B08 Amendment 0001.pdf

PDF 374 KB Posted

Attached to
Replace Roofing - Building 210 Federal contract opportunity
Solicitation number
W52P1J-22-R-5004
Issued by
Department of the Army Materiel Command Joint Munitions Command

About this file

This document is an amendment to a solicitation for roof replacement services. The Army Contracting Command - Rock Island is seeking proposals to replace the roofing on Building 210 at the Rock Island Arsenal in Rock Island, Illinois. The work includes removing the existing roofing systems from two roof areas and installing a new fully adhered EPDM roofing membrane system with no ballast. Specification sections and submittal requirements were revised on specified dates in July 2022. Questions received from contractors were answered to clarify insulation, decking, and membrane material requirements as well as restrictions on working hours and roof access. Proposals are due to the listed points of contact by email by the amended date.

View the file

Other files for this federal contract opportunity

Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

0011795901 2022-0353

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

See Summary of Changes

1. CONTRACT ID CODE PAGE OF PAGES

J 1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 15-Jul-2022

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W52P1J22R5004

X 9B. DATED (SEE ITEM 11)

22-Jun-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

15-Jul-2022

CODE

ARMY CONTRACTING COMMAND - ROCK ISLAND

3055 RODMAN AVENUE

ROCK ISLAND IL 61299-8000

W52P1J 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W52P1J22R5004

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 0001

The purpose of this Amendment is:

1. To Answer the following Contractor questions.

A. 20 psi (specs) or 25 psi (plans) insulation required?

Answer: Insulation shall be 25 psi per the requirements listed on the plans.

B. Since this is a reroof, can 1/8”/ft tapered insulation be used in lieu of ¼”/ft. (see G-004) to reduce costs? I have all areas 4-wayed to the drains so ponding shouldn’t be an issue.

Answer: Insulation taper shall be ¼ inch per foot. Note that the upper roof (Drawings A-105 and A-106) slopes at ½” per foot from the ridge to the roof perimeter on the north and south.

C. Deck conditions to determine attachment.

Answer: Existing lower roof deck is metal. Existing upper roof deck is concrete with a thickness of 6”.

D. Cover board manufacturer and size as well as vapor barrier to be used (see specs).

Answer: Refer to revised Specification Section 07 22 00 dated 15 July 2022.

E. With the added insulation, the new height of insulation will be over the door sills on the penthouses of the upper roof area. How should this be handled?

Answer: The insulation taper and thickness will need to be adjusted to accommodate existing conditions.

Variations will be addressed on a case by case basis during construction.

F. The specification calls for REINFORCED 90 mil EPDM, this is not available, however NON-Reinforced

90 mil is available which qualifies for the 25 year warranty as specified, is 90 mil NON-Reinforced membrane acceptable?

Answer: 90 mil non-reinforced membrane will be acceptable. Refer to the revised Specification Section 07 53 23, date 15 July 2022

G. Roofing membrane is specified as 90 mil reinforced EPDM. Firestone Building Products and Carlisle

Syntec manufacturers are not making this product. (Will 60 Mil reinforced EPDM or Fleece-backed EPDM be acceptable?) Please clarify.

Answer: Refer to the response in question six above.

H. In the SOW for this project it shows standard working hours of 0600 to 1700 Monday through Friday. It later lists Special Conditions hours of 5:30 PM Friday to 6:00 AM Monday. I am assuming the intent is to do all of the work over the weekends so as to not be disruptive and the standard hours shown are just general information for other projects.

Answer: Working Hours listed in the SOW have been revised. Refer to the revised SOW, dated 11 July 2022.

I. Drawings sheet A-101: Which service provider are we to coordinate with for realigning the TV satellite dish?

Answer: Dish provider appears to be the Dish Network.

J. Is there a sheet metal specification? What gauge is the slip counterflashing, counterflashing, and rain collar at Details A1, A3/A-501 and A4/A502?

Answer: Refer to Specification Section 07 60 00, revised 15 July 2022.

K. What is the cover board insulation material? What is the desired thickness?

Answer: Refer to the response in question 4 above.

L. Is there a minimum R Value of 30.0 required for insulation?

Answer: Refer to the latest edition of the International Energy Code.

M. Which roof areas are mechanically fastened EPDM?

Answer: The references to mechanically fastened have been removed from the specifications. Refer to Specification Section 07 53 23 revised 15 July 2022.

N. Which Roof Areas are Fully adhered EPDM?

Answer: Refer to the response in question 13 above.

O. Can the roof debris be removed from the roof through a chute for both roof areas? Or does roof debris need to be craned off of the roof?

Answer: A chute is acceptable for the low roof only.

P. How will personnel access the roof? Stair tower, ladder or through inside of building?

Answer: Access to the roof for personnel and hand tools will be through the inside of the building.

Q. Is there a specific manufacturer and color for the EPDM?

Answer: There is no specific manufacturer or list of manufacturer’s. The color of the EPDM shall be black.

R. Has a core sample been done?

Answer: A core sample was taken during the site visit. The lower roof had tapered insulation from 2” in the center to 8” in the NW corner. The upper roof was 2 ¼” thick insulation.

S. A portion of the roof is ballast and the other is regular EPDM but it's unclear if the ballast portion of the roof will be replaced with new ballast or discarded altogether and replaced with only EPDM or if both sections will be ballasted.

Answer: Both sections of the roof will be only EPDM with no ballast.

2. To incorporate the revised Scope of Work, dated 11 July 2022

3. To incorporate the following revised sections of Appendix A, Specifications

a. Specification Section 07 22 00, dated 15 July 2022

b. Specification Section 07 53 23, dated 15 July 2022

c. Specification Section 07 60 00, dated 15 July 2022

4. To incorporate revised Submittal Register, dated 14 July 2022

5. To provide POC information for submitting proposals.

***********IMPORTANT************

COPY THE FOLLOWING WHEN SUBMITTING YOUR PROPOSALS

JULIE.K.CULLITON.CIV@ARMY.MIL

DAVID.M.WEINDRUCH.CIV@ARMY.MIL

6. All other terms and conditions remain unchanged.

(End of Summary of Changes)