calculation to generate the Project Schedule. Prepare the Project Schedule using the Precedence Diagram Method (PDM).

3.2.3.2. Level of Detail Required. Develop the Project Schedule to an appropriate level of detail. Failure to develop the Project Schedule to an appropriate level of detail, as determined by the KO, will result in its disapproval. The KO will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:

a. Activity Durations. Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods. Procurement activities are defined herein.

b. Permit Activities. Include permit activities, when required, with the necessary conferences and follow-up actions and dates. Include the permitting schedule in the Project Schedule, showing the sequence of events involved in carrying out the project permit tasks within the specific contract period. This shall be at a detailed level of scheduling sufficient to identify all major permitting tasks, including those that control the flow of work.

c. Procurement Activities. Tasks related to the procurement of long lead materials or equipment shall be included as separate activities in the project schedule. Long lead materials and equipment are those materials that have a procurement cycle of over 30 days. Examples of procurement process activities include, but are not limited to: submittals, approvals, procurement, delivery, start-up, and testing.

d. Mandatory Tasks. The following tasks (as required) must be included and properly scheduled:

1. Submission of closeout submittals, equipment commissioning, controls testing plan submission, controls testing, performance verification testing, other systems testing, Contractor’s internal project inspection, correction of punchlist from the Contractor’s pre-final inspection, final inspection.

2. Government Activities. Show Government and other agency activities that could impact progress. These activities include, but are not limited to: approvals, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.

3. Contract Line Item Number (CLIN) Coding. Code all activities to the CLIN on the CLIN Schedule to which the activity belongs. An activity shall not contain more than one CLIN code. CLIN code all activities, even when an activity is not cost loaded (to include preconstruction and post construction activities).

3.2.4. Scheduled Project Completion and Activity Calendars. The schedule interval shall extend from Notice to Proceed (NTP) date to the required contract completion date. The contract completion activity (End Project) shall finish based on the required contract duration in the accepted contract proposal, as adjusted for any approved contract time extensions. The first scheduled work period shall be the day after NTP is received by the Contractor. Schedule activities on a calendar to which the activity logically belongs.

Activities may be assigned to a 7-day calendar when the contract assigns calendar day durations for the activity such as a Government Acceptance activity. Assign the Category of Work Code - Weather Sensitive Installation to those activities that are weather sensitive. Original durations must account for anticipated normal adverse weather. The Government will interpret all work periods not identified as non-work periods on each calendar as meaning the Contractor intends to perform work during those periods.

3.2.4.1. Project Start Date. The schedule shall start no earlier than the date on which the NTP was acknowledged.

Include as the first activity in the project schedule an activity called “NTP”.

3.2.4.2. Project Completion Date. Constrain completion of the last activity in the schedule by the contract completion date. Schedule calculations shall result in a negative float when the calculated early finish date of the last activity is later than the contract completion date. Include as the last activity in the project schedule an activity called "Project Completion”.

3.2.5. PROJECT SCHEDULE SUBMISSIONS: The Contractor shall provide the submissions as described below:

3.2.5.1. Project Schedule Submission. Submit the Project Schedule for approval within 7 calendar days after NTP.

The schedule shall demonstrate a reasonable and realistic sequence of activities which represent all work through the entire contract performance period. The Project Schedule shall be at a reasonable level of detail as determined by the KO. This requirement is in addition to any required schedules or submittals submitted in response to a Request for Proposal (RFP).

3.2.5.2. Project Schedule Updates. At the request of the KO, the Contractor shall provide and submit an updated Project Schedule. These submissions will enable the KO to assess the Contractor's progress. If the Contractor fails or refuses to furnish the information and Project Schedule data, which in the judgment of the KO or authorized representative is necessary for verifying the Contractor's progress, the Contractor shall be deemed not to have provided an estimate upon which progress payment may be made.

3.2.6. REQUESTS FOR TIME EXTENSIONS: In the event the Contractor believes they are entitled to an extension of the contract performance period, completion date, or any interim milestone date, furnish the following for a determination by the KO: justification, project schedule data, and supporting evidence (Ex: daily reports showing delays) as the KO may deem necessary. Submission of proof of excusable delay, based on revised activity logic, duration, and costs (updated to the specific date that the delay occurred) is a condition precedent to any approvals by the Government. In response to each RFP issued by the Government, the Contractor shall submit a schedule impact analysis demonstrating whether or not the change contemplated by the Government impacts the critical path.

3.2.6.1. Justification of Delay. The Project Schedule shall clearly display that the Contractor has used, in full, all the float time available for the work involved with this request. The KO's determination as to the number of allowable days of contract extension shall be based upon the Project Schedule updates in effect for the time period in question, and other factual information. Actual delays that are found to be caused by the Contractor's own actions, which result in a calculated schedule delay, will not be a cause for an extension to the performance period, completion date, or any interim milestone date.

3.2.6.2. Unexcused Delays. Unexcused delays will result in a disapproval of any time extension request and the Contractor will be required to complete the work within the original period of performance. If the Contractor cannot complete the work within the original period of performance, the Contractor will be required to provide consideration to the Government in order to receive a time extension. Consideration will be established on a case by case basis but examples include but are not limited to extended warranty period, upgraded materials, etc.

3.3. Accident Prevention Plan:

3.3.1. Use a qualified person to prepare the written site-specific APP. Prepare the APP in accordance with the format and requirements of USACE EM 385-1-1 and as supplemented herein. Cover all paragraph and subparagraph elements in USACE EM 385-1-1, Appendix A, "Minimum Basic Outline for Accident Prevention Plan". Specific requirements for some of the APP elements are described below. The APP shall be job-specific and address any unusual or unique aspects of the project or activity for which it is written.

The APP shall interface with the Contractor's overall safety and health program. Include any portions of the Contractor's overall safety and health program referenced in the APP in the applicable APP element and made site specific. The Government considers the prime Contractor to be the "controlling authority" for all work site safety and health of the subcontractors. Contractors are responsible for informing its subcontractors of the safety provisions under the terms of the contract and the penalties for noncompliance, coordinating the work to prevent one craft from interfering with or creating hazardous working conditions for other crafts, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out. The APP shall be signed by the person and firm (senior person) preparing the APP, the Contractor, the on-site superintendent, the designated site safety and health officer and any designated CSP and/or CIH.

3.3.2. Submit the APP to the Government personnel within 14 calendar days prior to the date of the preconstruction conference for acceptance. Work cannot proceed without an accepted APP.

3.3.3. Once accepted by the KO or their representative, the APP and attachments will be enforced as part of the contract. Disregarding the provisions of this contract or the accepted APP will be cause for stopping of work, at the discretion of the KO, until the matter has been rectified.

3.3.4. Once work begins, changes to the accepted APP shall be made with the knowledge and concurrence of the KO, or their representative, project superintendent, SSHO, and quality control manager. Should any hazard become evident, stop work in the area, secure the area, and develop a plan to remove the hazard. Notify the KO within 24 hours of discovery. Eliminate/remove the hazard. In the interim, take all necessary action to restore and maintain safe working conditions in order to safeguard on-site personnel, visitors, the public (as defined by ASSE/SAFE A10.34,) and the environment.

3.3.5. Copies of the accepted plan will be maintained at the KO's office and at the job site. Continuously review and amend the APP, as necessary, throughout the life of the contract. Incorporate unusual or high-hazard activities not identified in the original APP as they are discovered.

4. PROJECT REQUIRED SUBMITTALS:

4.1. Pre-Construction Submittals:

4.1.1. Quality Control Plan – Plan shall list Contractor points of contact (POC’s) with phone numbers and list any subcontractor’s used with POC’s and phone numbers.

4.1.2. Accident Prevention Plan with activity hazard analysis (AHA’s)

4.1.3. Environmental Protection Plan

4.1.4. Hazardous materials list with safety data sheet for each material (see section 15.7). HJB Form 225 may be required.

4.1.5. Construction/Project Schedule

4.1.6. Training and Completion Letters (AT/FP, OPSEC, iWATCH, E-Verify)

4.1.7. Submittal Register (ENG Form 4288-R)

4.2. Construction Submittals:

4.2.1. Manufacturer’s equipment specification sheets. All applicable items such as model numbers, sizes, and accessories shall be indicated using arrows or highlight.

4.2.2. Applicable materials meeting specifications of SOW.

4.3. Closeout Submittals:

4.3.1. Operation and Maintenance (O&M) manual to include:

4.3.1.1. Contractor’s Warranty Letter

4.3.1.2. Equipment operations and maintenance manual

4.3.1.3. Startup and test reports

4.3.1.4. Checklists

4.3.2. One printed Operation and Maintenance (O&M) manual in 3-ring binder

4.3.3. The Contractor shall provide a letter of non-retention for all contract documents, plans, drawings, and specifications after the destruction of all copies that are not required by the Contractor to meet legal requirements.

4.3.4. HJB Form 953

4.3.5. 1354(s) if required

4.3.6. As-Built Drawings if required

5. DRAWINGS , SPECIFICATIONS & CODES:

5.1. Drawings

5.1.1. The drawings outlined below are attached:

1. Drawi ng Numb er

2. Sheet Num ber

3. Title 4. Rev Numb er

5. Date

6. 7. 8. Attachment #1 – Specs/Equipment Locations 9. 10.

11. 12. 13. Attachment #2 – Site Pictures/PDS 14. 15.

5.1.2. Dimensions and utility locations are approximate and must be verified in the field.

5.2. Specifications

5.2.1. As referenced in the SOW

5.3. Codes

5.3.1.1. Applicable Unified Facilities Criteria (UFC)

5.3.1.2. UFC 1-200-01: General Building Requirements

5.3.1.3. UFC 1-200-02: High Performance and Sustainable Building Requirements

5.3.1.4. ASA IE&E SDD policy

5.3.1.5. UFC 1-201-01 Non-Permanent DOD Facilities in Support of Military Operations

5.3.1.6. EM 385-1-1 (http://www.publications.usace.army.mil/USACEPublications/EngineerManuals.aspx)

5.3.1.7. National Electrical Code, NFPA 70

5.3.1.8. National Fire Protection Association (NFPA) Codes

5.3.1.9. Telecommunication Industry Association/Electrical Industry Association Wiring Standards (Building

Telecommunication Wiring Standards)

5.3.1.10. Army Installation Information Infrastructure Architecture Policy (I3A)

5.3.1.11. JBLM Design Standard specifications (https://www.lewis-mcchord.army.mil/designstandards/index1.htm)

5.3.1.12. JBLM 420-1

5.3.1.13. JBLM Master Plan, which includes Architectural Appearance Standards

5.3.1.14. PWE-707, Standard Operating Procedure for Construction and Demolition (C&D) Waste Planning and

Reporting (Available through Government Project Manager) National Pollutant Discharge Elimination System (NPDES) small Municipal Separate Storm Sewer Systems (MS4) Permit No. WAS-026638. Use guidance documents found at https://home.army.mil/lewis-mcchord/index.php/my-Joint-Base-Lewis-Mcchord/all-services/public_works-environmental_division/stormwater.

6. SAFETY:

6.1 In addition to the detailed requirements included in the provisions of this contract, comply with USACE EM 385-1-1, and all Federal, state, and local, laws, ordinances, criteria, rules, and regulations. Submit matters of interpretation of standards to the appropriate administrative agency for resolution before starting work. Where the requirements of this specification, applicable laws, criteria, ordinances, regulations, and referenced documents vary, the most stringent requirements govern.

6.2 Activity Hazard Analysis (AHA):

6.2.1 The AHA format shall be in accordance with USACE EM 385-1-1. Submit the AHA for review at least 14 calendar days prior to the start of a project; an accepted AHA is required to start onsite work. Format subsequent AHA’s as amendments to the APP. The analysis should be used during daily inspections to ensure the implementation and effectiveness of the activity's safety and health controls.

6.2.2 The AHA list will be reviewed periodically (at least monthly) and updated as necessary when procedures, scheduling, or hazards change.

6.2.3 Develop the activity hazard analyses using the project schedule as the basis for the activities performed.

Any activities listed on the project schedule will require an AHA. The AHA will be developed by the Contractor, supplier, or subcontractor and provided to the prime Contractor for submittal to the KO or their representative.

6.3 HOT WORK: Required

6.3.1 Obtain a permit prior to performing hot work (welding, cutting, etc.) or operating other flame-producing/spark producing devices. The JBLM Fire Prevention Branch provides a training for Contractors so that they may self-issue hot work permits. CONTRACTORS ARE REQUIRED TO MEET ALL CRITERIA BEFORE BEING ABLE TO SELF ISSUE A PERMIT. The contractor will provide at least two (2) twenty (20) pound 4A:20 BC rated extinguishers for normal hot work. All extinguishers shall have current inspection tags, approved safety pin, and tamper resistant seal. It is also mandatory to have a designated FIRE WATCH for any hot work done at this activity. The Fire Watch shall be trained in accordance with NFPA 51B and remain on site for a minimum of 30 minutes after completion of the task or as specified on the hot work permit.

6.3.2 When starting work in the facility, require personnel to familiarize themselves with the location of the nearest fire alarm boxes and place in memory the emergency Fire Department phone number. ANY FIRE, NO MATTER HOW SMALL, SHALL BE REPORTED TO THE RESPONSIBLE FIRE DEPARTMENT

IMMEDIATELY.

6.3.3 Obtain services from a NFPA Certified individual for HOT WORK within or around flammable materials (such as heating preformed thermoplastic) that have the potential for flammable or explosive atmospheres.

6.4 ARC/FLASH HAZARD ANALYSIS: Required

6.4.1 Contractor shall provide an Arc Flash Hazard Analysis and Final Report IAW NFPA 70E and IEEE 1584-

2004a for all newly installed electrical panels. For new panels the Contractor must provide and install new arc flash and shock hazard labels per NFPA 70E and IEEE 1584-2004a. Labels must include the following:

6.4.2 Titled: Arc Flash and Shock Hazard

6.4.3 System Voltage

6.4.4 Hazard risk category

6.4.5 Arc flash hazard boundary

6.4.6 Flash hazard distance

6.4.7 Minimum Personal Protective Equipment

6.4.8 Shock hazard when cover is removed

6.4.9 Limited, Restricted, and Prohibited approach distance

6.4.10 Date the arc flash sturdy was completed

6.4.11 Specific equipment name for each label

6.4.12 The protective device maximum trip time and location

6.4.13 The name of the company who completed the arc flash study with telephone number.

6.5 SAFETY LOCKOUT/TAGOUT PROCEDURES: Required

6.5.1 Contractor shall ensure that each employee is familiar with and complies with these procedures and 29

CFR 1910.147.

6.5.2 The Government will, at the contractor's request, apply lockout/tagout tags and take other actions that, because of experience and knowledge, are known to be necessary to make the particular equipment safe to work on.

6.5.3 No person, regardless of position or authority, shall operate any switch, valve, or equipment that has an official lockout/tagout tag attached to it, nor shall such tag be removed except as provided in this section.

6.5.4 No person shall work on any equipment that requires a lockout/tagout tag unless he/she, his or her immediate supervisor, project leader, or a subordinate has in his/her possession the stubs of the required lockout/tagout tags.

6.5.5 When work is to be performed on electrical circuits, only qualified personnel shall perform work on electrical circuits.

6.5.6 A supervisor who is required to enter an area protected by a lockout/tagout tag will be considered a member of the protected group provided he notifies the holder of the tag stub each time he enters and departs from the protected area.

6.5.7 Identification markings on building light and power distribution circuits shall not be relied on for established safe work conditions.

6.5.8 Before clearance will be given on any equipment other than electrical (generally referred to as mechanical apparatus), the apparatus, valves, or systems shall be secured in a passive condition with the appropriate vents, pins, and locks.

6.5.9 Pressurized or vacuum systems shall be vented to relieve differential pressure completely.

6.5.10 Vent valves shall be tagged open during the course of the work.

6.5.11 Where dangerous gas or fluid systems are involved, or in areas where the environment may be oxygen deficient, system or areas shall be purged, ventilated, or otherwise made safe prior to entry.

7. CONTRACTOR QUALITY CONTROL (CQC) DAILY REPORTS:

7.1. Maintain current daily records providing factual evidence that required quality control activities and/or tests have been performed. Contractor shall use the Government provided daily inspection form. Daily inspection forms shall start at first day of NTP and continue until the project is 100% complete. Indicate a description of trades working on the project, the number of personnel working and hours worked, weather conditions encountered, equipment on site and hours used, and any delays encountered. Cover both conforming and deficient features and include a statement that equipment and materials incorporated in the work and workmanship comply with the contract. Additionally, annotate job safety evaluations/observations and their results, and any instructions given/received and any conflicts in plans and/or specifications. Furnish the electronic copy of the report to the Government daily within 24 hours after the date covered by the report.

Reports need to be submitted for days on which no work is performed. As a minimum, prepare and submit one report for every 7 days of no work and on the last day of a no work period. All calendar days must be accounted for throughout the life of the contract. The first report following a day of no work will be for that day only. Reports must be signed and dated by the CQC Manager or Site Superintendent.

8. CONTRACTOR PERSONNEL AND SUB-CONTRACTOR QUALIFICATIONS:

8.1. The Government will not exercise any supervision or control over Contractor or subcontractor employees performing work under this contract. Such employees shall be accountable solely to the Contractor, not the Government. The Contractor, in turn, shall be accountable to the Government for all Contractor employees.

8.2. The Contractor shall take appropriate personnel action, as required, in the event any employee becomes involved with civilian or local authorities because of misconduct. The Contractor’s employees are subject to the same general rules of conduct while on the Government installation that apply to Government civilian employees.

8.3. The Government reserves the right to refuse access to Government installation grounds to any Contractor employee if the KO determines it to be in the best interest of the Government.

8.4. The Contractor shall not allow any employee to perform work under the contract while under the influence of alcohol, drugs, or any other incapacitating agent.

8.5. The Contractor shall provide a Site Superintendent at the work site during any construction and shall be the main point of contact for the Government QA. The Site Superintendent shall not be delegated to a subcontractor. If the Site Superintendent is responsible for multiple projects, they need not be at the project site at all times as long as they visit the project site at least once per work day and are available on-site within four hours if needed.

8.6. The Contractor shall provide a Site Safety and Health Officer (SSHO) as required in the EM385-1-1. The Contractor SSHO may be assigned other duties in addition to the duties required as SSHO. The SSHO may not be delegated to subcontractor.

8.6.1. Provide and designate an individual as the Site Safety and Health Officer (SSHO). Provide a site SSHO at the work site at all times to perform safety and occupational health management, surveillance, inspections, and safety enforcement for the Contractor. The Contractor Quality Control (CQC) person can be the SSHO on this contract. Meet the following requirements within the SSHO (Level 3):

8.6.1.1. A minimum of 5 years safety work on similar projects.

8.6.1.2. 30-hour OSHA construction safety class or equivalent within the last 5 years.

8.6.1.3. An average of at least 24 hours of formal safety training each year for the past 5 years.

8.6.1.4. Competent person training as needed.

8.6.2. Construction Safety Hazard Awareness Training: In addition to the above experience, education, and training requirements, the SSHO must have completed the course entitled "Construction Safety Hazard Awareness Training for Contractors". If the SSHO does not have a current certification, they must obtain the course certification within sixty (60) calendar days from award.

8.6.3. SSHO Duties (to include but not limited to):

8.6.3.1. Conduct daily safety and health inspections and maintain a written log which includes area/operation inspected, date of inspection, identified hazards, recommended corrective actions, estimated and actual dates of corrections. Attach safety inspection logs to the Contractors' daily quality control report.

8.6.3.2. Conduct mishap investigations and complete required reports. Maintain the OSHA Form 300 and Daily Production reports for prime and subcontractors.

8.6.3.3. Maintain applicable safety reference material on the job site to include required equipment inspections.

8.6.3.4. Attend the preconstruction conference, pre-work meetings including preparatory inspection meeting, and periodic in-progress meetings.

8.6.3.5. Implement and enforce accepted APP and AHA.

8.6.3.6. Maintain a safety and health deficiency tracking system that monitors outstanding deficiencies until resolution. Post a list of unresolved safety and health deficiencies on the safety bulletin board.

8.6.3.7. Ensure subcontractor compliance with safety and health requirements.

8.7. The Contractor shall provide a Construction Quality Control (CQC) System Manager. The CQC System

Manager may be assigned other duties in addition to the duties required as CQC System Manager. CQC System Manager may also be the SSHO, Project Manager, or Lead Trades person. The CQC and Site Superintendent may not be the same person. The CQC may not be delegated to subcontractor. The Contractor shall also provide an alternate CQC System Manager. The alternate CQC System Manager may not be delegated to the subcontractor. The requirements for the alternate are the same as the CQC System Manager.

8.7.1. The CQC is required to possess specialized skills to assure the required work is being performed properly.

The Contractor's CQC staff must maintain a presence at the job site at all times during progress of the work and have complete authority and responsibility to take any action necessary to ensure contract compliance.

8.7.2. The CQC System Manager must be a graduate engineer, graduate architect, or a graduate of construction management, with a minimum of 5 years construction experience on construction similar to this contract or a construction person with a minimum of 10 years in related work.

8.7.3. As required, the Contractor shall provide as part of the CQC organization specialized personnel to assist the CQC System…