Maintenance on and Repair Multiple Drainage Channels
Solicitation number
W91151-16-B-0017
Issued by

About this file

RFI-Amendment P00001

View the file

Other files

File Type Posted
16-B-0017_Bid_Abstract.pdf PDF
TE_B_-_Revised_Drawings.pdf PDF
Site_Vist_Log_16-B-0017.pdf PDF
TE_A_-_Specifications.pdf PDF
TE_C_Division_1_General_Requirements.pdf PDF
TE_B_-_Drawings.pdf PDF
Solicitation_16-B-0017.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DIRECTORATE OF PUBLIC WORKS

ENGINEERING DIVISION (CONTRACTING SECTION)

BLDG 4610, ENGINEER DRIVE

FORT HOOD TX 76544-5055

0010867357 AD012083P-0

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The solicitation w as amended to post response to industry Request for Information (RFIs), revised synopsis and draw ings and changes to w ork experience section 00100. In addition, the bid opening date w as extended to 15 Sep 2016 @ 1:30 pm.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 13

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 12-Sep-2016

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W91151-16-B-0017

X 9B. DATED (SEE ITEM 11)

11-Aug-2016

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

12-Sep-2016

CODE

MISSION AND INSTALLATION CONTRACTING

MISSION CONTRACTING OFFICE (MCO)

BUILDING 1001, ROOM W103

1001 761ST TANK BATTALION AVE

FORT HOOD TX 76544-5025

W91151 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE W91151

FACILITY CODECODE

EMAIL:TEL:

W91151-16-B-0017

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

RESPONSE RFIS

AD012083P – COMBINE DRAINAGE PROJECTS:

1) Can the box culverts be poured in place versus precast?

Answer: The box culverts may be cast-in-place as long as the requirements shown in the design drawings are met.

2) Are the wing headwalls and wing walls still required to be provided in coordination with box culverts? There was some confusion about this as during site visit the question was asked if there was still any headwall work required and it was not clear if it was answered yes or no.

Answer: Headwalls and wing walls will only be placed where stated in the design drawings, which is only identified in the REPAIR FAILING DRAINAGE CHANNEL SE AREA OF RUNWAY site at RGAAF (see sheet 2C3).

Otherwise, all other culverts, headwalls, and wing walls will be left intact.

Regarding Drainage easement maintenance project:

1) During the site visit it was explained that all work to be done was at each of the 4 end locations and at the culvert between site 3 and site 4 channels. Furthermore, it was conveyed that no disturbance of trees and plant life would be part of the work in those channels, but looking at the drawings it shows that approx. a couple hundred feet of each channel on each end must have tress and vegetation disturbed and areas worked. Can you please provide more clarification?

Answer: See revised design drawings.

Regarding all three stand-alone projects:

1) Is there any export materials anticipated? If so, will these be required to be hauled off if any or can they be stockpiles onsite for later use by customer?

Answer: After cut and fill, cut material to be hauled off (or export materials) is anticipated at all three sites. The material at REPAIR EROSION AT TAXIWAY B AND F CENTER (HAAF) may be spread (not stockpiled) in other areas within the proximity of the project site with the approval of the airfield manager. For bidding purposes, however, include cost to haul off remaining cut material from all three sites.

2) Spec section 01 33 00, part 1 states: “The attached submittal register contains the required items the

Contractor shall submit for Government approval”. The specification is 3201 pages and the submittal register is 147 pages. Both include contain many items that do not pertain to the scope of this project. Is the government going to provide a submittal register and specifications tailored to this project in an amendment?

Answer: Specification 01 33 00, section 1.7 Submittal Register states, “Maintain and manage the submittal register, as the work progresses. Contractor is responsible for ensure all material and products used on the job site are identified and submitted to the government.” Also it states, “The original list provided by the government may not be all inclusive and additional submittals may be required.” The contractor is responsible for editing and providing the submittal register for review and approval to the government.

3) If no amendment is issued, who makes the final determination of which spec’s are used and what items are required to be submitted?

Answer: Contractor shall follow the specification per the material and equipment being used on the contract.

4) If no amendment is issued, Is the contractor responsible for editing the spec’s and submittal register and include the cost of those man hours in their proposal?

Answer: Contractor is responsible for ensuring all material and products used on the job site are identified and submitted to the government

5) Spec section 01 33 00, part 1 states: “all electronic submittals (disk) shall be on a CD-R disk only……….A hardcopy eng form 4025 shall accompany the CD-R and electronic form submitted by e-mail to COR. Are submittals submitted to the Government on CD with hardcopy 4025 and an e-mailed 4025 to the COR?;

a. “OR” are all submittals transmitted electronically to the COR as described in para 1.5.1?

Answer: All submittals that can be submitted by email is permitted. If an electronic submission is required that cannot be done by email due to size of files or requirement then they are to be done on CD-R- If a physical item is to be submitted for review then hardcopy is required.

6) Spec section 01 33 00, para 1.10 states: “For any rejection of a submittal the QCM has 1 days to resubmit unless directed otherwise from the KO.” One day is not enough time to change, rebuild and resubmit any submittal. Is this an error in the specifications?

Answer: This is not an error. The contactor has 1 day to resubmit or request additional time from the KO

7) During the site visit, it was mentioned that some of the sites need a SWPPP. Does each individual site require a SWPPP or can they be combined in one?

Answer: The government has no issue with the SWPPPs for all three sites being combined into one as long as the final SWPPP meets all of the TCEQ permit requirements for each site. If combined into one, the SWPPP will remain open and active until all three sites meet the final stabilization criteria. A notice of intent (NOI) must be submitted if land disturbance exceeds 5 acres.

8) Traffic Control around the air field was briefly discussed during the site visit. Site 1 (Murphy road area) appears to need some minor traffic control. The spec’s call for the TCP to be developed by a “roadway design engineer or traffic engineer”. Is this type of traffic control plan required for these sites?

Answer: A traffic control plan (TCP) will not be required if lane closure for an intermittent period of time is necessary, only advanced coordination with the COR and flaggers will be required. However, a TCP developed by the designated person as stated in the specifications will be required if full road closure or an extended single lane closure (more than 1 week) is required.

9) The solicitation calls for a project sign. There is not a location shown on the drawings for a project sign at any of the sites. Which site or sites get a project sign and where should it be erected?

Answer: See revised ‘Project Synopsis’. Project signs are not required for any of the project sites.

10) During the site visit the question was asked if a separate Superintendent was required for each work site. Ms

Lewis stated “yes, but the government would accept a Foreman if he met the qualifications”. Spec section 01 45 01.00 20, para 3.1 3-Key Personal does not address the qualifications of a Foreman. What are the qualifications for a Foreman on this project?

Answer: A Superintendent shall be required within 15 mins area of the job site if managing multiple job sites for this contract only.

11) Does this project require more than one Superintendent?

Answer: A Superintendent shall be required within 15mins area of the job site if managing multiple job sites for this contract only.

12) Will this project require more than one Quality Control Manager?

Answer: Contractor shall provide adequate QCM. There shall be only one Quality Control Manager.

13) Spec section 01 57 20.00 10, para 1.4 states: “-----Appointment of an Environmental Manager and the necessity of an Environmental Protection Plan shall be determined by the DPW Environmental Division.” Does this project require an Environmental Manger and Environmental Protection Plan?

Answer: Environmental Manager can be a dual role except with QCM. No plan is required

14) Will a gate guard be required at the entrances to the (both) Air Fields? If so, what qualifications / equipment do they need?

Answer: At REPAIR FAILING DRAINAGE CHANNEL SE AREA OF RUNWAY (RGAAF) and REPAIR EROSION AT TAXIWAY B AND F CENTER (HAAF), a gate guard is only required if the gate needs to be left open (i.e. hauling material in or out, etc.). In which case, see ‘AIRCRAFT OPERATIONS AREA – SECURITY’ on sheet 2G3 and F.1 through F.11 on sheet 3G2 in the revised design drawings regarding gate guard duties and procedures. No special training or equipment is required. Otherwise, the contractor shall assign one person with key control that will maintain a log of authorized personnel entering and leaving the site and will ensure the gate is locked immediately after personnel enters and exits the site.

REVISED SYNPOSIS

Revised Project Synopsis Maintenance Multiple Drainage Channels

Project No. AD012083P September 7, 2016

DESCRIPTION OF WORK: The purpose of the project is to perform maintenance on and repair multiple drainage channels at various locations throughout Fort Hood to include the following:

The following drawings are included as part of the Solicitation.

COMBINED PROJECT GENERAL SHEETS

G-1 COVER SHEET

G-2 INDEX OF DRAWINGS

DRAINAGE EASEMENT MAINTENANCE

1G-1 COVER SHEET

1G-2 GENERAL NOTES

1C-1 OVERALL SITE PLAN

1C-2 PLAN/PROFILE – STA 0+00.00 - STA 7+00.00

1C-3 PLAN/PROFILE – STA 7+00.00 - STA 9+47.40

1C-4 PLAN/PROFILE – STA 50+00.00 - STA 50+18.49

1C-5 PLAN/PROFILE – STA 100+00.00 - STA 107+00.00

1C-6 PLAN/PROFILE – STA 107+00.00 - STA 108+46.05

1C-7 SITE DETAILS I

1C-8 SITE DETAILS II

REPAIR FAILING DRAINAGE CHANNEL SE AREA OF RUNWAY

2G-1 COVER SHEET

2G-2 GENERAL NOTES I

2G-3 GENERAL NOTES II

2C-1 OVERALL SITE PLAN

2C-2 PLAN/PROFILE – STA. 100+00 – STA. 105+10.17

2C-3 PLAN/PROFILE – STA. 1000+00 – STA. 1006+00.40

2C-4 SITE DETAILS I

2C-5 SITE DETAILS II

2C-6 GABION BASKETS

2C-7 SINGLE BOX CULVERTS PRECAST 6’-0” SPAN

2C-8 BOX CULVERTS - PRECAST MISCELLANEOUS DETAILS

2C-9 CONCRETE WING WALLS W/ FLARED WINGS FOR SKEWED BOX CULVERTS

2C-10 GROUTED SLOPING BOULDER DROP STRUCTURE

2C-11 GROUTED SLOPING BOULDER DROP STRUCTURE – DETAILS

2C-12 APPROACH LIGHTING TOWER – DETAIL I

2C-13 APPROACH LIGHTING TOWER – DETAIL II

REPAIR EROSION AT TAXIWAY B AND F CENTER

3G-1 COVER SHEET

3G-2 GENERAL NOTES I

3G-3 GENERAL NOTES II

3C-1 OVERALL SITE PLAN

3C-2 PLAN/PROFILE – STA. 100+00 – 105.32.98

3C-3 PLAN/PROFILE – STA. 200+00 – 205+91.00

3C-4 SITE DETAILS

One set of solicitation documents, including plans, specifications, and miscellaneous data, will be furnished to the contractor in Adobe PDF format. After award, one set of Adobe PDF contract drawings and PDF specifications, and one set of MicroStation format drawings (if available) will be furnished to the Contractor on CD. Reference publications will not be furnished. Contractor shall immediately check furnished drawings and notify the Government of any discrepancies.

A project construction sign will not be required for this project. Contractor shall keep all permits and other documents required to be on the job site in a 3-ring binder or posed on a bulletin board within the construction area.

PERFORMANCE PERIOD: Barring any contingencies that arise during construction, the Government requires this project be completed within 180 calendar days. Completion is defined as completion of all contractual obligations.

Drainage Easement Maintenance – Perform maintenance and repair erosion along the drainage channels and embankments in the vicinity of Murphy Road, 37th Street, and Hellcat Road. The following work shall be included:

The contractor shall:

Remove vegetation, sediment and debris along headwall aprons. Remove joint sealants, thoroughly clean out joints, spray herbicide as recommended in the drawings with the approval of the Fort Hood IPMC, and reseal. Nationwide permit (NWP) 3(a) shall be followed regarding maintenance and repair of culverts, headwalls, aprons, stilling basins, and low water crossings.

Remove sediment and debris from inside the existing concrete culverts. NWP 3(a) shall be followed.

Remove existing deteriorated joint sealant inside of the concrete culvert located on the north side of Site 2 in the drawings. Thoroughly clean out joint and reseal. NWP 3(a) shall be followed.

Clear and grub trees and vegetation and remove accumulated sediment and debris along the drainage channels, within the limits of repair.

Cut the vegetation along the channels in between the limits of repair in such a manner that does not cause soil disturbance.

Reshape drainage channels, within the limits of repair, to conform to the trapezoidal cross sections shown in the “SITE DETAILS I” sheet. See “PLAN/PROFILE – STA 0+00.00 - STA

7+00.00”, “PLAN/PROFILE – STA 7+00.00 - 9+47.40”, “PLAN/PROFILE – STA 50+00.00 -

50+18.49”, “PLAN/PROFILE – STA 100+00.00 - 107+00.00”, and “PLAN/PROFILE – STA 107+00.00 - 108+46.05” sheets for proposed profiles and grading plans. Nationwide permit (NWP) 41 shall be followed regarding reshaping existing drainage ditches constructed in waters of the United States.

Stabilize embankments along Sta. 0+00 to 9+47.40 with a rock rip rap and non-woven geotextile revetment as shown in the “SHOULDER STABILIZATION TYPICAL SECTION” detail in the drawings. Ensure that the bed of the channel in between the limits of repair is not disturbed.

Install a rip rap apron at the outlet and inlet of Site 1 and 2.

All disturbed areas within Sites 4 and 5 shall be stabilized with hydraulic mulch seed.

Install Bermuda sod and ScourStop, or similar, per the manufacturer’s recommendations in the areas indicated in the drawings.

All disturbed areas, not otherwise stabilized (i.e. rip rap, sod, ScourStop), shall be stabilized with hydraulic mulch seed.

Repair Failing Drainage SE Area of Runway – Repair erosion, to include an approximate 9-foot drop-off, along the existing drainage channel and replace the existing 60-inch CMP and damaged security fence line located on the southeast area of the runway at Robert Gray Army Airfield (RGAAF). The following work shall be included:

Temporarily relocate the existing approach lighting tower and demolish the existing foundation.

Ensure temporary location does not impact the airfield operations.

Demolish the fence line adjacent to the culvert outlet, where indicated in the drawings. Provide temporary fencing.

Demolish 60-inch CMP and the asphalt road, where indicated in the drawings.

drainage channel.

Reshape drainage channel to conform to the trapezoidal cross sections shown in the “SITE

DETAILS I” sheet. See “PLAN/PROFILE STA. 100+00 - 105+10.17”, and “PLAN/PROFILE STA.

1000+00 – 1006+00.40” sheets for proposed profile and grading plan. Nationwide permit (NWP) 41 shall be followed regarding reshaping existing drainage ditches constructed in waters of the United States.

All disturbed areas shall be stabilized with hydraulic mulch seed. Install a turf reinforcement mat

(TRM) per the manufacturer’s recommendations in the areas indicated in the drawings.

Construct a grouted sloping boulder drop structure as shown in “GROUTED SLOPING BOULDER DROP” and “GROUTED SLOPING BOULDER DROP DETAILS” sheets. See “PLAN/PROFILE – STA. 1000+00 – STA. 1006+00.40” for proposed profile and grading plan.

Install three 6-foot by 5-foot reinforced concrete box (RCB) culverts with a headwall, wing walls, a concrete apron, and a rip rap apron at the inlet and outlet per TXDOT standards. Ensure headwalls are perpendicular to the flow of water and the RCB culverts run parallel to each other.

Nationwide permit (NWP) 3(a) shall be followed regarding maintenance and repair of culverts, headwalls, aprons, stilling basins, and low water crossings.

Install security grates at the opening of each RCB culvert inlet, per UFC 4-022-03 requirements, as shown in the “TYPICAL GRATE AT INLET” detail in the drawings.

Replace the asphalt road as shown in the “PROPOSED TYPICAL SECTION” detail in the drawings.

Realign and install the fence line, a minimum 5-feet from the pavement edge, to match existing.

Cast-in-place a 15-foot by 12-foot foundation and mount the approach lighting tower, per UFC 3-

260-01 requirements, on pedestals to match the existing x-, y-, and z- coordinates.

Repair Erosion at Taxiway B and F Center – Repair erosion at Hood Army Airfield (HAAF) along the northeast side of Taxiway B and north side of Taxiway F. The following work shall be included:

Clean out the existing catch basin.

Reshape shoulder and the existing v-shaped channel to a trapezoidal channel that conforms to the grades shown in the “SITE DETAILS” sheet. See “PLAN/PROFILE – STA. 100+00 – STA.

105.32.98” and “PLAN/PROFILE – STA. 200+00 – STA. 205+91.00” sheets for proposed profiles and grading plans.

Spread topsoil over all disturbed areas to a depth that, after settlement, provides the required depth. Disk or scarify to a minimum depth of 4-inch and stake ‘Big Rolls’ of Bermuda sod, ensuring final grades are flush with existing adjacent areas. Ensure entire area has positive drainage and is free from abrupt changes in slope.

SECTION 00010 - SOLICITATION CONTRACT FORM

The required response date/time has changed from 08-Sep-2016 02:00 PM to 15-Sep-2016 01:30 PM.

TABLE OF CONTENTS

The Table of Contents has changed from:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Exhibit A Specifications 3313 11-JAN-2016 Exhibit B Drawings 35 25-APR-2016 Exhibit C Division 1 General

Requirements

110 11-JAN-2016

Attachment Appendix A 111 11-JAN-2016 to:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Exhibit A Specifications 3313 11-JAN-2016 Exhibit C Division 1 General

Requirements

110 11-JAN-2016

Attachment Appendix A 111 11-JAN-2016 Attachment B Revised Drawings 35 12-SEP-2016

The following have been modified:

SYNPOSIS

PROJECT SYNOPSIS

Maintenance Multiple Drainage Channels

Project No. AD012083P

DESCRIPTION OF WORK: The purpose of the project is to perform maintenance on and repair multiple drainage channels at various locations throughout Fort Hood to include the following:

The following drawings are included as part of the Solicitation.

COMBINED PROJECT GENERAL SHEETS:

G-1 COVER SHEET

G-1 INDEX OF DRAWINGS

DRAINAGE EASEMENT MAINTENANCE

1G-1 COVER SHEET

1G-2 GENERAL NOTES

1C-1 OVERALL SITE PLAN

1C-2 PLAN/PROFILE – STA 0+00.00 - STA 2+50.00

1C-3 PLAN/PROFILE – STA 2+50.00 - STA 9+47.40

1C-4 PLAN/PROFILE – STA 50+00.00 - STA 50+18.49

1C-5 PLAN/PROFILE – STA 100+00.00 - STA 107+00.00

1C-6 PLAN/PROFILE – STA 107+00.00 - STA 108+46.05

1C-7 SITE DETAILS I

1C-8 SITE DETAILS II

REPAIR FAILING DRAINAGE CHANNEL SE AREA OF RUNWAY

2G-1 COVER SHEET

2G-2 GENERAL NOTES I

2G-3 GENERAL NOTES II

2C-1 OVERALL SITE PLAN – DEMOLITION

2C-2 OVERALL SITE PLAN – IMPROVEMENTS

2C-3 PLAN/PROFILE – STA. 100+00 – STA. 105+10.17

2C-4 PLAN/PROFILE – STA. 1000+00 – STA. 1006+00.40

2C-5 SITE DETAILS I

2C-6 SITE DETAILS II

2C-7 GABION BASKETS

2C-8 SINGLE BOX CULVERTS PRECAST 6’-0” SPAN

2C-9 BOX CULVERTS - PRECAST MISCELLANEOUS DETAILS

2C-10 CONCRETE WING WALLS W/ FLARED WINGS FOR SKEWED BOX CULVERTS

2C-11 GROUTED SLOPING BOULDER DROP STRUCTURE

2C-12 GROUTED SLOPING BOULDER DROP STRUCTURE – DETAILS

2C-13 APPROACH LIGHTING TOWER – DETAIL 1

2C-14 APPROACH LIGHTING TOWER – DETAIL II

REPAIR EROSION AT TAXIWAY B AND F CENTER

3G-1 COVER SHEET

3G-2 GENERAL NOTES

3C-1 OVERALL SITE PLAN

3C-2 PLAN/PROFILE – STA. 100+00 – 105.32.98

3C-3 PLAN/PROFILE – STA. 200+00 – 205+91.00

3C-4 SITE DETAILS

One set of solicitation documents, including plans, specifications, and miscellaneous data, will be furnished to the contractor in Adobe PDF format. After award, one set of Adobe PDF contract drawings and PDF specifications, and one set of MicroStation format drawings (if available) will be furnished to the Contractor on CD. Reference publications will not be furnished. Contractor shall immediately check furnished drawings and notify the Government of any discrepancies.

A project construction sign will be required for this project. Contractor shall keep all permits and other documents required to be on the job site in a 3-ring binder or posed on a bulletin board within the construction area.

PERFORMANCE PERIOD: Barring any contingencies that arise during construction, the Government requires this project be completed within 180 calendar days. Completion is defined as completion of all contractual obligations.

Drainage Easement Maintenance – Perform maintenance and repair erosion along the drainage channels and embankments in the vicinity of Murphy Road, 37th Street, and Hellcat Road. The following work shall be included:

Remove vegetation, sediment and debris along headwall aprons. Remove joint sealants, thoroughly clean out joints, spray herbicide as recommended in the drawings with the approval of the Fort Hood IPMC, and reseal. Nationwide permit (NWP) 3(a) shall be followed regarding maintenance and repair of culverts, headwalls, aprons, stilling basins, and low water crossings.

Remove sediment and debris from inside the existing concrete culverts. NWP 3(a) shall be followed.

Remove existing deteriorated joint sealant inside of the concrete culvert located on the north side of Site 2 in the drawings. Thoroughly clean out joint and reseal. NWP 3(a) shall be followed.

drainage channels, within the limits of repair.

Cut the vegetation along the channels in between the limits of repair in such a manner that does not cause soil disturbance.

Reshape drainage channels, within the limits of repair, to conform to the trapezoidal cross sections shown in the “SITE DETAILS I” sheet. See “PLAN/PROFILE – STA 0+00.00 - STA 2+50.00”, “PLAN/PROFILE – STA 2+50.00 - STA 9+47.40”, “PLAN/PROFILE – STA 50+00.00 - STA 50+18.49”, “PLAN/PROFILE – STA 100+00.00 - STA 107+00.00”, and “PLAN/PROFILE – STA 107+00.00 - STA 108+46.05” sheets for proposed profiles and grading plans. Nationwide permit (NWP) 41 shall be followed regarding reshaping existing drainage ditches constructed in waters of the United States.

Stabilize embankments along Sta. 0+00 to 9+47.40 with a rock rip rap and non-woven geotextile revetment as shown in the “SHOULDER STABILIZATION TYPICAL SECTION” detail in the drawings. Ensure that the bed of the channel in between the limits of repair is not disturbed.

Install a rip rap apron at the outlet and inlet of Site 1 and 2.

All disturbed areas within Sites 4 and 5 shall be stabilized with hydraulic mulch seed.

Install Bermuda sod and ScourStop, or similar, per the manufacturer’s recommendations in the areas indicated in the drawings.

All disturbed areas, not otherwise stabilized (i.e. rip rap, sod, ScourStop), shall be stabilized with hydraulic mulch seed.

Repair Failing Drainage SE Area of Runway – Repair erosion, to include an approximate 9-foot drop-off, along the existing drainage channel and replace the existing 60-inch CMP and damaged security fence line located on the southeast area of the runway at Robert Gray Army Airfield (RGAAF). The following work shall be included:

Temporarily relocate the existing approach lighting tower and demolish the existing foundation.

Ensure temporary location does not impact the airfield operations.

Demolish the fence line adjacent to the culvert outlet, where indicated in the drawings. Provide temporary fencing.

Demolish 60-inch CMP and the asphalt road, where indicated in the drawings.

drainage channel.

Reshape drainage channel to conform to the trapezoidal cross sections shown in the “SITE DETAILS I” sheet. See “SITE PLAN – GRADING AND PROFILE” sheets for proposed profile and grading plan. Nationwide permit (NWP) 41 shall be followed regarding reshaping existing drainage ditches constructed in waters of the United States.

All disturbed areas shall be stabilized with hydraulic mulch seed. Install a temporary rolled erosion control product (RECP) or turf reinforcement mat (TRM) per the manufacturer’s recommendations in the areas indicated in the drawings.

Construct a grouted sloping boulder drop structure as shown in “GROUTED SLOPING

BOULDER DROP” and “GROUTED SLOPING BOULDER DROP DETAILS” sheets. See “PLAN/PROFILE – STA. 1000+00 – STA. 1006+00.40” for proposed profile and grading plan.

Construct size ‘D’ gabion baskets and install along the bottom of the channel every 10-feet alternating sides where shown in the drawings.

Install three 6-foot by 5-foot reinforced concrete box (RCB) culverts with a headwall, wing walls, a concrete apron, and a rip rap apron at the inlet and outlet per TXDOT standards. Ensure headwalls are perpendicular to the flow of water and the RCB culverts run parallel to each other.

Nationwide permit (NWP) 3(a) shall be followed regarding maintenance and repair of culverts, headwalls, aprons, stilling basins, and low water crossings.

Install security grates at the opening of each RCB culvert outlet, per UFC 4-022-03 requirements, as shown in the “TYPICAL GRATE AT OUTLET” detail in the drawings.

Replace the asphalt road as shown in the “PROPOSED TYPICAL SECTION” detail in the drawings.

Realign and install the fence line, a minimum 5-feet from the pavement edge, to match existing.

Cast-in-place a 20-foot by 15-foot foundation and mount the approach lighting tower, per UFC 3-

260-01 requirements, on pedestals to match the existing x-, y-, and z- coordinates.

Repair Erosion at Taxiway B and F Center – Repair erosion at Hood Army Airfield (HAAF) along the northeast side of Taxiway B and north side of Taxiway F. The following work shall be included:

Clean out the existing catch basin.

Reshape shoulder and the existing v-shaped channel to a trapezoidal channel that conforms to the grades shown in the “SITE DETAILS” sheet. See “PLAN/PROFILE – STA. 100+00 – STA.

105.32.98” and “PLAN/PROFILE – STA. 200+00 – STA. 205+91.00” sheets for proposed profiles and grading plans.

Spread topsoil over all disturbed areas to a depth that, after settlement, provides the required depth. Disk or scarify to a minimum depth of 4-inch and stake ‘Big Rolls’ of Bermuda sod, ensuring final grades are flush with existing adjacent areas. Ensure entire area has positive drainage and is free from abrupt changes in slope.

SECTION 00100 - BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS

The following have been modified:

SPECIAL NOTICE

Any bids received in response to this solicitation SHALL carry a 120 day acceptance period before prices need to be verified, extended or re-negotiated.

Public Bid Openings: Will be conducted in QA Conference Room, Building 4610, Engineer Drive, Fort Hood, Texas. Please refer to Block 8 (Address Offer to) of the SF 1442. Anyone wishing to attend the bid opening MUST notify the Contracting Officer of record in this solicitation no later than 7 SEP 2016 with a firm commitment to attend.

(End of special requirements)

Public Bid Openings mailing address:

Directorate of Public Works ATTN: Engineering Division (CONTRACTING SECTION) Building 4610 Engineer Drive Fort Hood, TX 76544

WORK EXPERIENCE

The prime contractor shall demonstrate that it possesses general construction contract management by providing at least three examples of five years of relevant work experience in an awarded contract similar to the requirements stated in this solicitation. Documentation shall be submitted with the bid/offer and include the contract number, the date of contract award, the customer's name and contact information, the awarded dollar value, a description of all work elements included in the contract, the number and type of specialty trades needed to complete the contract, and the period of time allocated for completion of the work. Federal work experience is preferred; however, the Government will accept work experience from both State and institutional and commercial contracts as well. No residential work experience will be considered appropriate for this purpose. Failure to provide this documentation may reject a bid/offer as non-responsive and no further consideration will be given to that bidder/offeror for award of this contract.

SUBCONTRACTOR LIST

Offerors shall submit a list of proposed subcontractors as an attachment to their quote/offer. If offeror does not intend on utilizing subcontractors (self-perform), offeror shall state so in their bid.

MANDATORY ATTENDANCE – PRE-BID AND PRE-CONSTRUCTION CONFERENCES

The Contracting Officer reserves the right to conduct a pre-bid/pre-proposal conference in conjunction with the site visit. The contractors that bid must attend the site visit to be considered responsive to the instructions in the solicitation. IF contractors who submit a bid did not attend the site visit, then they shall be considered non-responsive to the instructions provided in the solicitation. The Contracting Officer will review solicitation submittal requirements, and other administrative matters critical for successful and timely performance of the work.

The Contractor shall, at the discretion of the Contracting Officer, attend a Government coordinated preconstruction conference within 10 calendar days of contract award. As a minimum, the conference shall be attended by the contractor’s appointed project manager, the superintendent, the Quality Control Manager (QCM), and administrative personnel responsible for preparation of contract documents, certified payroll records and invoices. The contractor shall deliver letter appointments of its key personnel that include each individual’s duties, roles and responsibilities.

(End of Summary of Changes)