F2L3CE7192A101

(MLWR09-1077) Replace Sprinkler System at ACFT Washrack, B2827 Kunsan AB

Notice to Offerors: Funds are not presently available for this project. No contract aw ard w ill be made until appropriated funds are made available. The Government reserves the right to cancel this solicitation, either before or after the closing date.

This is a Non-Work Plan task order for the follow ing MATOC Contractors Only: W91QVN-14-D-0031, -0032, -0033-, -0035, -0036, -0037, -0038, -0039, -0040, -0041, -0044, -0045, -0046, -0047, -0048, -0049, -0050.

OFFERORS MUST COMPLY WITH THE FOLLOWING:

A. Site Visit: Offerors w ho intend to propose on this solicitation are strongly encouraged to attend site visit. See site visit Clause FAR 52.236-27 in Section L. Offerors are required to have a valid Korean Identif ication card w hen attending the site visit orientation.

B. SUBMISSION OF PROPOSAL:

1. The PROPOSAL shall be submitted by 13:00 hours on the closing date of RFP through https://w w w .fbo.gov/

2. Section K: Offerors must complete all portions of Section K and submit it through https://w w w .fbo.gov/by 13:00 hours on the closing date of RFP.

SSG CHITI, MICHAEL C. 315-782-4567

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

25-Aug-2017

(RFP)

(IFB)

X

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________365 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________Section F

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

YES X NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________15 Sep 2017 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee is, X is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______90 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

411TH CONTRACTING SUPPORT BRIGADE, KOREA

RCO KUNSAN, UNIT #2112

APO AP 96264-2112

UNITED STATES OF AMERICA (THE)

W90VN7

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

01:00 PM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX:TEL: TEL: FAX:

W90VN7-17-R-0029 46

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

W90VN7-17-R-0029

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Lot MLWR09-1077, Replace Sprinkler System

FFP

The Contractor shall provide all labor, tools, equipment, transportation, materials and other necessary resources for Project MLWR09-1077, Replace Sprinkler Sys at ACFT Washrack, B2827 in accordance with the Statement of Work (SOW).

FOB: Destination

PURCHASE REQUEST NUMBER: F2L3CE7192A101

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

War Hazard (0)

FFP

War Hazard (0)

NET AMT

Section C - Descriptions and Specifications

STATEMENT OF WORK

TECHNICAL SPECIFICATIONS

FOR

MLWR09-1077

REPAIR FIRE PROTECTION SYSTEM

ACFT WASHRACK, B-2827

KUNSAN AIR BASE

(NON-WORK PLAN TASK ORDER BY MATOC)

8TH CIVIL ENGINEER SQUADRON

KUNSAN AIR BASE, KOREA

JUNE 2017

DETAILED-SPECIFICATION

The specification sections listed below are applicable to this project. The specifications are from the “Standard Technical Specifications for O&MA Projects, Korea”, dated Jan 2014, located on the 411th CSB Web Page, https://www.usfk.mil/ Resources/ContractingwithUSFK.aspx. The electronic version of the specifications is Acrobat® PDF format and can be read with the Acrobat Reader software.

INDEX

SECTION NO TITLE

DIVISION 01 - GENERAL REQUIREMENTS

013000 Administrative Requirements 013201 Project Schedule 013300 Submittal Procedures 013526 Governmental Safety Requirements 014200 Sources for Reference Publications’ 014500 Contractor Quality Control 015000 Temporary Construction Facilities 015720 Environmental Protection 015800 Project Identification 017800 Closeout Submittals 017823 Operation and Maintenance Data

DIVISION 02 - EXISTING CONDITIONS

024100 Demolition and Deconstruction

DIVISION 03 - CONCRETE

033004 Concrete for Minor Structures

DIVISION 05 - METALS

051200 Structural Steel 055013 Miscellaneous Metal Fabrications

DIVISION 06 - WOOD

061000 Rough Carpentry

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

071113 Bituminous Damp-proofing 072116 Mineral Fiber Blanket Insulation 072400 Exterior Insulation and Finish Systems 074114 Protected Metal 074213 Metal Wall Panels 076000 Flashing and Sheet Metal 076114 Steel Standing Seam Roofing 079200 Joint Sealants

DIVISION 08 - OPENINGS

081113 Steel Doors and Frames 087100 Door Hardware 089100 Metal Louvers

DIVISION 09 - FINISHES

092200 Supports for Plaster and Gypsum Board 092900 Gypsum Board 095100 Acoustical Ceilings 099000 Paints and Coatings

DIVISION 22 - PLUMBING

220000 Plumbing, General Purpose

DIVISION 23 - HEATING, VENTILATING, AND AIR CODITINGS

230000 Air Supply, Distribution, Ventilation, and Exhaust Systems 230300 Basic Mechanical Materials and Methods 230593 Testing, Adjusting, and balancing for HVAC 230700 Thermal Insulation for Mechanical System

230800.0010 Commissioning of HVAC systems

230953.0020 Space temperature control systems

232300 Refrigerant Piping 235200 Heating Boilers

238202.0010 Unitary heating and cooling equipment

238300.0020 Electric Space Heating Equipment

DIVISION 26 - ELECTRICAL

262000 Interior Distribution System 265100 Interior Lighting

DIVISION 31 – EARTHWORK

310000 Earthwork 311100 Clearing and Grubbing

DIVISION 32 - EXTERIOR IMPROVEMENTS

321116 Base Course for Rigid and Subbases for Flexible Paving 321123 Aggregate and/or Graded-Crushed Aggregate Base Course 321210 Bituminous Tack and Prime Coats 321211 Bituminous Surface Treatment 321216 Hot-Mix Asphalt (HMA) For Roads

321313.06 Portland Cement Concrete Pavement for Roads and Site Facilities 321613 Concrete Sidewalks and Curbs and Gutters

321724.0010 Pavement Markings

329223 Sodding

DIVISION 33 – UTILITIES

331100 Water Distribution 333000 Sanitary Sewers 334000 Storm Drainage Utilities 337002 Underground Electrical Distribution

NOTE: Wherever "Special Clause" or "Special Provisions" appears in OM&A sections substitute "clauses and/or special provisions of this contract."

CHANGES TO THE STANDARD TECHNICAL DETAIL SPECIFICATIONS:

The following Supplemental Specification sections are added to the Standard Technical Specifications for O&MA Projects, Korea and form a part of the specifications. (see attachment at end of the specification):

SUPPLEMENTAL SPECIFICATIONS

DIVISION 21 - FIRE SUPPRESSION

211313.0010 Wet Pipe Sprinkler System, Fire Protection

211339 High Expansion Foam (HEF) Fire Protection Systems 213000 Fire Pumps

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

283164.0010 Fire Detection and Alarm System, Addressable

DIVISION 1 GENERAL REQUIREMENTS

SECTION 1A STATEMENT OF WORK

INDEX

1A-1 DESCRIPTION OF WORK

1A-2 PRINCIPAL FEATURES

1A-3 OTHER COVERNMENT DOCUMENS PUBLICATIONS

1A-4 PERFORMANCE PERIOD

1A-5 LIST OF DRAWINGS

1A-6 GENERAL CONDITIONS

1A-7. ENVIRONMENTAL PROTECTION SPECIFICATION

1A-8 LIST OF GOVERNMENT FURNISHED MATERIALS (GFM) AND CONTRACTOR

INSTALLATION (CI) – US OFF-SHORE.

1A-1. Description of Work: The work under project MLWR09-1077, REPAIR FIRE PROTECT SYS AT ACFT WASHRACK HANGAR, B2827consists of furnishing all labor, equipment, materials, transportation and supervision necessary to perform all the work as shown on the drawings and indicated herein. Unless otherwise specified in this task order, the contractor shall comply the terms and conditions of Indefinite Delivery, Indefinite Quantity (IDIQ) Multiple Award Task Order Contract (MATOC) issued by 411th CSB, Korea.

CONTRACT TYPE: This is an individual NON-WORK PLAN TASK ORDER of Indefinite Delivery, Indefinite Quantity (IDIQ) Multiple Award Task Order Contract (MATOC) issued by 411th CSB, Korea.

1A-2. Principal Features: This project includes the detailed specifications and drawings as provided under this task order.

2. SCOPE of WORK:

Schedule #1, Repair (K): All work shall be in accordance with the attached drawings and specifications.

2.1. CIVIL WORK

2.1.1. Restore PCC pavement.

2.1.2. Install water line to fire pump room.

2.1.3. Install sewer line to fire pump room.

2.2. ARCH WORK

2.2.1. Saw-cut the existing metal siding between the existing hangar and fire pump room to attach a new fire pump room.

2.2.2. Construct a new fire pump room and fire water tank with concrete slab, wall, EIFS, standing seam metal roof, thermal insulated metal door, concrete stoop, concrete splash block, protected metal gutter, downspout, aluminum louver and 1 metric ton monorail hoist crane per exterior/interior finish schedule and door schedule.

2.2.3. Clean and paint the existing wall in Supply Rm, Office and Storage per the floor plan drawing.

2.2.4. Repair by replacing the existing ceiling per finish schedule.

2.2.5. Replace the existing floor finishes per Finish schedule after cutting, chipping out, patching with cement mortar bed on the existing concrete slab and concrete pad.

2.2.6. Demolish the existing small storage building with concrete roof, concrete slab, concrete masonry unit wall, metal door, concrete stoop, louver and wall fan.

2.2.7. Demolish the existing container office in the hangar bay.

2.2.8. Infill with metal siding after removing the existing intake louver in Mechanical room.

2.2.9. Saw-cut the existing metal siding to provide aluminum intake louver in Mechanical room.

2.3. STRL WORK

2.3.1. Repair by replacement of fire pump system with a new fire pump room, fire water underground tank, concrete slab, wall, steel roof beam and standing seam metal roof.

2.4. MECH WORK

HVAC

2.4.1. Repair by replacement of facility heating hot water system with new oil fired hot water boiler, hot water circulation pump, expansion tank, air separator, controls, and associated piping.

2.4.2. Repair by replacement of hangar space heating system with new heating and ventilation units, hot water vertical discharge unit heaters, controls, and associated ductwork and piping.

2.4.3. Repair by replacement of hangar space exhaust system with new roof top mounted exhaust fans, controls and associated ductwork.

2.4.4. Repair by replacement of exhaust systems servicing the Mechanical (107) Fire Pump

(101) and Equipment (105) Rooms with new sidewall mounted exhaust fans, controls and associated ductwork.

2.4.5. Repair by replacement of heating systems servicing the Mechanical (107) Fire Pump

(101) Rooms with new hot water unit heater, controls and associated piping.

2.4.6. Repair by replacement of heating systems servicing the Supply (103), Equipment (105), and Toilet (106) Rooms with new hot water finned tube radiators, controls and associated piping.

2.4.7. Repair by replacement of cooling and heating systems servicing the Office Rooms (104 & hangar office) with new split system heat pump units, controls and associated piping.

2.4.8. Repair by replacement of cooling system servicing the Fire Pump Room (101) with new split system air conditioning unit, controls and associated piping.

2.4.9. All Mechanical systems shall be tested, adjusted, and balanced by the contractor in strict accordance with applicable sections of Division 15 - Mechanical O&MA Standard Technical Specifications for Miscellaneous Projects, Korea. The HVAC Testing, Adjusting, and Balancing (TAB) report shall be submitted to the project COR for government review and approval.

PLUMBING

2.4.10. Repair by replacement of the oil fired domestic hot water heater, hot water circulation pump, expansion tank, air separator, controls, and associated piping servicing the Hangar (102) wash rack equipment with new, as indicated on plans.

2.4.11. Repair by replacement of electric domestic hot water heater and associated piping servicing Toilet Room (106) with new.

2.4.12. Repair by replacement of existing deteriorated domestic hot and cold water piping, as indicated on plans.

2.4.13. Repair by replacement of existing deteriorated sewer and vent piping, as indicated on plans.

2.4.14. Repair by replacement of existing deteriorated bathroom plumbing fixtures, including water closet, urinal, lavatories, and associated piping, with new.

FIRE PROTECTION

2.4.15. Repair by replacement of existing deteriorated AFFF fire suppression system, controls, and associated piping with new wet-pipe sprinkler and high-expansion foam systems, controls, and associated piping, as indicated on plans.

2.5. ELEC WORK

LIGHTING SYSTEM

2.5.1. Repair by replacement of existing light fixtures with new light fixtures except hangar (102).

2.5.2. Repair by replacement of existing emergency unit with new emergency unit as indicated on the plan.

2.5.3. Repair by replacement of existing light switches with new switch in Supply room

(103) & Toilet (106).

POWER SYSTEM

2.5.4. Repair by replacement of existing, deteriorated receptacle with new receptacles.

2.5.5. Repair by replacement of existing, deteriorated power connection wires, safety switch, motor starter and etc. with new connection wires, safety switch, motor starter and etc.

2.5.6. Repair by replacement of existing deteriorated panelboards with new panelboards.

2.5.7. Repair by replacement of existing, deteriorated secondary line with new secondary line.

2.5.8. Repair by replacement of existing, deteriorated pull box, current transformer’s box and watthour meter with new current transformer’s box and watthour meter.

Schedule #II, New Construction (L): None

1A-3. Other Government Documents and Publications.

a. UFC 4-022-01, Security Engineering Entry Control Facilities/Access Control Points.

b. UFC 4-022-02, Selection and Application of Vehicle Barrier.

c. UFC 4-022-03, Security Fences and Gates.

d. UFC 3-120-01, Sign Standard, dated 1 March 2014.

e. UFC 3-201-01, Civil Engineering, dated 1 June 2013.

f. UFC 3-250-01FA Pavement Design for Roads, Streets, Walks and Open Storage Areas, dated 6 January 2004.

g. UFC 1-200-01 Unified Facilities Criteria Design: General Building Requirements dated 1 July 2013.

h. UFC 3-101-01, Unified Facilities Criteria Design: Fire Protection Engineering for Facilities: Architecture, dated 26 September 2006, including Change 3, I March 2013.

i. UFC 3-600-01, Unified Facilities Criteria Design: Fire Protection Engineering for Facilities for Buildings, dated 9 February 2012, Change 1, 1 March 2013.

j. UFC 4-010, DoD Unified Facilities Criteria: Minimum Antiterrorism Standards for Buildings, dated 9 February 2012, Change 1, dated 1 October 2013.

k. UFC 4-022-01, Unified Facilities Criteria Design: Security Engineering Entry Control facilities/Access Control Points, dated 25 May 2005.

l. TI 800-01, Technical Instructions Design Criteria, dated 20 July 1998 with revision thru 16 Sep 2005.

m. NEPA 101, Life Safety Code, 2012 Edition.

n. International Building Code (IBC), 2012 Edition.

o. Engineering Regulations.

ER 1110-345-100: Design Policy for Military Construction.

ER 1110-345-700: Design Analysis.

ER 1110-345-720: Specifications

p. DoD ABAAG, Department of Defense Architectural Barrier Act Accessibility Guidelines, 31 October 2008.

q. Occupational Safety and Health Standards (29 CFR Parts 1910, OSHA).

r. BHMA/ANSI Standard for Hardware.

s. UFC 3-410-01 Heating, Ventilating and Air Conditioning, 1 July 2013.

t. UFC 3-420-01 Design: Plumbing Systems 25 Oct 2004 including change "8", 27 Oct 2009.

u. ASHRAE Standard 62.1-2010 Ventilation for Acceptable Indoor Air Quality.

v. UFC 3-501-01, Electrical Engineering with Change 2, 2 July 2012.

w. UFC 3-520-01, Interior and Exterior Lighting and Controls, with Change2, I September 2012.

x. UFC 3-530-01, Exterior Electrical Power Distribution, with Chang 1, 1 July 2012.

y. IEEI C2 2012: National Electrical Safety Code.

z. NEPA 70: National Electrical Code, 2011.

aa. TM 5-811-1, Electrical Power Supply and Distribution, February 1995.

bb. Manual on Uniform Control Device for Streets and Highways issued by Federal Highway Administration

cc. Standard Technical Specifications for OMA Projects, Korea

dd. Architectural Compatibility and Design Guide of Kunsan Air Base, ROK (I Jun 2009)

1A-4. PROJECT DURATION: 360 calendar days upon receipt of NTP (Notice to Proceed)

4.1 Contractor must attend pre-construction conference prior to notice to proceed (NTP) being issued and needs to submit construction schedule prior to pre-construction conference.

1A-5. LIST OF DRAWINGS: The work shall conform to the following contract drawings and standard detail drawings (dated Oct 2014, issued by the Department of the Army, Installations Management Agency, Korea Region Office and located on the 411th CSB Web Page to Fedbizops (https://www.fbo.gov/) all of which form a part of the specifications.

ITEM NO TITLE

G-001 TITLE SHEET, SCHEDULE OF DRAWINGS & CROSS REFERENCING

CONVENTIONS

G-002 PROJECT LOCATION PLAN

C-001 CIVIL ABBREVIATIONS, NOTES, LEGEND & SCOPE OF WORK

CD101 REMOVAL PLAN

CS102 SITE LAYOUT PLAN

CU201 UTILITY LINE PROFILES

CP501 PAVEMENT DETAILS – 1

CP502 PAVEMENT DETAILS – 2

CU503 WATER DETAILS – 1

CU504 WATER DETAILS – 2

CU505 WATER DETAILS – 3

AE001 ABBREVIATIONS, MATERIAL INDICATIONS & SYMBOLS

AE002 GENERAL NOTES & SCOPE OF WORKS

AE101 EXISTING/ REMOVAL FLOOR PLAN

AE102 NEW BASEMENT FLOOR PLAN

AE103 NEW GROUND FLOOR PLAN

AE104 ROOF PLAN

AE105 REFLECTED CEILING PLAN

AE201 ELEVATIONS

AE301 CROSS SECTIONS

AE401 WALL SECTIONS

AE501 CEILING DETAILS

AE502 ROOF DETAILS

AE503 MISC DETAILS-1

AE504 MISC DETAILS-2

AE601 INTR/ EXTR FINISH SCHEDULE & MATERIAL COLOR SCHEDULE

AE602 SIGNAGE PLAN, SCHEDULE & DETAILS

AE603 DOOR/ LOUVER SCHEDULE, TYPES & DETAILS

SF001 GENERAL NOTES, DESIGN DATA & TYPICAL DETAILS

SF101 FOUNDATION, GROUND FLOOR & ROOF FRAMING PLANS

SF301 CROSS SECTIONS

SF302 CROSS SECTION AND PARTIAL ENLAGED SECTIONS

SF501 DETAILS

MH001 LEGEND & ABBREVIATIONS

MH002 GENERAL NOTES & SCOPE OF WORK

MD101 EXISTING/REMOVAL HVAC PLAN

MD401 EXISTING/REMOVAL MECH RM HVAC PARTIAL PLAN

MH101 NEW HVAC DUCT / PIPING PLAN

MH401 NEW MECH RM HVAC PARTIAL PLAN

MH501 HVAC MISC. DETAILS-1

MH502 HVAC MISC. DETAILS-2

MH601 MECHANICAL EQUIPMENT SCHEDULE

MH602 HVAC SYSTEM CONTROL DIAGRAM - 1

MH603 HVAC SYSTEM CONTROL DIAGRAM – 2

MH604 HVAC SYSTEM CONTROL DIAGRAM – 3

MH901 MECH RM HVAC PIPING ISOMETRIC DIAGRAM

PD401 EXISTING/REMOVAL MECH RM PLUMBING PIPING PARTIAL PLAN

PP101 NEW PLUMBING PIPING PLAN

PP401 NEW MECH RM PLUMBING PIPING PARTIAL PLAN

PP501 PLUMBING MISC. DETAILS

PP901 MECH RM PLUMBING PIPING ISOMETRIC DIAGRAM

E-001 LEGEND AND ABBREVIATION

E-002 GENERAL NOTES AND SCOPE OF WORK

ES101 EXIST/NEW EXTERIOR ELECTRICAL DISTRIBUTION PLAN

ES501 DETAILS-1

ES502 DETAILS-2

ED101 REMOVAL/EXIST LIGHTING PLAN

ED102 REMOVAL/EXIST POWER PLAN

EL101 NEW/EXIST LIGHTING PLAN

EL501 NON-STANDARD LIGHT FIXTURE DETAILS & SCHEDULES

EP101 NEW/EXIST POWER PLAN

EP601 REMOVAL/EXIST/NEW POWER ONE-LINE DIAGRAMS

EP602 EXIST PANELBOARD CONN. DIAGRAMS & LOAD SCHEDULES-1

EP603 LOAD SCHEDULES-2

F-001 FIRE PROTECTION NOTES, SYMBOLS AND ABBREVIATIONS

F-002 FIRE PROTECTION NOTES

LP101 LIFE SAFETY PLAN

FD101 GROUND FLOOR - FIRE PROTECTION DEMOLITION PLAN

FD102 ENLARGED - FIRE PROTECTION DEMOLITION PLAN

FD103 GROUND FLOOR - FIRE ALARM DEMOLITION PLAN

FX101 FIRE PROTECTION PLAN

FX102 IHANGAR CEILING - FIRE PROTECTION PLAN

FX301 ENLARGED FIRE PUMP ROOM - SPRINKLER AND FOAM PIPING

SECTION

FX401 ENLARGED FIRE PUMP ROOM - SPRINKLER AND FOAM PIPING PLAN

FX501 FIRE PROTECTION DETAILS

FX502 FIRE PROTECTION DETAILS

FA101 GROUND FLOOR - FIRE ALARM PLAN

FA102 GROUND FLOOR - FIRE SUPPRESSION ALARM PLAN

FA501 FIRE ALARM DETAILS

FA502 FIRE ALARM DETAILS

FA601 FIRE ALARM/MASS NOTIFICATION RISER DIAGRAM

FA602 FIRE ALARM SEQUENCE OF OPERATIONS

FA603 FIRE SUPPRESSION SEQUENCE OF OPERATIONS

1A-6. GENERAL CONDTIONS

1. SPECIFICATIONS: The project shall comply with the MLWR09-1077, REPAIR FIRE PROTECT SYS AT ACFT WASHRACK HANGAR, B2827, Kunsan AB, Korea, Contract (100%) Technical Specifications. The Standard Technical Specifications for O&MA (Operation & Maintenance Army) Projects, Korea dated Jan 2014 are available on the 411th CSB Web Page, https://www.usfk.mil/ Resources/ContractingwithUSFK.aspx.

2. ALERTS: During military alerts or special operations, anticipated not to exceed forty (40) working days per year of contract duration, the contractor may be denied access to the base or the work areas. When the contractor is prohibited from access to the base or worksite for one (1) day or less per month, no adjustment in the contract time will be made. When the contractor is prohibited access for more than one (1) day per month, an adjustment to the contractor’s schedule will be made by the Contracting Officer (KO).

3. DAILY REPORTING: The contractor Project Manager shall be responsible to report to the COR or Government project inspector at 0800 during normal work days, or at 1700 during night shifts . The contractor project manager shall provide the COR or Government project inspector with a daily report detailing the work which is being accomplished at the worksite. Failure on the project manager’s part to report to the COR or Government project inspector will result in a letter being forwarded to the KO recommending appropriate action by the KO for the contractor’s lack of coordinating the daily work report.

4. NOTIFICATION OF INSPECTIONS: Prior to starting work at the work site, the contractor shall inform the COR of the actual date that the contractor intends to start work. The contractor shall also give the COR or project inspector no less than a seven (7) work day notice prior to each concrete placement, asphalt placement field test, protective coating, or any other work deemed necessary by the COR or project inspector. The contractor shall also give at least a seven (7) work day written notification of the pre-final and final inspections to the COR. The Construction Management Element of the 8th Civil Engineering Squadron is located in building #705, Kunsan Air Base, Korea; base phone extension is 782-6197 or commercial (063) 470-

6197. (CDRL 1)

5. CLOSE-OUT/TURNOVER MATERIALS: The contractor shall be responsible for providing the following materials as part of final turnover to the U.S. Government: AS-built drawings shall be submitted to COR for review and acceptance in electronic format utilizing AutoCAD 2006 or higher and submitted on CD/DVD format (3 copies). Operations and Maintenance (O&M) training shall be provided to U.S. Government personnel on new mechanical systems NLT (7) work days, not counting weekends, prior to final acceptance.

O&M Manuals shall be submitted in both electronic and hard copy format (3 copies each) (7) work days prior to final acceptance. Turnover of all new facility keys and salvageable material (if any) shall be submitted to COR or project inspector. Contractor shall prepare DD form 1354 (Transfer and Acceptance of DOD Real Property) with type and quantity of construction material installed. When all materials have been turned over, the COR or project inspector will notify the KO so that the final payment may be released. Up to fifteen (15%) percent of the total contract amount may be withheld pending complete turnover of material stated in this paragraph."

(CDRL 2)

6. AIR FORCE MATERIALS: All salvageable materials removed from the worksite shall remain the property of the U.S. Government. All other such materials shall be disposed of by the contractor IAW AF regulations, upon coordination with the COR or project inspector.

Applicable AF regulations include AFI 32-7001 (Environmental Management), AFPAM 32- 7043 (Hazardous Waste Management Guide), AFI 32-1052 (Facility Asbestos Management), AFI 32-7042 (Waste Management), UFC 4-451-10N (Hazardous Waste Storage, and UFC 1- 900-01 (Methods for the Reduction, Reuse, and Recycling of Demolition Waste) and their source reference documents. Unclear or conflicting information between these documents can be clarified via RFI from the contractor to 8 CES/CENMP.

7. CONTRACTOR’S EQUIPMENT: All contractor equipment used in the performance of this contract shall be subject to a functional and safety inspection(s) at any time by the COR or project inspector IAW U.S. Air Force Safety Regulations and EM 385-1-1, U.S. Army Corps of Engineers Safety and Health Requirements Manual. Any equipment found not to be functional or safe shall be immediately repaired, replaced, or removed from the worksite by the contractor.

Additionally, the contractor will provide the COR or construction inspector a listing of all equipment to be used on site prior to the start of work, NLT (10) days after NTP. Applicable U.S. Air Force Safety Regulations include UFC 3-560-01 (Electrical Safety, O&M; with Change 4), AFI 32-1064 (Electrical Safe Practices), AFI 91-302 (Air Force Occupational and Environmental Safety, Fire Protection, and Health Standards) and AFPAM 91-210 (Contract

Safety... although this is more for our use in setting up contracts than for the contractor in executing them) and their source reference documents. Unclear or conflicting information between these documents can be clarified via RFI from the contractor to 8 CES/ CENMP.

(CDRL 3)

8. MATERIAL COMPLIANCE: The contractor shall be responsible to ensure that all materials used in the performances of the contract meet the specifications and requirements of this contract. Material(s) not meeting the specifications or not approved on AF Form 3000, Material Approval Submittal (or shall not be transported to the worksite. The COR or Base Civil Engineer Officer will be the approving authority for all materials used in the performance of this contract. All material(s) shall be new and the standard product of a manufacturer who is regularly engaged in the manufacturing of such products. Any materials used in the performance of this contract not approved on an AF Form 3000 shall be removed and replaced, at the expense of the contractor, and not the U.S. Government unless the government determines that the item does meet the specifications in the contract.

9. CONTRACTOR-FURNISHED MATERIAL AND CONTRACTOR-FURNISHED

EQUIPMENT (CFM/CFE): All CFM/CFE, including construction equipment, will not be permitted to enter Kunsan Air Base unless each item is approved on a DD Form 1149, Requisition and Invoice/Shipping Document. The contractor shall be responsible to notify the COR or Base Civil Engineer Officer at least three (3) work days prior to the arrival of, or removal of, any CFM/CFE at Kunsan Air Base. DD Form 1149 is available on open source internet (http://www.dcma.mil/dcman/NPP/files/dd1149.pdf).

10. CONTRACTOR’S TEMPORARY FACILITES: Erection of any facility by the contractor shall be coordinated with the COR or project inspector. An approved U.S.

Government Real Estate Permit from the Base Civil Engineer (BCE) shall be in the contractor’s possession before erection of any facility. Any contractor erected facility shall be removed and the area cleaned within seven (7) calendar days in normal installation access areas and (5) duty days in installation restricted areas after completion of the contract requirements and prior to final invoice payment.

11. Air Force (AF) FORM 103, BASE CIVIL ENGINEERING WORK CLEARANCE

REQUEST:

Prior to starting any work, The contractor shall be responsible to have a valid AF Form 103, Base Civil Engineering Work Clearance Request (dig permit) in his possession. No work shall be performed under this contract without a valid AF Form 103 in the contract’s possession. Request for a Base Civil Engineering Work Clearance Request shall be submitted to the COR or Base Civil Engineer Officer a minimum of ten (10) calendar days prior to starting any work under the terms of this contract.

12. SAFETY: AFOSHSTD91-501 (Air Force Occupational and Environmental Safety, Fire Protection, and Health Standard) shall be complied with. All AFOSH standards shall be complied with as applicable. The contractor shall also comply with applicable sections of EM 385-1-1, U.S. Army Corps of Engineers Safety and Health Requirements Manual.

13. FIRE PROTECTION: The contractor shall comply with the provisions of the Base Fire Protection program, 607 AOGI (Air Operations Group Instruction) 32-2001. The contractor shall provide suitable fire extinguishers at any material storage area constructed by the contractor as well as at the work site(s). The contractor shall ensure that all contractor employees understand that there will be no smoking inside or within 50 feet of any U.S. Government facility, at any time, during performance of work under this contract. The COR or project inspector will identify to the contractor the designated smoking area(s) for the contractor’s employees prior to starting any work. The contractor shall ensure that all contractor employees are aware of the designated smoking area(s) and shall ensure that all contractor employees use the designated smoking area.

Any contractor employee found smoking in any U.S. Government facility, at any time, will be removed from the work site by the COR or project inspector. The COR or project inspector will notify the KO of the removal of any contractor employee for violation of the “no smoking” policy.

14. BURNING/WELDING OPERATIONS: The contractor shall be responsible to obtain a burning/ welding permit prior to any burning or welding operation. The contractor shall notify the COR or project inspector not less than five (5) work days prior to such operations and shall return the permit to the U.S. Government inspector at the completion of the permit period.

Contractor shall provide fire watch during all open flame/ welding work.

15. VERIFICATION OF ACTUALITIES: (FAR Clause 52.236-2 Site Visit)

16. HOUSEKEEPING: (FAR Clause 52.236-12 Cleaning Up / 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities and Improvement & 52.236-13 Accident Prevention)

17. BASE ACCESS: The contractor shall be required to obtain base access to Kunsan Air Base to perform the requirements of this contract. The contractor shall be responsible to submit a base access request letter no later than five (5) calendar days prior to start this contract. It shall be the responsibility of the contractor to prepare the necessary base access paperwork IAW USFKregulation 190-7, Installation Access Control, and submit it to the COR or project inspector. USFK regulation 190-7 is available on open source internet (http://8tharmy.korea.army.mil/g1_AG/Programs_Policy/PublicationsRecords/Regu lations/USFK/USFK%20Reg%20190-7%20Installation%20Access%20Control2013.pdf

18. ANTITERRORISM (AT) and OPERATIONS SECURITY (OPSEC):

18.1 AT Level I training: This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area. All contractor employees, to include subcontractor employees, requiring access to USAF installations, facilities and controlled access areas shall complete AT Level I awareness training within 14 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer. AT level I awareness training is available at the following website: http://jko.jten.mil

18.2 Access and general protection/security policy and procedures: This standard language is for contractor employees with an area of performance within USAF controlled installation, facility, or area. Contractor and all associated sub-contractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

18.3 For contractors that do not require CAC, but require access to a DoD facility or installation: Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

18.4 iWATCH Training: This standard language is for contractor employees with an area of performance within an USAF controlled installation, facility or area. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 14 calendar days of contract award and within 14 calendar days of new employees commencing performance with the results reported to the COR NLT 30 calendar days after contract award.

18.5 Threat Awareness Reporting Program: For all contractors with security clearances.

Per AR 381-12 Threat Awareness and Reporting Program (TARP), contractor employees must receive annual TARP training by a CI agent or other trainer as specified in 2-4b.

19. REPAIR WORK: It shall be the contractor’s responsibility to repair all areas of patch work to match existing areas. This work shall include all areas inside of the facility as well as any other areas that the contractor may have damaged during the performance of work under the terms of this contract.

20. CONTRACTOR’S RESPONSIBILITIES: It shall be the responsibility of the contractor to have full control of all contractor personnel during the performance of work under the terms of the contract. The contractor shall be responsible to ensure that no contractor personnel receive any instructions for addition/deletion of work from any Government personnel including the COR or project inspector. Any instructions for additional work shall only be issued by the KO.

The contractor shall be responsible for any cost incurred for any additional work, which is not identified in the contract documents to include the specifications or on the contract drawings.

The contractor shall be responsible to inform the COR or project inspector of any request form any Government personnel for additional work. The contractor shall provide the COR or project inspector with name and office of the individual requesting the additional work and the type of additional work being requested. The COR or project inspector will take the necessary actions to inform the KO to prevent such situation.

21. PROGRESS SCHEDULE: The contractor shall prepare and submit the progress schedule as specified in the Standard Technical Specifications for O&MA Projects, Korea.

22. DRAWING SUBMITTALS: All drawings shall be submitted prior to the start of any work. Any additional drawings (As-built, field changes, etc.) shall be submitted to the COR or project inspector no later than ten (45) calendar days prior to contract completion for delivery orders with period of performances (PoP) less than 180 days and (60) days prior to contract completion delivery orders with PoP’s greater than 180 days. If submittal cannot be submitted within the timeframe the contractor must notify the COR or project inspector in writing why he/she cannot meet the requirement.

23. UTILITY OUTAGES/ROAD CLOSURES: The Contractor shall be the responsibility of the contractor to request, in writing, to the COR or project inspector, a minimum of thirty (30) calendar days in advance for any water outage, electrical outage, or road closure. The contractor shall provide a requested date and estimated time for the water outage, electrical outage, or road closure. The COR or project inspector will be responsible for determining the impact of the water outage, electrical outage, or road closure. The COR or project inspector will also be responsible for the processing of the contractor’s request for a water outage, electrical outage, or road closure. The contractor shall have written approval from the COR or project inspector before any water outage, electrical outage, or road closure. (CDRL 5)

24. ASBESTOS CONTAINING MATERIALS: No asbestos containing materials (ACM) shall be used under this contract. ACM is any material containing more than 1% asbestos by weight, either along or mixed with other fibrous on non-fibrous materials.

25. OZONE DEPLETING SUBSTANCES: No Class I ODS shall be used in the performance of this contract, nor be provided as a part of the equipment. This prohibition shall prevail over any other provision, specification, drawings or referenced documents.

26. MATERIAL SAFETY DATA SHEETS (MSDS): It shall be the responsibility of the contractor to furnish Material Safety Data Sheets (MSDS), in English and Korean, for all hazardous material(s) used under the terms and conditions of this contract. The type of materials that the contractor shall submit MSDSs for include, but is not limited to, paint, primer, lacquer, stain, joint compound, caulking, exterior insulation systems, emergency exit lights, cleaning fluids, oil, etc., and any other type of product deemed necessary by the Contracting Officer’s Representative (COR) or Base Civil Engineer Officer , required by U.S. Government Environment Laws and Regulations, or Korean Environmental Laws and Regulations.

a. SUBMITTAL REQUIRMENTS:

(1) The contractor shall be responsible to process these Material Safety Data Sheets (MSDS) on an AF Form 3000, Material Approval Submittal. The AF Form 3000 shall be submitted to the COR or project inspector no later than fifteen (15) calendar days after the Notice to Proceed (NTP) is issued by the Contracting Officer (KO). The contractor shall submit four (4) copies of the AF Form 3000 with carbon paper. The contractor shall submit the AF Form 3000 to the COR or project inspector for review prior to submitting the AF Form 3000 with carbon paper. It will be the responsibility of the COR or project inspector to verify the AF Form 3000 to ensure that all hazardous materials are submitted in the proper format. (CDRL 6)

(2) It shall be the responsibility of the contractor to list each type of hazardous material on the AF Form 3000. The contractor shall also be responsible to list the quantity, unit of measure (i.e.: each, liter, gallon, etc.), and size of container(s). It will be the responsibility of the COR or project inspector to verify these quantities and containers prior to initialing off on the AF Form 3000.

(3) After verification of all hazardous materials by the COR or project inspector and the contractor, the COR or project inspector will then be responsible to process this AF Form 3000. After receiving approval for all hazardous materials, it will be the responsibility of the COR or project inspector to provide the KO and contractor with a copy of the signed AF Form 3000 for the official files.

(4) After receiving approval of all hazardous materials required under the terms and conditions of this contract, the contractor shall be responsible to process these Material Safety Data Sheets (MSDS) through the HazMart Pharmacy located in building #823, military telephone DSN 782-5247, commercial telephone (063) 470-5247. The HazMart Pharmacy will be responsible to issue a bar code for each hazardous material that shall be affixed to each container by the contractor. The contractor shall be responsible to post an approved copy of the AF Form 3000 at the worksite storage area as well as keep a signed copy by AF Form 3000 in the contractor’s field office.

(5) It shall be the responsibility of the contractor to provide the COR with a new AF Form 3000 for any additional hazardous materials brought onto Kunsan Air Base throughout the term of the contract. This shall include any new materials as well as any additional quantities over and above the originally quantities.

(a) HAZARDOUS MATERIALS STORAGE: The contractor shall be responsible to store all hazardous materials in an approved storage container or storage area. This storage container may be either a metal or wood locker which is capable of being secured when not in use as well as at the end of each workday. The contractor shall be responsible to provide an approved storage location for large quantities of hazardous materials which can also be secured when not in use as well as at the end of each workday. The contractor shall be responsible to keep an approved AF Form 3000 on the inside of the door to the storage container and also keep a copy of the approved AF Form 3000 posted at the storage area

(b) DISPOSAL REQUIREMENTS FOR HAZARDOUS MATERIALS: The contractor shall be the responsibility of the contractor to remove and dispose of any remaining hazardous materials upon completion of the contract to include the removal of hazardous materials from the worksite as well as the contractor’s field office area. The contractor shall be responsible to dispose of these remaining hazardous materials, off the installation, at the contractor’s own expense, in strict accordance with existing Korean Environmental Laws and Regulations. The contractor shall be responsible to notify the COR or project inspector prior to disposing of any hazardous materials off the installation to ensure that all hazardous materials are properly handled and disposed of correctly. After use of final disposal of all hazardous materials, it will be the responsibility of the COR or project inspector to notify the HazMart Pharmacy of the final disposition of the hazardous material in order for the HazMart Pharmacy to update the AF-EMIS database.

(c) HAZARDOUS MATERIAL SPILLS: In the event that the contractor accidentally spills any hazardous materials at the worksite, the contractor shall be the responsibility of the contractor to immediately notify 8 CES/CEAN, Environmental section located in Building #705, military telephone DSN 782-6239/6240, commercial telephone (063) 470-2312/6337. The contractor shall be responsible to identify the location of the spilled material, the quantity of spilled material, and the type of spilled material. The contractor shall also be responsible to notify the COR or project inspector. The contractor shall not under any conditions, remove and dispose of any spilled hazardous material(s) without prior approval of 8 CES/CEAN.

27. DISPOSAL REQUIRMENTS: The contractor shall be responsible to designate, in writing, to the COR or project inspector the exact location(s) for the disposal of the steel revetment, soil, and concrete. The contractor shall also be responsible to provide the COR or project inspector with a copy of the license for the disposal location(s) issued by the Korean Government. The contractor shall be responsible to accompany the COR or project inspector on a site visit of the disposal location(s) prior to the removal and disposal of any steel revetment, soil, or concrete.

The COR or project inspector will be responsible to complete a DD Form 1901, Plant Visit Request/Report for each of the disposal locations. The COR or project inspector will be responsible to provide the KO with a copy of the DD Form 1901 identifying any discrepancies which may not conform to the contract requirements. It will be the responsibility of the KO to review this DD Form 1901 and to determine any corrective actions that the contractor shall be responsible to comply with. The contractor shall also be responsible to notify the COR immediately in the event that the disposal location(s) are no longer licensed or capable of disposing of the steel revetment, soil, or concrete in accordance with AFI 32-7042 (Waste Management).

28. ESCORT PRIVILEGE: Personnel of the Contractor or any representative of the contractor entering Kunsan AB shall abide by all security regulations imposed by Installation Commander at all times and shall be subject to security checks. Contractor personnel and property shall be subject to search and seizure upon entering the confines of the installation, while on, and upon leaving the confines of Kunsan AB.

a. Escort Privileges: The Contractor shall be responsible to obtain escorting privileges on base passes for the Contract Manager (CM), Quality Control (QC) Manager, Safety Manager with a limit of three (3) persons and one (1) vehicle pass per base pass. It is the Contractor’s responsibility to ensure that the escorting official has full control over all escorted individuals at all times. Any individual found on the installations unescorted will be removed from the installation and the escort official’s escorting privileges will be immediately withdrawn. Any individual removed from these installations will not be authorized further access to these installations.

b. Return Post Passes: On the contract completion date, the contractor shall turn in all passes that were issued for this contract to the sponsor and final payment will not be processed until such items are returned.

29. Contractor personnel: (FAR Clause 52.236-6 Superintendence by the Contractor

1A-7. ENVIRONMENTAL PROTECTION SPECIFICATION

PART 1 GENERAL

1.1 ENVIRONMENTAL MANAGEMENT SYSTEM

a. Contractor shall ensure all workers are familiar with the goals of the Kunsan AB

Environmental Management System (EMS) as stated in the installation’s Environmental Policy Statement and have an awareness of EMS.

b. The Environmental Policy Statement commits the installation 1) to compliance with the requirements of USFK regulation 201-1, Korea Environmental Governing Standards (KEGS) and other applicable legal and policy requirements, 2) for continued environmental improvement and pollution prevention, 3) to reduce risk from environmental impacts of base activities, and 4) understanding that everyone on the installation is responsible for complying with the environmental regulations.

c. The Contractor's work under this contract shall conform with all operational controls…