LIMWS RFI Questions and Answers
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFI_LIMWS_FBO_Posting_Amendment_2.pdf | ||
| RFI_LIMWS_FBO_Posting_Amendment_1.pdf | ||
| RFI_LIMWS_13APR2018.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Final LIMWS RFI Questions and Answers 17 April 2018
1. The Procurement Action Description seeks production representative prototypes, additional system development, and support. Is this a solicitation for additional production based on an existing LIMWS Technical Data Package (TDP)? No. The Government has not received a Level III LIMWS Technical Data Package (TDP).
2. If so, can the TDP be made available for the purposes of this RFI? No. The Government will not receive a TDP in support of this RFI.
3. If the above is not the case, is there a desire to receive information regarding the development and production of a non-incumbent LIMWS capability? Yes. The Government would accept information regarding a non-incumbent LIMWS capability.
4. What is the purpose of the delta critical design review? If required, the CDR will evaluate data that will not be available at the baseline CDR date.
5. What is meant by retrofit of A-Kit based on risk reduction and development testing? The retrofit would include any lessons learned or design changes to the new A-kits being developed as a result of the risk reduction and development testing.
6. When is A-Kit installation expected? Approximately 4QFY18.
7. What is the schedule for the USG testing events to be supported? Government testing is planned for 4QFY18 through 2QFY19.