PART IV SPECIFICATIONS

PROVIDE/REPLACE CONCRETE and MISCELLANEOUS ITEMS REQUIREMENTS CONTRACT

WOR # 200004586741

INDEX

SECTION NO. DESCRIPTION

DIVISION 1 - GENERAL REQUIREMENTS

01010 Summary of Work 01300 Submittals

DIVISION 2 - SITE WORK

02050 Demolition 02560 Bituminous Tack and Prime Coats 02594 Repair of Bituminous Pavements 02703 Hot-Mix Asphalt (HMA) For Roads 02832 Concrete Segmental Retaining Wall System 02935 Turf

DIVISION 3 - CONCRETE

03200 Concrete Reinforcing 03300 Cast-In-Place Concrete

DIVISION 4 – MASONRY

04200 Masonry

DIVISION 5 – METALS

05520 Metal Railings

DIVISION 6 – 16 (NOT USED)

PROVIDE/REPLACE CONCRETE and MISCELLANEOUS ITEMS REQUIREMENTS CONTRACT

200004586741

SECTION 01010

SUMMARY OF WORK

1 DESCRIPTION OF WORK:

1.1 Work to be Done: The work consists of furnishing all plant, labor, equipment, supplies, and materials, and performing all work in accordance with these specifications and drawings as indicated at Fort Leonard Wood, Missouri and the Lake of the Ozarks Recreation Area (LORA).

1.2 Location: The site of the proposed work is in the Training Area and Cantonment Area of the Fort Leonard Wood Military Reservation, Fort Leonard Wood, Missouri and the Lake of the Ozarks Recreation Area (LORA), Linn Creek, Mo

2 PRINCIPAL FEATURES: The work to be performed will include, but not be limited to, providing and replacing concrete and other miscellaneous items in accordance with (IAW) the attached Task List in Technical Exhibit A and specifications. This contract will be a delivery order style contract. All work required shall be on a requirement basis as directed by the Contracting Officer on a delivery order. The Contractor will be paid only for actual quantity of work performed for each Task Item.

3. BACKFILLING: The Contractor shall backfill as required to return the site to original contour or meet new construction. Ponding water is unacceptable.

4. TURF: The Contractor shall seed, fertilize and mulch all disturbed areas. See Section 02935 Turf.

5 SEQUENCE OF WORK: The area concerned in this project is Government owned and will be in use during the course of this project.

6 SCHEDULING:

6.1 The Contractor shall schedule all activity at the job site through the DPW Contract Inspection Branch a minimum of 24 hours in advance of work.

6.2 Contractor shall schedule his working hours to coincide with the working hours of the military reservation. Normal working hours of the reservation are 7:30 a.m. to 4:00 p.m., Monday thru Friday, legal public holidays excepted. The Contractor shall not perform work on the reservations beyond the aforementioned working hours without the written approval of the Contracting Officer.

6.3 If the Contractor, for his convenience, desires to perform work during other than normal working hours or on other than normal workdays, he shall notify the Contracting Officer and the Directorate of Public Works Inspection Branch at least 72 hours in advance. The Contractor shall not perform work beyond the normal working hours or normal workdays without written approval of the Contracting Officer and the DPW Inspection Branch approval. The Contractor shall reimburse the Government for any additional expense occasioned the Government thereby, such as, but not limited to, overtime pay for Government inspectors, utilities service, etc.

6.4 Time extensions due to adverse weather or material lead time, must be received in writing prior to scheduled completion date.

7 UTILITY INTERRUPTIONS: Coordinate with the Contracting Officer, DPW Contract Inspection Branch, and the user for any utility work that interrupts service to the facility, any area outside the facility, or any real property facility. Establish a schedule of interruptions listing starting and ending times of disconnection 48 hours prior to interruption.

8 FIELD MEASUREMENTS: The Contractor shall verify all measurements at the project site and shall be responsible for all dimensions, fittings, and the proper installation of all materials and equipment specified.

9 PERMITS: The Contractor shall be responsible for obtaining permits for each worksite.

9.1 Digging: A digging permit is required prior to ANY earthwork operations. The DPW Contract Inspection Branch will assist the Contractor in obtaining this free permit.

9. 2 Land Disturbance: A land disturbance permit is required for any projects that disturb one (1) acre or more.

Land disturbance is defined as any activity that disturbs the roots of vegetation such as clearing, grubbing and grading.

The Contractor shall apply for the permit from the Missouri Department of Natural Resources (MODNR), after the FLW Environmental Office has approved the permit application. MODNR by law may take up to 180 days to review and issue a permit. Copy of the permit shall be forwarded to the DPW Environmental Office. The Contractor shall not begin land disturbance operations until they have received and complied with the MODNR permit. MODNR charges a fee for the permits.

9.3 Hot Work Permit: The Contractor shall obtain a written “Hot Work Permit” (DA Form 5383-R) prior to commencing all hot work outside an approved shop area. Permits will be issued by the FLW Fire & Emergency Services at Fire Station #1, Bldg. 580, Phone: (573) 596-0883. The Contractor shall be liable for any fire loss to Government property attributable to negligence on the part of the Contractor, including failure to comply with fire prevention measures prescribed by terms of this contract. The Inspection Branch will assist the Contractor in obtaining this free permit

9.4 Confined Space Permit: The Contractor shall obtain a written “Confined Space Permit” prior to commencing all confined space activity above and/or below ground. Title 29 CFR 1910.146 OSHA (Confined Space Entry) and FLW Regulation 385-7 sets forth the definition of confined spaces and establishes responsibility and procedures for protection of personnel that shall be entering, work in, and existing confines space. If a permit is required the Contractor shall contact the FLW Fire Department, Fire Station #1, Assistant Chief of Operations, Bldg 580, Phone: (573) 596-0883 prior to, and after the permit required entry is conducted. The Contractor shall keep the permit copy within the work area until all workers have been accounted for after completion of the workday. The Inspection Branch will assist the Contractor in obtaining this free permit.

10 SAFETY REQUIRMENTS:

10.1 General Safety: During progress of work, the Contractor shall protect all personnel, whether Government or civilian, from any and all safety hazards caused by the construction operations. The contractor shall follow all Federal, State and local laws in accordance with 29 CFR 1910 (General Industries Standards), and 29 CFR 1926 (Construction Standards).

10.2 Fire Prevention: The current version of FLW Regulation 420-2 “Post Fire Regulations” is by this reference made a part of this solicitation and resultant contract. The Contractor’s operation shall conform to all applicable portions of this document. All personnel entering on duty as Contractor’s employees shall be instructed in the fire prevention program of the Post and shall be advised of the requirement of the Post Fire Regulations as they pertain to this particular contract.

10.3 Traffic Control: Contractor shall provide all temporary signs and markers as necessary to maintain safety in the worksite. All signs shall conform to the latest edition of the Manual of Uniform Control Devices (MUTCD) and shall be coordinated with, and approved by, DPW Inspection Branch. Contractor shall ensure road user movement is inhibited as little as practical.

11. SPECIAL REQUIREMENTS:

11.1 Use of Fire Hydrants – The temporary use of fire hydrants as sources of water is not authorized without prior approval by the Fire Department, 596-0886. Fire hydrant connections shall include an approved backflow preventer. Use of backflow preventers must comply with Missouri Department of Natural Resources, Division 60, Public Drinking Water Program, Chapter 11 – Backflow Prevention, Title 10CSR60-11. Government furnished backflow preventers shall be utilized and are available at Bldg. 1601, Water Treatment Plant on a first come basis. The Contractor shall be required to sign a hand receipt prior to obtaining a backflow preventer. The Contractor shall be accountable to return the checked out backflow preventer equipment undamaged and as soon as possible. The contractor shall furnish and use an approved fire plug wrench to open and close the hydrant. Pipe wrenches shall not be used. When the hydrant is not being used it shall be shut off. When the need for the hydrant is finished, the hydrant shall be shut off, the temporary connection and backflow preventer shall be removed, the fire hydrant caps shall be replaced and the Fire Department shall be notified that the hydrant will no longer be used.

12. SECURITY:

12.1 In unoccupied facilities, the Contractor shall be responsible for the security of the facility; i.e., all exterior doors shall be locked, windows closed and locked, etc.

12.2 The Contractor shall not be on site without prior notification to the DPW Contract Inspection Branch.

12.3 Contractor personnel shall have valid civilian ID’s.

13 APPLICABLE PUBLICATIONS/REFERENCES: The publications referenced herein after shall be the most recent at the time of solicitation, unless otherwise specified at the beginning of each Specification Section under paragraph 1.

APPLICABLE PUBLICATIONS and or REFERENCES.

14 WORKSITE HOUSEKEEPING:

14.1 The Contractor shall remove all trash and disposal material from the worksite before the end of each day, to the extent it is consistent with standard construction practices on Government work sites. The Contractor shall take all possible precautions to maintain the work site, at all times, in a condition that will prevent damage or injury to person or property, Government or otherwise. The above precautions shall include protection from weather conditions. The Contractor shall be responsible for all damages caused by the negligent acts or omissions of his employees, sub-contractors, or agents during Contract performance.

14.2 Materials to be used within 1 week of delivery and scrap material to be used as work progresses shall not be required to be in screened area. However, all such items shall be placed in an orderly manner (i.e. dirt, rock, etc., in piles and stackable items such as pipe, brick, lumber, etc., stacked off the ground on pallets in an orderly manner).

14.3 Grass and weeds at work/storage site shall be kept at a height of 4”or less. Work site/storage site shall be policed for trash and disposal material a minimum of once per day.

14.4 All trailer and material storage sites shall have an identification board/sign, with company and job name on it, i.e. ABC Construction – ABC building complex. Signs shall meet the following criteria: min 3’ X 3’ max of 4’ X 8’ in size, 3” high legible print, and be approved by DPW Inspection Branch.

15 RESPONSIBLITY FOR DAMAGE

15.1 Damage to Personal Property: The Contractor shall be solely responsible for all damage to Government and occupant personal property caused by the Contractors’ personnel, subcontractors, his agents, or by the performance of his work.

15.2 Damage by Negligence: Damage resulting in gas leaks, electrical outages, loss of heat during cold weather, water leaks, unsecured facilities, weather damage, or oil/hazardous waste spills shall be responded to by the Contractor within 2 hours and repaired within one workday. If the Contractor fails to comply with these requirements, the Government reserves the right to repair the damage and charge the cost to the Contractor. Contractor shall protect all areas through which he will be transporting demolition debris or construction materials. Any damaged turf, sidewalks, roads, vegetation, site amenities, etc, shall be replaced or repaired by the Contractor prior to final Contract closeout.

16 DISPOSAL OF MATERIALS: All materials removed and not reused or designated as salvage material in this project shall become the property of the Contractor, unless otherwise specified, and shall be the Contractor's responsibility for lawful disposal.

16.1 The Contractor may use the Fort Leonard Wood Compost area for the disposal of wood chips, leaves, and grass clippings generated by this project.

16.2 All other wastes generated during Contractor operations shall be disposed of off post by the Contractor at his/her expense.

16.2.1 The disposal of demolition waste is regulated by the Missouri Department of Natural Resources under Chapter 260, Revised Statutes of Missouri and 10 Code of State Regulations Chapter 80-4. Such waste, in types and quantities established by the Department, shall be taken to a demolition landfill or a sanitary landfill off of the Installation for disposal. The Contractor shall provide any information requested by the landfill operator to complete forms required by the Missouri Department of Natural Resources or other Government-required landfill records.

16.2.2 Wastes classified as hazardous wastes under the Resource Conservation and Recovery Act shall be disposed of off the installation, unless otherwise specified in this contract. No hazardous waste shall be disposed of without prior review of the disposal documents, and the approval of the Contracting Officer and the Directorate of Public Works Environmental Coordinator, or his designated representative. The Contractor shall provide an original copy of the disposal document from the approved EPA or State permitted disposal facility for each shipment of hazardous waste generated in this project to the Contracting Officers Representative.

17 ACCESS AND GENERAL PROTECTION/SECURITY POLICY AND PROCEDURES:

17.1 All Contractor and sub-contractor personnel performing tasks on this SOW shall comply with all applicable installation, facility and area commander installation/facility access and local security policies and procedures which will be provided to the Contractor by a Government representative upon written request to the Contracting Officer. Contractor shall provide all information required for background checks to meet installation access requirements as performed by the installation Provost Marshal Office, Director of Emergency Services or Security Office. Requesting Contractor shall submit request for installation pass to the KO at https://vcc1.icmvcc.com/im3500/. There is no charge to the Contractor for this pass. Contractor personnel shall comply with all personal identity verification requirements as directed by DoD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of the base contract to this task order, should the Force Protection Condition (FPCON) at any facility or installation change, the Government may require changes in Contractor security matters or processes.

17.1.1 In the event that the automated system at https://jkodirect.jten.mil is not available (e.g., server problems), Level I AT Awareness Training can be provided by a qualified instructor. However, if the training is not completed online, the Level I AT Awareness Instructor qualification must be coordinated with the Installation Antiterrorism Officer (or Installation Security equivalent) and the resultant name(s) of approved instructors shall be provided to the KO.

17.2 Antiterrorism (AT) Level I Training: All contractor and sub-contractor employees requiring access to Army installations, facilities and controlled access areas shall complete AT Level I awareness training available at https://jkodirect.jten.mil.Users need to enroll in "Course #JS-US007-14" to receive credit for the training within 10 calendar days of contract award; or for new employees within 10 working days of beginning performance on this contract. Contractor shall submit certificates of completion for all personnel to the KO within five calendar days of completion of the training. There is no charge to the Contractor for this training. The burden to complete this training is approximately 1-hour per employee.

17.3 iWatch Training: Within 10 calendar days of contract award and within 10 calendar days of new

Contractor employees commencing work on this contract, all Contractor and sub-contractor employees shall review the FLW Directorate of Emergency Services (DES) web link for iWatch training located at http://www.wood.army.mil/LEC/iWatch/iWatch.htm. This locally developed training will inform employees of the types of behavior to watch for and how to report suspicious activity. Suspicious activity shall be reported to the KO.

There is no charge to the Contractor for this review. The burden to complete this training is approximately 20-minutes per employee.

17.4 OPSEC Standard Operating Procedure/Plan (SOP): The KO will ensure the contractor (after selected) is aware of the MSCoE OPSEC Plan and is in compliance with the MSCoE OPSEC Plan during contract performance.

17.5 OPSEC Training: New contractor employees must complete Level I OPSEC training within 30 calendar days of their reporting for duty in accordance with AR 530-1. All contractors shall complete annual OPSEC Awareness training if the contract duration is longer than 30-days. MSCoE OPSEC Officer will provide https://jkodirect.jten.mil/ https://jkodirect.jten.mil/ training. Coordination of training shall be through Rick Bowser, (573)563-2402. Proof of training, including a detailed listing of attendees, shall be provided to the KO. A nominal fee shall be charged to the Contractor for this training equal to 1-hour of Government time. The burden to complete this training is approximately 1-hour per training evolution. There are no restrictions to number of attendees in a given training evolution.

17.5.1 All costs associated with employee training and review must be included in the CLIN prices bid/offered for the underlying requirement. No other payments are authorized.

17.5.2 Contractor shall reimburse the Government for classroom OPSEC training. The established fee is $30 per face-to-face training session conducted. Contractor personnel may all attend the same training session; however, in the event of new hires, additional session(s) shall be required. Contractor shall submit payment to the US Treasury, Attention: Budget Officer, MSCoE G-8, 14000 MSCoE Loop, Ste 335, Fort Leonard Wood, MO 65473.

SECTION 01300

SUBMITTALS

1. General: All items of equipment and/or materials that are defined or described in the contract require submission in accordance with this section. Brochures, samples, certificates of compliance, test reports, as applicable, shall be submitted by the Contractor to the Contracting Officer, and approval given by the Contracting Officer before any equipment or material is installed under this contract.

1.1. All of the data required shall be submitted prior to inclusion into the Work. Approval of materials and equipment requiring color selection will be withheld until all of the required information has been submitted and is in the hands of the Contracting Officer. All submissions must be in sufficient detail to adequately determine that the item will meet the requirements of this specification.

1.2. All submittals shall be transmitted to the Contracting Officer for review and approval within 30 calendar days after contract award date on Engineer Form 4025 in quadruplicate. The forms shall be completed as directed. No submittal will be accepted unless it is on the subject form. The forms will be furnished to the Contractor by the Government. All attachments to the transmittal form, such as catalog cuts, brochures, certifications, etc., shall be submitted in four (4) copies.

1.3. The Contractor shall complete and submit to the Contracting Officer for approval, five copies of ENG Form 4288 Submittal register. At a minimum, the submittal register shall include a listing of all items listed in paragraph 2 of this Section. This submittal register shall be provided with the initial set of submittals the Contractor submits for approval.

ENG form 4288 will be furnished to the Contractor by the Government. This register will be maintained by the Government to insure that all required materials are submitted and approved IAW the contract requirements.

1.4. Scheduling: A minimum of 14 calendar days will be scheduled for review and approval of material submittals and possible resubmittal of any items subject to approval. For shop drawings submittals, a minimum of 21 calendar days will be allowed for review and approval and possible resubmittal. Unless otherwise specified in the contract, the Notice to Proceed with performance will be issued within 50 calendar days after contract award date. If shop drawings are required, Notice to Proceed with performance will be issued within 60 calendar days after contract award date. The scheduling shall be coordinated with the approved progress schedule.

2. MATERIAL APPROVAL SUBMITTALS:

At a minimum the following list of materials will require approval under the Contract Clause, FAR 52.236-5, titled Material and Workmanship. The Contracting Officer may require submission of additional materials as deemed necessary. If additional items are required to be submitted a revised ENG form 4288, SUBMITTAL REGISTER, shall be prepared by the Contractor and submitted with the additional material submittals. The Contractor shall not proceed with any work using materials which are subject to approval, until materials are approved.

Sections, material, certificates, and/or procedures requiring approval:

02050 Demolition 02560 Bituminous Tack and Prime Coats 02594 Repair of Bituminous Pavements 02703 Hot-Mix Asphalt (HMA) For Roads 02832 Concrete Segmental Retaining Wall System 02935 Turf 03200 Concrete Reinforcing 03300 Cast-In-Place Concrete 04200 Masonry 05520 Metal Railings

NOTE: For specific quantities and types of materials to be submitted see the individual SECTIONS

SECTION 02050

DEMOLITION

PART 1 - GENERAL

1.1 SUBMITTALS: The procedures proposed for the accomplishment of this contract shall be submitted for approval. The procedures shall provide for safe conduct of the work, careful removal and disposition of materials indicated, protection of property which is to remain undisturbed, coordination with other work in progress, and timely disconnection of utility services. The procedures shall include a detailed description of the methods and equipment to be used for each operation, and the sequence of operations.

1.2 GENERAL REQUIREMENTS: The work includes demolition and/or removal of all construction indicated or specified. All materials resulting from demolition work, except as indicated or specified otherwise, shall become the property of the Contractor and shall be removed from the limits of Government property. Rubbish and debris shall be removed from Government property daily unless otherwise directed so as to not allow accumulation inside or outside the buildings. Materials that cannot be removed daily shall be stored in areas specified by the Contracting Officer. The Contractor shall carefully coordinate the work of this section with all other work.

1.3 DUST CONTROL: The amount of dust resulting from demolition shall be controlled to avoid creation of a nuisance in the surrounding area. Use of water will not be permitted.

1.4 PROTECTION:

1.4.1 Protection of Existing Work: Before beginning any digging or demolition work, the Contractor shall carefully survey the existing work and examine the drawings and specifications to determine the extent of the work. The Contractor shall take all necessary precautions to insure against damage to existing work to remain in place, to be reused, or to remain the property of the Government, and any damage to such work shall be repaired or replaced as approved by the Contracting Officer at no additional cost to the Government. The Contractor shall construct and maintain shoring, bracing, and supports as required. The Contractor shall insure that structural elements are not overloaded and be responsible for increasing structural supports or adding new supports as may be required as a result of any cutting, removal, or demolition work performed under any part of this Contract

1.5 BURNING: The use of burning at the project site for the disposal of refuse and debris will not be permitted.

1.6 USE OF EXPLOSIVES: Use of explosives will not be permitted.

1.7 AVAILABILITY OF WORK AREAS: Areas in which demolition work is to be accomplished will be available in accordance with the schedule established by the Contracting Officer.

PART 2 - EXECUTION

2.1 EXISTING FACILITIES:

2.1.1 Utilities: When utility lines are encountered that are not indicated on the drawings the Contracting Officer shall be notified.

2.2 DISPOSITION OF MATERIAL:

2.2.1 Material for Contractor Salvage: Material for Contractor salvage shall be stored as approved by the Contracting Officer. Salvage materials shall be removed from Government property before completion of the Contract.

Material for salvage shall not be sold on the site.

2.3 CLEAN-UP:

2.3.1 Debris and Rubbish: Debris and rubbish shall be removed from area of work and job site as soon as possible.

2.3.2 Debris Control: Debris and Contractor salvage shall be removed and transported in a manner as to prevent spillage on streets or adjacent areas.

SECTION 02560

BITUMINOUS TACK AND PRIME COATS

PART 1 GENERAL

1.1 REFERENCES: The publications listed below form a part of this specification to the extent referenced.

The publications are referred to within the text by the basic designation only.

AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS

(AASHTO)

AASHTO M 226 (1980; R 2008) Standard Specification for Viscosity-Graded

Asphalt Cement

AASHTO M 81 (1992; R 2008) Standard Specification for Cutback Asphalt (Rapid-Curing Type)

AASHTO M 82 (1975; R 2008) Standard Specification for Cutback Asphalt

(Medium-Curing Type)

AASHTO T 102 (2009; R 2013) Standard Method of Test for Spot Test of Asphaltic Materials

AASHTO T 40 (2002; R 2006) Sampling Bituminous Materials

ASTM INTERNATIONAL (ASTM)

ASTM D1250 (2008) Standard Guide for Use of the Petroleum

Measurement Tables

ASTM D140 (2014) Standard Practice for Sampling Bituminous Materials

ASTM D2026 (2015) Cutback Asphalt (Slow-Curing Type)

ASTM D2027 (2013) Cutback Asphalt (Medium-Curing Type)

ASTM D2028 (2015) Cutback Asphalt (Rapid-Curing Type)

ASTM D2397 (2013) Standard Specification for Cationic Emulsified Asphalt

ASTM D2995 (1999; R 2009) Determining Application Rate of

Bituminous Distributors

ASTM D3381 (2013) Viscosity-Graded Asphalt Cement for Use in Pavement Construction

ASTM D946 (2009a) Penetration-Graded Asphalt Cement for Use in

Pavement Construction

ASTM D977 (2013; E 2014) Emulsified Asphalt

U.S. GREEN BUILDING COUNCIL (USGBC)

LEED BD+C (2009; R 2010) Leadership in Energy and Environmental

Design(tm) Building Design and Construction (LEED-NC)

1.2 SUBMITTALS: Submit the following in accordance with Section 01300 SUBMITTAL PROCEDURES:

Manufacturer's descriptive data: asphalt emulsions

Equipment and methods for application of bituminous spray applications

1.3 DELIVERY, STORAGE, AND HANDLING:

Inspect the materials delivered to the site for contamination and damage. Unload and store the materials with a minimum of handling.

1.4 ENVIRONMENTAL REQUIREMENTS:

Apply bituminous coat only when the surface to receive the bituminous coat is dry. Apply bituminous coat only when the atmospheric temperature in the shade is 10 degrees C 50 degrees F or above and when the temperature has not been below 2 degrees C 35 degrees F for the 12 hours prior to application, unless otherwise directed.

PART 2 PRODUCTS

2.1 PLANT, EQUIPMENT, MACHINES AND TOOLS:

Plant, equipment, machines and tools used in the work are subject to approval and must be maintained in a satisfactory working condition at all times. Calibrated equipment such as asphalt distributors, scales, batching equipment, spreaders and similar equipment, must have been recalibrated by a calibration laboratory within 12 months prior to commencing work and every 12 months thereafter, by such laboratory from the date of recalibration, during the term of the contract.

2.1.1 Bituminous Distributor

Provide a distributor with pneumatic tires of such size and number that the load produced on the base surface does not exceed 650 psi of tire width to prevent rutting, shoving or otherwise damaging the base surface or other layers in the pavement structure. Design and equip the distributor to spray the bituminous material in a uniform coverage at the specified temperature, at readily determined and controlled rates from 0.05 to 2.0 gallons per square yard, with a pressure range of 25 to 75 psi and with an allowable variation from the specified rate of not more than plus or minus 5 percent, and at variable widths. Include with the distributor equipment a separate power unit for the bitumen pump, full-circulation spray bars, tachometer, pressure gauges, volume-measuring devices, adequate heaters for heating of materials to the proper application temperature, a thermometer for reading the temperature of tank contents, and a hand hose attachment suitable for applying bituminous material manually to areas inaccessible to the distributor. Equip the distributor to circulate and agitate the bituminous material during the heating process.

2.1.2 Heating Equipment for Storage Tanks

The equipment for heating the bituminous material shall be steam, electric, or hot oil heaters. Provide steam heaters consisting of steam coils and equipment for producing steam, so designed that the steam cannot get into the material. Fix an armored thermometer to the tank with a temperature range from 40 to 400 degrees F so that the temperature of the bituminous material may be determined at all times.

2.1.3 Power Brooms and Power Blowers

Use power brooms and power blowers suitable for cleaning the surfaces to which the bituminous coat is to be applied.

2.2 PRIME COAT:

2.2.1 Emulsified Asphalt

Provide emulsified asphalt conforming to ASTM D977, Type SS-1 or SS1h ASTM D2397/D2397M, Type CSS-1 or CSS-1h.

2.3 TACK COAT:

2.3.1 Emulsified Asphalt

Provide emulsified asphalt conforming to ASTM D977, Type SS-1 or SS1h; or to ASTM D2397/D2397M, Type CSS-1 or CSS-1h. Dilute the emulsified asphalt with equal parts of water. The base asphalt used to manufacture the emulsion shall show a negative spot when tested in accordance with AASHTO T 102 using standard naphtha.

PART 3 EXECUTION

3.1 PREPARATION OF SURFACE:

Immediately before applying the bituminous coat, remove all loose material, dirt, clay, or other objectionable material from the surface to be treated by means of a power broom or blower supplemented with hand brooms. The surface shall be dry and clean at the time of treatment.

3.2 APPLICATION RATE:

The exact quantities within the range specified, which may be varied to suit field conditions, will be determined by the Contracting Officer.

3.2.1 Tack Coat

Apply bituminous material for the tack coat in quantities of not less than 0.05 gallon nor more than 0.15 gallon per square yard of pavement surface.

3.2.2 Prime Coat

Apply bituminous material for the prime coat in quantities of not less than 0.18 gallon nor more than 0.35 gallon per square yard of pavement surface.

3.3 APPLICATION TEMPERATURE:

3.3.1 Viscosity Relationship

Asphalt application temperature shall provide an application viscosity between 10 and 60 seconds, Saybolt Furol.

Furnish the temperature viscosity relation to the Contracting Officer.

3.3.1 Temperature Ranges

The viscosity requirements determine the application temperature to be used. The following is a normal range of application temperatures:

Degrees F

Emulsions

SS-1 70-160

SS-1h 70-160

CSS-1 70-160

CSS-1h 70-160

*These temperature ranges exceed the flash point of the material and care should be taken in their heating.

3.4 APPLICATION:

3.4.1 General

Following preparation and subsequent inspection of the surface, apply the bituminous prime or tack coat with the Bituminous Distributor at the specified rate with uniform distribution over the surface to be treated. Properly treat all areas and spots missed by the distributor with the hand spray. Until the succeeding layer of pavement is placed, maintain the surface by protecting the surface against damage and by repairing deficient areas at no additional cost to the Government. If required, spread clean dry sand to effectively blot up any excess bituminous material. No smoking, fires, or flames other than those from the heaters that are a part of the equipment are permitted within 25 feet of heating, distributing, and transferring operations of bituminous material other than bituminous emulsions. Prevent all traffic, except for paving equipment used in constructing the surfacing, from using the underlying material, whether primed or not, until the surfacing is completed. The bituminous coat shall conform to all requirements as described herein.

3.4.2 Prime Coat

Apply the bituminous material uniformly over the surface to be treated at a pressure range of 25 to 75 psi; the rate shall be as specified above in paragraph APPLICATION RATE. To obtain uniform application of the prime coat on the surface treated at the junction of previous and subsequent applications, spread building paper on the surface for a sufficient distance back from the ends of each application to start and stop the prime coat on the paper and to ensure that all sprayers will operate at full force on the surface to be treated. Immediately after application remove and destroy the building paper.

3.4.3 Tack Coat

Apply tack coat at the locations shown on the drawings. Apply the tack coat when the surface to be treated is dry.

Immediately following the preparation of the surface for treatment, apply the bituminous material by means of the bituminous distributor, within the limits of temperature specified herein and at a rate as specified above in paragraph APPLICATION RATE. Apply the bituminous material so that uniform distribution is obtained over the entire surface to be treated. Treat lightly coated areas and spots missed by the distributor with the bituminous material. Following the application of bituminous material, allow the surface to cure without being disturbed for period of time necessary to permit setting of the tack coat. Apply the bituminous tack coat only as far in advance of the placing of the overlying layer as required for that day's operation. Maintain and protect the treated surface from damage until the succeeding course of pavement is placed.

3.5 CURING PERIOD:

Following application of the bituminous material and prior to application of the succeeding layer of pavement, allow the bituminous coat to cure and to obtain evaporation of any volatiles or moisture. Maintain the coated surface until the succeeding layer of pavement is placed, by protecting the surface against damage and by repairing and recoating deficient areas. Allow the prime coat to cure without being disturbed for a period of at least 48 hours or longer, as may be necessary to attain penetration into the treated course. Furnish and spread enough sand to effectively blot up and cure excess bituminous material.

3.6 TRAFFIC CONTROLS:

Keep traffic off surfaces freshly treated with bituminous material. Provide sufficient warning signs and barricades so that traffic will not travel over freshly treated surfaces.

-- End of Section --

SECTION 02594

REPAIR OF BITUMINOUS PAVEMENTS

PART 1 - GENERAL

1.1 REFERENCES: The publications listed in Section 02560: BITUMINOUS TACK AND PRIME COATS and SECTION 02703: HOT-MIX ASPHALT (HMA) FOR ROADS apply to this specification.

1.2 SUBMITTALS: The following shall be submitted in accordance with Section 01300

SUBMITTALS:

1.2.1. The submittals listed in Section 02560: BITUMINOUS TACK AND PRIME COATS and SECTION 02703: HOT-MIX ASPHALT (HMA) FOR ROADS apply to this specification.

1.2.2. Information on parts and procedures for raising existing manhole covers and frames.

1.3 EQUIPMENT: Machines, tools, and equipment used in the performance of the work required by this section shall be approved before the work is started and shall be maintained in satisfactory condition at all times.

1.4 WEATHER LIMITATIONS: Bituminous spray applications shall not be applied if air or pavement temperatures are below 60 degrees F or if there is any possibility that the application will freeze before it has cured. No application shall be placed if rain is probable before the application will have sufficient time to cure. Unless otherwise directed, bituminous courses shall not be constructed when temperature of the surface of the existing base course is below 40 degrees F.

PART 2 - PRODUCTS

2.1 BITUMINOUS PAVING MIXTURE shall conform to the requirements of Section 02703: HOT-

MIX ASPHALT (HMA) FOR ROADS.

2.2 TACK COAT shall be in accordance with Section 02560: BITUMINOUS TACK AND PRIME

COATS.

2.3 PRIME COAT shall be in accordance with Section 02560: BITUMINOUS TACK AND PRIME

COATS

PART 3 - EXECUTION

3.1 REPAIR OF BITUMINOUS PAVEMENTS:

3.1.1 Contractor shall erect adequate barriers to prevent vehicular access to areas to be repaired, and shall maintain such barriers to prevent damage to repaired areas.

3.1.2 Fuel- or oil-soaked pavement, base and subbase or subgrade material and pavement which is otherwise deteriorated structurally shall be removed and replaced with hot asphalt concrete where directed by the Contracting Officer. Remove the surface and base to a depth of 10 inches, extending at least a foot into good pavement outside the defective area. Cut out such areas in a square or rectangle with the faces straight and vertical. Compact the base thoroughly. Apply a prime coat to the compacted base. Apply a tack coat to the vertical faces. Backfill with hot asphalt concrete. Spread carefully to prevent segregation of the mix. Compact in layers if the hole is more than six inches deep. Compact each layer thoroughly with a vibratory plate compactor or other equipment suited to the size of the job. The finished compacted surface shall have the same grade as the surrounding pavement.

3.1.3 The Contractor shall raise existing manhole covers and frames to them flush with surrounding the pavement surface as directed by the Contracting Officer.

END OF SECTION

SECTION 02703

HOT-MIX ASPHALT (HMA) FOR ROADS

1.1 REFERENCES: The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS

AASHTO M 156 (2013) Standard Specification for Requirements for Mixing Plants for Hot-Mixed, Hot-Laid Bituminous Paving Mixtures

AASHTO M 320 (2010) Performance-Graded Asphalt Binder

ASPHALT INSTITUTE (AI)

AI MS-02 (2015; 7th Ed) Mix Design Methods for Asphalt

AI MS-22 (2001; 2nd Ed) Construction of Hot-Mix Asphalt Pavements

ASTM INTERNATIONAL (ASTM)

ASTM C 117 (2013) Materials Finer Than 75 micrometer (No. 200) Sieve in

Mineral Aggregates by Washing

ASTM C 1252 (2006) Uncompacted Void Content of Fine Aggregate (as

Influenced by Particle Shape, Surface Texture, and Grading)

ASTM C 131 (2014) Resistance to Degradation of Small-Size Coarse Aggregate by Abrasion and Impact in the Los Angeles Machine

ASTM C 136 (2014) Sieve Analysis of Fine and Coarse Aggregates

ASTM C 142 (2010) Clay Lumps and Friable Particles in Aggregates

ASTM C 29 (2009) Bulk Density ("Unit Weight") and Voids in Aggregate

ASTM C 566 (2013) Total Evaporable Moisture Content of Aggregate by

Drying

ASTM C 88 (2013) Soundness of Aggregates by Use of Sodium Sulfate or

Magnesium Sulfate

ASTM D 140 (2014) Sampling Bituminous Materials

ASTM D 1461 (2011) Moisture or Volatile Distillates in Bituminous Paving

Mixtures

ASTM D 2041 (2011) Theoretical Maximum Specific Gravity and Density of Bituminous Paving Mixtures

ASTM D 2172 (2011) Quantitative Extraction of Bitumen from Bituminous Paving Mixtures

ASTM D 2419 (2014) Sand Equivalent Value of Soils and Fine Aggregate

ASTM D 242 (2009) Mineral Filler for Bituminous Paving Mixtures

ASTM D 2489 (2008) Estimating Degree of Particle Coating of Bituminous-

Aggregate Mixtures

ASTM D 2726 (2014) Bulk Specific Gravity and Density of Non-Absorptive

Compacted Bituminous Mixtures

ASTM D 2950 (2014) Density of Bituminous Concrete in Place by Nuclear Methods

ASTM D 3381 (2013) Viscosity-Graded Asphalt Cement for Use in Pavement Construction

ASTM D 3665 (2012) Random Sampling of Construction Materials

ASTM D 3666 (2013) Minimum Requirements for Agencies Testing and

Inspecting Road and Paving Materials

ASTM D 4125 (2010) Asphalt Content of Bituminous Mixtures by the Nuclear Method

ASTM D 4791 (2010) Flat Particles, Elongated Particles, or Flat and Elongated

Particles in Coarse Aggregate

ASTM D 4867 (2009) Effect of Moisture on Asphalt Concrete Paving Mixtures

ASTM D 5444 (2015) Mechanical Size Analysis of Extracted Aggregate

ASTM D 6307 (2010) Asphalt Content of Hot Mix Asphalt by Ignition Method

ASTM D 946 (2009a) Penetration-Graded Asphalt Cement for Use in Pavement Construction

STATE OF CALIFORNIA DEPARTMENT OF TRANSPORTATION (CDT)

CDT Test 526 (2002) Operation of California Profilograph and Evaluation of

Profiles

U.S. ARMY CORPS OF ENGINEERS (USACE)

COE CRD-C 171 (1995) Standard Test Method for Determining Percentage of

Crushed Particles in Aggregate

STATE OF MISSOURI DEPARTMENT OF TRANSPORTATION (MODOT)

SEC 401 (2011) Missouri Standard Specifications for Highway Construction – Plant Mix Bituminous Base Course

1.2 DESCRIPTION OF WORK: The work shall consist of pavement courses composed of mineral aggregate and asphalt material heated and mixed in a central mixing plant and placed on a prepared course. HMA designed and constructed in accordance with this section shall conform to the lines, grades, thicknesses, and typical cross sections shown on the drawings. Each course shall be constructed to the depth, section, or elevation required by the drawings and shall be rolled, finished, and approved before the placement of the next course.

1.3 SUBMITTALS: The following shall be submitted in accordance with Section 01300

SUBMITTAL PROCEDURES:

Mix Design

Asphalt Cement Binder

Copies of certified test data.

Amount, type and description of any modifiers blended into the asphalt cement binder

Testing Laboratory

Certification of compliance.

Plant Scale Calibration Certification

Equipment for placement and compaction of asphalt concrete.

Herbicide for treating vegetation growing in existing pavement

1.4 ASPHALT MIXING PLANT: Plants used for the preparation of hot-mix asphalt shall conform to the requirements of ASTM D 995 with the following changes:

a. Truck Scales. The asphalt mixture shall be weighed on approved certified scales at the Contractor's expense. Scales shall be inspected and sealed at least annually by an approved calibration laboratory.

b. Testing Facilities. The Contractor shall provide laboratory facilities at the plant for the use of the Government's acceptance testing and the Contractor's quality control testing.

c. Inspection of Plant. The Contracting Officer shall have access at all times, to all areas of the plant for checking adequacy of equipment; inspecting operation of the plant; verifying weights, proportions, and material properties; checking the temperatures maintained in the preparation of the mixtures and for taking samples. The Contractor shall provide assistance as requested, for the Government to procure any desired samples.

d. Storage Bins. Use of storage bins for temporary storage of hot-mix asphalt will be permitted as follows:

(1) The asphalt mixture may be stored in non-insulated storage bins for a period of time not exceeding 3 hours.

(2) The asphalt mixture may be stored in insulated storage bins for a period of time not exceeding 8 hours. The mix drawn from bins shall meet the same requirements as mix loaded directly into trucks.

1.5 HAULING EQUIPMENT: Trucks used for hauling hot-mix asphalt shall have tight, clean, and smooth metal beds. To prevent the mixture from adhering to them, the truck beds shall be lightly coated with a minimum amount of paraffin oil, lime solution, or other approved material. Petroleum based products shall not be used as a release agent. Each truck shall have a suitable cover to protect the mixture from adverse weather. When necessary to ensure that the mixture will be delivered to the site at the specified temperature, truck beds shall be insulated or heated and covers (tarps) shall be securely fastened.

1.6 ASPHALT PAVERS: Asphalt pavers shall be self-propelled, with an activated screed, heated as necessary, and shall be capable of spreading and finishing courses of hot-mix asphalt which will meet the specified thickness, smoothness, and grade. The paver shall have sufficient power to propel itself and the hauling equipment without adversely affecting the finished surface.

1.6.1 Receiving Hopper; The paver shall have a receiving hopper of sufficient capacity to permit a uniform spreading operation. The hopper shall be equipped with a distribution system to place the mixture uniformly in front of the screed without segregation. The screed shall effectively produce a finished surface of the required evenness and texture without tearing, shoving, or gouging the mixture.

1.7 ROLLERS: Rollers shall be in good condition and shall be operated at slow speeds to avoid displacement of the asphalt mixture. The number, type, and weight of rollers shall be sufficient to compact the mixture to the required density while it is still in a workable condition. Equipment which causes excessive crushing of the aggregate shall not be used.

1.8 WEATHER LIMITATIONS: The hot-mix asphalt shall not be placed upon a wet surface or when the surface temperature of the underlying course is less than specified in Table 1. The temperature requirements may be waived by the Contracting Officer, if requested; however, all other requirements, including compaction, shall be met.

Table 1. Surface Temperature Limitations of Underlying Course

Mat Thickness, inches Degrees F

3 or greater 40 Less than 3 45

PART 2 PRODUCTS

2.1 HOT-MIX ASPHALT MIXTURE: Hot-Mix Asphalt mixture shall conform to Section 401 of the Missouri Standard Specifications for Highway Construction (2011) for “Base” and BP1 mixtures.

2.2 RECYCLED ASPHALT PAVEMENT: Recycled Asphalt Pavement (RAP) may be used in any mixture. A maximum of 10 percent may be used in surface mixtures and a maximum of 20 percent may be used in subsurface mixtures. No shingles may be added to any mixture.

PART 3 EXECUTION

3.1 PREPARATION OF ASPHALT BINDER MATERIAL: The asphalt cement material shall be heated avoiding local overheating and providing a continuous supply of the asphalt material to the mixer at a uniform temperature. The temperature of unmodified asphalts shall be no more than 325 degrees F when added to the aggregates. Performance-Graded (PG) asphalts shall be within the temperature range of when added to the aggregate.

3.2 PREPARATION OF MINERAL AGGREGATE: The aggregate for the mixture shall be heated and dried prior to mixing. No damage shall occur to the aggregates due to the maximum temperature and rate of heating used. The temperature of the aggregate and mineral filler shall not exceed 350 degrees F when the asphalt cement is added. The temperature shall not be lower than is required to obtain complete coating and uniform distribution on the aggregate particles and to provide a mixture of satisfactory workability.

3.3 PREPARATION OF HOT-MIX ASPHALT MIXTURE: The aggregates and the asphalt cement shall be weighed or metered and introduced into the mixer in the amount specified by the JMF.

The combined materials shall be mixed until the aggregate obtains a uniform coating of asphalt binder and is thoroughly distributed throughout the mixture. Wet mixing time shall be the shortest time that will produce a satisfactory mixture, but no less than 25 seconds for batch plants. The wet mixing time for all plants shall be established by the Contractor, based on the procedure for determining the percentage of coated particles described in ASTM D 2489, for each individual plant and for each type of aggregate used.

The wet mixing time will be set to at least achieve 95 percent of coated particles. The moisture content of all hot-mix asphalt upon discharge from the plant shall not exceed 0.5 percent by total weight of mixture as measured by ASTM D 1461.

3.4 PREPARATION OF THE UNDERLYING SURFACE:

3.4.3 Prior to application of asphalt to an existing asphalt pavement surface, the existing asphalt pavement surface shall be cleaned and accumulation of water removed.

3.4.3.1 The Contracting Officer may direct the Contractor to repair cracks or unsatisfactory areas according to Section 02594: REPAIR OF BITUMINOUS PAVEMENTS.

3.4.3.2 All dust, dirt, oil, grease, fuel, loose or flaky traffic paint, and other objectionable material shall be removed from the existing pavement surface.

3.4.3.3 All vegetation shall be removed, and these areas treated with a herbicide. The type of herbicide and method of application will require approval by the Contracting Officer.

3.4.4 Prior to application of asphalt to an existing rock base, the rock base shall be graded to a surface tolerance of 1/2" in 10 feet and shall be compacted.

3.5 PRIME COAT: Where bituminous paving mixture is placed over an unpaved base course, the base course shall be treated with a prime coat of bituminous material conforming to SECTION 02560:

BITUMINOUS TACK AND PRIME COATS.

3.6 TACK COAT: Contact surfaces of previously constructed or existing pavement, curbs, gutters and other structures shall be sprayed with a tack coat of bituminous material conforming to SECTION 02560:

BITUMINOUS TACK AND PRIME COATS.

3.7 TESTING LABORATORY: The laboratory used to develop the JMF shall meet the requirements of ASTM D 3666. The Government will inspect the laboratory equipment and test procedures prior to the start of hot mix operations for conformance to ASTM D 3666. The laboratory shall maintain the Corps certification for the duration of the project.