W911PT-19-Q-0131.pdf
PDF 972 KB Posted
- Attached to
- FIBER INSTALLATION AT WATERVLIET ARSENAL
- Solicitation number
- W911PT-19-Q-0131
About this file
Solicitation
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W911PT-19-Q-0131-0001.pdf | ||
| SITE_VISIT_INFORMATION.docx | DOCX document | |
| NY20190002_-_8-16-2019.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SEE SCHEDULE
REQUEST FOR QUOTATIONS
(THIS IS NOT AN ORDER) 1
PAGE OF PAGES
1. REQUEST NO. 2. DATE ISSUED RATING
W911PT19Q0131 30-Sep-2019 5a. ISSUED BY
8. TO: NAME AND ADDRESS, INCLUDING ZIP CODE
SEE SCHEDULE
IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in Block 5a. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this
Request for Quotations must be completed by the quoter.
11. SCHEDULE (Include applicable Federal, State, and local taxes)
ITEM NO.
(a)
SUPPLIES/ SERVICES
(b)
QUANTITY
(c)
UNIT
(d)
UNIT PRICE
(e) (f)
SEE SCHEDULE
AMOUNT
% No. %
NOTE: Additional provisions and representations [ ] are [ ] are not attached.
13. NAME AND ADDRESS OF QUOTER (Street, City, County, State, and ZIP Code)
14. SIGNATURE OF PERSON AUTHORIZED TO
SIGN QUOTATION
15. DATE OF
QUOTATION
16. NAME AND TITLE OF SIGNER (Type or print) (Include area code)
TELEPHONE NO.
AUTHORIZED FOR LOCAL REPRODUCTION STANDARD FORM 18 (REV. 6-95)
PREVIOUS EDITION NOT USABLE Prescribed by GSA FAR (48 CFR) 53.215-1(a)
THIS RFQ X[ ] IS [ ] IS NOT A SMALL BUSINESS SET-ASIDE
6. DELIVER BY (Date)
SEE SCHEDULE
AND/OR DMS REG. 1
UNDER BDSA REG. 2
4. CERT. FOR NAT. DEF.3. REQUISITION/PURCHASE
REQUEST NO.
ARMY CONTRACTING COMMAND-WARREN (WVA)
ATTN: CCTA-HDW/BLDG 10
1 BUFFINGTON STREET
WATERVLIET NY 12189-4000
9. DESTINATION (Consignee and address, including ZIP Code)
7. DELIVERY
[ ]X FOB
DESTINATION
[ ] OTHER
(See Schedule)
15-Oct-2019(Date)
PLEASE FURNISH QUOTATIONS TO THE ISSUING OFFICE IN BLOCK 5a ON OR BEFORE CLOSE OF BUSINESS:10.
518-266-4641MARIA DECRESCENZO
(Name and Telephone no.) (No collect calls)5b. FOR INFORMATION CALL:
d. CALENDAR DAYSc. 30 CALENDAR DAYSb. 20 CALENDAR DAYS12. DISCOUNT FOR PROMPT PAYMENT a. 10 CALENDAR DAYS
W911PT19Q0131
Section SF 30 - BLOCK 14 CONTINUATION PAGE
LOCAL NARRATIVES
A.__ NOTICE OF WATERVLIET ARSENAL INFORMATION/REQUIREMENTS
(a) IMPORTANT DELIVERY/QUALITY REQUIREMENTS:
(1) ALL OFFERORS MUST CAREFULLY REVIEW THE DELIVERY REQUIREMENT IN THE
REQUEST FOR QUOTE OR SOLICITATION. WHEN SUBMITTING AN OFFER/BID, PLEASE
ENSURE THAT YOU CAN MEET THE DELIVERY SCHEDULE.
(2) ON TIME DELIVERY IS VERY CRITICAL. THEREFORE, YOU MUST ADHERE TO THE
DELIVERY REQUIREMENTS INDICATED IN ANY RESULTANT AWARD. FAILURE TO
COMPLY WITH THE CONTRACTUAL DELIVERY SCHEDULE, MAY RESULT IN TERMINATION
OF THE ORDER OR REQUIRE CONSIDERATION IF THE GOVERNMENT ELECTS TO EXTEND
DELIVERY. (NOTE: Non-availability of raw materials, subcontractor issues, scheduling conflicts, should be considered at the time you are submitting your offer/bid. They are not acceptable excuses for failing to meet the delivery after award).
(3) PROVIDING QUALITY PRODUCTS THAT CONFORM TO THE CONTRACT ARE JUST AS
IMPORTANT AS MEETING THE REQUIRED DELIVERY. DELIVERY OF NON-CONFORMING
PRODUCTS RESULTS IN DELIVERY DELAYS AND INCREASED COSTS TO THE ARSENAL.
(4) PAST PERFORMANCE FOR QUALITY AND DELIVERY MAY BE A MAJOR
CONSIDERATION IN MAKING DETERMINATIONS FOR FUTURE CONTRACT AWARDS.
NOTICE: Throughout this document we may use the terms “we” and “you”, the term “we” means the government of the United States of America, and the term “you” means the contractor.
(b) WATERVLIET ARSENAL INFORMATION FOR CONTRACTORS:
“Watervliet Arsenal Information for Contractors” document is incorporated by reference in all solicitations and contracts. The full text version of the instructions is available at Internet address:
http://www.wva.army.mil/Documents/Contracting/WAIC.pdf Upon request, the contracting officer will make its full text available.”
POC - CONTRACT SPECIALIST/BUYER: Maria DeCrescenzo
TELEPHONE NUMBER: 518-266-4641
E-MAIL ADDRESS: maria.d.decrescenzo.civ@mail.mil
CONTRACTOR DUNS NUMBER/CAGE CODE/FAX NUMBER:
Please provide the following information for your company.
VENDOR NAME: _________________________
VENDOR POC: __________________________
POC PHONE: ____________________________
E-MAIL ADDRESS (see note below): __________________________
DUNS NUMBER _______________________
CAGE CODE (if known) __________________
TAX ID NUMBER ________________________
VENDOR FAX NUMBER ________________
NOTE: Your e-mail address is required so that in the event you receive the resultant award, we can e-mail it to you.
If we experience difficulties with e-mail, it will be data faxed.
(c) AWCF BULK FUND _X__ DOES ___ DOES NOT APPLY
(d) POSTERS:
(1) Contracts for Material, Supplies, Articles and Equipment Exceeding $15,000/Service Contract Labor Standards. Orders subject to these Acts require contractors to post WH Publication 1313, “Employee Rights on Government Contracts”.
(2) Construction Orders. Orders for construction require contractors to post WH Publication 1321, “Employee Rights under the Davis Bacon” and the Office of Federal Contract Compliance poster on “Equal Employment Opportunity is the Law.”
(3) These posters can be accessed electronically at http://www.dol.gov .
(4) Hard copies of the posters will be made available upon request to the contracting officer.
(e) PAYMENTS:
Any vendor that receives an award (except those paid by credit card or accommodation check) can view invoice payments made by DFAS at https://wawf.eb.mil/ using the “my invoice” system. You will be required to register in order to view payments. Payment information is maintained for 120 days from invoice payment. Vendors can find out when invoices have been paid by Electronic Funds Transfer (EFT), etc. This website can save valuable time and frustration over billing questions and it is a free service.
(f) RELEASE OF INFORMATION:
The contractor shall not release or authorize release of DoD specifications; acceptance test results; information involving critical military technology; or any other information in which the DoD maintains proprietary rights, or is otherwise confidential or classified. This restriction includes any endorsement by the Department of Army of a contractor. Release of information under the circumstances referenced above requires the prior written approval of the Contracting Officer responsible for this contract. It is the contractor’s responsibility to be familiar with, and comply with the requirements of Chapter 5, page 22, paragraph 5-48, of AR 360-1 may be found at http://www.usapa.army.mil/pdffiles/r360_1.pdf
C. __REQUEST FOR QUOTE RESPONSES (Oct 2016) (ACC-WRN (WVA))
ALL RESPONSES MUST BE ELECTRONIC. YOU MAY SUBMIT YOUR QUOTE RESPONSES USING ONE
OF THE FOLLOWING METHODS:
1) Email to maria.d.decrescenzo.civ@mail.mil
2) Federal Business Opportunities-FedBizOpps (FBO)
Requirements for the online FBO bid submission:
1. Vendors must login to the FBO System to be able to submit electronic responses for opportunities.
2. Vendors must also registered in the System for Award Management (SAM) at www.sam.gov (a Federal Government owned and operated free web site) and have a CAGE Code and CCR Marketing Partner Identification Number (MPIN).
3. Once logged into the FBO System, vendors will be asked to enter basic information and then will be directed to upload one or more files containing the offer and any additional information as outlined in the solicitation.
4. FBO will send an email to the email address on file for the user confirming the electronic submission.
5. For additional information on submitting electronic bid responses via the Federal Business Opportunities System reference the FBO Vendor Guide – Section 4.3.1 Submitting an Electronic Response Topic (https://www.fbo.gov/downloads/FBO_Vendor_Guide.pdf).
REQUEST FOR QUOTES MUST BE FILLED OUT COMPLETELY AND SENT IN ITS ENTIRETY TO BE
CONSIDERED RESPONSIVE.
C.__ Submission of Recordable Injuries and Illness Cases (Dec 2012) (ACC-Warren (WVA)) Watervliet Arsenal is pursuing OSHA Voluntary Protection Program (VPP) recognition. The VPP impacts all contractors whose employees cumulatively work more than 1000 hours per quarter within a calendar year at Watervliet Arsenal (herein referred to as “applicable contractors”).
It is the contractor’s responsibility to ensure its employees and managers are in full compliance with OSHA requirements and have a general understanding of VPP. Detailed information on VPP is available on the OSHA website at http://www.osha.gov/dcsp/vpp/index.html . All contractors, whether regularly involved in routine site operations or engaged in temporary projects such as construction or repair, must follow the safety and health rules of Watervliet Arsenal.
Applicable contractors are required to annually submit to Watervliet Arsenal, ATTN: TAWV-XO-S/Safety Office, Bldg. 10, 1 Buffington Street, Watervliet, NY 12189-4000 or email: usarmy.watervliet.tacom.list.wate-safety@mail.mil the following documents (covering the previous calendar year quarters) by 15 January:
- Total Case Incidence Rate (TCIR) - the number of recordable injuries and illness cases per 100 full-time employees that a site has experienced in a given time frame.
- Days Away, Restricted, and/or Transfer Case Incident Rate (DART) - Number of recordable injuries and illness cases per 100 full-time employees resulting in days away from work, restricted work activity, and/or job transfer that a site has experienced in a given time frame.
- OSHA Form 300A
Applicable contractors may submit the above immediately following the completion of a quarter, if desired.
H.__ SERVICES/CONSTRUCTION REQUIREMENTS
(a) SCHEDULE UNIT OF MEASURE NOTE: When "LOT" is stated as a unit of measure it is the equivalent to
"JOB".
(b) WORK PERFORMED ON-SITE AT WATERVLIET ARSENAL:
The contractor agrees that each employee working at Watervliet Arsenal will sign the “Contractor Personnel Agreement on Non-Disclosure of Watervliet Arsenal Technology below. Signatures must be received by the Contract Administrator before work may begin and any resultant delay won’t be considered an excusable delay to contract performance as defined in the contract clause “Default”. Additional copies of this Non-Disclosure Statement can be found on the Internet at http://www.wva.army.mil/Documents/Contracting/nondis.pdf
(d) CONTRACTOR PERSONNEL AGREEMENT ON NON-DISCLOSURE
OF WATERVLIET ARSENAL TECHNOLOGY
(1) The Undersigned, as an employee of _________________________ (Name of Firm) agrees to the following terms and conditions.
(2) Any knowledge gained, as a result of my being permitted on Watervliet Arsenal’s premises, concerning cannon production technology (as defined below) or other technology on any defense item being manufactured or developed at Watervliet Arsenal, will not be released outside of _________________________ (Name of firm) and/or the United States of America (this prohibition includes, but is not limited to, the company’s domestic and foreign subsidiaries, affiliates, etc.), nor will such technology be used to manufacture or assist another in the manufacture of cannon (as described below) or other defense items being manufactured or developed at Watervliet Arsenal, without the written prior approval of Watervliet Arsenal.
(3) Definitions:
(a) CANNON: is defined as any and all components/parts of a complete assembly consisting of a tube, breech mechanism, tube attachments, muzzle appendages, firing mechanisms, and all integral components.
It may also be a component of a weapons system of 40mm Bore or over such as tank guns, towed and self-propelled howitzers, naval guns, mortars and recoilless guns.
(b) CANNON PRODUCTION TECHNOLOGY: is defined as the technical data package and manufacturing technology.
(1) TECHNICAL DATA PACKAGE: cannon engineering drawings, specifications and standards.
(2) MANUFACTURING TECHNOLOGY: technical knowledge, documentation, assistance and equipment and machines used and/or useful in the manufacturing of cannon.
(c) TECHNICAL KNOWLEDGE: the know how collected, trade secrets, production experience and special skills necessary for the production of cannon and the technical information and inventions necessary for the manufacture of cannon and relating to the manufacture of cannon.
(d) TECHNICAL DOCUMENTATION: manufacturing technical data comprised of drawings, specifications, schemes, composition, descriptions, methods of calculations, instructions and other information necessary for the manufacture of cannon.
(e) TECHNICAL ASSISTANCE: all assistance required to make practical and economical use of the technology required to manufacture cannon, such as delivery of documentation, training of personnel, instructions, consultations and acquainting of specialists with the most economical method of using this technology in the manufacture of cannon.
(f) EQUIPMENT AND MACHINES: production machines, machine accessories, apparatuses, spare parts and tooling used for cannon manufacture.
TYPED OR PRINTED NAME, SIGNATURE DATE
TYPED OR PRINTED NAME, SIGNATURE DATE
TYPED OR PRINTED NAME, SIGNATURE DATE
(e) JOB SITE AVAILABILITY:
The work site will be available for performance during normal business hours:
Monday through Thursday Business Hours: 7:00 a.m. EST to 4:00 p.m. EST
Friday Business Hours: Every other Friday from 7:00 a.m. EST to 3:00 p.m. EST
Fridays will be staggered with every other Friday being a closed business day. The first Friday of 2017 to be closed is January 6, 2017.
Based on the above, service contractors should call contract/purchase order administrator in advance if service is scheduled for a Friday to determine if the Arsenal will be open for business.
When a federal holiday is normally observed on Friday, the Arsenal may be closed on the preceding Thursday. In this case, contact the contract/purchase order administrator in advance if scheduling service to determine if the Arsenal will be open for business.
Work at other than the above hours won’t be allowed unless the contractor makes an application at least 48 hours in advance and gets written contracting officer approval. No guarantee is made that the job site will be made available other than as stated above.
(f) CONTROL OF FOREIGN VISITORS TO WATERVLIET ARSENAL:
Offerors are advised that any employee or representative of their company who is not a U.S. citizen, (or is representing a foreign company) and is a U.S. citizen), planning on visiting the Watervliet Arsenal for the purpose of attending: bid conferences, bid openings, site visits, engineering services, or any other visit related to this solicitation will be escorted at all times by an arsenal representative while on the installation grounds.
Therefore, offerors must notify the Contracting Officer in advance (a minimum of two [2] weeks) of any proposed visit by a non-U.S. citizen or U.S. citizen representing a foreign firm, to assure proper clearance for entry into the arsenal. Failure to comply, or disclose a foreign national visitor, may subject the Contractor to the penalties set forth in 18 U.S.C.A. Section 1001, Chapter 14.
Due to manpower constraints, Watervliet Arsenal is often unable to provide escort services during contract performance. Therefore, if the resulting contract requires performance on Watervliet Arsenal property, employees, individuals or subcontractors representing the successful offeror who are not U.S. citizens may not, depending on staffing levels and the availability of escorts, be allowed access to the Arsenal for purpose of contract performance.
Be further advised that the inability of the Arsenal to provide escorts resulting in denial of access to Watervliet Arsenal of the aforementioned personnel will not be considered an excusable delay to contract performance as defined in the contract clause “Default” contained in the contract. Therefore, offerors should consider the above contingencies during offer preparation.
(h) CONTRACTOR IDENTIFICATION:
Contractor employees shall identify themselves as contractor personnel by introducing themselves or being introduced as contractor personnel and displaying distinguishing badges or other visible identification for meetings with Government personnel. In addition, contractor personnel shall appropriately identify themselves as contractor employees in telephone conversations and in formal and informal written correspondence, and when working in situations where their actions could be construed as official government acts.
CLAUSES INCORPORATED BY FULL TEXT
252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (DEC 2018)
(a) Definitions. As used in this clause—
“Department of Defense Activity Address Code (DoDAAC)” is a six position code that uniquely identifies a unit, activity, or organization.
“Document type” means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).
“Local processing office (LPO)” is the office responsible for payment certification when payment certification is done external to the entitlement system.
“Payment request” and “receiving report” are defined in the clause at 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.
(b) Electronic invoicing. The WAWF system provides the method to electronically process vendor payment requests and receiving reports, as authorized by Defense Federal Acquisition Regulation Supplement (DFARS) 252.232- 7003, Electronic Submission of Payment Requests and Receiving Reports.
(c) WAWF access. To access WAWF, the Contractor shall—
(1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and
(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.
(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the “Web Based Training” link on the WAWF home page at https://wawf.eb.mil/.
(e) WAWF methods of document submission. Document submissions may be via web entry, Electronic Data Interchange, or File Transfer Protocol.
(f) WAWF payment instructions. The Contractor shall use the following information when submitting payment requests and receiving reports in WAWF for this contract or task or delivery order:
(1) Document type. The Contractor shall submit payment requests using the following document type(s):
(i) For cost-type line items, including labor-hour or time-and-materials, submit a cost voucher.
(ii) For fixed price line items—
(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the Contracting Officer.
N/A
(B) For services that do not require shipment of a deliverable, submit either the Invoice 2in1, which meets the requirements for the invoice and receiving report, or the applicable invoice and receiving report, as specified by the Contracting Officer.
CONSTRUCTION PAYMENT INVOICE
(iii) For customary progress payments based on costs incurred, submit a progress payment request.
(iv) For performance based payments, submit a performance based payment request.
(v) For commercial item financing, submit a commercial item financing request.
(2) Fast Pay requests are only permitted when Federal Acquisition Regulation (FAR) 52.213-1 is included in the contract.
[Note: The Contractor may use a WAWF “combo” document type to create some combinations of invoice and receiving report in one step.]
(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.
Routing Data Table*
Field Name in WAWF Data to be entered in WAWF
Pay Official DoDAAC HQ0303
Issue By DoDAAC W911PT
Admin DoDAAC** W911PT
Inspect By DoDAAC N/A
Ship To Code N/A
Ship From Code N/A
Mark For Code N/A
Service Approver (DoDAAC) N/A
Service Acceptor (DoDAAC) N/A
Accept at Other DoDAAC N/A
LPO DoDAAC N/A
DCAA Auditor DoDAAC N/A
Other DoDAAC(s) (Contracting Officer) W911PT
(4) Payment request. The Contractor shall ensure a payment request includes documentation appropriate to the type of payment request in accordance with the payment clause, contract financing clause, or Federal Acquisition Regulation 52.216-7, Allowable Cost and Payment, as applicable.
(5) Receiving report. The Contractor shall ensure a receiving report meets the requirements of DFARS Appendix F.
(g) WAWF point of contact.
(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity’s WAWF point of contact.
N/A
(2) Contact the WAWF helpdesk at 866-618-5988, if assistance is needed.
(End of clause)
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Lot
FIBER INSTALLATION
FFP
To cover the cost of labor, material and equipment for INSTALL TWO NEW
SECTIONS OF SEVEN CHAMBER TUBE CABLE DETAILED BELOW.
FIBERDYNE WOULD THEN PERFORM THE ACTUAL INSTALLATION OF
A TOTAL OF (2) TWO 24F, SINGLEMODE, AIR BLOWN FIBER CABLES AT
WATERVLIET ARSENAL. (1) ONE 24F SM CABLE WOULD BE
INSTALLED BETWEEN BUILDING 110 AND BUILDING 40 AND (1) ONE
24F SM CABLE WOULD BE INSTALLED BETWEEN BUILDING 110 AND
BUILDING 25. All work will be performed under Scope of Work, which is attached and incorporated.
Wage Determination NY 2 Revision dated 8/16/2019 applies and is incorporated.
100% Payment Bonds are required.
Magnitude of the projects is between $100,000 and $250,000.
Technical Point of Contact is Jerry Ryan.
FOB: Destination
NSN: AASSVC9137015A
MILSTRIP: W16H1F9137015A
PURCHASE REQUEST NUMBER: W16H1F9137015A
PSC CD: N060
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0002 1 Lot
OPTION BLDG 35 ICS CAT 6
FFP
To cover the cost of labor, material and equipment for INSTALLATION OF CAT
6 PLENUM RATED DATA LINES TO 8 NEW CUTTING MACHINES ON THE
FLOOR IN BUILDING 35. All work will be performed under Scope of Work, which is attached and incorporated.
Wage Determination General Decision Number: NY 2 Dated 8/16/2019 applies and is incorporated.
Magnitude of this Project is between $25,000 and $100,000.
Period of Performance is 30 calendar days from receipt of Notice to Proceed
Technical Point of Contact is Jerry Ryan.
100% Payment and/or Performance Bonds are required.
FOB: Destination
NSN: AASSVC925202KA
MILSTRIP: W16H1F925202KA
PURCHASE REQUEST NUMBER: W16H1F925202KA
PSC CD: N060
NET AMT
Section C - Descriptions and Specifications
SCOPE OF WORK
STATEMENT OF WORK (SOW)
FOR
Air Blown Fiber cables install of (2) 24F, Singlemode, at Building 20(Rm. 105) to Building 25(3rd Floor, Rm. 328)
· Within Building 40-Rm. 1-205 and the “Attic” TDU Location.
AT
Watervliet Arsenal
Installation Management, Information 4 September 2019
PART 1 GENERAL
SUMMARY OF WORK
1.1.1 Project Description
a. This Statement of Work (SOW) defines the effort required for (2) 24F, Singlemode, Air Blown Fiber cables installed at Building 20(Rm. 105) to Building 25(3rd Floor, Rm. 328) and Within Building 40-Rm. 1-205 and the “Attic” TDU Location.
b. Contractor will provide approximate fiber lengths of 5,100’ (Bldg. 110 to Bldg. 40) and 1,950’ (Bldg. 110 to Bldg. 25)
1.1.2 Location of Work
a. The work is located at Building 20, 25 and 40 approximately as indicated. The exact location will be shown by the Contracting Officer.
1.1.3 Period of Performance
a. The contractor shall be required to (i) commence work under this contract within 7 calendar days after the date the contractor receives notice to proceed, (ii) prosecute the work diligently, and (iii) complete the entire work ready for use not later than 30 calendar days after notice to proceed was given. The time stated for completion shall include final cleanup of the premises.
1.1.4 Hours of Operation
a. Normal duty hours are 7:00 AM through 4:00 PM, Monday through Thursday, and 7:00 AM through 3:00 PM on select Fridays (the arsenal is closed every-other Friday). Federal holidays are non-work days. If a federal holiday falls on a Saturday or Sunday, the preceding Friday or following Monday is a work holiday.
SUBMITTALS
1.1.5 General Submittal Requirements
a. The contractor shall provide submittal documents via e-mail to the Contracting Officer for review and approval. Provide all physical (non-document) submittals (including but not limited to material swatches, samples, etc.) directly to the Contracting Officer for review and approval. All submittals require government approval unless otherwise explicitly stated.
b. The contractor shall reference APPENDIX A “Consolidated List of Submittals” for the complete list of required submittals.
1.1.6 Contractor Safety Plan
a. The contractor shall submit a safety plan which is specific to the work activity being performed under the scope of this project for Government review and approval.
1.1.7 Lockout / Tagout (LOTO) Acknowledgement
a. The Contractor shall sign and submit a “Lockout/Tagout (LOTO) Notification Acknowledgement Record” prior to working on or de-energizing any electrical equipment.
1.1.8 Asbestos Notification Acknowledgement Record
a. The contractor shall sign the “Asbestos Notification Acknowledgement Record” and submit this form to the Project COR prior to starting project work.
1.1.9 Project Schedule
a. The contractor shall create a project schedule and submit for Government review and approval.
b. The project schedule shall detail the phases of work and the overall timeline for the execution of the work. The contractor shall include delivery dates, appropriate milestones, and shall clearly detail any requirements for work performed outside of regular hours of operation.
GENERAL REQUIREMENTS
1.1.10 Watervliet Arsenal Information for Contractors (WAIC)
a. The contractor shall perform all work in strict conformance with Watervliet Arsenal Instructions for Contractors (WAIC). The contractor shall read and understand this document prior to submitting a proposal. The WAIC is publically available at:
<http://www.wva.army.mil/Documents/Contracting/WAIC.pdf>
1.1.11 Utility Outage Requests and Utility Connection Requests
a. Schedule work to minimize outages. For utility outages and connections required during the execution of work that affect existing systems, coordinate schedule with COR. Schedule utility outages and connections to minimize disruptions to the Government. No additional payment will be provided for utility outages and connections required to be performed outside the regular work hours.
b. The contractor shall notify the Contracting Specialist a minimum of two (2) business days before the contractor starts work. The contractor shall notify the COR a minimum of seven (7) business days before the shut-down of a utility or building service.
1.1.12 Safety Requirements
a. The contractor is required to provide the proper control of hazardous energy (lockout/tagout) per
OSHA 29 CFR 1910.147.
b. The contractor shall inspect the project work site prior to starting work, and shall request a copy of the asbestos building inspection records to verify the location and description of known asbestos-containing materials.
ON-SITE PERMITS
1.1.13 Excavation (Dig Permit)
a. The clearance of buried utilities will be performed by the Government in advance of the Contractor performing subsurface work, unless otherwise explicitly stated.
b. The Contractor shall obtain a copy of the completed Utility Clearance Permit (WVA Form 420-2-E) from the COR prior to performing subsurface work. Verify existing utility locations indicated on contract drawings, within area of work.
1.1.14 Hot Work and Confined Space
a. Obtain permit for welding, burning, use of flame, or entry into confined space from WVA Fire
Department by calling (518)266-5990 each day the permit is to be used.
APPLICABLE DOCUMENTS
1.1.15 References
a. The following references accompany this Statement of Work and are a part thereof.
i. Watervliet Arsenal Instructions for Contractors (WAIC).
ii. NFPA 70 – National Electric Code (NEC).
CONTRACTOR EQUIPMENT
1.1.16 Equipment Identification
a. The contractor shall create and affix a label to all large equipment, dumpsters, and other mobilized property, which is weather-resistant (laminated, or within a see-thru label hanger), securely affixed to the equipment or visible through a window, and which clearly displays the General Contractor’s:
i. Company Name, POC Name (first, last), POC phone number, Project Number.
1.1.17 Waste Dumpster
a. The contractor shall place any waste dumpsters in a manner that does not interfere with thru-traffic.
b. Place waste dumpsters with a minimum of 33’ clearance from any building. The final location shall be coordinated with, and approved by the COR before any dumpsters are mobilized.
c. Cover all waste dumpsters when not in use, and before the end of each work shift. The cover shall be weather-tight.
d. Note: The Contractor shall be required to retain and submit copies of all Bills of Lading and Weight
Slips associated with the disposal of construction and demolition C&D) debris.
PART 2 PRODUCTS
GENERAL
All work shall be in strict accordance with product manufacturer’s instructions and specifications, including but not limited to manufacturer guidance for storage, staging, application, installation, and disposal of the product.
2.1.1 Hazardous Materials
a. The contractor shall submit Safety Data Sheets (SDS) for all hazardous materials to be used.
2.1.2 Asbestos, Mercury, Lead, PCB
a. Unless otherwise stated, all materials for this project shall be new. All products shall not contain any asbestos, mercury, chromium/lead paint, Class I Freon, and Polychlorinated Biphenyls (PCB), and shall state such on the manufacturer’s original packaging.
2.1.3 DoD Green Procurement Program
a. All construction materials shall meet the applicable requirements of the DoD Green Procurement
Program, specifically recycled content products, environmentally preferable products and services, biobased products, energy-and water-efficient products, alternate fuel vehicles and alternative fuels, products using renewable energy, and alternatives to hazardous or toxic chemicals as found at <http://www.acq.osd.mil/dpap/cpic/cp/docs/USA001967-08-DPAP.pdf>.
PRODUCTS
a. 24F Singlemode Cable (and ancillary product for connections)
b. Chamber tube cable (Sumitomo part # FB24SX, or equal product)
PART 3 EXECUTION
ITEMS OF WORK
3.1.1 Contractor shall provide equipment, materials (including freight) and labor for the install of a Sumitomo (or equal) (7) chamber tube cable between the following: Bldg. 20(Rm. 105) to Bldg. 25(3rd Floor, Rm. 328) and · Within Bldg. 40-Rm. 1-205 and the “Attic TDU Location.”
3.1.2 Contractor to install and terminate the necessary 24F SM ABF cables between the locations listed above.
A total of (2) 24F SM cable spans will be installed and terminated.
3.1.3 Contractor will install (1) 24F SM ABF cable to be installed between Bldg. 110(main data room), through the tunnel, through the TDU in the Bldg. 35 “Doghouse”(Rm. 106), through the TDU at Door C24 in Bldg. 35, through Bldg. 25(3rd floor, Rm. 328), through Bldg. 20(Rm. 105), to the “7 tube” tube cable on the wall in Bldg. 20 (adjacent to door “A0”) and to Bldg. 40(2nd floor “Vault,” Rm. 205)
3.1.4 Contractor will install (1) 24F SM between Bldg. 110(main data room), through the tunnel, through the TDU in the Bldg. 35 “Doghouse” (Rm. 106), through the TDU at Door C24 in Bldg. 35 and to Bldg. 25(3rd floor, Rm. 328).
3.1.5 Contractor shall also provide and install a total of (4) of 1U high rack mount fiber distribution centers to support and patch up to 72fibes, or a Wall Mount Termination Box for 12 Ports, each loaded with (2) 6 position SC panels, pre-loaded with 6 duplex, SC/UPC, SM adapters to facilitate the terminations to take place on each end of both cables to be installed.
3.1.6 Contractor will assess and provide any indoor general-purpose clear tube” from existing TDU’s that had been previously installed in all closet locations listed above in order to transition to the fiber distribution centers in each location.
3.1.7 Contractor will then terminate all newly installed fiber strands with the appropriate Singlemode, SC/UPC connectors. (Assume a total of 96 terminations, at three separate locations).
3.1.8 Contractor will manage and label the newly installed and terminated fibers per industry standards in conjunction with the assistance of Watervliet Arsenal IT and facilities personnel.
3.1.9 Contractor will test all newly installed fiber strands uni-directionally from each point of termination with an OTDR at 1310nm/1550nm and will provide these test results to the customer upon completion of the job.
CLOSEOUT REQUIREMENTS
3.1.10 Construction and Demolition Debris
a. The Contractor shall submit copies of all Bills of Lading and Weight Slips associated with the disposal of construction and demolition (C&D) debris and/or recycled materials, under this scope of work. Submit documentation per Appendix A, “Consolidated List of Submittals”.
3.1.11 Cleanup of Work Site
a. The contactor shall clean all work areas and remove all tools, equipment, debris, materials, and all waste from the premises.
b. The contractor shall remove all debris from any remote holding locations, to include any excavation and concrete equipment chute cleanout debris.
c. The contractor shall remove their equipment from Watervliet Arsenal premises within five (5) working days after completion of project work.
3.1.12 Restoration of Work Site
a. The contractor shall repair any items, building surfaces, equipment or miscellaneous items which were damaged during the execution of this SOW. Items that cannot be repaired to restore original function or aesthetics shall be replaced in kind by the Contractor at no additional charge to the Government.
3.1.13 Warranty
a. The contractor shall provide a 1 year warranty on all workmanship and product installed.
PART 4 APPENDICES
a. Consolidated List of Submittals
APPENDIX A: Consolidated List of Submittals Line Item Submitted Submittal Needed By Submittal Reviewed By (Office)
1 Safety Data Sheets for Hazardous Materials
(SDS)
NLT 7 Calendar Days After Award
Safety Office
2 Signed Contractor Asbestos Notification Form NLT 7 Calendar Days After Award
Environmental Office
3 Signed Lockout/Tagout (LOTO) Notification Acknowledgement Record
NLT 7 Calendar Days After Award
Safety Office
4 Project Schedule NLT 7 Calendar Days After Award
COR
5 Contractor Safety Plan NLT 7 Calendar Days After Award
COR
6 Bills of Lading, Dump Slips for C&D Debris and Recycled Materials
Before Closeout Environmental Office
7 7 Chamber Cable Tube Product Data Sheet NLT 7 Calendar Days After Award
COR
8 Rack Mount Distribution Centers Product Data Sheet
NLT 7 Calendar Days After Award
COR
9 24F, Singlemode, Air Blown Fiber cables Product Data Sheet
NLT 7 Calendar Days After Award
COR
10 Indoor general-purpose clear tube Product Data Sheet
NLT 7 Calendar Days After Award
COR
11 Singlemode, SC/UPC connectors Product Data Sheets
NLT 7 Calendar Days After Award
COR
APPENDIX B: Quality Assurance Surveillance Plan (QASP)
PURPOSE
This Quality Assurance Surveillance Plan (QASP) will be used as a guide to Government Quality Assurance Personnel (QAP). It provides a systematic method to evaluate the services the contractor is required to furnish.
SURVEILLANCE PROCEDURES
Timeliness: Progress is maintained to assure compliance with completion time.
Quality: Conformance with statement of work and industry standards.
Tasks: Performed according to statement of work requirements.
Problem Resolution: Contractor submits deliverables in accordance with the contract and resolves any deficiencies identified by the government in the final submission. Following final submission, contractor resolves any additional deficiencies identified by the government and resubmits and or corrects within one week.
Delivery: Contractor submits each deliverable in accordance with the statement of work and terms of the contract.
PERFORMANCE AREAS
Management Responsiveness: Evaluate the adequacy of the contractor’s responsiveness and their ability to keep the government informed of work progress and provides for early problem identification and effective corrective action plans.
Schedule Control: Evaluate the contractor’s adherence to completion schedule.
Performance: The contractor will be evaluated as to the workmanship and adherence to the statement of work.
EVALUATION CRITERIA
(Outstanding). Indicates performance clearly exceeds contractual requirements. The area of evaluation contains few minor problems for which corrective actions appear highly effective.
(Satisfactory). Indicates performance clearly meets contractual requirements. The area of evaluation contains some minor problems for which the corrective actions appear satisfactory.
(Unsatisfactory). Indicates the contractor failed to satisfy contractual requirements and recovery is not likely in a timely manner. The area of evaluation contains serious problems for which the corrective actions were ineffective.
DOCUMENTATION
Documentation used to perform surveillance will consist of random government inspections and inspection records, as well as the evaluation of final work product delivery by the project COR/COTR.
RATING
Contractor will be given an overall rating of Outstanding, Satisfactory, or Unsatisfactory by the Government Technical point of contact or Contracting Specialist Representative, if appointed, using the above 3 evaluation criteria.
SCOPE OF WORK - OPTION
STATEMENT OF WORK (SOW)
FOR
INSTALL OF FIBER OPTIC CABLE, CONDUIT & CAT6 AT 8 (EIGHT) NEW CUTTING MACHINES
AT
Watervliet Arsenal
Installation Management, Information 16 September 2019
PART 5 GENERAL
SUMMARY OF WORK
5.1.1 Project Description
a. This Statement of Work (SOW) defines the effort required to network 8 new cutting machines located in building 35. One strand of armored single mode fiber is to be run from central pillar (network enclosure) in B bay to main data room centrally located in production.
Customer will install a wall-mount rack (network enclosure) on plywood and will mount on the central pillar. Three (3) Cat 6 Plenum rated data lines are to be run from the central pillar (network enclosure) to each of the 8 new cutting machines on the floor of Building 35. All Ethernet cabling is to be terminated in a 48 port cat6 panel which is to be provided and installed by the vendor inside of the network enclosure. 1 orange cat 6 is to be run to the control unit, 1 orange and 1 blue cat 6 through the gray machine trough to support and connect computers which will be located on the computer tower.
The cable runs and fiber will be supported with j hooks or conduit where needed. All cable runs will be mounted out of crane operations and away from accidentally being hit by forklifts, etc.
5.1.2 Location of Work
a. The work is located at Building 35 as indicated. The exact location will be shown by the
Contracting Officer.
5.1.3 Period of Performance
a. The contractor shall be required to (i) commence work under this contract within 7 calendar days after the date the contractor receives notice to proceed, (ii) prosecute the work diligently, and (iii) complete the entire work ready for use not later than 30 calendar days after notice to proceed was given. The time stated for completion shall include final cleanup of the premises.
5.1.4 Hours of Operation
a. Normal duty hours are 7:00 AM through 4:00 PM, Monday through Thursday, and 7:00 AM through 3:00 PM on select Fridays (the arsenal is closed every-other Friday). Federal holidays are non-work days. If a federal holiday falls on a Saturday or Sunday, the preceding Friday or following Monday is a work holiday.
SUBMITTALS
5.1.5 General Submittal Requirements
a. The contractor shall provide submittal documents via e-mail to the Contracting Officer for review and approval. Provide all physical (non-document) submittals (including but not limited to material swatches, samples, etc.) directly to the Contracting Officer for review and approval. All submittals require government approval unless otherwise explicitly stated.
b. The contractor shall reference APPENDIX A “Consolidated List of Submittals” for the complete list of required submittals.
5.1.6 Contractor Safety Plan
a. The contractor shall submit a safety plan which is specific to the work activity being performed under the scope of this project for Government review and approval.
5.1.7 Lockout / Tagout (LOTO) Acknowledgement
a. The Contractor shall sign and submit a “Lockout/Tagout (LOTO) Notification Acknowledgement Record” prior to working on or de-energizing any electrical equipment.
5.1.8 Asbestos Notification Acknowledgement Record
a. The contractor shall sign the “Asbestos Notification Acknowledgement Record” and submit this form to the Project COR prior to starting project work.
5.1.9 Project Schedule
a. The contractor shall create a project schedule and submit for Government review and approval.
b. The project schedule shall detail the phases of work and the overall timeline for the execution of the work. The contractor shall include delivery dates, appropriate milestones, and shall clearly detail any requirements for work performed outside of regular hours of operation.
GENERAL REQUIREMENTS
5.1.10 Watervliet Arsenal Information for Contractors (WAIC)
a. The contractor shall perform all work in strict conformance with Watervliet Arsenal Instructions for Contractors (WAIC). The contractor shall read and understand this document prior to submitting a proposal. The WAIC is publically available at:
<http://www.wva.army.mil/Documents/Contracting/WAIC.pdf>
5.1.11 Utility Outage Requests and Utility Connection Requests
a. Schedule work to minimize outages. For utility outages and connections required during the execution of work that affect existing systems, coordinate schedule with COR. Schedule utility outages and connections to minimize disruptions to the Government. No additional payment will be provided for utility outages and connections required to be performed outside the regular work hours.
b. The contractor shall notify the Contracting Specialist a minimum of two (2) business days before the contractor starts work. The contractor shall notify the COR a minimum of seven (7) business days before the shut-down of a utility or building service.
5.1.12 Safety Requirements
a. The contractor is required to provide the proper control of hazardous energy (lockout/tagout) per
OSHA 29 CFR 1910.147.
b. The contractor shall inspect the project work site prior to starting work, and shall request a copy of the asbestos building inspection records to verify the location and description of known asbestos-containing materials.
ON-SITE PERMITS
5.1.13 Excavation (Dig Permit)
a. The clearance of buried utilities will be performed by the Government in advance of the Contractor performing subsurface work, unless otherwise explicitly stated.
b. The Contractor shall obtain a copy of the completed Utility Clearance Permit (WVA Form 420-2-E) from the COR prior to performing subsurface work. Verify existing utility locations indicated on contract drawings, within area of work.
5.1.14 Hot Work and Confined Space
a. Obtain permit for welding, burning, use of flame, or entry into confined space from WVA Fire
Department by calling (518)266-5990 each day the permit is to be used.
APPLICABLE DOCUMENTS
5.1.15 References
a. The following references accompany this Statement of Work and are a part thereof.
i. Watervliet Arsenal Instructions for Contractors (WAIC).
ii. NFPA 70 – National Electric Code (NEC).
CONTRACTOR EQUIPMENT
5.1.16 Equipment Identification
a. The contractor shall create and affix a label to all large equipment, dumpsters, and other mobilized property, which is weather-resistant (laminated, or within a see-thru label hanger), securely affixed to the equipment or visible through a window, and which clearly displays the General Contractor’s:
i. Company Name, POC Name (first, last), POC phone number, Project Number.
5.1.17 Waste Dumpster
a. The contractor shall place any waste dumpsters in a manner that does not interfere with thru-traffic.
b. Place waste dumpsters with a minimum of 33’ clearance from any building. The final location shall be coordinated with, and approved by the COR before any dumpsters are mobilized.
c. Cover all waste dumpsters when not in use, and before the end of each work shift. The cover shall be weather-tight.
d. Note: The Contractor shall be required to retain and submit copies of all Bills of Lading and Weight
Slips associated with the disposal of construction and demolition C&D) debris.
PART 6 PRODUCTS
GENERAL
All work shall be in strict accordance with product manufacturer’s instructions and specifications, including but not limited to manufacturer guidance for storage, staging, application, installation, and disposal of the product.
6.1.1 Hazardous Materials
a. The contractor shall submit Safety Data Sheets (SDS) for all hazardous materials to be used.
6.1.2 Asbestos, Mercury, Lead, PCB
a. Unless otherwise stated, all materials for this project shall be new. All products shall not contain any asbestos, mercury, chromium/lead paint, Class I Freon, and Polychlorinated Biphenyls (PCB), and shall state such on the manufacturer’s original packaging.
6.1.3 DoD Green Procurement Program
a. All construction materials shall meet the applicable requirements of the DoD Green Procurement
Program, specifically recycled content products, environmentally preferable products and services, biobased products, energy-and water-efficient products, alternate fuel vehicles and alternative fuels, products using renewable energy, and alternatives to hazardous or toxic chemicals as found at <http://www.acq.osd.mil/dpap/cpic/cp/docs/USA001967-08-DPAP.pdf>.
PRODUCTS
a. CAT 6 Plenum Rated Data Lines Cable (and ancillary product for connections)
b. One 48 Port Cat 6 Patch Panel
PART 7 EXECUTION
ITEMS OF WORK
7.1.1 Contractor shall provide equipment, materials (including freight) and labor for the install of Cat 6 plenum rated data lines to 8 new cutting machines on the floor.
7.1.2 This will consist of 1 Orange cat 6 to the control unit, 1 Orange and 1 Blue Cat 6 through machine.
7.1.3 Contractor will install One 48 port cat 6 patch panel will be installed in the customer provided wall rack.
7.1.4 The Government will install the wall rack onto plywood and mount the plywood onto the central pillar location.
7.1.5 From the central pillar location the 3 Cat 6 runs shall be installed on each of the 8 machines.
7.1.6 One 6 Strand MM Armored fiber connection shall be installed from the pillar location to the main data room centrally located in the production area.
7.1.7 All new installed cable runs and fiber shall be supported with either j-hooks or conduit, and mounted as such that they are at a height that cannot be hit by forklift or other ground traffic; as well as crane operations.
7.1.8 Contractor will then terminate all newly installed fiber strands with the appropriate Singlemode, SC/UPC connectors.
7.1.9 Contractor will manage and label the newly installed and terminated fibers per industry standards in conjunction with the assistance of Watervliet Arsenal IT and facilities personnel.
7.1.10 Contractor will test all newly installed fiber strands uni-directionally from each point of termination with an OTDR at 1310nm/1550nm and will provide these test results to the customer upon completion of the job.
CLOSEOUT REQUIREMENTS
7.1.11 Construction and Demolition Debris
a. The Contractor shall submit copies of all Bills of Lading and Weight Slips associated with the disposal of construction and demolition (C&D) debris and/or recycled materials, under this scope of work. Submit documentation per Appendix A, “Consolidated List of Submittals”.
7.1.12 Cleanup of Work Site
a. The contactor shall clean all work areas and remove all tools, equipment, debris, materials, and all waste from the premises.
b. The contractor shall remove all debris from any remote holding locations, to include any excavation and concrete equipment chute cleanout debris.
c. The contractor shall remove their equipment from Watervliet Arsenal premises within five (5) working days after completion of project work.
7.1.13 Restoration of Work Site
a. The contractor shall repair any items, building surfaces, equipment or miscellaneous items which were damaged during the execution of this SOW. Items that cannot be repaired to restore original function or aesthetics shall be replaced in kind by the Contractor at no additional charge to the Government.
7.1.14 Warranty
a. The contractor shall provide a 1 year warranty on all workmanship and product installed.
PART 8 APPENDICES
a. Consolidated List of Submittals
APPENDIX A: Consolidated List of Submittals Line Item Submitted Submittal Needed By Submittal Reviewed By (Office)
1 Safety Data Sheets for Hazardous Materials
(SDS)
NLT 7 Calendar Days After Award
Safety Office
2 Signed Contractor Asbestos Notification Form NLT 7 Calendar Days After Award
Environmental Office
3 Signed Lockout/Tagout (LOTO) Notification Acknowledgement Record
NLT 7 Calendar Days After Award
Safety Office
4 Project Schedule NLT 7 Calendar Days After Award
COR
5 Contractor Safety Plan NLT 7 Calendar Days After Award
COR
6 Bills of Lading, Dump Slips for C&D Debris and Recycled Materials
Before Closeout Environmental Office
7 7 Chamber Cable Tube Product Data Sheet NLT 7 Calendar Days After Award
COR
8 Singlemode, SC/UPC connectors Product Data Sheets
NLT 7 Calendar Days After Award
COR
9 Cat 6 Plenum Rated Data Lines NLT 7 Calendar Days after Award
COR
10 Hanging Devices NLT 7 Calendar Days after Award
COR
11 One 48 Port Cat 6 Patch Panel NLT 7 Calendar Days after Award
COR
APPENDIX B: Quality Assurance Surveillance Plan (QASP)
PURPOSE
This Quality Assurance Surveillance Plan (QASP) will be used as a guide to Government Quality Assurance Personnel (QAP). It provides a systematic method to evaluate the services the contractor is required to furnish.
SURVEILLANCE PROCEDURES
Timeliness: Progress is maintained to assure compliance with completion time.
Quality: Conformance with statement of work and industry standards.
Tasks: Performed according to statement of work requirements.
Problem…