Performance Work Statement

For

Office Trailer Electrical Service and Supplies

W81EWF91613842

Product/Service Description:

The United States Army Corps of Engineers (USACE) Field Research Facility (FRF) in Duck, NC request bids for electrical service and supplies to power 5 rental office trailers and 1 rental toilet trailer with reserve capability to supply power to an additional 5 office trailers on their property, located at 1261 Duck Rd, Duck, NC 27949. The electrical installation shall be performed by a licensed electrician and coordinated with the local utility company. All electrical equipment, conductors, cabinets, disconnects, and panels, shall conform to all local codes, ordinances, national electric code, and utility company requirements. All exterior equipment and devices shall be weatherproof and rain tight.

Requirements:

1. Install a current transformer (CT) cabinet (provided by FRF) on a pressure treated placard also provided by the FRF at 1261 Duck Rd, Duck, NC 27949.

2. Coordinate with the local utility company which will supply 1000 amp service to CT cabinet.

3. Provide and install five 200 amp main panel/disconnects on 5 pressure treated placards

(provided by the FRF).

4. Provide and install all conductors and required accessories to bring power from the CT cabinet to the 200 amp panels. The conductors shall be buried in ground. The approximate lengths of conductors will be 20 ft. to 100 ft. in length (see attached site plan).

5. Provide a 20 amp GFI receptacle on the main CT cabinet placard or on one of the 200 amp panel/disconnect placards.

6. Provide and install conductors from the five 200 amp panel/disconnects to the five office trailers and the one toilet trailer. The conductors shall be buried. The trailers require 60 to 100 amps.

7. Provide all electrical circuits and equipment with grounding to codes.

Option 1/ Year 2

1. Provide and install conductors from the five 200 amp panel/disconnects to the five additional office trailers and the one toilet trailer. The conductors shall be buried. The trailers require 60 to 100 amps.

2. Provide all electrical circuits and equipment with grounding to codes.

3. Disconnect 10 office trailers and one toilet trailer at end of use.

Option 2/Year 2

1. Perform work described in Option 1

2. Remove buried conductors that run to trailers

3. Remove the five 200 amp main panel/disconnects and GFI receptacle.

Period of Performance:

Based upon trailer delivery and coordination with Dominion Power, work is to be completed within one week or trailers being delivered and Dominion Power installing power at CT cabinet (whichever is later).

Installation Location at 1261 Duck Rd. Duck, NC 27949

Area of proposed work

CT cabinet

200 Amp panels