AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. Contract ID Code Page Of

2. Amendment/Modification No.

3. Effective Date

4. Requisition/Purchase Req No.

5. Project No. (If applicable)

6. Issued By Code 7. Administered By (If other than Item 6) Code

8. Name And Address Of Contractor (No., Street, City, County, State and Zip Code)

9A. Amendment Of Solicitation No.

9B. Dated (See Item 11)

10A. Modification Of Contract/Order No.

10B. Dated (See Item 13) Code Facility Code

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing items 8 and 15, and returning ____________ copies of the amendments: (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. Accounting And Appropriation Data (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATIONS OF CONTRACTS/ORDERS

It Modifies The Contract/Order No. As Described In Item 14.

A. This Change Order is Issued Pursuant To: The Changes Set Forth In Item 14 Are Made In

The Contract/Order No. In Item 10A.

B. The Above Numbered Contract/Order Is Modified To Reflect The Administrative Changes (such as changes in paying office, appropriation data, etc.) Set

Forth In Item 14, Pursuant To The Authority of FAR 43.103(b).

C. This Supplemental Agreement Is Entered Into Pursuant To Authority Of:

D. Other (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return _______________ copies to the Issuing Office.

14. Description Of Amendment/Modification (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. Name And Title Of Signer (Type or print)

16A. Name And Title Of Contracting Officer (Type or print)

15B. Contractor/Offeror 15C. Date Signed 16B. United States Of America 16C. Date Signed

By (Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070

PREVIOUS EDITIONS UNUSABLE

30-105-02 STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

SEE SCHEDULE

X

Firm Fixed Price

0002 2023APR12

W56HZV

ACC-DTA

6501 E. 11 MILE RD.

DETROIT ARSENAL, MI 48397-5000

JUSTINE BROUGHTON

EMAIL: JUSTINE.R.BROUGHTON.CIV@ARMY.MIL

W56HZV-23-Q-0028

2023FEB02

X

X 2023APR17

/SIGNED/

2 signed

SEE SECOND PAGE FOR DESCRIPTION

1 4

CONTINUATION SHEET

Reference No. of Document Being Continued Page of

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SUPPLEMENTAL INFORMATION

Buyer Name: JUSTINE BROUGHTON

Buyer Office Symbol/Telephone Number: CCTA-APS-B/(586)282-7504

Type of Contract 1: Firm Fixed Price

Kind of Contract: Supply Contracts and Priced Orders

Weapon System: Howitzer, Light Towed, 105mm, M119A1

*** End of Narrative A0000 ***

SOLICITATION: W56HZV-23-Q-0028

AMENDMENT: 0002

1. The purpose of this amendment is to:

SECTION B:

a) ADD CLIN 0001AB, First Article Test.

SECTION E:

b) Change clause 52.211-8, Time of Delivery, as follows:

FROM:

ITEM NO. QUANTITY WITHIN DAYS

AFTER CONTRACT AWARD

CLIN 0001AA 5 EA 180 DAYS WITHOUT FAT; 210 DAYS WITH FAT

CLIN 0001AB 3 EA 180 DAYS WITHOUT FAT; 210 DAYS WITH FAT

CLIN 0002AA 5 EA 150 DAYS WITHOUT FAT; 180 DAYS WITH FAT

TO:

ITEM NO. QUANTITY WITHIN DAYS

AFTER CONTRACT AWARD

CLIN 0001AA 5 EA 180 DAYS WITHOUT FAT; 210 DAYS WITH FAT

CLIN 0001AB 1 EA 180 DAYS WITHOUT FAT; 210 DAYS WITH FAT

CLIN 0002AA 5 EA 150 DAYS WITHOUT FAT; 180 DAYS WITH FAT

2. This concludes all Sections affected by this Amendment

*** END OF NARRATIVE A0003 ***

2 4

W56HZV-23-Q-0028

PIIN/SIIN

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

SUPPLIES OR SERVICES AND PRICES/COSTS

0001 PLUNGER ASSEMBLY

NSN: 1015-01-340-6103

0001AB FIRST ARTICLE TEST 1 LO $ __________________ __________________

SERVICE REQUESTED: PLUNGER ASSEMBLY

FIRST ARTICLE TEST REPORT (FATR), PURSUANT TO THE

REQUIREMENTS LISTED IN:

SECTION E.3.: SUPPLEMENTAL REQUIREMENTS TO FIRST

ARTICLE APPROVAL (CONTRACTOR TESTING); and

FAR CLAUSE 52.209-3: FIRST ARTICLE APPROVAL -

CONTRACTOR TESTING (SEE I FOR ADDITIONAL INFORMATION)

The FATR is due 45 days after contract award.

FATR approval/disapproval will be determined by the

Procuring Contracting Officer (PCO) identitified at time of contract award. Goverment approval/disapproval days: 30.

(End of narrative B001)

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Destination

Deliveries or Performance _________________________

DEL REL CD QUANTITY DAYS AFTER AWARD __________ ______________ ________________

001 1 0045

3 4

Reference No. of Document Being Continued Page of

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

DELIVERIES OR PERFORMANCE

Status Regulatory Cite Title Date Status Regulatory Cite Title Date _______ _______________ ______________________________________________________________________ ____________ _______ _______________ ______________________________________________________________________ ____________

1 CHANGED 52.211-8 TIME OF DELIVERY JUN/1997

(a) The Government requires delivery to be made according to the following schedule:

REQUIRED DELIVERY SCHEDULE

ITEM NO. QUANTITY WITHIN DAYS

AFTER CONTRACT AWARD

CLIN 0001AA 5 EA 180 DAYS WITHOUT FAT; 210 DAYS WITH FAT

CLIN 0001AB 1 EA 180 DAYS WITHOUT FAT; 210 DAYS WITH FAT

CLIN 0002AA 5 EA 150 DAYS WITHOUT FAT; 180 DAYS WITH FAT

The Government will evaluate equally, as regards time of delivery, offers that propose delivery of each quantity within the applicable delivery period specified above. Offers that propose delivery that will not clearly fall within the applicable required delivery period specified above, will be considered nonresponsive and rejected. The Government reserves the right to award under either the required delivery schedule or the proposed delivery schedule, when an offeror offers an earlier delivery schedule than required above. If the offeror proposes no other delivery schedule, the required delivery schedule above will apply.

OFFERORS PROPOSED DELIVERY SCHEDULE

ITEM NO. QUANTITY WITHIN DAYS

AFTER DATE OF

CONTRACT

(b) Attention is directed to the Contract Award provision of the solicitation that provides that a written award or acceptance of offer mailed, or otherwise furnished to the successful offeror, results in a binding contract. The Government will mail or otherwise furnish to the offeror an award or notice of award not later than the day award is dated. Therefore, the offeror should compute the time available for performance beginning with the actual date of award, rather than the date the written notice of award is received from the

Contracting Officer through the ordinary mails. However, the Government will evaluate an offer that proposes delivery based on the

Contractors date of receipt of the contract or notice of award by adding

(1) five calendar days for delivery of the award through the ordinary mails, or

(2) one working day if the solicitation states that the contract or notice of award will be transmitted electronically. (The term working day excludes weekends and U.S. Federal holidays.) If, as so computed, the offered delivery date is later than the required delivery date, the offer will be considered nonresponsive and rejected.

(End of Clause)

4 4

SUPPLEMENTAL INFORMATION
SUPPLIES OR SERVICES AND PRICES/COSTS
DELIVERIES OR PERFORMANCE