| Question | |||
| Number | Question | Government Response | |
| 1 | Are there any drawings available for the drainwork (i.e. do we know the locations of all underground drains) in order to avoid damage? | The As-built drawings are not avaliable yet. | |
| 2 | Is ground penetration x-ray required? | No, ground penetration is not required, however please call DigSafe 811 or 888-DIG-SAFE (344-7233) for assistance with location of underground utilities. | |
| 3 | In area's 1-6 what is the maximum and minimum distance required around these areas? | Maximun distance is around the Egde of the stone and the minimum distance vaires based on locations of various decorative boulders preventing an exact minimum distance from being given. | |
| 4 | The plans show the fence along Heritage lane to be 6’ tall and the SOW claims the fence to be 4’ tall which is correct? | SOW is correct. The fencing is 4 ft tall. | |
| 5 | Will the fence have top rail bottom rail top tension wire bottom tension wire or any combination of these? | Yes, the fence should have top and bottom tension wire. | |
| 6 | What is the size of the chain link mesh and the finished gauge of the mesh? | Standard 9-gauge chain link fence for commercial use. | |
| 7 | Will the fence finish be galvanized of Color coated? | black color coated. | |
| 8 | Are there any specifications on the chain link fence and gate materials that you can share with us? | Child safe opening (gate) (push and lift). | |
| 9 | Are there under ground as-builds readily available? | No, see question 1 and 2. | |
| 10 | Can the government identify where the two gates are located on the 6ft fence? | There is only a 4 ft fence. One gate as described by environmental engineer around Area1, second between 9-10 unit. | |
| 11 | Are there any noise constraints? | No, there are no noise constraints however all work must occur during normal working hours 7am to 4pm. |