W58RGZ18R0158.pdf
PDF 160 KB Posted
- Attached to
- PUMP AXIAL PISTON
- Solicitation number
- W58RGZ18R0158
About this file
Solicitation W58RGZ-18--R-0158
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W58RGZ18R0158-0005.pdf | ||
| W58RGZ18R0158_AMEND_0004.pdf | ||
| W58RGZ18R0158_AMEND_0003.pdf | ||
| W58RGZ18R0158-0002.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER AND AWARD 1. This Contract Is A Rated Order Under
DPAS (15 CFR 700)
Rating Page of Pages
2. Contract Number 3. Solicitation Number 4. Type of Solicitation 5. Date Issued 6. Requisition/Purchase Number Sealed Bid (IFB)
Negotiated (RFP)
7. Issued By Code 8. Address Offer To (If Other Than Item 7)
NOTE: In sealed bid solicitations ‘offer’ and ‘offeror’ mean ‘bid’ and ‘bidder’.
SOLICITATION
9. Sealed offers in original and copies for furnishing the supplies or services in the Schedule will be received at the place specified in item 8, or if handcarried, in the depository located in until (hour) local time (Date).
Caution - Late Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and conditions contained in this solicitation.
10. For Information A. Name B. Telephone (No Collect Calls) C. E-mail Address
Call: Area Code Number Ext.
11. Table Of Contents
(X) Sec. Description Page(s) (X) Sec. Description Page(s)
Part I - The Schedule Part II - Contract Clauses A Solicitation/Contract Form I Contract Clauses
B Supplies or Services and Prices/Costs Part III - List Of Documents, Exhibits, And Other Attach.
C Description/Specs./Work Statement J List of Attachments D Packaging and Marking Part IV - Representations And Instructions E Inspection and Acceptance K Representations, Certifications, and F Deliveries or Performance Other Statements of Offerors G Contract Administration Data L Instrs., Conds., and Notices to Offerors H Special Contract Requirements M Evaluation Factors for Award
OFFER (Must be fully completed by offeror) NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.
12. In compliance with the above, the undersigned agrees, if this offer is accepted within _____ calendar days (60 calendar days unless a different period is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.
13. Discount For Prompt Payment 10 Calendar Days (%) 20 Calendar Days (%) 30 Calendar Days (%) Calendar Days (%) (See Section I, Clause No. 52.232-8)
14. Acknowledgment of Amendments (The offeror acknowledges Amendment No. Date Amendment No. Date receipt of amendments to the SOLICITATION for offerors and related documents numbered and dated):
15A. Name and Code Facility 16. Name and Title of Person Authorized to Sign Offer Address of (Type or Print) Offeror
15B. Telephone Number 15C. Check if Remittance Address is 17. Signature 18. Offer Date Area Code Number Ext. Different From Above – Enter such
Address In Schedule
AWARD (To be completed by Government)
19. Accepted As To Items Numbered 20. Amount 21. Accounting And Appropriation
22. Authority For Using Other Than Full And Open Competition: 23. Submit Invoices To Address Shown In Item
10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)
24. Administered By (If other than Item 7) Code 25. Payment Will Be Made By Code
26. Name of Contracting Officer (Type or Print) 27. United States Of America 28. Award Date
(Signature of Contracting Officer)
IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.
AUTHORIZED FOR LOCAL REPRODUCTION Standard Form 33 (Rev. 9-97) Previous edition is unusable Prescribed By GSA-FAR (48 CFR) 53.214(c)
W58RGZ-18-R-0158
X
2018MAR27
2018APR2705:00pm
DOA1
2018MAR27 SEE SCHEDULE
W58RGZ
ARMY CONTRACTING COMMAND-REDSTONE
REDSTONE ARSENAL AL 35898-5280
MELANIE H. EARLEY
(256)876-2047
CCAM-ALL
MELANIE.D.HELSEREARLEY.CIV@MAIL.MIL
X 1 25
1 50
X 1
X 4 X 12
X 14 X 15 X 19
X 28
X 31
X 34
X 40
X 41
X 47
X 49
CONTINUATION SHEET
Reference No. of Document Being Continued Page of
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SECTION A - SUPPLEMENTAL INFORMATION
Buyer Name: MELANIE H. EARLEY
Buyer Office Symbol/Telephone Number: CCAM-ALL/(256)876-2047
Type of Contract 1: Firm Fixed Price
Kind of Contract: Maintenance Contracts
*** End of Narrative A0000 ***
1. Reserved ________
2. This is a five (5) year Firm-Fixed-Price (FFP) Indefinite Delivery Indefinite Quantity (IDIQ) contract pursuant to FAR 52.216-22.
The minimum quantity applicable to this solicitation is 150. The estimated maximum quantity is 630.
3.There is an adequate Depot Maintenance Work Requirement for the repair of PUMP AXIAL PISTON. Depot Maintenance Work Requirement DMWR-1-
4320-275 and Maintenance Engineering Orders (MEOs): C6930, E1836, E1837, E1838, W1834, E1835, E1937, C6715D, E2080, C6041, E1488, C6121, C7026, C6583G of the Overhaul/Repair of the Pump Axial Piston.
4. When Applicable, the contractor is reminded to complete the Foreign Military Sales (FMS) Customer DA FORM 2410 (Component Removal and Repair Overhaul Record), submitted with the item for repair, in accordance with DA Pamphlet 738-751 and TB-1500-341-01. Upon completion of repair, if authorized, the contractor is reminded to fill out U.S. Army DA Form 2410 and return it to the FMS customer with the repaired asset(s), along with the FMS customer version of the DA Form 2410.
5. The FMS Customer and geographical location(s) for deliveries, inspection and acceptance points are unknown at this time.
6. Subject to the availability of funds, any quantities ordered will be priced at the unit price established for the ordering period in which they are ordered. Funds shall be obligated by issuance of Delivery Orders and not by the contract itself.
7. The minimum quantity set forth herein shall be obligated on Delivery Order (DO) 0001, to be issued simultaneously with the award of the contract. Any additional quantities ordered will be priced at the firm fixed price in effect during the ordering period in which they are ordered.
8. The Government will not be required to obtain the contractor's signature prior to the issuance of an order.
9. The Government intends to award only one basic Fixed Price IDIQ contract as a result of this solicitation.
10. The Government has segregated the estimated quantities into five ordering periods. However, this does not preclude exercising the
Government's right under FAR 52.216-19 by ordering the maximum quantity specified in FAR 52.216-19(b)(1) at any time during the five year ordering period.
Ordering Period 1 will be from date of contract award through 365 days after contract award (DACA).
Ordering Period 2 will be from 366 DACA through 730 DACA.
Ordering Period 3 will be from 731 DACA through 1,095 DACA.
Ordering Period 4 will be from 1,096 DACA through 1,460 DACA.
Ordering Period 5 will be from 1,461 DACA through 1,825 DACA.
11. Please insert your firm fixed unit prices for the 1st, 2nd, 3rd, 4th, and 5th ordering periods in the spaces provided under each
CLIN/SubCLIN.
12. For purposes of Block 12 on page 1, the offer acceptance period is 120 days from the date for receipt of offers specified in Block
9, unless a different period is inserted by the offeror in the blank in Block 12.
13. No Government Furnished Materials (GFM), other than the reparable assets and reusable containers, will be provided.
14. Offers shall be submitted in accordance with FAR Clause 52.215-1. Facsimile and electronic submissions are not authorized.
Proposals shall be mailed to:
Army Contracting Command - Redstone
ATTN: Melanie Helser Earley, CCAM-ALA
Bldg. 5303, 2nd Floor
Redstone Arsenal, AL 35898-5280
15. If any offeror chooses to hand carry their proposal, the offeror must reach the appointed location (identified as building 5300, 2 50
REPRINT
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
5300 Martin Road, Redstone Arsenal, AL 35898, Foyer) by the date and time as stated in block 9 on page 1 of the solicitation. Please be advised that Redstone Arsenal is a restricted facility and should an offeror choose to hand carry a proposal, a minimum of 72 hours notice to the Contracting Officer is required in order to ensure access by the closing date/time of the solicitation. Any unauthorized entity must be identified as having a need, as validated by the Contracting Officer, in order to gain access to the post. The contracting office must notify the Gate personnel, who monitor post access, a minimum of 48 hours prior to an entity gaining entrance to the restricted post. Please note that any proposals delivered late as a result of failure to comply with the procedure will not be accepted, IAW FAR 52.215-1 entitled "Instructions to Offerors-Competitive Acquisition".
16.Reserved
17.Reserved
18.The contractor shall provide with their proposal a response that addresses the contractor's plan to meet all government special tooling and test equipment requirements with either:
1. Physical possession of the required tools, 2. Confirmed requisitions for the required tools, 3. Confirmed arrangements for subcontracting the processes requiring the special tools, or 4. Specific plans describing their technical approach to develop equivalent tools.
Critical Tools and Test and Inspection Equipment
Requiring AED Approval for Substitutes:Test equipment or equivalent used for testing of pump. (Chapter 9 of DMWR 1-4320-275)
19. The Contractor may be requested to submit additional cost or pricing data if only one offer is received IAW DFARS Clause 252.215-
7008, entitled "Only One Offer."
20. The contractor is instructed to put the following words in the remarks column of the DD 250/WAWF: "Repair and Return Process D6".
21. Access to DLA EMALL is NOT authorized. ___
22. The National Defense Authorization Act for Fiscal Year 1993, Public Law 102-484, Section 326, prohibits use of Other Direct Cost
(ODC) in Department of Defense contracts awarded on or after 1 June 1993, unless appropriate authority is granted.
23. The following websites are provided for the purpose of obtaining/reviewing various Army publications and technical manuals/bulletins:
A. - Technical Manuals and Bulletins
B. - DA Pamphlets and Army Regulations
24. COMPLETE THE FOLLOWING CONTRACTOR POINT OF CONTACT INFORMATION:
NAME: _________________________________________
TELEPHONE NUMBER: _____________________________
FAX NUMBER: ___________________________________
E-MAIL ADDRESS: _______________________________
*** END OF NARRATIVE A0001 ***
3 50
PIIN/SIIN
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS
0001 PVA
0001AA PRODUCT VERIFICATION AUDIT (PVA) $ ________________________________ __________________
SERVICE REQUESTED: PVA
CLIN CONTRACT TYPE:
Firm Fixed Price
THIS IS A FIRM FIXED PRICE CLIN.
This CLIN represents the Product Verification
Audit (PVA) for the Pump Axial Piston, NSN: 4320-
01-158-0893
Offeror is required to fill in a proposed firm fixed unit price for the PVA:
$__________(FFP)
The PVA shall be in accordance with Narrative in
Section E, "Product Verification Audit (PVA)
Statement of Work".
PVA shall be conducted within 90 days after receipt of reparables. The Contractor shall prepare 3 units for the PVA. The Contractor is required to notify the Government Quality Office for scheduling of the PVA by email to the following address:
QS-Contracts@amrdec.army.mil
With copy emailed to the Contract Specialist at:
candice.d.burwell.civ@mail.mil
The Contractor will prepare and forward, through the cognizant Government Quality Element, the
Finalized Audit Reports within 10 working days after completion of the PVA to both email addresses above.
NOTE: A copy of the cover letter for the report shall be forwarded to the Contract Specialist at:
U.S. Army Contracting Command - Redstone
Attn: Candice Burwell, CCAM-ALM
Bldg. 5303, 2nd Floor
Redstone Arsenal, AL 35898-5280
Failure to pass the PVA may lead to Termination________________________________________________ for Default of the contract.____________________________
Payment Instructions:_____________________
The Contractor will go into Wide Area Work Flow
(WAWF) to receive payment for the PVA. The
Contractor shall use DODAAC W58H0Z when
4 50
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
submitting the PVA invoice in WAWF.
(End of narrative C001)
Inspection and Acceptance _________________________
INSPECTION: Destination ACCEPTANCE: Destination
Deliveries or Performance _________________________
0002 PUMP AXIAL PISTON
NSN: 4320-01-158-0893
Mfr CAGE: 8V613
Mfr Part Number: 7-311810022-3
0002AA OVERHAUL/REPAIR PUMP AXIAL PISTON (U.S.) $ $ ________________________________________ ______________ __________________
COMMODITY NAME: PUMP AXIAL PISTON
CLIN CONTRACT TYPE:
Firm Fixed Price
CLIN 0002AA is for the overhaul of the AH-64
Pump Axial Piston for US Army requirements.
INPUT NSN:4320-01-158-0893
INPUT PART NUMBER:7-311810022-3
OUTPUT NSN:4320-01-158-0893
OUTPUT PART NUMBER:7-311810022-3
Offeror is required to fill in proposed firm-fixed-unit prices for ordering periods 1 through 5:
ORDERING PERIOD 1 - U/P $_________ (FFP) MIN QTY 150
EA
ORDERING PERIOD 2 - U/P $_________ (FFP) EST QTY 100
EA
ORDERING PERIOD 3 - U/P $_________ (FFP) EST QTY 100
EA
ORDERING PERIOD 4 - U/P $_________ (FFP) EST QTY 100
EA
ORDERING PERIOD 5 - U/P $_________ (FFP) EST
QTY 75 EA
This Firm Fixed Price (FFP) CLIN includes all
5 50
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
labor charges, mandatory and non-mandatory replacement parts and material, preservation, packaging, packing, marking, and data items necessary to return the unit to a serviceable condition as stated in section C entitled
Statement of Work/Specifications - Government
Specifications.
THIS IS A FIRM-FIXED-PRICE CLIN.
(End of narrative C001)
Packaging and Marking _____________________
PACKAGING/PACKING/SPECIFICATIONS:
SEE PACKAGING REQUIREMENT, SECTION J ATTACH 001
UNIT PACK: 001 INTERMEDIATE PACK: 000
LEVEL PRESERVATION: Military
LEVEL PACKING: A
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
Deliveries or Performance _________________________
FOB POINT: Origin
0003 PUMP AXIAL PISTON
NSN: 4320-01-158-0893
Mfr CAGE: 8V613
Mfr Part Number: 7-311810022-3
0003AA OVERHAUL/ REPAIR PUMP AXIAL PISTON(FMS) $ $ _______________________________________ ______________ __________________
COMMODITY NAME: PUMP AXIAL PISTON
CLIN CONTRACT TYPE:
Firm Fixed Price
CLIN 0003AA is for the overhaul/repair of the AH-
64 Pump Axial Piston for FMS requirements.
INPUT NSN:
4320-01-158-0893
INPUT PART NUMBER:
7-311810022-3
OUTPUT NSN: 4320-01-158-0893
OUTPUT PART NUMBER:
7-311810022-3
6 50
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
This CLIN will be used only if an FMS customer requires this item. If no FMS customers are identified, the United States Army requirer may utilize the FMS quantity. The estimated quantities are listed below. The FMS customer and geographical locations for deliveries, inspection and acceptance points are unknown at this time.
FMS quantities cannot exceed 105 each.
Offeror is required to fill in proposed firm-fixed-unit prices for ordering periods 1 through
5:
ORDERING PERIOD 1 - U/P $_________ (FFP) EST QTY
30 EA
ORDERING PERIOD 2 - U/P $_________ (FFP) EST QTY
20 EA
ORDERING PERIOD 3 - U/P $_________ (FFP) EST QTY
20 EA
ORDERING PERIOD 4 - U/P $_________ (FFP) EST QTY
20 EA
ORDERING PERIOD 5 - U/P $_________ (FFP) EST QTY
15 EA
INDIVIDUAL DELIVERY ORDERS WILL BE ISSUED FOR
THIS CLIN.
This Firm Fixed Price (FFP) CLIN includes all mandatory and non-mandatory parts, labor charges, preservation, packaging, packing, marking, and data items necessary to return the unit, to a serviceable condition, as stated in Section C, Statement of Work.
(End of narrative C001)
Packaging and Marking _____________________
PACKAGING/PACKING/SPECIFICATIONS:
SEE PACKAGING INSTRUCTIONS, SECTION J ATTCH 001
UNIT PACK: 001 INTERMEDIATE PACK: 000
LEVEL PRESERVATION: Military
LEVEL PACKING: A
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
Deliveries or Performance _________________________
FOB POINT: Origin
0004 PUMP AXIAL PISTON
7 50
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
0004AA SCRAP $ __________________ __________________
SERVICE REQUESTED: PUMP AXIAL PISTON
CLIN CONTRACT TYPE:
Firm Fixed Price
THE GOVERNMENT'S ESTIMATED QUANTITY PER
ORDERING PERIOD IS 10 EACH FOR PROPOSAL
EVALUATION PURPOSES ONLY.
Offeror is required to fill in proposed firm-fixed-unit prices for ordering periods 1 through 5:
ORDERING PERIOD 1 - $_________ (FFP) EST QTY 10 EA
ORDERING PERIOD 2 - $_________ (FFP) EST QTY 10 EA
ORDERING PERIOD 3 - $_________ (FFP) EST QTY 10 EA
ORDERING PERIOD 4 - $_________ (FFP) EST QTY 10 EA
ORDERING PERIOD 5 - $_________ (FFP) EST QTY
10 EA
Scrap assets from CLINs 0002AA and 0003AA shall be in accordance with Section C clause entitled
Statement of Work/Specifications - Government
Specifications.
Units authorized to be scrapped in accordance with Section C shall be reflected as an increase in CLIN 0004AA with a corresponding decrease in quantity and funds in CLINs 0002AA and 0003AA.
In the event the Procuring Contracting Officer
(PCO) determines that certain items should be scrapped, the Contractor shall scrap such items at the fixed-unit price in Section B hereof and make disposition in accordance with the
Contractor's approved Government property procedures.
The Government may, at its discretion, replace any items scrapped by input of additional assets and said scrap quantities will not count as part of the total maximum quantity.
Scrap requires authorization by the PCO via formal modification. In no event shall the
Contractor scrap an item prior to receiving a contractual modification for a unit.
THIS IS A FIRM-FIXED-PRICE CLIN.
(End of narrative C001)
8 50
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
Deliveries or Performance _________________________
0005 PUMP AXIAL PISTON
0005AA CONTAINERS $ __________________ __________________
SERVICE REQUESTED: PUMP AXIAL PISTON
CLIN CONTRACT TYPE:
Firm Fixed Price
SERVICE REQUESTED: CONTRACTOR FURNISH CONTAINERS
CLIN CONTRACT TYPE:
Firm Fixed Price
SHIPPING CONTAINERS
ORDERING PERIOD 1 U/P ______(FFP) 10 EA, EST QTY
ORDERING PERIOD 2 U/P ______(FFP) 10 EA, EST QTY
ORDERING PERIOD 3 U/P ______(FFP) 10 EA, EST QTY
ORDERING PERIOD 4 U/P ______(FFP) 10 EA, EST QTY
ORDERING PERIOD 5 U/P ______(FFP) 10 EA, EST QTY
SUPPLEMENTAL INFORMATION: V 8110-00-254-5708 MS24347-
5;CAP CONNECTOR.
THE CONTRACTOR SHALL PROVIDE CONTAINERS, IN
ACCORDANCE WITH ATTACHMENT 0001, PACKAGING
REQUIREMENT INSTRUCTIONS AND SECTION C, ENTITLED
'STATEMENT OF WORK/SPECIFICATIONS GOVERNMENT
SPECIFICATIONS' AND 'REUSABLE CONTAINERS'.
THE GOVERNMENT CANNOT DETERMINE, AT THE TIME OF
CONTRACT AWARD, HOW MANY OF THE ASSETS TO BE
OVERHAULED WILL BE RECEIVED BY THE CONTRACTOR IN
UNSERVICEABLE CONTAINERS OR RECEIVED WITHOUT
CONTAINERS. IF ASSETS ARE RECEIVED IN UNSERVICEABLE
CONTAINERS OR WITHOUT CONTAINERS, THE CONTRACTOR, IAW
SECTION C, 'STATEMENT OF WORK', SHALL SUBMIT A REPORT
OF DISCREPANCY (ROD), SF FORM 364, THROUGH THEIR
GOVERNMENT QAR FOR VERIFICATION WITHIN 7 WORKING DAYS
TO THE ADDRESS SHOWN ON DATA ITEM A001. PRIOR
APPROVAL OF THE PCO IS REQUIRED TO PURCHASE NEW
CONTAINERS.
(End of narrative C001)
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
9 50
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
Deliveries or Performance _________________________
0006 CONTRACT DATA REQUIREMENTS LIST (CDRLS) _______________________________________
This CLIN is Not Separately Priced (NSP).
Pricing for data shall be included in the unit price of CLINs 0002AA and 0003AA.
The Contractor shall provide data items A001-A003 in accordance with the Contract Data Requirements List, see Exhibits A-E.
(End of narrative A001)
A001 (TAMMS-A) $ ** NSP ** _________ __________________
SERVICE REQUESTED: CDRL A001
CLIN CONTRACT TYPE:
Firm Fixed Price
SERVICE REQUESTED: CDRL A001
DATA ACQUISITION DOCUMENT NUMBER:DI-SESS-81758A
Submission of the Report of Shipping and Packaging
Discrepancy (ROD) shall occur within 10 days of discovery of the discrepancy.
See Exhibit A of this solicitation/contract for
ROD Guidance.
(End of narrative C001)
Deliveries or Performance _________________________
A003 QUALITY DEFICIENCY REPORT $ ** NSP ** _________________________ __________________
SERVICE REQUESTED: CDRL A003
CLIN CONTRACT TYPE:
Firm Fixed Price
DATA ACQUISITION DOCUMENT NUMBER: DI-QCIC-80736
10 50
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
No report is necessary unless there is a deficiency.
Contractor shall submit NO LATER THAN 10 days after discovery of deficiency.
(End of narrative C001)
Deliveries or Performance _________________________
A004 CONTRACT DEPOT MAINTENANCE (CDM) PRODUCTION REPORT $ ** NSP ** __________________________________________________ __________________
SERVICE REQUESTED: CDRL A004
CLIN CONTRACT TYPE:
Firm Fixed Price
SERVICE REQUESTED:
PUMP AXIAL PISTON
DATA ACQUISITION DOCUMENT NUMBER: DI-PSSS-81995
(End of narrative C001)
(End of narrative C002)
Deliveries or Performance _________________________
A005 REPORT OF SHIPPING (ITEM) AND PACKAGING _______________________________________
DISCREPANCY $ ** NSP ** ___________ __________________
SERVICE REQUESTED: CDRL A005
CLIN CONTRACT TYPE:
Firm Fixed Price
DATA ACQUISITION DOCUMENT NUMBER: DI-MGMT-80503
Submission of the Report of Shipping and Packaging
Discrepancy shall occur within 10 days of discovering the discrepancy.
(End of narrative C001)
Deliveries or Performance _________________________
11 50
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SECTION C - DESCRIPTION/SPECIFICATIONS/WORK STATEMENT
STATEMENT OF WORK/SPECIFICATIONS - GOVERNMENT SPECIFICATIONS
a. The Contractor, as an independent Contractor, and not as an agent or employee of the Government, shall furnish all services, facilities, labor, parts, materials, equipment, tools and data (other than Government Furnished Property, necessary to accomplish the inspection and overhaul/repair required to return the items as specified in Section B, to condition code A as defined by Army Regulation 725-50. The input/output configuration shall be as defined in Section B herein. Upon completion of the overhaul/repair, as applicable, the items shall be packaged as defined in Section D of this contract and shipped to the destination(s) specified in Section F of each delivery order.
b. Prior to commencement of overhaul/repair, the Contractor shall disassemble and inspect the item to the extent necessary to determine the complete cost to overhaul/repair. The Contractor shall continue the overhaul/repair process on all end items when the total cost to overhaul/repair does not exceed $5,158.77. The overhaul/repair prices shown in Section B for
CLINs 0002AA and 0003AA are firm fixed price. The Contractor will be required to complete the overhaul/repair at the Firm-
Fixed-Price (FFP) shown in the contract on all end items regardless of the damage as long as the total cost to overhaul/repair does not exceed $5,158.77. The Contractor will be required to provide other than certified cost and pricing data and a Report of Discrepancy (ROD) signed by the DCMA QAR to the Procuring Contracting Officer (PCO) to confirm that the total cost to overhaul/repair will exceed $5,158.77. This data shall include at minimum material cost (80% of material cost will be supported by current vendor quotes), labor hours, labor rates, overheads, G&A, and profit rate. More information to support the Contractor's price may be requested by the Government. In no event will any asset be scrapped prior to an approved modification by the PCO. No additional funding will be provided except for approved instances (via signed formal modification) related to missing parts. For missing parts, the Government may provide additional funding or provide the missing parts as GFM to complete the overhaul/repair of the end item. The Contractor shall submit a ROD to the contracting office, and resolution for missing parts will be provided via contract modification. The Contractor is not authorized to purchase missing parts unless and until a modification is processed and approved by the Contracting Office. The Government cannot guarantee the condition of the assets sent to the Contractor for overhaul/repair. Any estimates in the DMWR shall not be relied upon for bidding purposes.
c. In the event that the total price to overhaul/repair is determined (approved by PCO) to exceed $5,158.77, the
Contractor shall scrap such assets at the fixed unit price in Section B hereof and make disposition in accordance with (IAW) the Contractor's approved Government property procedures. Such scrapped items shall count toward the quantities ordered hereunder. The Government may, at its discretion, replace any scrapped items by input of additional assets, and said scrap quantities will not count as part of the total maximum quantity. Any other parts other than those determined to be scrapped must be overhauled at the firm fixed price in the awarded contract.
d. Overhaull/Repair shall be accomplished IAW Depot Maintenance Work Requirement (DMWR)
DMWR-1-4320-275. The applicable DMWR contains detailed proceducres regarding IUID requirements for this component. The procedures can be found in MEO's E1834, E1835, E1836, and E1837. Additional MEOs required for this competitie contract include
C4598, E1838 and E1937.
e. Critical Safety Item: N/A
f. Upon receipt of the reparables, containers shall be reviewed for serviceability. Containers shall be considered serviceable unless one or more of the following conditions exist: (1) containers are structurally damaged to include functional damage to the suspension system, cracks or holes to the container hull, hull deformity to the extent the container cannot be closed (or sealed where required), or dents that will interfere with the item envelope; (2) corrosion has progressed to the point where fit, function or the life of the container is affected. Items received without containers or containers determined to be unserviceable shall be processed IAW the Contractor's locally approved Government Property procedures.
Components received improperly packaged, damaged with corrosion/deterioration or those with shipping discrepancies shall be reported IAW DI-MGMT-80503, data item A005, Exhibit E.
g. Any Contractor paint facility which is used in the performance of this contract shall comply with the Environmental
Protection Agency and Occupational Safety and Health Administration standards for painting as implemented by TM 55-1500-345-
23, CH12, Painting and Marking of Army Aircraft.
h. Data and reports shall be submitted IAW the Contract Data Requirements List, DD Form 1423, Section J, Exhibits A-
E.Data shall be packaged, packed and marked as necessary to assure safe delivery to the addresses indicated on the DD Form(s)
1423. All RODs shall be approved by the QAR prior to sending to the Contracting Officer. All RODs sent to the Contracting
Officer without QAR concurrence will be returned to the Contractor without response.
i. Product Verification Audit (PVA): The Contractor shall conduct the PVA IAW CLIN 0001AA and Section E, Product
Verification Audit (PVA) Statement of Work, as specified in Section E of the Solicitation/Contract.
j. The Army Maintenance Management System - Aviation (TAMMS-A): The Contractor shall prepare TAMMS data IAW DI-SESS-
81758 and the TAMMS instructions attached to the solicitation/contract. The Contractor shall complete the forms and records as
12 50
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
specified in DA PAM 738-751, TB 1-1500-341-01, TM 1-1500-328-23.
k. Reserved.
l. The items the Contractor shall overhaul/repair are identified below:
Input NSN P/N
4320-01-158-0893 7-311810022-3
Output NSN P/N
4320-01-158-0893 7-311810022-3
m. The overhaul/repair planned quantity for 5 years is minimum 150, maximum 3300. Input will be 30 days after receipt of order (ARO). Output shall be as specified in the solicitation/contract schedule. Serviceable assets shall be returned to
W62G2T.
(1) 1st year qty 150 (4) 4th year qty 100
(2) 2nd year qty 100 (5) 5th year qty 75
(3) 3rd year qty 100
n. The Contractor shall provide the Contract Depot Maintenance (CDM) Production Report IAW DI-PSSS-81995, data item A004, Exhibit D.
o. Reserved.
p. Reserved.
q. The Government reserves the right to replace any items scrapped.
r. Reserved.
s. The contractor shall prepare the Quality Deficiency Report IAW DI-QCIC-80736, data item A003, Exhibit C.
t. Reserved.
u. Shipping Containers: NSN: 8145-00-301-2987, P/N 13414-017 shall be utilized. If containers are not reparable or if assets are not delivered in the approved containers, the containers shall be Contractor Furnished Materiel. Shipment: The method of shipment must use a procedure so that the package can be tracked in case the shipment is not received by AMCOM.
(End of Clause)
*** END OF NARRATIVE C0001 ***
13 50
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SECTION D - PACKAGING AND MARKING
BAR CODE MARKINGS
Bar Code Markings are required in accordance with the latest revision of MIL-STD-129 and ISO/IEC 16388 - Information Technology -
Automatic Identification and Data Capture Techniques - Bar Code Symbology Specification - Code 39.
*** END OF NARRATIVE D0001 ***
14 50
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SECTION E - INSPECTION AND ACCEPTANCE
This document incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at these addresses:
http://farsite.hill.af.mil/ or https://www.acquisition.gov/
If the clause requires additional or unique information, then that information is provided immediately after the clause title.
Regulatory Cite Title Date Regulatory Cite Title Date _______________ ______________________________________________________________________ ____________ _______________ ______________________________________________________________________ ____________
E-1 52.246-2 INSPECTION OF SUPPLIES--FIXED-PRICE AUG/1996
E-2 52.246-4 INSPECTION OF SERVICES--FIXED-PRICE AUG/1996
E-3 52.246-16 RESPONSIBILITY FOR SUPPLIES APR/1984
E-4 52.246-11 HIGHER-LEVEL CONTRACT QUALITY REQUIREMENT DEC/2014
(a) The contractor shall comply with the higher-level quality standard(s) listed below.
(b) The contractor shall include applicable requirements of the higher-level quality standard(s) listed in paragraph (a) of this clause and the requirement to flow down such standards, as applicable, to lower-tier subcontracts in--
(1) Any subcontract for critical and complex items (see 46.203(b) and (c)); or
(2) When the technical requirements of a subcontract require--
(i) Control of such things as design, work operations, in-process control, testing and inspection; or
(ii) Attention to such factors as organization, planning, work instructions, documentation control, and advanced metrology.
(End of clause)
E-5 PVA SOW
Purpose: The purpose of this PVA SOW is to provide guidance to the contractor in the preparation for and execution of the PVA. The primary concept of the PVA is to validate that the contractor's overhaul processes and procedures comply with contract technical requirements. The PVA candidate(s) are used to evaluate that the contractor processes and procedures are adequate to ensure component integrity.
(a) The Contractor shall perform overhaul and present for acceptance THREE units of Lot/Item 0001AA as specified in this contract.
This clause does not supersede instructions contained in depot overhaul work requirements, commercial overhaul manuals, or other applicable documents. It does not relieve the contractor from maintaining a quality system that will assure overhauled items conform to contractual requirements. Contractors may request to delay scheduled PVAs in frequency or waive PVA requirements of selected items in cases where accumulated objective evidence indicates that a consistent quality item is being delivered. The Command's actions will be based on the overall performance history, failure impact, supply impact, length of program, and nonscheduled PVAs accomplished by the
AMRDEC Engineering Directorate (ED). Like or similar items may be grouped for these purposes provided concurrence is obtained from
AMRDEC ED. The contractor may be directed by the Contracting Officer (CO) to increase or decrease the scope of a PVA pursuant to the
"Changes" clause of the contract.
(b) The Contractor shall:
(1) With the concurrence of the cognizant government quality element and AMCOM, schedule and perform PVA as required by the terms of the contract or as otherwise required.
(2) Notify AMCOM through the cognizant government quality assurance element, with information copy to the AMRDEC ED, ATTN: QS-
Contracts@amrdec.army.mil, of the date the PVA candidates will be available. Notification shall be provided at least 20 working days prior to the selected date if facilities are within the Continental United States. If facilities are outside the Continental United
States, notification shall be provided at least 95 working days prior to the selected date to allow sufficient time for travelers to gain theater clearance.
(3) Provide technical personnel, tooling, measuring and test equipment, work area, forms, and clerical assistance, as required, to perform the PVA. If test cell or other specialized equipment is required; notification of readiness for PVA shall include the availability of these.
(c) The initial PVA will be performed on one of the first three (3) items overhauled. The PVA candidate will be selected by the AMRDEC
PVA Team Chairman at random from the three (3) tendered for acceptance to the Government. For reoccurring audits, if any, the audit candidate will be selected by the PVA Team Chairman from all completed items currently available.
15 50
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
(d) The item selected for PVA will be inspected for adherence to preservation, packaging, packing, and marking requirements prior to removal from the shipping container. A visual inspection and functional test will be performed prior to disassembly.
(e) The PVA Team will review the shop travelers, production processes, procedures, tooling, and equipment used to overhaul the item being audited for adequacy and conformance to the contractual requirements. The PVA will include verification through objective evidence that all of the inspection, testing, measuring and diagnostic equipment used in the inspection/test of the PVA candidate are maintained in accordance with applicable calibration standards.
(f) Disassembly will be performed in an area accessible only to audit personnel. Normally, audit participation will be limited to specified production and quality assurance personnel of the contractor activity, the cognizant government Quality Assurance
Representative (QAR), and the AMRDEC PVA Team Chairman and team personnel.
(g) Visual inspection, dimensional checks (such as backlash, end clearance, running clearance, etc.) and nondestructive testing are accomplished during and after disassembly IAW applicable technical directives. Findings are recorded for comparison with historical data and conformance evaluation. A 100% inspection (or as set forth in relevant specifications) of all physical characteristics, to include but not limited to, any dimensions, certifications for materials, processes and/or procedures, as well as any other requirements which may be set forth by other applicable specifications, or in any procurement packages, technical drawings. Depot Maintenance Work
Requirements (DMWRs), Maintenance Engineering Orders (MEOs), and/or any other special/functional testing as set forth in this contract.
(h) Applicable accessories and components will be functionally tested and inspected to contractual/work specifications. The PVA team will review subcontractor certifications for testing and inspections. At the request of the PVA Team Chairman, processes (such as shotpeening, heat treating, etc.) performed by subcontractors will also be audited. Contractor shall be able to demonstrate that all testing, inspection procedures, and acceptance methods are documented in the appropriate area of the overhaul documents, and are approved and controlled by management.
(i) The PVA item shall be reassembled and functionally tested IAW applicable specifications and made ready for government aceptance including preservation, packing, packaging, marking, and update of historical records and all applicable documentation.
(j) Conduct of the PVA will be planned in a manner that adequately allows examination/audit of all procedures involved. Each step in the process shall be analyzed to determine compliance to specifications. It may not be logical or possible, due to time constraints, to track the same item throughout the PVA; therefore, at the AMRDEC PVA Team Chairman's discretion, examination of representative assemblies amy be used as evidence of compliance to specification requirements. The AMRDEC PVA Team Chairman will determine the scope and detail of the PVA process. The AMRDEC PVA Team Chairman may delegate follow-up actions to the government QAR, when it is determined to be prudent to the PVA.
(k) During the course of the PVA, the PVA Team Chairman may request progress meetings to provide status to the contractor. After the
PVA is completed, the AMRDEC PVA Team Chairman will conduct an exit critique attended by all concerned contractor personnel and the cognizant government QAR. The context of the audit findings and corrective actions will be discussed and any disputes will be resolved.
Findings, classifications, and corrective actions will be discussed and determinations made as to cause of defect established (i.e., workmanship, tooling, technical requirements, etc.). The contractor's management personnel shall take immediate action to correct and preclude recurrence of all defects attributable to failure to comply with requirements.
(l) All defects will be recorded on the AMRDEC PVA Audit Finding Record by the PVA Team. The PVA Team Chairman will provide copies of each Finding to the contractor quality assurance element and the cognizant government QAR. This will allow immediate actions to begin in the resolution of the defect. Corrective actions as well as actions taken to prevent recurrence shall also be documented on this form by the contractor. The form shall be signed, as a minimum, by the contractor's quality manager or designated representative and the AMRDEC PVA Team Chairman. Further actions outlined below pertain to specific actions required by the contractor depending on the classification of the defects.
1. Observation: In the event an observation Finding is discovered, the contractor is not required to provide a written response, but it is encouraged to do so.
2. Minor: In the event a minor defect is discovered, the following actions shall be taken:
a. The contractor shall isolate the cause of the defect and initiate corrective actions.
b. All minor defects shall require a written response addressing corrective actions taken and actions taken to prevent recurrence.
c. In the event a minor defect is a recurring deficiency, regardless of weapon system or date when original discrepancy was noted, it will be written into the report as a minor defect, but the corrective actions required below for a major defect will apply.
3. Major: In the event a major defect is discovered, the following actions shall be taken:
a. The contractor shall halt any work in progress at the responsible station until corrective action is acceptable to the PVA Chairman.
b. The contractor shall provide the QAR information reflecting the total quantity shipped, if any, and to what destination pertaining to any item that could contain the identified defect.
16 50
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
c. The contractor shall determine impact of the defect on products previously delivered under this contract, if any, and initiate corrective action to address those units at no additional cost to AMCOM.
d. The contractor shall isolate the cause of the defect and initiate corrective actions. All findings shall require an in-depth written response outlining corrective actions to prevent recurrence.
e. The contractor shall review/revise work documents for the specified operation responsible for the defect to ascertain that they are complete, adequate, and sufficiently defined to assure that, if followed and completed by both production, maintenance and inspection personnel, they will provide objective evidence of a quality operation.
f. The contractor shall assure the cognizant QAR and the AMRDEC PVA Team Chairman that positive, effective, corrective action has been initiated that will prevent recurrence of the cited defect. This assurance can be verbal at first, however, a written report from the contractor quality element containing all corrective actions completed and actions taken to prevent recurrence shall be provided to the QAR and the AMRDEC PVA Team Chairman within 24 hours after the verbal response.
4. Critical: In the event a critical defect is discovered, the following actions shall be taken:
a. All actions outlined in paragraph 3 above shall be completed.
b. Upon request, the contractor shall provide the AMRDEC Aviation Engineering Directorate technical information necessary for the issuance of a Safety of Flight Message or Aviation Safety Action Message to the field (if necessary).
c. Government acceptance/release of product will cease immediately until corrective actions are acceptable to the contracting officer.
NOTE: Systemic quality and overhaul process discrepancies that affect the outcome of product(s) outside the scope of the PVA will require the cognizant QAR to issue a Corrective Action Request.
(m). Upon completion of the disassembly and testing portion of the selected PVA candidate, without finding any critical or major defects, the other two completed candidates will be released as PVA candidates. In the event that a critical or major defect is found in the audit candidate, the contractor shall satisfy the PVA Team Chairman that such a defect does not exist in the other 2 PVA candidates prior to acceptance, and effective corrective action has been initiated to preclude reoccurrence of the defect.
(n). The contractor shall prepare and forward, through the cognizant government quality element, finalized audit reports within ten
(10) working days after completion of the PVA to Commander, U.S. Army Research Development and Engineering Command, ATTN: QS-
Contracts@amrdec.army.mil, Redstone Arsenal, AL 35898-5000 and the Acquisition Center address as shown on Order 0001. (In the event reorganization changes this address, the contractor will be notified of the new, correct address by the CO). The report shall include:
1. Name and location of contractor
2. Contract number or equivalent
3. Descriptive noun, national stock number, part number, and serial number of the item audited
4. Complete description of each audit finding, with corrective action taken, and action taken to prevent recurrence.
5. The audit report shall be signed, as a minimum, by the contractor's quality manager or his designated representative.
Objections, accompanied with explanations, on any audit finding(s) shall be specifically annotated and forwarded to AMCOM for resolution. Objection by the contractor as to the existence of a defect or as to its classification will be resolved by the PVA
Chairman. Further non-concurrence will be referred to the PCO for final resolution IAW the clause entitled "Disputes" as stated in the contract.
(o) The AMRDEC PVA Chairman will acknowledge receipt of the Final Audit Report and complete the following within 10 working days of receipt:
1. Review the Final PVA Report for compliance and completeness
2. Review the report for acceptance/rejection of corrective action and actions taken to prevent recurrence.
3. Forward a written reply to the AMCOM CO and/or cognizant government quality element, recommending acceptance or rejection of the Final Audit Report.
4. If the Final Audit Report is disapproved, the Contractor shall repeat any or all PVA tests, per Government request. If deemed in the best interests of the government, contract termination may be initiated. Upon request for additional tests, the
Contractor shall make any necessary changes, modifications, or repairs to the PVA item. All costs related to these tests are to be borne by the Contractor, including any and all costs for additional tests following disapproval. The Contractor shall then conduct the tests and deliver a revised report to the Government under the terms and conditions and within the time specified by the Government.
These actions must be coordinated with the cognizant government QAR. The Government shall take action on this report within 10 working days. The Government reserves the right to require an equitable adjustment of the contract price for any extension of the delivery schedule, or for any additional costs to the Government related to these tests.
(p) The PVA unit is to be representative of the deliverable quantity. The Contractor shall overhaul both the PVA item and the contractual quantity at the same facility. In the event that there is a change to the process planning (i.e. changes in process sources, parts sources, or location where work is to be performed) after approval of the Final Audit Report, the contractor is required to provide notification of such changes to the CO, so that a determination can be made whether a new PVA is warranted. Notification is required 10 business days prior to shipment of the next delivery.
(q) The PVA candidates shall be shipped IAW contract delivery schedules or released to supply activity upon acceptance of the Final
Audit Report. The Contractor SHALL NOT retain the PVA item approved under this contract to serve as the manufacturing standard of acceptance.
17 50
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
(r) If the Contractor fails to deliver any PVA on time, or the Contracting Officer disapproves any PVA, the Contractor shall be deemed to have failed to make delivery within the meaning of the Default clause of this contract.
(s) Before PVA approval, the acquisition of materials or components for, or the commencement of overhaul of, the balance of the contract quantity is at the sole risk of the Contractor. Before PVA approval, the costs thereof shall not be allocable to this contract for (1)
Progress payments, or (2) termination settlements if the contract is terminated for the convenience of the Government.
(t) In cases where this PVA is a part of the Source Approval Request (SAR) process, the process planning will be considered approved upon receipt of an approval memorandum from AMRDEC Aviation Engineering Directorate (AED). If the component is a Critical Safety Item
(CSI), see those specific contract clauses for other requirements that may also be audited during the PVA. PVA approval is contingent on contractor submission and AED approval of changes to manufacturing planning, to correct defects identified during PVA.
(u) Unless otherwise specified in this contract, any end item destroyed or exceeds reparable limites during the PVA process is not to be considered as part of the contract quantity. The full quantity of acceptable and serviceable items must be delivered.
*** END OF NARRATIVE E0001 ***
E-6 Calibration
The calibration of Test, Measurement and Diagnostic Equipment shall be in accordance with American National Standards Institute/National
Conference of Standards Laboratories (ANSI/NCSL) Z540-3-2006 (General Requirements for Calibration Laboratories and Measuring and Test
Equipment) or ISO 10012:2003 (Quality Assurance Requirements for Measuring Equipment). Terminology shall be as defined by International
Organization for Standardization (ISO) 8402, Quality Management and Quality Assurance - Vocabulary.
*** END OF NARRATIVE E0002 ***
18 50
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SECTION F - DELIVERIES OR PERFORMANCE
This document incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at these addresses:
http://farsite.hill.af.mil/ or https://www.acquisition.gov/
If the clause requires additional or unique information, then that information is provided immediately after the clause title.
Regulatory Cite Title Date Regulatory Cite Title Date _______________ ______________________________________________________________________ ____________ _______________ ______________________________________________________________________ ____________
F-1 52.242-15 STOP-WORK ORDER (AUG 1989) -- ALTERNATE I (APR 1984) APR/1984
F-2 52.242-15 STOP-WORK ORDER AUG/1989
F-3 52.242-17 GOVERNMENT DELAY OF WORK APR/1984
F-4 52.247-29 F.O.B. ORIGIN FEB/2006
F-5 52.247-34 F.O.B. DESTINATION NOV/1991
F-6 52.247-48 F.O.B. DESTINATION--EVIDENCE OF SHIPMENT FEB/1999
F-7 52.247-52 CLEARANCE AND DOCUMENTATION REQUIREMENTS--SHIPMENTS TO DOD AIR OR FEB/2006
WATER TERMINAL TRANSSHIPMENT POINTS
F-8 52.247-55 F.O.B. POINT FOR DELIVERY OF GOVERNMENT-FURNISHED PROPERTY JUN/2003
F-9 252.211-7007 REPORTING OF GOVERNMENT-FURNISHED PROPERTY AUG/2012
F-10 252.211-7003 ITEM UNIQUE IDENTIFICATION AND VALUATION MAR/2016
(a)…