AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. Contract ID Code Page Of
2. Amendment/Modification No.
3. Effective Date
4. Requisition/Purchase Req No.
5. Project No. (If applicable)
6. Issued By Code 7. Administered By (If other than Item 6) Code
8. Name And Address Of Contractor (No., Street, City, County, State and Zip Code)
9A. Amendment Of Solicitation No.
9B. Dated (See Item 11)
10A. Modification Of Contract/Order No.
10B. Dated (See Item 13) Code Facility Code
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing items 8 and 15, and returning ____________ copies of the amendments: (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. Accounting And Appropriation Data (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATIONS OF CONTRACTS/ORDERS
It Modifies The Contract/Order No. As Described In Item 14.
A. This Change Order is Issued Pursuant To: The Changes Set Forth In Item 14 Are Made In
The Contract/Order No. In Item 10A.
B. The Above Numbered Contract/Order Is Modified To Reflect The Administrative Changes (such as changes in paying office, appropriation data, etc.) Set
Forth In Item 14, Pursuant To The Authority of FAR 43.103(b).
C. This Supplemental Agreement Is Entered Into Pursuant To Authority Of:
D. Other (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return _______________ copies to the Issuing Office.
14. Description Of Amendment/Modification (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. Name And Title Of Signer (Type or print)
16A. Name And Title Of Contracting Officer (Type or print)
15B. Contractor/Offeror 15C. Date Signed 16B. United States Of America 16C. Date Signed
By (Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070
PREVIOUS EDITIONS UNUSABLE
30-105-02 STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
SEE SCHEDULE
X
Firm Fixed Price
0005 2019MAY13
W58RGZ
ARMY CONTRACTING COMMAND-REDSTONE
REDSTONE ARSENAL AL 35898-5280
ANDREW CAMERON
EMAIL: ANDREW.E.CAMERON.CIV@MAIL.MIL
W58RGZ-18-R-0152
2018MAY31
X
X 2019JUN14 01:00am
/SIGNED/
2 signed
SEE SECOND PAGE FOR DESCRIPTION
1 13
CONTINUATION SHEET
Reference No. of Document Being Continued Page of
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SECTION A - SUPPLEMENTAL INFORMATION
Buyer Name: ANDREW CAMERON
Buyer Office Symbol/Telephone Number: CCAM-AL-M/(256)842-7478
Type of Contract 1: Firm Fixed Price
Kind of Contract: Maintenance Contracts
*** End of Narrative A0000 ***
1. This item is not a Crtical Safety Item (CSI). ______________________________________________
2. This is a five (5) year Firm-Fixed-Price (FFP) Indefinite Delivery Indefinite Quantity (IDIQ) contract pursuant to FAR 52.216-22.
3. This is a Full and open Competition. Depot Maintenance Work Requirement (DMWR) 1-2840-248-1/2/3/4 is available for the overhaul of the Stage 1, Nozzle.
4. Reserved.
5. Reserved.
6. Subject to the availability of funds, any quantities ordered will be priced at the unit price established for the ordering period in which they are ordered. Funds shall be obligated by issuance of Delivery Orders and not by the contract itself.
7. The minimum quantity set forth herein shall be obligated on the first delivery (DO), to be issued simultaneously with the award of the contract. Any additional quantities ordered will be priced at the firm fixed price in effect during the ordering period in which they are ordered.
8. The Government will not be required to obtain the contractor's signature prior to the issuance of an order.
9. The Government intends to award only one basic Fixed Price IDIQ contract as a result of this solicitation.
10. The Government has segregated the estimated quantities into five ordering periods. However, this does not preclude exercising the
Government's right under FAR 52.216-19 by ordering the maximum quantity specified in FAR 52.216-19(b)(1) at any time during the five year ordering period.
Ordering Period 1 will be from date of contract award through 365 days after contract award (DACA).
Ordering Period 2 will be from 366 DACA through 730 DACA.
Ordering Period 3 will be from 731 DACA through 1,095 DACA.
Ordering Period 4 will be from 1,096 DACA through 1,460 DACA.
Ordering Period 3 will be from 1,461 DACA through 1,825 DACA.
11. Please insert your firm fixed unit prices for the 1st, 2nd, 3rd, 4th, and 5th ordering periods in the spaces provided under each
CLIN/SubCLIN.
12. For purposes of Block 12 on page 1, the offer acceptance period is 120 days from the date for receipt of offers specified in Block
9, unless a different period is inserted by the offeror in the blank in Block 12.
13. No Government Furnished Materials (GFM), other than the reparable assets and reusable containers, will be provided.
14. Offers shall be submitted in accordance with FAR Clause 52.215-1. Facsimile and electronic submissions are not authorized.
Proposals shall be mailed to:
Army Contracting Command - Redstone
ATTN: Andrew E. Cameron, CCAM-ALB
Bldg. 5303, 2nd Floor
Redstone Arsenal, AL 35898-5280
15. If any offeror chooses to hand carry their proposal, the offeror must reach the appointed location (identified as building 5300, 5300 Martin Road, Redstone Arsenal, AL 35898, Foyer) by the date and time as stated in block 9 on page 1 of the solicitation. Please be advised that Redstone Arsenal is a restricted facility and should an offeror choose to hand carry a proposal, a minimum of 72 hours notice to the Contracting Officer is required in order to ensure access by the closing date/time of the solicitation. Any unauthorized entity must be identified as having a need, as validated by the Contracting Officer, in order to gain access to the post. The contracting office must notify the Gate personnel, who monitor post access, a minimum of 48 hours prior to an entity gaining entrance to
2 13
W58RGZ-18-R-0152
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
the restricted post. Please note that any proposals delivered late as a result of failure to comply with the procedure will not be accepted, IAW FAR 52.215-1 entitled "Instructions to Offerors-Competitive Acquisition".
16. Reserved
17. The contractor shall provide with their proposal a response that addresses the contractor's plan to meet all government special tooling and test equipment requirements with either:
1. Physical possession of the required tools, 2. Confirmed requisitions for the required tools, 3. Confirmed arrangements for subcontracting the processes requiring the special tools, or 4. Specific plans describing their technical approach to develop equivalent tools.
18. The Contractor may be requested to submit additional cost or pricing data if only one offer is received IAW DFARS Clause 252.215-
7008, entitled "Only One Offer."
19. The contractor is instructed to put the following words in the remarks column of the DD 250/WAWF: "Repair and Return Process D6".
20. Access to DLA EMALL is NOT authorized. ___
21. The National Defense Authorization Act for Fiscal Year 1993, Public Law 102-484, Section 326, prohibits use of Other Direct Cost
(ODC) in Department of Defense contracts awarded on or after 1 June 1993, unless appropriate authority is granted.
22. The following websites are provided for the purpose of obtaining/reviewing various Army publications and technical manuals/bulletins:
A. https://liw.logsa.army.mil/etmapp/#/etm/home - Technical Manuals and Bulletins
B. http://www.apd.army.mil/ - DA Pamphlets and Army Regulations
23. COMPLETE THE FOLLOWING CONTRACTOR POINT OF CONTACT INFORMATION:
NAME: _________________________________________
TELEPHONE NUMBER: _____________________________
FAX NUMBER: ___________________________________
E-MAIL ADDRESS: _______________________________
*** END OF NARRATIVE A0001 ***
The purpose of Amendment 0005 is to incorporate the following changes:
1. The Upgrade requirement is hereby removed from this solicitation. CLIN 0002AA, Narrative A0001, and Narrative C0001 have been revised to remove all references to Upgrades, NSN 2840-01-509-0307, and P/N 6071T04G29.
2. The FMS requirement is hereby removed from this solicitation. CLIN 0003AA has been deleted in its entirety; all quantities previously applicable to this CLIN have been re-allocated to CLIN 0002AA. Additionally, CLIN 0004AA, CLIN 0005AA, Narrative A0001, and Narrative
M0001 have been revised to remove all FMS references.
3. Clause 52.246-11 is hereby revised to specify a more current quality standards.
4. Narrative C0001 has been revised to remove the information concerning paint facilities, as painting is not required for the Stage 1
Nozzle.
5. The required turnaround time for this solicitation is hereby changed to 90 days. Narratives F0001 and F0002 have been updated accordingly.
6. The deadline for receipt of proposals is hereby extended to 7 June 2019.
3 13
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
7. All other terms and conditions remain the same.
*** END OF NARRATIVE A0006 ***
4 13
PIIN/SIIN
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS
0002 STAGE 1 NOZZLE
NSN: 2840-01-584-9634
Mfr CAGE: 24113
Mfr Part Number: 6071T04G32
0002AA OVERHAUL (US) $ $ _______________ ______________ __________________
COMMODITY NAME: STAGE 1 NOZZLE
CLIN CONTRACT TYPE:
Firm Fixed Price
CLIN 0002AA is for the overhaul of the T700
Engines Stage 1, Nozzle for US Army requirements.
INPUT NSNs:
2840-01-584-9634
INPUT PART NUMBERS:
6071T04G32
OUTPUT NSN: 2840-01-584-9634
OUTPUT PART NUMBER: 6071T04G32
Offeror is required to fill in proposed firm-fixed-unit prices for ordering periods 1 through 5:
ORDERING PERIOD 1 - U/P $_________ (FFP) MIN QTY 5 EA
ORDERING PERIOD 2 - U/P $_________ (FFP) EST QTY 150
EA
ORDERING PERIOD 3 - U/P $_________ (FFP) EST QTY 150
EA
ORDERING PERIOD 4 - U/P $_________ (FFP) EST QTY 150
EA
ORDERING PERIOD 5 - U/P $_________ (FFP) EST QTY 169
EA
Overhaul shall be in accordance with Section
C Clause entitled Statement of
Work/Specifications-Government
Specifications.
This Firm Fixed Price (FFP) CLIN includes all labor charges, mandatory and non-mandatory replacement parts and material, preservation, packaging, packing, marking, and data items necessary to return the unit to a serviceable condition as stated in section C entitled
5 13
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
Statement of Work/Specifications - Government
Specifications.
THIS IS A FIRM-FIXED-PRICE CLIN.
(End of narrative C001)
Packaging and Marking _____________________
PACKAGING/PACKING/SPECIFICATIONS:
IAW MIL-STD-129
LEVEL PRESERVATION: Military
LEVEL PACKING: B
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
0003AA DELETED _______
0004AA SCRAP $ _____ __________________
SERVICE REQUESTED: SCRAP
CLIN CONTRACT TYPE:
Firm Fixed Price
THIS CLIN APPLIES TO U.S. ASSETS________________________________
SECTION C - Description/Specifications/Work Statement_________
Units from CLIN 0002AA shall be scrapped or returned in accordance with (IAW) Section C, Statement of
Work/Specifications - Government Specifications.
Units determined to be scrap IAW Section C shall be reflected as an increase to CLIN 0004AA with a corresponding decrease in quantity and funds in CLIN
0002AA as appropriate. In the event the PCO determines that certain items are scrap, the
Contractor shall make disposition IAW the
Contractor's approved Government property procedures.
Scrapped items shall count toward the minimum quantities ordered hereunder. The Government may, at its own discretion, reduce any items determined scrap by input of additional assets and said scrap quantities will not count as part of the total maximum quantity. Scrap requires authorization by the
Contracting Officer via formal modification. In no event shall the Contractor scrap an item prior to receiving a contractual modification for a unit.
THIS IS A FIRM FIXED PRICE CLIN.
OFFEROR IS REQUIRED TO FILL IN PROPOSED UNIT PRICES
FOR THE FIVE (5) ORDERING PERIODS:
6 13
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
ORDERING PERIOD 1 - U/P $__________(FFP) 10 EA, EST
QTY
ORDERING PERIOD 2 - U/P $__________(FFP) 10 EA, EST
QTY
ORDERING PERIOD 3 - U/P $__________(FFP) 10 EA, EST
QTY
ORDERING PERIOD 4 - U/P $__________(FFP) 10 EA, EST
QTY
ORDERING PERIOD 5 - U/P $__________(FFP) 10 EA, EST
QTY
The quantites estimated here are for evaluation purposes only.
(End of narrative C001)
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
0006 CONTRACT DATA REQUIREMENTS LIST (CDRL) ______________________________________
This CLIN is "Not Separately Priced" (NSP). Pricing for data shall be included in the unit prices of CLIN
0002AA.
The Contractor shall provide Data Items A001 - A005 in accordance with the Contract Data Requirements
List, Exhibits A, B, C, D, and E.
(End of narrative A001)
7 13
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SECTION C - DESCRIPTION/SPECIFICATIONS/WORK STATEMENT
1C-1 Statement of Work/Specifications Government Specifications
a. The Contractor, as an independent Contractor, and not as an agent or employee of the Government, shall furnish all services, facilities, labor, parts, materials, equipment, tools, and data (other than Government Furnished Property), necessary to accomplish the inspection and overhaul for Stage 1 Nozzle that is required to return the items as specified by Section B, to condition code A as defined by Army Regulation 725-50. The input/output configuration shall be as defined in Section B herein. Upon completion of the overhaul, as applicable, the items shall be packaged as defined in each individual delivery order of the contract and shipped to the destination(s)specified in each individual delivery order.
b. Prior to commencement of overhaul, the Contractor shall disassemble and inspect the item to the extent necessary to determine the complete cost to overhaul. The Contractor shall continue the overhaul process on all end items when the total cost to overhaul does not exceed $21,223.12. The overhaul line items shown in section B are firm-fixed price. The contractor will be required to complete the overhaul on all end items regardless of the damage as long as the total contractor cost to overhaul does not exceed $21,223.12. The contractor will be required to provide data other than certified cost and pricing data and a report of discrepancy signed by the DCMA
QAR to the Procuring Contracting Officer (PCO) to confirm the total cost to overhaul will exceed $21,223.12. This data will include at minimum material cost (80% of material cost will be supported by current vendor quotes), labor hours, labor rates, overheads, G&A, and profit rate. More information to support the contractor's price may be requested by the Government. In no event will an asset be scrapped prior to an approved modification by the Contracting Officer. No additional funding except for missing parts will be provided to the contractor to complete the overhaul of the end item. The firm fixed prices in the overhaul CLINs must include/cover all mandatory and non-mandatory parts as required by the Depot Maintenance Work Requirement (DMWR). The Government cannot guarantee the condition of the assets sent to the Contractor for overhaul.
c. In the event that the total contractor cost to overhaul is determined (approved by PCO) to exceed $21,223.12, the contractor shall scrap such assets at the fixed unit price in CLIN 0004AA of section B hereof and make disposition in accordance with (IAW) the contractor's approved Government property procedures. Such scrapped items shall count toward the minimum quantities ordered hereunder.
The Government may, at its discretion, replace any items scrapped by input of additional assets, and said scrap quantities will not count as part of the total maximum quantity. Any item other than those determined to be scrapped must be overhauled at the firm fixed price in the awarded contract.
d. Overhaul shall be accomplished IAW Depot Maintenance Work Requirement (DMWR) DMWR-1-2840-248-1/2/3/4, Dated 09/30/2014, Change
#2.
e. Critical Safety Item: N/A
f. Upon receipt of the repairables, containers shall be reviewed for serviceability. Containers shall be considered serviceable unless one or more of the following conditions exist: (1) containers are structurally damaged to include functional damage to the suspension system, cracks or holes to the container hull, hull deformity to the extent the container cannot be closed (or sealed where required), or dents that will interfere with the item envelope; (2) corrosion has progressed to the point where fit, function or the life of the container is affected. Items received without containers or containers determined to be unserviceable shall be processed IAW the
Contractor's locally approved Government Property procedures. Components received improperly packaged, damaged with corrosion/deterioration or those with shipping discrepancies shall be reported IAW DI-MGMT-80503.
g. Reserved.
h. Data and reports shall be submitted IAW the Contract Data Requirements List, DD Form 1423, Exhibit A. Data shall be packaged, packed and marked as necessary to assure safe delivery to the addresses indicated on the DD Forms(s) 1423.
i. Product Verification Audit (PVA): The Contractor shall conduct the PVA in accordance with the PVA SOW found in section E of the solicitation/contract.
j. The Army Maintenance Management System - Aviation (TAMMS-A): The Contractor shall prepare TAMMS data IAW DI-SESS-81758 and the
TAMMS instructions attached to the solicitation/contract. The Contractor shall complete the forms and records as specified in DA PAM 738-
751, TB 1-1500-341-01, TM 1-1500-328-23.
k. Serial Number Report Requirement (SNRR): N/A
l. The items the Contractor shall repair are identified below:
Input NSN P/N
2840-01-584-9634 6071T04G32
Output NSN P/N
2840-01-584-9634 6071T04G32
8 13
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
m. The overhaul planned quantity for 5 years is minimum 5, maximum 624. Input will be 30 days after receipt of order
(ARO). Output shall be as specified in the solicitation/contract delivery schedule, located in paragraph 12 of page 35.
Serviceable assets shall be returned to PLANT 7001, RIC BR4, W562RM.
n. Inventory Transactions - The contractor shall prepare the following reports:
1. The contractor shall prepare a Contract Depot Maintenance Production Report IAW DI-PSSS-81995.
2. The contractor shall complete and maintain the DD Form 1348-1A receipt for repairables on all shipments IAW DI-MISC-80508 and DD Form
1348-1A. The contractor shall complete the DD Form 1348-1A, Block 10 (indicates the quantity received), along with Block 22 (signature), and Block 23 (date). Printed names, name/date stamps, and initials shall not be acceptable. If a DD Form 1348-1A is not delivered with the shipment, a DD Form 1348-1A is located at:
The contractor shall prepare this data to include the following corresponding receipt information:
A. National Stock Number (NSN) - (Positions 8-22)
B. Condition Code - (Position 71)
C. Unit Price - (Positions 74-80)
D. Total Price - (Block 1)
E. Actual Quantity Received - (Block 10)
F. Nomenclature - (Block 17)
G. Signature and Date - (Blocks 22 and 23)
If there are any questions with the above information please contact: usarmy.redstone.usamc.mbx.immc-smb-ammo@mail.mil
o. Reserved
p. Reserved.
q. The Government reserves the right to replace any items scrapped.
r. Overhaul Repair Report: N/A
s. Quality Deficiency Report: The Contractor shall prepare the Quality Deficiency Report IAW DI-QCIC-80736.
t. Supplier Interface and Oversight: The Contractor shall prepare the Process Plan IAW DI-MISC-80508, QE-STD-2, and the M&O Plan
Description and Guidance Instructions. See and select "AMCOM Maintenance and Overhaul (M&O) SAR."
u. Shipping Containers NSN: 8145-01-302-1026, P/N: 15715 shall be utilized. If containers are not reparable or if assets are not delivered in the approved containers, the containers shall be Contractor Furnished Materiel. Shipment: The method of shipment must use a procedure so that the package can be tracked in case the shipment is not received by AMCOM.
Additional Requirements
1. Engine Test Cell for testing per DMWR Chapter 4, with instrumentation and accuracy to adequately measure all parameters required by DMWR. The contractor shall provide a complete description of the test cell facility.
2. One T700GE701D correlation engine is required to correlate the test cell IAW MEO-P5828A. MEO requires that the correlation engine be run on Original Equipment Manufacturer (OEM) or depot test cell, and should be maintained at the contractor site for the duration of contract production, for use in verifying test cells.
3. Auxiliary accessory components for use in engine testing, that are not received and shipped with each production engine, but are required for testing.
*** END OF NARRATIVE C0001 ***
9 13
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SECTION E - INSPECTION AND ACCEPTANCE
Status Regulatory Cite Title Date Status Regulatory Cite Title Date _______ _______________ ______________________________________________________________________ ____________ _______ _______________ ______________________________________________________________________ ____________
E-1 CHANGED 52.246-11 HIGHER-LEVEL CONTRACT QUALITY REQUIREMENT DEC/2014
(a) The contractor shall comply with the higher-level quality standard(s) listed below.
ISO 9001:2015 and AS9100D, OR EQUIVALENT with prior approval from Procurement Contracting Officer.
(b) The contractor shall include applicable requirements of the higher-level quality standard(s) listed in paragraph (a) of this clause and the requirement to flow down such standards, as applicable, to lower-tier subcontracts in--
(1) Any subcontract for critical and complex items (see 46.203(b) and (c)); or
(2) When the technical requirements of a subcontract require--
(i) Control of such things as design, work operations, in-process control, testing and inspection; or
(ii) Attention to such factors as organization, planning, work instructions, documentation control, and advanced metrology.
(End of clause)
10 13
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SECTION F - DELIVERIES OR PERFORMANCE
12 Delivery Schedule
(a) The Contractor agrees to accept the 5 quantity of reparables immediately upon issuance of a contract/delivery order(s). These items will be overhauled under the first DO, to be issued simultaneously with the award of this contract action. Input of the reparables by the Government and output of the completed items as specified in Section B, shall be accomplished in accordance with the following schedule:
No. of Days After
(1) Input by Government: ITEM NO. ________ QTY___ Award of Contract/Order_______________________
0002AA 3 30
2 180
(2) Government's Required Output Schedule: ________
No. of Days After
ITEM NO.________ QTY___ Award of Contract/Order_______________________
0002AA 3 150
2 270
The Government will evaluate equally, as regards time of delivery, offers that propose delivery of each quantity within the applicable delivery period specified above. The Government reserves the right to award under either the required delivery schedule or the proposed delivery schedule, when an offeror offers an earlier delivery schedule than required above. If the offeror proposes no other delivery schedule, the required delivery schedule above will apply.
(3) Offerors Proposed Output Schedule:
No. of Days After
ITEM NO. QTY Award of Contract/Order ________ ___ _______________________
The delivery schedule for all data and reports is as specified on the DD Form 1423, Exhibits A - E.
*** END OF NARRATIVE F0001 ***
13 Delivery of Additional Quantities
Additional quantities of Item 0002 up to the maximum quantity specified in Section B, if and when ordered in accordance with delivery order procedures, shall be delivered at a maximum monthly rate of 5 each per month commencing 90 days after receipt of reparables.
*** END OF NARRATIVE F0002 ***
11 13
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
12 13
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SECTION M - EVALUATION FACTORS FOR AWARD
M-3 Evaluation Factors for Award
The award of this contract shall be made to the responsive and responsible offeror whose proposal is evaluated at the lowest total cost to the Government, based on the following factors which shall be evaluated for each item:
(a) Overhaul/Repair (US)
The sum of the offeror's proposed firm fixed unit price(s) for each applicable line item as stated in Section B multiplied by the firm quantity; or, in the case of an indefinite delivery type contract, multiplied by the Government's estimated yearly quantities, as applicable and as stated in Section B, for each year; plus
(b) Product Verification Audit (PVA)
The offeror's firm fixed unit price(s) stated in Section B; plus
(c) Contractor Furnished Containers
The offeror's proposed firm fixed unit price(s) for each applicable line item as stated in Section B multiplied by the quantity; or, in the case of an indefinite delivery type contract, multiplied by the Government's estimated yearly quantities, as applicable and stated in Section B, as set forth therein; plus
(d) Scrap
The offeror's proposed firm fixed unit price(s) for each applicable line item as stated in Section B multiplied by the quantity; or, in the case of an indefinite delivery type contract, multiplied by the Government's estimated yearly quantities, as applicable and stated in Section B, as set forth therein; plus
(e) Government Property
The rental value of Government Property pursuant to the provision in Section M entitled "Evaluation Procedures to Eliminate
Competitive Advantages from Rent-Free Use of Government-Owned Production and Research Property"; plus any other factor required to be evaluated by law or regulation.
*** END OF NARRATIVE M0001 ***
13 13
| SECTION A |
| SECTION B |
| SECTION C |
| SECTION E |
| SECTION F |
| SECTION M |
File details come from the government source that posted it.