SOLICITATION

View the file

Other files

File Type Posted
Sol_Amendment_2_W911N2-17-Q-0030.pdf PDF
Sol_Amendment_W911N2-17-Q-0030-0001.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SEE ADDENDUM

(No Collect Calls)

W911N2-17-Q-0030 19-Apr-2017

b. TELEPHONE NUMBER

717-267-8714

8. OFFER DUE DATE/LOCAL TIME

04:00 PM 19 May 2017

5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1449 (REV. 2/2012)

Prescribed by GSA – FAR (48 CFR) 53.212

(TYPE OR PRINT)

(SIGNATURE OF CONTRACTING OFFICER)

ADDENDA ARE

26. TOTAL AWARD AMOUNT (For Gov t. Use Only )

23.

CODE 10. THIS ACQUISITION IS

SUCH ADDRESS IN OFFER

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT

BELOW IS CHECKED

TELEPHONE NO.

W911N29. ISSUED BY

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK

7. FOR SOLICITATION

INFORMATION CALL:

a. NAME

ALLEN G. MILLER JR.

2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER

(TYPE OR PRINT)

30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER

30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA

0 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.

25. ACCOUNTING AND APPROPRIATION DATA

1. REQUISITION NUMBER

20.

ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

W25G1Q7038011S

ARE NOT ATTACHED

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

. YOUR OFFER ON SOLICITATION

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

% FOR:SET ASIDE:UNRESTRICTED OR X

SMALL BUSINESSX

17a.CONTRACTOR/ CODE FACILITY

OFFEROR CODE

LETTERKENNY ARMY DEPOT

LETTERKENNY CONTRACTING OFFICE - ACC

1 OVERCASH AVENUE, ATTN: CCAM-ALK, BLDG 2S

CHAMBERSBURG PA 17201-4150

18a. PAYMENT WILL BE MADE BY CODE

RATED ORDER UNDER

DPAS (15 CFR 700)

13a. THIS CONTRACT IS A

13b. RATING

CODE15. DELIVER TO CODE W25G1Q 16. ADMINISTERED BY

12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

SEE SCHEDULE

14. METHOD OF SOLICITATION

RFQ IFB RFPX

DIRECTORATE OF OPS PLANNING & SUPPORT

BLDG 370 ASRS DOOR 18 AMLD-PLX

LETTERKENNY ARMY DEPOT

CHAMBERSBURG PA 17201-4150

TEL: FAX:

717-2679834FAX:

TEL: SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

8(A)

HUBZONE SMALL

BUSINESS

SIZE STANDARD:

NAICS:

333517

X

OFFER DATED

29. AWARD OF CONTRACT: REF.

DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND

EMAIL:

TEL:

31c. DATE SIGNED

SEE SCHEDULE

SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT

24.22.21.19.

WOMEN-OWNED SMALL BUSINESS (WOSB)

ELIGIBLE UNDER THE WOMEN-OWNED

SMALL BUSINESS PROGRAM

EDWOSB

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

(CONTINUED)

PAGE 2 OF24

ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED

32b. SIGNATURE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

37. CHECK NUMBER

FINALPARTIALCOMPLETE

36. PAYMENT35. AMOUNT VERIFIED

CORRECT FOR

34. VOUCHER NUMBER

FINAL

33. SHIP NUMBER

PARTIAL

38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY

41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT

41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE

42a. RECEIVED BY (Print)

42b. RECEIVED AT (Location)

42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS

STANDARD FORM 1449 (REV. 2/2012) BACK

Prescribed by GSA – FAR (48 CFR) 53.212

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

SEE SCHEDULE

20.

SCHEDULE OF SUPPLIES/ SERVICES

21.

QUANTITY UNIT

22. 23.

UNIT PRICE

24.

AMOUNT

19.

ITEM NO.

W911N2-17-Q-0030

Section SF 1449 - CONTINUATION SHEET

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Each

ELECTRIC PRESS BRAKE

FFP

LVD Dyna Press, Part Number: 40/15 PLUS, or Equivalent in accordance with the purchase description.

FOB: Destination

NSN: 40/15PLUS:80651

MILSTRIP: W25G1Q7038011S

PURCHASE REQUEST NUMBER: W25G1Q7038011S

NET AMT

SOLICITATION NOTES

1. System for Award Management (SAM): In accordance with FAR 4.1102, Offerors shall be registered in the SAM database in order to be eligible for contract award. No award will be made to an Offeror not registered.

Registration can be accomplished at https://www.sam.gov/portal/public/SAM/. Registration in this database shall remain active.

2. Annual Representations and Certifications: In accordance with FAR 4.1201, Offerors shall complete electronic annual representations and certifications within SAM as part of required registration. Registration in this database shall remain active and can be accessed at https://www.sam.gov/portal/public/SAM/.

3. Questions: Questions regarding this solicitation shall be submitted to the Contracting Officer, in writing, at least 10 calendar days prior to the closing date. Questions submitted after this time will be answered at the discretion of the Contracting Officer. The Contracting Officer for this action is Kristin Robson, kristin.e.robson.civ@mail.mil

4. Award without Discussions: The Government intends to award without discussions, offerors should submit their best prices in their initial offer. If FAR Provision 52.212-2, Evaluation-Commercial Items, is included, Offerors must submit all information requested therein in order for the Government to determine technical acceptability.

5. Amendments: The Offeror shall submit to the Contracting Officer signed copies of all amendments issued to this solicitation. Failure to comply may cause your proposal to be rejected.

6. Payment: Payment for this action will be made by Electronic Funds Transfer (EFT) through the Defense Finance and Accounting Services (DFAS) utilizing Wide Area Work Flow (WAWF). See 252.232-7006 for more information.

7. Period for Acceptance of Offers: The Offeror agrees to hold the prices in its offer firm for 60 calendar days from the date specified for receipt of offers.

8. Set- Aside: The proposed contract is 100% set-aside for small business concerns.

9. FOB Destination: Unless otherwise stated in the solicitation, Offerors shall provide FOB Destination prices.

10. Insurance (Fixed Price): Pursuant to the requirements of FAR clause 52.228-5 Insurance-Work on a Government Installation, the contractor shall obtain and maintain at least the following kinds of insurance and minimum liability coverage during any period of contract performance:

a. Workmen's Compensation and occupational disease coverage as required by law except that, if this contract is to be performed in a state which does not require or permit private insurance, then compliance with the statutory or administrative requirements in any such state will be satisfactory. The required Workmen's Compensation Insurance shall extend to cover employers' liability for accidental bodily injury or death and for occupational disease with a minimum liability limit of $100,000.

b. Comprehensive General Liability Insurance in the minimum limit of $500,000 per occurrence for bodily injury liability.

c. Comprehensive Automotive Liability Insurance with minimum limits of $200,000 per person and $500,000 per occurrence for bodily injury, and a minimum limit of $200,000 per occurrence for property damage.

11. Site Visit: A site visit is scheduled for 02 May 2017 at 10:00 Eastern Daylight Time. Site visit attendance is urged but is not mandatory; however, failure to attend a site visit shall not be a reason for price increases to the contract after contract award. Submit the names of all attendees to Contract Specialist Allen Miller, allen.g.miller6.civ@mail.mil This site visit will include access to restricted/classified areas. In order to obtain access, attendees must provide the following information – Name, date of birth and social security number. Submit this information no later than 28 April 2017 at 12:00 PM EST. Offerors who do not submit this information will not be given access to the site. All attendees will meet at Building 2S, Directorate of Contracting, 1 Overcash Avenue, Letterkenny Army Depot, Chambersburg, PA. Offerors are required to obtain a visitor’s pass from the Main Gate prior to arriving at Building 2S. Please allow at least 45 minutes for this process. You must provide a current picture identification, vehicle registration and proof of insurance to obtain a pass.

PURCHASE DESCRIPTION

LETTERKENNY ARMY DEPOT

PURCHASE DESCRIPTION

CNC ELECTRIC PRESS BRAKE

BLDG 350 ANNEX

1.0 GENERAL

1.1 SCOPE: Request the purchase of one (1) LVD Dyna-Press 40/15 Plus, or equivalent, Computer Numerically Controlled (CNC) electric press brake. This specification establishes the minimum requirements for the purchase of contractor installed electric press brake at Letterkenny Army Depot (LEAD). The contractor shall provide all professional architectural, engineering and construction services for the preparation of all necessary drawings, specifications, calculations, cost estimates and related design, permits, fabrication, construction, installation and testing services for the completion of this project. The press brake shall be installed turnkey in accordance with Original Equipment Manufacturer specification and standards. Specifications are based upon commercially available products and shall meet or exceed the minimum requirements specified in section 4.0 Specifications.

1.2 GENERAL INFORMATION:

1.2.1 Place and Performance of Installation: All work shall be performed in building 350 Annex between the hours of 6:00 AM and 3:30 PM, Monday thru Thursday, exclusive of Federal Holidays and special depot closures (typically the Monday before or Thursday after Federal Holidays that fall on a Saturday, Sunday, Tuesday or Thursday). Other hours, weekend, and holiday work will be considered separately as requested by the contractor with adequate advanced notice and approved by the Contracting Officer.

1.2.2 Security Requirements: Contractor and all associated sub-contractor’s employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Risk Management or Security Office. Contractor workforce shall comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes. The contractor and all associated subcontractor employees shall also comply with adjudication standards and processes using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

1.2.3 Security, Safety and Fire Protection: All work shall comply with LEAD Regulation 385-1 and Pamphlet 385-

4. The equipment and the installation shall also meet all the safety criteria set forth in OSHA 1926.501 and

ANSI/ASSE Z359.

1.2.4 Media Devices: All pictures shall be taken by LEAD representative and approved before release.

1.2.5 AT Level I Awareness Training: All contractor employees, to included subcontractor employees, requiring access to Army Installations, facilities, and controlled access areas shall complete AT Level 1 awareness training within 30 calendar days after contract start date and within 30 calendar days of new employees commencing performance. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 15 calendar days after completion of training. AT level 1 awareness training is available on the Letterkenny Army Depot homepage – www.lead.army.mil.

1.2.6 Physical Security: The contractor shall safeguard all Government property provided for contractor use. At the close of each work period, Government facilities, equipment and materials shall be secured.

1.2.7 iWATCH Training: The contractor and all associated sub-contractors with an area of performance within an Army-controlled installation, facilities or area shall brief all employees on the local iWATCH program. This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR or contracting officer. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance. The contractor shall report completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 15 calendar days after completion of training. iWATCH training is available on the Letterkenny Army Depot homepage – www.lead.army.mil.

1.2.8 OPSEC Training: Per AR 530-1, Operations Security, new contractor employees and associated sub-contractor employees shall complete Level I OPSEC training within 30 calendar days of their reporting for duty and annually thereafter. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 15 calendar days after completion of training. Level 1 OPSEC training is available on the Letterkenny Army Depot homepage – www.lead.army.mil.

1.2.9 Badges: Identification badges will be issued for admittance of personnel before performing work or service on this contract. The identification badge is the property of the US Government and must be returned upon termination or demand. The contractor/vendor agrees that he will ensure all badges issued to employees are returned to the Badge and Identification Section, Security Division, Letterkenny Army Depot promptly on termination of need or on expiration, which occurs first. The badge room is located in Bldg 2, phone # 717-267-5301. Hours of operation are 7:30 AM to 3:30 PM, Monday thru Friday, exclusive of Federal Holidays.

2.0 GOVERNMENT FURNISHED PROPERTY AND MATERIALS:

2.1 Government Furnished Property and Materials: The Government will provide the facilities, equipment, materials and/or services listed below:

2.1.1 Facilities: The Government will provide clear access to all working areas necessary for the contractor to perform the installation outlined, during the specified hours listed in section 1.2.

2.1.2 Equipment: none

2.1.3 Materials: Stock material for testing.

2.1.4 Services: none

2.2 Site Preparation: Letterkenny Army Depot will provide a clear area for installation of the press brake.

2.3 Utilities: LEAD will provide adequate utilities for the installation and operation of the machines within 50’ of the equipment disconnect. LEAD will also provide temporary utilities for the operation of equipment required for the installation of the industrial equipment.

2.4 Delivery and Storage: The Government will not be responsible for loading, unloading, or providing any extended storage, prior to installation, of materials or equipment as part of this contract.

3.0 CONTRACTOR RESPONSIBILITIES: The contractor shall be responsible for the following

3.1 Installation Requirements: Design and Installation: The contractor shall provide all parts, labor, and services for the design, fabrication and installation of the press brake. The contractor shall provide competent English speaking personnel to place the system in operation and to conduct the acceptance tests and training of depot personnel. The contractor, through his service personnel, shall be fully responsible for the offloading, installation, activation, and testing of the system and the service personnel shall remain until system activation and testing has successfully been completed. The contractor shall make all connections to existing utilities necessary for proper operation. The contractor shall remove and dispose all packaging and preservative material. Removed components shall not be taken from the Depot property. Removed components shall be placed in a location designated by the TPOC. Under no circumstances should the contractor plan on gratuitous Depot assistance during installation, activation, and testing such as diagnosis, troubleshooting, or repair of the system. The contractor shall be responsible to inform all workers, direct or contracted, and ensure they follow the information within this specification. The contractor shall also have a representative onsite to manage the project and be the point of contact (POC) to communicate and coordinate with Letterkenny’s POC.

3.2 Post Processor: None.

3.3 Project Schedule: A project schedule shall be submitted by the contractor, within 30 days after receipt of the purchase order, to include a timeline for material delivery, installation, testing and training.

3.4 Utility Requirements: The contractor shall provide certified utility requirements within 15 days after receipt of the purchase order. They shall include type, number of connections, and requirements.

3.5 Field Verification: It shall be the responsibility of the contractor to verify, in the field, all measurements, locations of structures and utilities, and any other physical conditions which would affect the progress, or quantity of work. Any errors by the contractor, due to omission of field verification, shall not be the basis for any increase in contract price. Where existing utilities or other obstructions interfere with the progress of the contract, the contractor shall provide all materials and labor to relocate all obstructions as required and approved by the Contracting Officer.

3.6 Special Foundation: None.

3.7 Utility Installation: Utilities are to be run overhead. The contractor shall provide all materials, equipment, tools, and labor necessary for the installation of all utilities.

3.8 Disposal Of Materials And Equipment: All salvageable materials and equipment removed by the contractor shall be delivered to the Depot Property Disposal Yard, Facilities Engineering Division warehouse, or other sites as directed by the Contracting Officer, or his representative and shall remain the property of the Government. Delivery shall be made during normal operating hours of the receiving activity. No Government materials or equipment shall be removed from the reservation by the contractor. All packing, packaging, and scrap material accumulated during the performance of the contract shall be removed and disposed of properly by the contractor.

3.9 Dust Control: The contractor shall control the amount of dust generated during the installation of the system foundation and components, and shall prevent the spread of dust to occupied portions of the building. Use of water will not be permitted when it will result in, or create, hazardous or objectionable conditions such as ice, flooding or pollution.

3.10 Protection of Existing Structures and Equipment: The contractor shall take all necessary precautions to insure against damage to existing structures and equipment to remain in place.

3.11 Wiring: All electrical work and materials shall be in compliance with the National Electrical Code and National Electrical Manufacturers Association. All electrical installations shall be inspected and accepted by a certified electrician. All work shall be subject to inspection by LEAD electricians.

3.12 Pipe: Schedule 40 (minimum) black steel pipe, valves, and all materials necessary, shall be supplied and installed to provide the equipment with required adequate air and water supplies.

3.13 Fluids: The contractor shall provide all necessary fluids and chemical additives required for the start-up and proper operation of the equipment. The contractor shall supply LEAD with MSDSs for all the necessary fluids within 30 days after award of contract.

3.14 Permits: The contractor shall be responsible for determining and obtaining all necessary permits, fees, licensing, insurance, and bonding to perform and complete this installation.

4.0 SPECIFICATIONS:

4.1 Machine Options: The LVD DYNA-PRESS 40/15 Plus electric press brake, or equivalent, shall have the following minimum options:

LIGHT GUARD PROTECTION (DP 5300)

ELECTRICAL CABINET AIR CONDITIONER (DP 8500)

RIGGING

INSTALLATION AND START UP

INSTRUCTION

4.2 Machine Control System: The press brake shall have an FANUC type control, or equivalent. All machine functions shall be controlled and monitored through the operator’s control panel/interface and shall be capable of being set through machine code input into the control. Each control shall include, but not limited to, the following minimum features:

4.2.1 The DYNA-PRESS 40/15 Plus with CADMAN Touch-B control, or equivalent:

15 inch Color touchscreen display Emergency Shutdown Buttons ISO Standard G-Code compatible

4.2.2 Software Compatibility: None.

4.3 Machine Features: The machines shall include, but not limited to, the following minimum features:

4.3.1 LVD DYNA-PRESS 40/15 Plus, OR EQUIVALENT:

44 Ton Press Force, minimum 60 inch work length, minimum 60 inch distance between frames

7.9 inch stroke, min.

Working height of 35 inches, min.

Max. working speed of 59 inches/minute, minimum Approach and Return speed of up to 236 inches/minute Maximum footprint of 83 inch wide x 48 inch deep Wila Style Tooling Compatibility CNC Controlled Axes; Y, X, R, Z1, and Z2 Back Gauge Configuration of X-R-Z1-Z2 Axes.

Ball Screw Driven Ram 15” Touchscreen Mounted On Attached Arm (Not On Ram) Cadman Touch-B Controller Adjustable height arm support LED lighting in work zone Self-leveling base Hand and foot controls Designed for operator to bend parts while standing or sitting

4.3.2 Automatic Lubrication: The system shall include a centralized lubrication system to automatically provide lubricant to critical components. Means shall be provided to ensure adequate lubrication to all moving parts. All oil holes, grease fittings and filler caps shall be easily accessible.

4.3.3 Power Requirements: All power requirements shall be 480V 3ph. If any requirement is not, the contractor shall supply all required transformers.

4.3.4 Painting: All surfaces to be painted shall be cleaned of all foreign matter. The equipment shall be painted IAW standard commercial practice that shall not be less than one coat of primer and one coat of finish color.

4.3.5 Energy Efficiency: All equipment that directly consumes energy in normal operation shall be designed and constructed for the highest degree of energy efficiency as governed by the latest developments available within industry.

4.4 Safety and Environmental Requirements:

4.4.1 Equipment Hazards: All hazards inside the machinery shall be guarded against unauthorized access. Clearly visible signs and symbols shall warn personnel in the area, and interlocks, safety mats and redundant deactivation systems shall guard against accidental access to the tooling and moving parts. Guards shall be easily removable to facilitate inspection, maintenance, or repair.

4.4.2 Mercury Restriction: The equipment shall not contain mercury compounds nor be exposed to free mercury during manufacture.

4.4.3 Asbestos Restriction: Asbestos and materials containing asbestos shall not be used in or on the equipment.

4.4.4 PCB Restriction: Equipment and materials containing Polychlorinated Biphenyl (PCB) shall not be shipped to Letterkenny Army Depot.

4.4.5 Fire Extinguishers: The LEAD R 385-1 designates the type and number of fire extinguishers required to perform the contracted work. The LEAD Fire Department will not provide any extinguisher support. The contractor can gain the above information through a pre-construction conference, visiting the fire department, or phone 717-267-8231.

4.4.6 Use of Portable Gas or Arc Equipment: The contractor shall obtain a permit, from the LEAD Fire Department, to use portable gas or arc equipment for cutting, welding or open flame operations. The Fire Department will require one day advance notice to permit necessary inspection before actually starting work, and notification when work is finished to allow for re-inspection. The Fire Department can be notified by calling ext. 8231. The contractor shall take necessary precautions to prevent fires IAW NFPA Standard No. 51B and LEAD R 420-13.

4.4.7 Spills: Any spills or releases of materials or wastes must be reported immediately to the site supervisor, the LEAD Fire Department, and the LEAD Environmental Office per the LEAD Installation spill Contingency Plan (ISCP). Any such spills or releases generated by the contractor shall be contained, cleaned and disposed of by the contractor per the direction of the LEAD on-scene coordinator.

5.0 DRAWINGS AND MANUALS: Two sets (each) of paper and one (each) CD of operator instruction manuals, maintenance service manuals, and parts listing manuals shall be provided for the furnished systems. These manuals shall be written in the English language.

6.0 WARRANTY: The contractor shall furnish with the equipment a standard commercial warranty or full one year warranty (parts, labor, and shipping, at minimum), whichever is greater. The contractor shall provide commercial warranties for any subcontracted components that will be underwritten. The contractor shall supply all corresponding warranty contact names and phone numbers before the end of the project. The warranty shall be effective beginning immediately after final acceptance of the equipment and not before that time.

7.0 PRESERVATION, PACKAGING AND DELIVERY: The contractor shall utilize standard commercial methods for preservation and packaging appropriate for each unit and acceptable to commercial carriers. As a minimum, all areas susceptible to damage from exposure to the elements shall be preserved and/or packed to prevent damage. The contractor shall be responsible for ensuring the equipment is delivered to LEAD in good condition.

8.0 INSPECTION AND ACCEPTANCE:

6.1 Quality Conformance Inspection: The equipment shall be examined for design, construction, materials, components, and workmanship to determine compliance with the contract and this specification. Any deviation from these requirements shall be cause for rejection.

6.2 Tests: The contractor shall be responsible for developing test procedures to demonstrate compliance with the requirements of this specification. All test procedures shall be submitted to and approved by Depot Technical Point of Contact (TPOC) prior to the start of testing. To support the testing procedures, LEAD will provide a supply of material for use during the performance tests and training. The material may include mild steel and other materials of varying thicknesses, depending upon availability. The contractor shall run, successfully, a proven part program through their controller. The part shall be run from their controller and checked for accuracy of the part and program. The contractor shall prove out all problems.

6.3 Training: The contractor shall be responsible for providing training of four (4) Depot personnel in the operation of the equipment and software and four (4) Depot personnel in the maintenance of the equipment supplied under this contract. All instructions, oral and written, shall be in the English language. The project LEAD TPOC will coordinate with individuals to be trained upon successful completion of all installation and test specifications.

6.4 Final Acceptance: Once all conditions of this contract are met, final acceptance will be after 100 hours of continuous operation without a breakdown or failure, or 14 days, whichever comes first. If the machine has a failure or breakdown and it is determined that is the fault of the machine hardware or software, the operating time and 14 days timeframe start over each time this happens. After the 100 hour operating time or 14 days have been met, final payment of this contract will be made.

7.0 APPLICABLE DOCUMENTS:

OSHA Safety and Health Standards 29 CFR 1910 Occupational Safety and Health Standards (copies may be obtained at http://www.osha.gov)

Letterkenny Army Depot (LEAD) Publications:

LEAD Regulation 385-1: LEAD Safety and Occupational Health Program LEAD Pamphlet 385-4 – Safety Requirements for Security, Safety, and Fire Prevention for Contractors Performing Work on LEAD (Copies may be obtained at LEAD Directorate of Contracting, Bldg 2)

National Fire Protection Association NFPA Standard 70 – National Electric Code NFPA Standard 79 – Electrical Standard for Industrial Machinery (copies may be obtained from http://www.nfpa.org/)

INSPECTION AND ACCEPTANCE TERMS

Supplies/services will be inspected/accepted at:

CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

0001 Destination Government Destination Government

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC

0001 90 dys. ADC 1 DIRECTORATE OF OPS PLANNING &

SUPPORT

BLDG 370 ASRS DOOR 18 AMLD-PLX

LETTERKENNY ARMY DEPOT

CHAMBERSBURG PA 17201-4150

FOB: Destination

W25G1Q

CLAUSES INCORPORATED BY REFERENCE

52.204-7 System for Award Management OCT 2016 52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-10 Reporting Executive Compensation and First-Tier

Subcontract Awards

OCT 2016

52.204-13 System for Award Management Maintenance OCT 2016 52.204-16 Commercial and Government Entity Code Reporting JUL 2016 52.204-18 Commercial and Government Entity Code Maintenance JUL 2016 52.204-19 Incorporation by Reference of Representations and

Certifications.

DEC 2014

52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment

OCT 2015

52.209-10 Prohibition on Contracting With Inverted Domestic Corporations

NOV 2015

52.212-1 Instructions to Offerors--Commercial Items JAN 2017 52.212-3 Alt I Offeror Representations and Certifications--Commercial

Items (JAN 2017) Alternate I

OCT 2014

52.212-4 Contract Terms and Conditions--Commercial Items JAN 2017 52.219-6 Notice Of Total Small Business Set-Aside NOV 2011 52.219-28 Post-Award Small Business Program Rerepresentation JUL 2013 52.222-3 Convict Labor JUN 2003 52.222-19 Child Labor -- Cooperation with Authorities and Remedies OCT 2016 52.222-21 Prohibition Of Segregated Facilities APR 2015 52.222-26 Equal Opportunity SEP 2016 52.222-36 Equal Opportunity for Workers with Disabilities JUL 2014 52.222-50 Combating Trafficking in Persons MAR 2015 52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011 52.223-18 Encouraging Contractor Policies To Ban Text Messaging

While Driving

AUG 2011

52.225-13 Restrictions on Certain Foreign Purchases JUN 2008 52.225-18 Place of Manufacture MAR 2015 52.228-5 Insurance - Work On A Government Installation JAN 1997 52.232-23 Assignment Of Claims MAY 2014 52.232-33 Payment by Electronic Funds Transfer--System for Award

Management

JUL 2013

52.232-39 Unenforceability of Unauthorized Obligations JUN 2013 52.232-40 Providing Accelerated Payments to Small Business

Subcontractors

DEC 2013

52.233-3 Protest After Award AUG 1996 52.233-4 Applicable Law for Breach of Contract Claim OCT 2004

52.237-2 Protection Of Government Buildings, Equipment, And Vegetation

APR 1984

52.242-15 Stop-Work Order AUG 1989 52.247-34 F.O.B. Destination NOV 1991 252.203-7000 Requirements Relating to Compensation of Former DoD

Officials

SEP 2011

252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013 252.203-7005 Representation Relating to Compensation of Former DoD

Officials

NOV 2011

252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7004 Alt A System for Award Management Alternate A FEB 2014 252.204-7008 Compliance With Safeguarding Covered Defense Information

Controls

OCT 2016

252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting

OCT 2016

252.225-7002 Qualifying Country Sources As Subcontractors DEC 2016 252.225-7048 Export-Controlled Items JUN 2013 252.232-7003 Electronic Submission of Payment Requests and Receiving

Reports

JUN 2012

252.232-7010 Levies on Contract Payments DEC 2006 252.243-7001 Pricing Of Contract Modifications DEC 1991 252.244-7000 Subcontracts for Commercial Items JUN 2013 252.247-7023 Transportation of Supplies by Sea APR 2014

CLAUSES INCORPORATED BY FULL TEXT

52.211-6 BRAND NAME OR EQUAL (AUG 1999)

(a) If an item in this solicitation is identified as “brand name or equal,” the purchase description reflects the characteristics and level of quality that will satisfy the Government's needs. The salient physical, functional, or performance characteristics that “equal” products must meet are specified in the solicitation.

(b) To be considered for award, offers of “equal” products, including “equal” products of the brand name manufacturer, must--

(1) Meet the salient physical, functional, or performance characteristic specified in this solicitation;

(2) Clearly identify the item by--

(i) Brand name, if any; and

(ii) Make or model number;

(3) Include descriptive literature such as illustrations, drawings, or a clear reference to previously furnished descriptive data or information available to the Contracting Officer; and

(4) Clearly describe any modifications the offeror plans to make in a product to make it conform to the solicitation requirements. Mark any descriptive material to clearly show the modifications.

(c) The Contracting Officer will evaluate “equal” products on the basis of information furnished by the offeror or identified in the offer and reasonably available to the Contracting Officer. The Contracting Officer is not responsible for locating or obtaining any information not identified in the offer.

(d) Unless the offeror clearly indicates in its offer that the product being offered is an “equal” product, the offeror shall provide the brand name product referenced in the solicitation.

(End of provision)

52.212-1 INSTRUCTIONS TO OFFERORS--COMMERCIAL ITEMS (JAN 2017)

ADDENDUM TO FAR 52.212-1, INSTRUCTIONS TO OFFERORS--COMMERCIAL ITEMS:

Paragraph (c) is changed to read: Period for acceptance of offers. The Offeror agree to hold the prices in its offer firm for 60 calendar days from the date specified for receipt of offers, unless another time period is specified in an addendum to the solicitation.

(End of Addendum)

52.212-2 EVALUATION--COMMERCIAL ITEMS (OCT 2014)

(a) The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered. The following factors shall be used to evaluate offers:

(b) Options. The Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. The Government may determine that an offer is unacceptable if the option prices are significantly unbalanced. Evaluation of options shall not obligate the Government to exercise the option(s).

(c) A written notice of award or acceptance of an offer, mailed or otherwise furnished to the successful offeror within the time for acceptance specified in the offer, shall result in a binding contract without further action by either party. Before the offer's specified expiration time, the Government may accept an offer (or part of an offer), whether or not there are negotiations after its receipt, unless a written notice of withdrawal is received before award.

(End of provision)

ADDENDUM TO FAR 52.212-2, BASIS OF AWARD:

A. General Information:

1. The basis of award will be the Lowest Priced, Technically Acceptable offer. Offerors must receive a rating of Technically Acceptable in all factors/subfactors in order for their overall proposal to be determined Technically Acceptable.

2. By submission of its offer, the offeror accedes to all solicitation requirements, including terms and conditions, and technical requirements.

3. The Government intends to make award without discussions, unless the Contracting Officer determines that discussions are necessary. Offerors should provide their most favorable prices in their initial offers.

B. Non-Price Evaluation Factor:

1. Factor 1 - Technical: The offeror shall submit descriptive literature such as illustrations, drawings, or other information to demonstrate compliance with requirements detailed in the specifications.

C. Price Evaluation Factor: Offerors shall complete the Schedule B with pricing for each Contract Line Item Number (CLIN).

D. Proposals will be evaluated initially independently of the price to determine the Offerors’ ability to meet the Government’s requirement set forth in the solicitation. The Government may make a final rating determination based on the proposal as submitted without requesting any further information. For all proposals determined to be Technically Acceptable, the offer providing the lowest price will receive the contract award.

1. Offerors’ technical proposals will receive an overall rating based on the following:

(a) Technically Acceptable: Offeror meets all requirements or technical specifications or has submitted all documentation requested in any technical evaluation criteria and all documentation meets the standard set forth in the solicitation.

(b) Technically Unacceptable: Offerer fails to meet all requirements or technical specifications or has failed to comply in submitting requested documentation in any technical evaluation criteria or the submitted documentation fails to meet the standard set forth in the solicitation.

(End of Addendum)

52.212-5 CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT STATUTES OR

EXECUTIVE ORDERS—COMMERCIAL ITEMS (DEVIATION 2013-O0019) (JAN 2017)

(a) Comptroller General Examination of Record. The Contractor shall comply with the provisions of this paragraph

(a) if this contract was awarded using other than sealed bid, is in excess of the simplified acquisition threshold, and does not contain the clause at 52.215-2, Audit and Records -- Negotiation.

(1) The Comptroller General of the United States, or an authorized representative of the Comptroller General, shall have access to and right to examine any of the Contractor’s directly pertinent records involving transactions related to this contract.

(2) The Contractor shall make available at its offices at all reasonable times the records, materials, and other evidence for examination, audit, or reproduction, until 3 years after final payment under this contract or for any shorter period specified in FAR Subpart 4.7, Contractor Records Retention, of the other clauses of this contract. If this contract is completely or partially terminated, the records relating to the work terminated shall be made available for 3 years after any resulting final termination settlement. Records relating to appeals under the disputes clause or to litigation or the settlement of claims arising under or relating to this contract shall be made available until such appeals, litigation, or claims are finally resolved.

(3) As used in this clause, records include books, documents, accounting procedures and practices, and other data, regardless of type and regardless of form. This does not require the Contractor to create or maintain any record that the Contractor does not maintain in the ordinary course of business or pursuant to a provision of law.

(b)

(1) Notwithstanding the requirements of any other clause in this contract, the Contractor is not required to flow down any FAR clause, other than those in this paragraph (b)(1) in a subcontract for commercial items. Unless otherwise indicated below, the extent of the flow down shall be as required by the clause—

(i) 52.203-13, Contractor Code of Business Ethics and Conduct (Oct 2015) (41 U.S.C. 3509).

(ii) 52.219-8, Utilization of Small Business Concerns (Oct 2014) (15 U.S.C. 637(d)(2) and (3)), in all subcontracts that offer further subcontracting opportunities. If the subcontract (except subcontracts to small business concerns) exceeds $650,000 ($1.5 million for construction of any public facility), the subcontractor must include 52.219-8 in lower tier subcontracts that offer subcontracting opportunities.

(iii) 52.222-17, Nondisplacement of Qualified Workers (May 2014) (E.O. 13495). Flow down required in accordance with paragraph (1) of FAR clause 52.222-17.

(iv) 52.222-21, Prohibition of Segregated Facilities (Apr 2015).

(v) 52.222-26, Equal Opportunity (Sep 2016) (E.O. 11246).

(vi) 52.222-35, Equal Opportunity for Veterans (Oct 2015) (38 U.S.C. 4212).

(vii) 52.222-36, Equal Opportunity for Workers with Disabilities (Jul 2014) (29 U.S.C. 793).

(viii) 52.222-37, Employment Reports on Veterans (Feb 2016) (38 U.S.C. 4212).

(ix) 52.222-40, Notification of Employee Rights Under the National Labor Relations Act (Dec 2010) (E.O. 13496).

Flow down required in accordance with paragraph (f) of FAR clause 52.222-40.

(x) 52.222-41, Service Contract Labor Standards (May 2014), (41 U.S.C. chapter 67).

(xi) ___ (A) 52.222-50, Combating Trafficking in Persons (Mar 2015) (22 U.S.C. chapter 78 and E.O. 13627).

___ (B) Alternate I (Mar 2015) of 52.222-50 (22 U.S.C. chapter 78 E.O. 13627).

(xii) 52.222-51, Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment--Requirements (May 2014) (41 U.S.C. chapter 67.)

(xiii) 52.222-53, Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services--Requirements (May 2014) (41 U.S.C. chapter 67)

(xiv) 52.222-54, Employment Eligibility Verification (Oct 2015).

(xv) 52.222-55, Minimum Wages Under Executive Order 13658 (Dec 2015) (E.O. 13658).

(xvi) 52.222-59, Compliance with Labor Laws (Executive Order 13673) (Oct 2016) (Applies at $50 million for solicitations and resultant contracts issued from October 25, 2016 through April 24, 2017; applies at $500,000 for solicitations and resultant contracts issued after April 24, 2017).

Note to paragraph (b)(1)(xvi): By a court order issued on October 24, 2016, 52.222-59 is enjoined indefinitely as of the date of the order. The enjoined paragraph will become effective immediately if the court terminates the injunction. At that time, DoD, GSA, and NASA will publish a document in the Federal Register advising the public of the termination of the injunction.

(xvii) 52.222-60, Paycheck Transparency (Executive Order 13673) (Oct 2016).

(xviii) 52.225-26, Contractors Performing Private Security Functions Outside the United States (Jul 2013) (Section 862, as amended, of the National Defense Authorization Act for Fiscal Year 2008; 10 U.S.C. 2302 Note).

(xix) 52.226-6, Promoting Excess Food Donation to Nonprofit Organizations. (May 2014) (42 U.S.C. 1792). Flow down required in accordance with paragraph (e) of FAR clause 52.226-6.

(xx) 52.247-64, Preference for Privately-Owned U.S. Flag Commercial Vessels (Feb 2006) (46 U.S.C. Appx 1241(b) and 10 U.S.C. 2631). Flow down required in accordance with paragraph (d) of FAR clause 52.247-64.

(2) While not required, the contractor may include in its subcontracts for commercial items a minimal number of additional clauses necessary to satisfy its contractual obligations.

(End of Clause)

52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

www.acquisition.gov

52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

www.acquisition.gov

(End of clause)

52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (APR 1984)

(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of"(DEVIATION)" after the date of the provision.

(b) The use in this solicitation of any DFARS (48 CFR Chapter 2) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.

52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES (APR 1984)

(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the clause.

(b) The use in this solicitation or contract of any DFARS (48 CFR Chapter 2) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.

252.211-7003 ITEM UNIQUE IDENTIFICATION AND VALUATION (MAR 2016)

(a) Definitions. As used in this clause-

Automatic identification device means a device, such as a reader or interrogator, used to retrieve data encoded on machine-readable media.

Concatenated unique item identifier means--

(1) For items that are serialized within the enterprise identifier, the linking together of the unique identifier data elements in order of the issuing agency code, enterprise identifier, and unique serial number within the enterprise identifier; or

(2) For items that are serialized within the original part, lot, or batch number, the linking together of the unique identifier data elements in order of the issuing agency code; enterprise identifier; original part, lot, or batch number;

and serial number within the original part, lot, or batch number.

Data Matrix means a two-dimensional matrix symbology, which is made up of square or, in some cases, round modules arranged within a perimeter finder pattern and uses the Error Checking and Correction 200 (ECC200) specification found within International Standards Organization (ISO)/International Electrotechnical Commission (IEC) 16022.

Data qualifier means a specified character (or string of characters) that immediately precedes a data field that defines the general category or intended use of the data that follows.

DoD recognized unique identification equivalent means a unique identification method that is in commercial use and has been recognized by DoD. All DoD recognized unique identification equivalents are listed at http://www.acq.osd.mil/dpap/pdi/uid/iuid_equivalents.html.

DoD item unique identification means a system of marking items delivered to DoD with unique item identifiers that have machine-readable data elements to distinguish an item from all other like and unlike items. For items that are serialized within the enterprise identifier, the unique item identifier shall include the data elements of the enterprise identifier and a unique serial number. For items that are serialized within the part, lot, or batch number within the enterprise identifier, the unique item identifier shall include the data elements of the enterprise identifier; the original part, lot, or batch number; and the serial number.

Enterprise means the entity (e.g., a manufacturer or vendor) responsible for assigning unique item identifiers to items.

Enterprise identifier means a code that is uniquely assigned to an enterprise by an issuing agency.

Government's unit acquisition cost means--

(1) For fixed-price type line, subline, or exhibit line items, the unit price identified in the contract at the time of delivery;

(2) For cost-type or undefinitized line, subline, or exhibit line items, the Contractor's estimated fully burdened unit cost to the Government at the time of delivery; and

(3) For items produced under a time-and-materials contract, the Contractor's estimated fully burdened unit cost to the Government at the time of delivery.

Issuing agency means an organization responsible for assigning a globally unique identifier to an enterprise, as indicated in the Register of Issuing Agency Codes for ISO/IEC 15459, located at http://www.aimglobal.org/?Reg_Authority15459.

Issuing agency code means a code that designates the registration (or controlling) authority for the enterprise identifier.

Item means a single hardware article or a single unit formed by a grouping of subassemblies, components, or constituent parts.

Lot or batch number means an identifying number assigned by the enterprise to a designated group of items, usually referred to as either a lot or a batch, all of which were manufactured under identical conditions.

Machine-readable means an automatic identification technology media, such as bar codes, contact memory buttons, radio frequency identification, or optical memory cards.

Original part number means a combination of numbers or letters assigned by the enterprise at item creation to a class of items with the same form, fit, function, and interface.

Parent item means the item assembly, intermediate component, or subassembly that has an embedded item with a unique item identifier or DoD recognized unique identification equivalent.

Serial number within the enterprise identifier means a combination of numbers, letters, or symbols assigned by the enterprise to an item that provides for the…

This is the start of the file's text. The full file is on GovTribe.