SOW - 20PW006 Revised.pdf

PDF 442 KB Posted

Attached to
Shipping and Receiving Area Renovation
Solicitation number
W911PT20Q0064
Issued by

View the file

Other files

File Type Posted
D1 - Administrative Area Shipping and Receiving Demolition Plan.pdf PDF
SOW - 20PW006.pdf PDF
SITEVISIT.DOC DOC document
Drawings - A-103 FLOORPLAN BASEMENT - BLDG 35.pdf PDF
W911PT20Q0064.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (SOW)

FOR

Renovate Administrative Area, Shipping and Receiving

AT

Watervliet Arsenal Building 35, Rms 13, 14, 15, & 17

Project #: 20PW006

Installation Management, Public Works Division Facilities Engineering (TAWV-IMP-F)

PART 1 GENERAL

1.1 SUMMARY OF WORK

1.1.1 Project Description

a. This Statement of Work (SOW) defines the effort required to update the finishes in rooms 13, 14, 15, & 17 of building 35. This includes; abating asbestos floor tile mastic and or cove base in rooms 13, 14, 15, & 17 installing a new drop ceiling in rooms 13, 14, and 15, and painting the walls and doors. Also included in this scope of work is building a proper wall with double doors on the south side of room 14 near the door. The flooring removal is all asbestos containing material and shall be abated through removal.

1.1.2 Location of Work

a. The work is located in rooms 13, 14, 15, & 17 of building 35, approximately as indicated. The exact location will be shown by the Contracting Officer.

1.1.3 Period of Performance

a. The contractor shall be required to (i) commence work under this contract within 7 calendar days after the date the contractor receives notice to proceed, (ii) prosecute the work diligently, and (iii) complete the entire work ready for use not later than 60 calendar days after notice to proceed was given. The time stated for completion shall include final cleanup of the premises.

1.1.4 Hours of Operation

a. Normal duty hours are 7:00 AM through 4:00 PM, Monday through Thursday, and 7:00 AM through 3:00 PM on select Fridays (the arsenal is closed every-other Friday). Federal holidays are non-work days. If a federal holiday falls on a Saturday or Sunday, the preceding Friday or following Monday is a work holiday.

1.2 SUBMITTALS

1.2.1 General Submittal Requirements

a. The contractor shall provide submittal documents via e-mail to the Contracting Officer for review and approval. Provide all physical (non-document) submittals (including but not limited to material swatches, samples, etc.) directly to the Contracting Officer for review and approval. All submittals require government approval unless otherwise explicitly stated.

b. The contractor shall reference APPENDIX A “Consolidated List of Submittals” for the complete list of required submittals.

1.2.2 Contractor Safety Plan

a. The contractor shall submit a safety plan which is specific to the work activity being performed under the scope of this project for Government review and approval.

1.2.3 Lockout / Tagout (LOTO) Acknowledgement

a. The Contractor shall sign and submit a “Lockout/Tagout (LOTO) Notification Acknowledgement Record” prior to working on or de-energizing any electrical equipment.

1.2.4 Asbestos Notification Acknowledgement Record

a. The contractor shall sign the “Asbestos Notification Acknowledgement Record” and submit this form to the Project COR prior to starting project work.

1.2.5 Project Schedule

a. The contractor shall create a project schedule and submit for Government review and approval.

b. The project schedule shall detail the phases of work and the overall timeline for the execution of the work. The contractor shall include delivery dates, appropriate milestones, and shall clearly detail any requirements for work performed outside of regular hours of operation.

1.2.6 Bills of Lading, Dump Slips for C&D Debris and Recycled Materials

1.2.7 Asbestos Submittals

a. The contractor shall provide submittals for the asbestos abatement per specification 02 82 13 – WVA Asbestos Abatement section 1.5.

1.2.8 Concrete Masonry Submittals

a. The contractor shall provide Material Safety Data Sheets (MSDS) for all necessary masonry materials.

b. The contractor shall provide product data sheets for the Concrete Masonry Unit (CMU) and the mortar mix.

1.2.9 Paint Submittals

a. The contractor shall provide product data for the sealant, primer, and paint as specified for the project.

b. The contractor shall provide color swatches for all specified colors.

c. The contractor shall provide MSDS and manufacturer’s installation instructions for all paints used.

1.3 GENERAL REQUIREMENTS

1.3.1 Watervliet Arsenal Information for Contractors (WAIC)

a. The contractor shall perform all work in strict conformance with Watervliet Arsenal Instructions for Contractors (WAIC). The contractor shall read and understand this document prior to submitting a proposal. The WAIC is publically available at:

<http://www.wva.army.mil/Documents/Contracting/WAIC.pdf>

1.3.2 Utility Outage Requests and Utility Connection Requests

a. Schedule work to minimize outages. For utility outages and connections required during the execution of work that affect existing systems, coordinate schedule with COR. Schedule utility outages and connections to minimize disruptions to the Government. No additional payment will be provided for utility outages and connections required to be performed outside the regular work hours.

b. The contractor shall notify the Contracting Specialist a minimum of two (2) business days before the contractor starts work. The contractor shall notify the COR a minimum of seven (7) business days before the shut-down of a utility or building service.

1.3.3 Safety Requirements

a. The contractor is required to provide the proper control of hazardous energy (lockout/tagout) per

OSHA 29 CFR 1910.147.

b. The contractor shall inspect the project work site prior to starting work, and shall request a copy of the asbestos building inspection records to verify the location and description of known asbestos-containing materials.

1.3.4 Fire Protection/Detection Coordination

a. The contractor shall coordinate with the Fire House and the Department of Public Works (DPW) Maintenance & Operations Group to secure all fire prevention and detection systems in and around work areas during work operations.

i. Maintenance & Operations: Michael Dennin 518-266-5830

ii. Fire Department: 518-266-5990 DPW

1.4 ON-SITE PERMITS

1.4.1 Excavation (Dig Permit)

a. The clearance of buried utilities will be performed by the Government in advance of the Contractor performing subsurface work, unless otherwise explicitly stated.

b. The Contractor shall obtain a copy of the completed Utility Clearance Permit (WVA Form 420-2-E) from the COR prior to performing subsurface work. Verify existing utility locations indicated on contract drawings, within area of work.

1.4.2 Hot Work and Confined Space

a. Obtain permit for welding, burning, use of flame, or entry into confined space from WVA Fire Department by calling (518)266-5990 each day the permit is to be used.

1.5 APPLICABLE DOCUMENTS

1.5.1 Drawings

http://www.wva.army.mil/Documents/Contracting/WAIC.pdf

a. The following drawings accompany this Statement of Work and are a part thereof.

i. D1 – Administrative Area Shipping and Receiving Demolition Plan

1.5.2 Specifications

a. The following specifications accompany this Statement of Work and are a part thereof.

i. 01 00 00 – WVA Front End

ii. 02 82 13 – WVA Asbestos Abatement

iii. 04 WVA 02 – Concrete Masonry Unit

iv. 08 13 00 – Metal Doors

v. 09 90 00 – Interior Paints and Coatings

1.5.3 References

a. The following references accompany this Statement of Work and are a part thereof.

i. Watervliet Arsenal Instructions for Contractors (WAIC).

ii. NFPA 70 – National Electric Code (NEC).

iii. AMC Environmental Requirements Supplement.

1.6 CONTRACTOR EQUIPMENT

1.6.1 Equipment Identification

a. The contractor shall create and affix a label to all large equipment, dumpsters, and other mobilized property, which is weather-resistant (laminated, or within a see-thru label hanger), securely affixed to the equipment or visible through a window, and which clearly displays the General Contractor’s:

i. Company Name, POC Name (first, last), POC phone number, Project Number.

1.6.2 Waste Dumpster

a. The contractor shall place any waste dumpsters in a manner that does not interfere with thru-traffic.

b. Place waste dumpsters with a minimum of 33’ clearance from any building. The final location shall be coordinated with, and approved by the COR before any dumpsters are mobilized.

c. Cover all waste dumpsters when not in use, and before the end of each work shift. The cover shall be weather-tight.

d. Note: The Contractor shall be required to retain and submit copies of all Bills of Lading and Weight Slips associated with the disposal of construction and demolition C&D) debris.

PART 2 PRODUCTS

2.1 GENERAL

All work shall be in strict accordance with product manufacturer’s instructions and specifications, including but not limited to manufacturer guidance for storage, staging, application, installation, and disposal of the product.

2.1.1 Hazardous Materials

a. The contractor shall submit Safety Data Sheets (SDS) for all hazardous materials to be used.

2.1.2 Asbestos, Mercury, Lead, PCB

a. Unless otherwise stated, all materials for this project shall be new. All products shall not contain any asbestos, mercury, chromium/lead paint, Class I Freon, and Polychlorinated Biphenyls (PCB), and shall state such on the manufacturer’s original packaging.

2.1.3 DoD Green Procurement Program

a. All construction materials shall meet the applicable requirements of the DoD Green Procurement Program, specifically recycled content products, environmentally preferable products and services, biobased products, energy-and water-efficient products, alternate fuel vehicles and alternative fuels, products using renewable energy, and alternatives to hazardous or toxic chemicals as found at <http://www.acq.osd.mil/dpap/cpic/cp/docs/USA001967-08-DPAP.pdf>.

2.1.4 Paint

a. To meet the Affirmative Procurement Program (Federal Government’s Buy Recycled Requirements) all paint used in the project shall adhere to the below listed requirements of the Comprehensive Procurement Guideline for recovered materials. This applies only to interior latex paint, only if available at the time of the project.

i. Reprocessed Latex Paint (White, Off-White, Pastel Colors) shall contain 20% Post consumer content.

ii. Reprocessed Latex Paint (Grey, Brown Earth tones, and Other Dark Colors) shall contain 50-99% Post consumer content.

iii. Consolidated Latex Paint shall contain 100% Post consumer content.

2.2 PRODUCTS

2.2.1 Primer

a. Primer shall be interior latex-based primer, low VOC, stain-blocking/stain-hiding formulation intended for the purpose of being applied over bare paper-faced drywall and unfinished wood. Color shall be white.

b. Provide substitute primer for unique surfaces or areas where the primer specified herein is not manufacturer approved for the application.

2.2.2 Paint

a. Paint shall be interior latex-based paint, low VOC, water based.

i. Wall paint color shall be Sherwin Williams 7631 CITY LOFT eggshell or color matched equivalent with COR approval.

ii. Trim paint color shall be Sherwin Williams 7673 PEWTER CAST semi-gloss or color matched equivalent with COR approval.

b. Doors shall be painted with a gloss marine grade enamel in Sherwin Williams 7673 PEWTER CAST or color matched equivalent with COR approval.

c. Provide substitute paint for unique surfaces or areas where the paint specified herein is not manufacturer approved for the application.

2.2.3 Suspended Ceiling

a. 2’x2’ white, tegular, fine fissured, ceiling tiles Grainger 6YLR3 or equivalent with COR approval.

b. Ceiling grid to be 15/16” wide, white color.

2.2.4 Cove Base

a. 6” high vinyl base molding from Johnsonite in #63 BURNT UMBER.

PART 3 EXECUTION

3.1 ITEMS OF WORK

3.1.1 Asbestos Abatement.

a. The contractor shall remove and properly abate all Asbestos in the form of floor tile mastic and wall cove molding where present.

i. Black mastic and wall cove molding is present and to be abated in rooms 13, 14, and 15.

ii. Wall cove molding is present and to be abated in room 17.

3.1.2 Suspended Ceiling Work.

a. The contractor shall renovate the suspended ceiling system in room 14.

i. The contractor shall remove all existing ceiling tiles in room 14.

ii. The contractor shall add ceiling grid members to convert the existing grid system into a 2’ x 2’ system.

iii. The contractor shall install new ceiling tiles matching those described in section 2.2.3

iv. The contractor shall replace all utilities removed from ceiling grid to include but not limited to; lights, fire alarm systems, air diffusers, etc.

b. The contractor shall remove all existing suspended ceiling tiles and grid in rooms 13 and 15.

i. The contractor shall replace the entire ceiling grid system with a new system matching that described in section 2.2.3.

ii. The contractor shall replace all utilities removed from ceiling grid to include but not limited to; lights, fire alarm systems, air diffusers, etc.

3.1.3 Concrete Masonry Unit Wall Infill.

a. The contractor shall remove the accordion style wall section in the South wall of room 14.

b. The contractor shall infill the area of the accordion style wall with concrete masonry unit per specification 04 WVA 02 – Concrete Masonry Unit.

c. The contractor shall install a double door with louvered vents. The doors shall open into room 14 with no middle post. The door latch shall secure into both the threshold and the top of the frame.

i. Frame and doors shall be installed per specification 08 13 00 – Metal Doors

3.1.4 Floor Finishing

a. The contractor shall repair any cracks, dips, or ridges in the concrete floor of rooms 13, 14, 15, and 17 before cleaning and polishing for a polished concrete finish.

i. The floor finish shall be of Level 2 finish by polishing to 400-grit resin bond abrasive.

ii. The floor finish shall not include a floor cut depth of anything beyond that necessary to remove pre-existing surface coatings.

3.1.5 Wall Finishing

a. The contractor shall repair any holes or cracks in the walls with appropriate material based on the wall material.

b. The contractor shall prime and paint the walls of rooms 13, 14, 15, and 17. All paints shall comply with specification 09 90 00 – Interior Paints and Coatings.

i. Walls shall be painted Sherwin Williams 7631 “CITY LOFT” in eggshell or color matching equivalent.

ii. Trim shall be painted Sherwin Williams 7673 “PEWTER CAST” in semi-gloss or color matching equivalent.

c. The contractor shall replace all floor cove base in rooms 13, 14, 15, and 17 per section 2.2.4.

3.1.6 Door Finishing

a. The contractor shall clean, prime, and paint all doors and door frames per section 2.2.2 b.

b. The contractor shall install door thresholds as needed.

3.2 CLOSEOUT REQUIREMENTS

3.2.1 Construction and Demolition Debris

a. The Contractor shall submit copies of all Bills of Lading and Weight Slips associated with the disposal of construction and demolition (C&D) debris and/or recycled materials, under this scope of work. Submit documentation per Appendix A, “Consolidated List of Submittals”.

3.2.2 Cleanup of Work Site

a. The contactor shall clean all work areas and remove all tools, equipment, debris, materials, and all waste from the premises.

b. The contractor shall remove all debris from any remote holding locations, to include any excavation and concrete equipment chute cleanout debris.

c. The contractor shall remove their equipment from Watervliet Arsenal premises within five (5) working days after completion of project work.

3.2.3 Restoration of Work Site

a. The contractor shall repair any items, building surfaces, equipment or miscellaneous items which were damaged during the execution of this SOW. Items that cannot be repaired to restore original function or aesthetics shall be replaced in kind by the Contractor at no additional charge to the Government.

b. Grass, trees, and other vegetation affected by project work shall be restored to same or better condition as existed prior to the start of project work. The Contractor shall prepare the affected areas to eliminate uneven areas and low spots. Remove foreign materials, weeds, and damaged soil. The

Contractor shall scratch the area to a depth of three (3) inches where topsoil is to be placed. Spread topsoil to a uniform, compacted depth of less than five (5) inches over areas to be reseeded. Rake until smooth. The Contractor shall seed, fertilize, and water the area to establish grass.

3.2.4 Warranty

a. The contractor shall provide a 1 year warranty on all workmanship.

b. The contractor shall provide all manufacturer’s warranties for items of work completed on this

SOW.

3.2.5 As-Built Drawings

a. The contractor shall provide as-built drawings reflecting any changes made to the drawings provided in this SOW.

PART 4 APPENDICES

a. Consolidated List of Submittals

b. Quality Assurance Surveillance Plan (QASP)

c. Acronym Definitions

d. AMC Environmental Requirements Supplement

APPENDIX A: Consolidated List of Submittals

Line Item Submitted Submittal Needed By Submittal Reviewed By (Office)

1 Safety Data Sheets for Hazardous Materials

(SDS)

NLT 7 Calendar Days After Award

Safety Office

2 Signed Contractor Asbestos Notification Form NLT 7 Calendar Days After Award

Environmental Office

3 Signed Lockout/Tagout (LOTO) Notification Acknowledgement Record

NLT 7 Calendar Days After Award

Safety Office

4 Project Schedule NLT 7 Calendar Days After Award

COR

5 Contractor Safety Plan NLT 7 Calendar Days After Award

COR

6 Bills of Lading, Dump Slips for C&D Debris and Recycled Materials

Before Closeout Environmental Office

7 Asbestos Submittals per specification 02 82 13 – WVA Asbestos Abatement

NLT 7 Calendar Days After Award

COR

8 Concrete Masonry Submittals per specification 04 WVA 02 – Concrete Masonry Unit

NLT 7 Calendar Days After Award

COR

9 Paint Submittals per specification 09 90 00 – Interior Paints and Coatings

NLT 7 Calendar Days After Award

COR

APPENDIX B: Quality Assurance Surveillance Plan (QASP)

PURPOSE

This Quality Assurance Surveillance Plan (QASP) will be used as a guide to Government Quality Assurance Personnel (QAP). It provides a systematic method to evaluate the services the contractor is required to furnish.

SURVEILLANCE PROCEDURES

Timeliness: Progress is maintained to assure compliance with completion time.

Quality: Conformance with statement of work and industry standards.

Tasks: Performed according to statement of work requirements.

Problem Resolution: Contractor submits deliverables in accordance with the contract and resolves any deficiencies identified by the government in the final submission. Following final submission, contractor resolves any additional deficiencies identified by the government and resubmits and or corrects within one week.

Delivery: Contractor submits each deliverable in accordance with the statement of work and terms of the contract.

PERFORMANCE AREAS

Management Responsiveness: Evaluate the adequacy of the contractor’s responsiveness and their ability to keep the government informed of work progress and provides for early problem identification and effective corrective action plans.

Schedule Control: Evaluate the contractor’s adherence to completion schedule.

Performance: The contractor will be evaluated as to the workmanship and adherence to the statement of work.

EVALUATION CRITERIA

(Outstanding). Indicates performance clearly exceeds contractual requirements. The area of evaluation contains few minor problems for which corrective actions appear highly effective.

(Satisfactory). Indicates performance clearly meets contractual requirements. The area of evaluation contains some minor problems for which the corrective actions appear satisfactory.

(Unsatisfactory). Indicates the contractor failed to satisfy contractual requirements and recovery is not likely in a timely manner. The area of evaluation contains serious problems for which the corrective actions were ineffective.

DOCUMENTATION

Documentation used to perform surveillance will consist of random government inspections and inspection records, as well as the evaluation of final work product delivery by the project COR/COTR.

RATING

Contractor will be given an overall rating of Outstanding, Satisfactory, or Unsatisfactory by the Government Technical point of contact or Contracting Specialist Representative, if appointed, using the above 3 evaluation criteria.

APPENDIX C: Acronym Definitions

CMU: Concrete Masonry Unit

COR: Contracting Officer’s Representative

COTR: Contracting Officer’s Technical Representative

EMT: Electrical Metallic Tubing

IMP-E: Installation Management Public Works - Environmental

IMP-F: Installation Management Public Works - Facilities Engineering

LBP: Lead Based Paint

LOTO: Lockout/Tagout

NEC: National Electric Code

NEMA: National Electrical Manufacturers Association

NLT: No Later Than

PCB: Polychlorinated Biphenyls

POC: Point of Contact

PSF: Pounds per Square Foot

QAP: Quality Assurance Personnel

QASP: Quality Assurance Surveillance Plan

SDS: Safety Data Sheets

SOW: Statement of Work

UFGS: Unified Facilities Guide Specifications

VOC: Volatile Organic Compound

WAIC: Watervliet Arsenal Instructions for Contractors

WVA: Watervliet Arsenal

SECTION 01 00 00 Page 1

SECTION 01 00 00

GENERAL INFORMATION

05/19

TABLE OF CONTENTS

1.1 ACCESS TO INSTALLATION

1.2 ON-SITE PERMITS

1.3 OCCUPANCY OF PREMISES

1.4 EXISTING WORK

1.5 LOCATION OF UNDERGROUND UTILITIES

1.6 WORK RESTRICTIONS

1.7 ADMINISTRATIVE REQUIREMENTS

1.8 PROJECT SCHEDULE

1.9 SAFETY

1.10 SECURITY

1.11 ENVIRONMENTAL

1.12 MEDIA

2.1 GREEN PROCUREMENT PROGRAM

2.2 PAINT

2.3 HAZARDOUS MATERIALS

3.1 CLOSEOUT REQUIREMENTS

1.1 ACCESS TO INSTALLATION

1.1.1 Badges

All personnel shall report to the Visitor Control Center (VCC) daily to be issued a paper pass which grants access to WVA. All personnel must provide a driver’s license or state identification card (picture ID) to the security officer prior to being issued a paper pass.

1.1.2 Access Policy

All contractor personnel entering the installation and requiring unescorted access must have a valid purpose to enter and be sponsored by a US government organization or a contractor providing support on the installation. They must have their identity proofed and vetted through the National Crime Information Center (NCIC) database, and be issued, or in possession of an authorized and valid access credential from the Watervliet Arsenal installation.

At the discretion of the Commander, US Army Watervliet Arsenal, any individual known to have a criminal background involving violence or meets the disqualifying standards in the Final Credentialing Standards for Issuing Personal Identity Verification Cards under HSPD-12 (31 JUL 2008) and local command guidance, SECTION 01 00 00 Page 2 may be denied access to the Watervliet Arsenal. Fingerprinting of employees and any other security procedures deemed necessary for the security of Watervliet Arsenal (vehicle searches or x-raying packages, bags, briefcases) may be required based on the Force Protection Condition level at the time of access and whether the installation or building location is identified as a restricted area or Mission Essential Vulnerable Area (MEVA).

Non-citizens of the U.S. may not be approved for access.

1.1.3 Traffic Control

Post Speed Limit is 15 mph. Parking is allowed in valid spaces only. All valid spaces are clearly marked with white lines on both sides of the space. Vehicles parked in other than valid spaces are subject to being issued traffic citations requiring a monetary fine and/or an appearance before the U.S. Magistrate in Albany, N.Y. Motorists within the confines of WVA are subject to all New York State Vehicle and Traffic Laws.

Any moving or nonmoving violation may result in a traffic citation being issued. Loading and unloading of vehicles will be allowed only for the amount of time required to perform the function.

Vehicles cannot be left unattended in other than valid parking spaces without explicit approval by the Contracting Officer. If a patrol officer can approach a vehicle, write a traffic citation, affix that citation to the vehicle, and depart the area with no one present at the vehicle, that vehicle is considered to be unattended.

1.1.4 Deliveries

Deliveries to contractors shall enter the post through the South Gate. Contractors expecting deliveries should notify the South Gate (266-5821) prior to the arrival of the delivery. The contractor’s representative must accept deliveries. Materials which are delivered to the site are the responsibility of the contractor. Storage and special conditions must be coordinated with the Contracting Officer.

1.2 ON-SITE PERMITS

1.2.1 Utility Outage Requests and Utility Connection Requests

Schedule work to minimize outages. For utility outages and connections required during the execution of work that affect existing systems, schedule outside the regular working hours or on weekends, as approved by the Contracting Officer.

Schedule utility outages and connections to minimize disruptions to the Government. No additional payment will be provided for utility outages and connections required to be performed outside the regular work hours. The Government will perform all utility isolation and re-energization. The contractor shall not isolate or re-energize any utility system without explicit approval from the Contracting Officer.

Submit requests for utility outages and connections in writing to the Contracting Officer for approval at least seven (7) calendar days in advance of the time required. In each request, state the system involved, area involved, approximate duration of outage, and the nature of work involved.

The Contractor shall sign and submit a “Lockout/Tagout (LOTO) Notification Acknowledgement Record” prior to working on or de-energizing any electrical equipment.

1.2.2 Hot Work Permits for Burning, Welding, Grinding

SECTION 01 00 00 Page 3

Obtain permit for welding, burning, use of flame, or entry into confined space from WVA Fire Department by calling (518)266-5990 each day the permit is to be used.

Whenever open flame devices are used, the contractor will provide an approved fire extinguisher. Minimum size will be a 10-pound chemical (A-B-C) powder or CO2.

Retain a worker at floor level at all times during cutting/welding operations with proper extinguishers to assure that sparks are properly controlled. Fire Watch personnel must also be provided for hot tar kettles while in use, with approved fire extinguisher and sandbag (dike) around tar kettle. Contractor must have a fire blanket to cover flammable material that cannot be moved.

1.2.3 Confined Space Entry Permits

Obtain permit for welding, burning, use of flame, or entry into confined space from WVA Fire Department by calling (518)266-5990 each day the permit is to be used.

All contracted work is subject to WVA Regulation 385-1 Confined space entry procedure. Contractors shall provide proof of training in confined space entry procedures. Contractor shall provide the COR a completed WVA Form 385-17-E, confined space entry permit or equivalent company form prior to starting any work within a confined space. Contractors shall provide their own calibrated confined space Monitors when entering all confined spaces. Contractors will have their own retrieval tripods and harnesses.

1.3 OCCUPANCY OF PREMISES

For all building(s) which will be occupied during performance of work under this Contract, the contractor shall arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.

1.4 EXISTING WORK

In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

1.5 LOCATION OF UNDERGROUND UTILITIES

Obtain digging permits prior to start of excavation, and comply with Installation requirements. For

Government-owned utilities, request clearance from the Contracting Officer. Clearance and marking will then be performed by the Government. The Contractor shall obtain a copy of the completed Utility Clearance Permit (WVA Form 420-2-E) from the Contracting Officer prior to digging. Verify existing utility locations indicated on contract drawings, within area of work.

Identify and mark all other utilities not managed and located by the Government via Dig Safe. Scan the site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities, and any type of obstruction not indicated, or specified to be removed, that is

SECTION 01 00 00 Page 4 indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.

1.6 WORK RESTRICTIONS

1.6.1 Work Hours

Visitors and Contractors will only be allowed access to Watervliet Arsenal during normal duty hours, which are 7:00 AM through 4:00 PM, Monday through Thursday, and 7:00 AM through 3:00 PM on select Fridays (the arsenal is closed every other Friday). Work may be performed on shutdown Fridays, after normal duty hours, Saturdays, Sundays or holidays only after the contractor has submitted their request two working days in advance through the project COR or technical point of contact for request evaluation and approval by the Contracting Officer. (Note: request approval is not guaranteed). If a federal holiday falls on a Saturday or Sunday, the preceding Friday or following Monday is a work holiday. The COR or Arsenal Point of Contact will submit a request to the Security Office and arrange for a responsible arsenal POC to be on post at all times when the visitor is on post.

1.6.2 Special Scheduling Requirements

Permission to interrupt any active roads, sidewalks, stairwells, primary corridors, or utility services must be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.

1.6.3 Notification of Attendance

The contractor is responsible to inform the COR and/or Project Inspector of their presence on post at all times. At the beginning and end of each workday, the Contractor is required to notify the COR and/or Project Inspector of location(s) on post where work is being performed or has been completed for the day.

It is the responsibility of the Contractor to inform all their sub-contractors of all the instructions for reporting attendance. Subcontractors are responsible to report project work attendance through the prime contractor to the COR whenever they are on post.

1.6.4 Vehicles in Buildings

Contractors' vehicles and equipment using fuel shall receive clearance from the Fire Chief before entering the building. Refueling of vehicles in a building requires Fire Department standby.

1.6.5 Trailers, Storage Containers, Temporary Offices

The placement of all storage shed/trailers/temporary offices are subject to the approval of the Public Works Division, the Watervliet Arsenal Fire department, and the Watervliet Arsenal Security Department. The contractor shall submit their placement request in writing 30 days in advance of the project COR or technical POC for request evaluation and approval. Note: request approval is not guaranteed.

All temporary sheds, trailers or offices within thirty feet of any Arsenal structure must be equipped with a temporary sprinkler system as required by NFPA 13. The Fire Inspection Staff will assist contractors in determining sprinkler requirements on site, upon request. Call extension 5990 for fire inspector assistance.

Prominently display the following information on all contractor and subcontractor, owned, leased or rented motorized and wheeled equipment, dumpsters, storage containers/sheds, trailers, and offices.

a. Contractor Company Name

SECTION 01 00 00 Page 5

b. Project Number/Contract Number or Equivalent

c. Point of Contact (POC) Name and Phone Number

1.6.6 Historical Items

The Contracting Officer or the COR reserves the right to declare any item or items resulting from removals, excavation, demolition, cleanup, or any other contract operation, as historically significant items. Included in this category are items of weaponry, ammunition, uniforms, equipment, relics, architectural features, archeological features or any other item that represents a part of the past history of the Arsenal. It is incumbent upon the contractor to report the finding of any item that may have historical significance. If the contractor discovers any item, which could be from the above category, all work will cease and the Contracting Officer or the COR will be contacted. These items shall remain in the property of the Arsenal and be delivered by the contractor to an area designated by the Contracting Officer or the COR. Historical items shall be carefully removed and carefully handled to prevent damage.

1.7 ADMINISTRATIVE REQUIREMENTS

1.7.1 Watervliet Arsenal Information for Contractors (WAIC)

The contractor shall perform all work in strict conformance with Watervliet Arsenal Instructions for Contractors (WAIC). The contractor shall read and understand this document prior to submitting a proposal.

The WAIC is publically available at: http://www.wva.army.mil/Documents/Contracting/WAIC.pdf

1.7.2 Preconstruction Meeting

After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the safety requirements, submittal requirements, scheduling programming, prosecution of the work, and clear expectations of the project requirements. Major subcontractors who will engage in the work must also attend.

1.7.3 Jobsite Documents

The Contractor shall be responsible to maintain a current copy of the Project Design Documents at the worksite(s), available to all Contractor and Subcontractor employees for reference. The Contractor shall promote the distribution of the SOW, drawings, and specification sections to all Contractor and Subcontractor foremen, site supervisors, and employees providing construction services at the Watervliet Arsenal.

1.7.4 Disposition of Materials and Equipment

The contractor shall furnish documentation of the final disposition of all materials and items leaving Watervliet Arsenal. If an item is resold intact, indicate such action for the item and the name and address of purchaser. If oil is drained from an item, provide documentation for both the oil and the item by identifying final disposition location and management method for each (e.g., recycled, incinerated, land filled). All materials and items leaving Watervliet Arsenal shall be managed strictly in accordance with all applicable environmental regulations. The contractor shall indicate intentions for all such materials and items at the pre-construction meeting, for approval by Watervliet Arsenal.

1.8 PROJECT SCHEDULE

Create a project schedule and submit for Government review and approval. The project schedule shall detail the phases of work and the overall timeline for the execution of the work. Include delivery dates, appropriate http://www.wva.army.mil/Documents/Contracting/WAIC.pdf

SECTION 01 00 00 Page 6 milestones, and clearly detail any requirements for work performed outside of regular hours of operation.

1.9 SAFETY

1.9.1 Emergencies

All emergencies must be reported regardless of scope. All fires must be reported regardless of size. All spills (oils, chemicals, fuels, coolants, etc.) must be reported regardless of size. Discovery of all pre-existing spills must also be reported regardless of size. First aid is available at the Arsenal Fire House 24 hours/day.

Emergency phone numbers:

Fire: Ext (518)266-5222

Ambulance: (518)266-5333

Security: (518)266-5444

Safety Hotline: (518)266-4537

Safety Manager: (518)266-5677

Industrial Hygiene: (518)266-4517 or (518)266-4516

Spill Hotline: (518)266-5888

1.9.2 Local Safety Rules

The contractor shall adhere to local safety rules which include, but are not limited to, the following.

a. Work area will be barricaded and appropriately marked.

b. The work area will be kept clean and orderly. Waste materials are to be located so as not to create a hazard.

c. Dust and noise are to be kept to a minimum and within allowable limits (OSHA AND ACGIH TLV’s and PEL’s), to be determined by the contracting representatives with the assistance of Industrial Hygiene and Safety.

d. Existing means of egress will be adequately maintained during construction.

e. Compressed gas cylinders shall be secured in an upright position.

f. Flashback protection is required for oxygen and acetylene welding.

g. Hand and portable power tools shall be maintained and used in a safe manner.

h. Ground fault circuit interrupters are to be used with portable electric powered tools.

i. Proper protective clothing & equipment (PPE) must be provided and worn where necessary.

j. Safety glasses must be worn in designated areas in the arsenal and within any designated construction work area.

SECTION 01 00 00 Page 7

k. Hard hats must be worn when overhead work is being performed.

l. Ladders are to be free of defects and secured from movement.

m. Scaffolds or elevated work platforms are to be properly erected and adequately guarded including guardrails, toe boards, etc, as required by OSHA.

n. Fall protection will be used whenever work is elevated above 6 feet.

o. Sides of all excavations in which employees are exposed to danger from moving ground shall be guarded by sloping, shoring, or other equivalent means.

p. Wheeled equipment (trailers, carts, etc.) must be free of defects and secured from movements.

q. Internal combustion engine exhausts are to be vented to the outside.

r. Bi-directional vehicles (fork trucks, dump trucks, shop carts, etc.) will be equipped with backup alarms.

s. Vehicular traffic flow in and out of building (work site) will be such so as to not endanger safety of personnel.

t. Material Safety Data Sheets for all chemicals/paints are to be made available at the work site and all containers of chemicals will be labeled for identification.

u. Lock-out/tag-out procedures per OSHA will be used as required.

1.9.3 Accident Prevention Plan

If required per Federal Acquisition Regulation construction clause 52.236-13(f), the contractor shall submit an Accident Prevention Plan prior to commencement of contract work.

1.9.4 Safety Data Sheets (SDS)

Submit SDS for all hazardous materials used on the project. SDS for paints, chemicals, and other liquids shall be made available at the work site and all containers shall be labeled for identification.

1.9.5 Lasers

All laser operations must be in accordance with ANSI Z13.6.1. The Radiation Safety Officer must be notified when a laser will be used on a worksite.

1.9.6 Radioactive Sources

Contractor must comply with U.S. Army requirements for Radioactive Sources well as Nuclear Regulatory Commission and local WVA requirements Watervliet Arsenal's Radiation Safety Officer (RSO), in the Safety Office phone: 518-266-5635, must be notified when any radioactive sources are to be brought into WVA and must be given a copy of required licenses. The Watervliet Arsenal RSO must also be provided a POC before materials are to be brought on post for any potential follow-up questions or required information. No one will be allowed to bring any radioactive source on post until an Army Radiation Permit is issued by the Commanding Officer through the WVA RSO.

SECTION 01 00 00 Page 8

1.9.7 Sound Levels

Sound levels in the vicinity of equipment installed under any project shall not exceed 85 BA following construction when the equipment is in use (measured by a sound level meter set for A scale, slow response).

The vicinity of installed equipment is defined as a distance not to exceed 1 meter from the equipment.

Techniques such as sound level averaging or exposure time weighting shall not be used to meet this requirement. If an 85-dBA limit is beyond the state of art for the equipment, documentation verifying the minimum level achievable shall be submitted to WVA for review and acceptance at time of equipment submittals. This documentation shall be provided and reviewed/approved prior to ordering any materials.

1.9.8 Gasoline Containers and Flammables

Gasoline will be stored in safety containers equipped with self-closing lids and other features as certified by the Underwriters' Laboratories. Flammable liquids will be kept in National Fire Protection Association or UL approved containers; Fire Department (extension 5990) will be called in event of a question. If gasoline or any other type fuel is kept in a portable tank it must have secondary containment or the tank be double walled and the product labeled on the side of the tank (i.e. flammable).

1.9.9 Emergency Evacuation

All contractor personnel working on the site will be responsible to be familiar with the building’s existing emergency evacuation plan, if available and applicable to the project’s worksite. The contractor shall provide the COR with the contractor’s emergency evacuation plan from the worksite if different from the existing emergency evacuation plan.

1.10 SECURITY

1.10.1 Elevated Threat Level Condition

Impact on contractor performance during increased FPCON during periods of increased threat. During FPCONs Charlie and Delta, services may be discontinued/postponed due to higher threat. Services will resume when FPCON level is reduced to level Bravo or lower.

1.10.2 Random Anti-Terrorism Measures Program (RAMP)

In accordance with AR 525-13, contractor personnel working on an installation are subject to participation in installation RAMP security program (e.g. vehicles, wearing of ID badges, etc) and installation security program.

1.10.3 Camera Use

The Security Office and Public Affairs Officer must approve all cameras use prior to any pictures being taken, to include using a photographic-capable cell phone as a photographic device. Requests must be submitted to the WVA COR then routed to Security and then to the Public Affairs Officer. Violations may result in the camera and film being confiscated and a citation being issued for an appearance before the U.S.

Magistrate in Albany, NY.

For any photos that have been approved by the Security Office and Public Affairs Officer be advised that the photos contain military imagery that is owned by the US Government: US Army Watervliet Arsenal. It is not to be used for any purpose other than the purpose for which it is furnished nor distributed or reproduced for any purpose to persons other than the individuals specified to receive it, or their employees, without written consent of the US Army Watervliet Arsenal.

SECTION 01 00 00 Page 9

All photos must be reviewed by the security office before the photo capture system (i.e., camera, cell phone, etc) has left the arsenal.

1.10.4 Explosives

The use of explosive materials is prohibited.

1.10.5 Contraband

Alcohol, illegal drugs, and any firearms are prohibited. Violations may result in the items being confiscated and a citation being issued for an appearance before the U.S. Magistrate in Albany, NY.

1.10.6 Restriction of Documents

Documents provided by WVA contain proprietary information and are to be used only in support of their current authorized release. Other requests for documents must be referred to the Contracting Officer, Army Contracting Command –Warren (ACC-WRN) (WVA), 1 Buffington Street, Watervliet, NY 12189.

Documents shall be destroyed to prevent disclosure and reconstruction of the contents upon completion of contracted work.

1.10.7 Security of Equipment

Contractors are responsible for securing all of their equipment. WVA is not responsible for stolen or lost items.

1.11 ENVIRONMENTAL

1.11.1 Asbestos

OSHA Regulation 29CFR1910 and NY State Industrial Code Rule 56, (12NYCRR56) shall be followed with regard to asbestos removal. If asbestos material is unexpectedly encountered during work, the contractor must contact the COR immediately. The contractor shall sign and submit the "Contractor Asbestos Notification Record" prior to starting work on any facility project.

All asbestos waste, except where WVA provides written authorization to do otherwise, shall be Properly containerized, labeled, manifested and disposed of by Contractor, at their expense, according to all Local, State and Federal laws. All manifests for such waste, including weights, shall be presented to WVA Environmental staff for signature at least 24 hours prior to removal from WVA for disposal. The Generator copy of each Manifest shall be left with Environmental at the time of signing, for WVA records.

All asbestos personnel shall provide their training certificates to the safety office prior to beginning work on the job site. Also all personnel shall have their training credentials with them at all times on the job site 34.

1.11.2 Oils and Chemicals

The contractor shall furnish and utilize secondary containment measures for all storage activities. The contractor shall protect oils and chemicals from rainwater at all times. Containers shall be appropriately closed and labeled; the load shall be adequately secured during all transportation on post. The contractor shall not abandon any oil and/or chemicals on post at WVA.

1.11.3 Use of Fire Hydrants

SECTION 01 00 00 Page 10

Fire hydrants shall not be used without the permission of Facilities Engineering and notification of the Fire Department (extension 5990). If permission is granted to use hydrants, the contractor will provide adapters, valves and hoses. A backflow preventer will also be required of the contractor. It is the responsibility of the contractor to insure the hydrants are shut off and have drained properly. The Fire Department must be notified when finished.

1.11.4 Backflow Prevention for Potable Water

Backflow prevention via certified double check valve or equivalent approved device is required for any connections to the arsenal water system throughout construction work.

1.11.5 Discharges

Unless granted prior written approval, there shall be no discharge to the sanitary sewer, the storm sewer, the industrial sewer system, or the Industrial Waste Treatment Plant (IWTP). Except when WVA has established with the contractor a prior written agreement regarding discharge of "purge water" originating from groundwater monitoring wells and/or "decontamination water" originating from activities associated with groundwater monitoring wells, there shall be no dumping of oil or chemicals or fluids to the ground.

1.11.6 Hazardous Waste Disposal

All hazardous waste shall be relinquished to WVA at a location on post as designated by the COR, thereafter WVA will be responsible for management of the hazardous waste. Hazardous waste shall be relinquished to WVA in accordance with the RCRA "three day" rule. Drums of hazardous waste shall not remain outdoors overnight. Other wastes include any spent material such as garbage, packaging, residues, construction and demolition debris, excavated soils and earthen materials not designated for immediate reuse, etc., which is known by WVA and/or demonstrated by the contractor via appropriate sampling and analysis to not be hazardous waste, where such a demonstration shall be to the satisfaction of WVA.

Contractor shall furnish and properly label new, unused, appropriate drums and/or containers (including, but not limited to, compliance with DOT's Performance Oriented Packaging Standards [POPS]) for containerizing waste.

Contractor supplied dumpsters shall be covered with water proof covers to prevent precipitation from entering the dumpster. Covers shall be secured in place whenever the contractor leaves the job site, and whenever precipitation is possible or occurring.

1.11.7 Non-hazardous Waste Disposal

The contractor is responsible for disposal of non-hazardous wastes. Disposal of wastes at private sites such as sites advertising clean fill wanted, etc. is prohibited. The contractor shall comply with 6 NYCRR Part 364 for all waste hauling activities.

The contractor shall furnish copies of documents for each waste shipment, such as Bills of Lading, etc (including "light weight" upon entering WVA, and "heavy weight" upon exiting WVA) through the COR to Facilities Engineering. The project shall not be considered complete until all waste shipment documentation has been submitted and accepted by the Contracting Office.

1.12 MEDIA

The Arsenal public affairs officer must approve any media announcement or press release that mentions the Watervliet Arsenal in either the headline or in the text of the release. Additionally, no media activity may occur on the Arsenal without prior coordination with the public affairs officer. Coordination or requests for

SECTION 01 00 00 Page 11 approval must be submitted to the public affairs officer at least two working days prior to the event.

2.1 GREEN PROCUREMENT PROGRAM

All construction materials shall meet the applicable requirements of the DoD Green Procurement Program, specifically recycled content products, environmentally preferable products and services, bio-based products, energy-and water-efficient products, alternate fuel vehicles and alternative fuels, products using renewable energy, and alternatives to hazardous or toxic chemicals.

2.2 PAINT

2.2.1 Lead and Chromium Free

All paints applied shall be lead-free and chromium free. Lead based paint is paint that contains more than six one hundredths of one percent, 0.06%, lead in weight.

2.2.2 Recycled Content Requirements

To meet the Affirmative Procurement Program (Federal Government’s Buy Recycled Requirements) all paint used in the project shall adhere to the below listed requirements of the Comprehensive Procurement Guideline for recovered materials. This applies only to interior latex paint, only if available at the time of the project.

Consolidated Latex Paint shall contain 100% Post consumer content.

a. Reprocessed Latex Paint (White, Off-White, Pastel Colors) shall contain 20% Post consumer content.

b. Reprocessed…