This document is a pre-proposal site visit presentation for a federal construction contract concerning the Rio de la Plata Flood Control Project in Dorado and Toa Baja, Puerto Rico. The U.S. Army Corps of Engineers is soliciting construction services under Solicitation No. W51DQV26RA002 for Supplemental Contract 1, which represents approximately $300,000,000 to $400,000,000 in estimated construction value. The contract type is firm-fixed-price Design-Bid-Build Construction using FAR Part 15 negotiations with full and open competition. Proposals must be submitted electronically via the Procurement Integrated Enterprise Environment (PIEE) by July 17, 2026, at 10:00 AM (AST). The estimated period of performance is 1,619 calendar days following the Notice to Proceed, with liquidated damages assessed at $23,940 per calendar day of delay. The contractor must perform 30% of the work with their own forces. A bid guarantee of 20% of the bid price or $3,000,000, whichever is less, is required, along with payment and performance bonds equal to the total bid price within 10 days of award. A subcontracting plan is mandatory for other than small business firms.
The project involves comprehensive river engineering and infrastructure work including approximately 1.78 million cubic meters of channel excavation, 772,000 cubic meters of levee fill placement, 160,000 cubic meters of scour protection stone placement, four concrete culvert structures (two on the west levee, two on the east levee), maintenance roads on levee crests, drainage ditches, and utility relocations for water lines, sewer lines, and electrical distribution systems. Key construction considerations include coordination with two municipalities, concurrent construction projects, traffic maintenance coordination with state agencies (DTOP and PRHTA), communication with La Plata Dam operators regarding water releases, and seismic remediation of soft soils through foundation treatment options. Technical inquiries must be submitted via ProjNet (Bidder Inquiry Key: H7UFYV-N7MD93) with closure ten calendar days prior to bid closing. All amendments must be acknowledged in block 19 of Standard Form 1442, with bidders required to monitor SAM.gov and PIEE for published amendments. The site visit will depart from Gazebo Rio de la Plata in Dorado, with four planned stops at specified GPS coordinates to view the project area.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Site_Visit_Sign_In_Sheet_W51DQV26RA002_25June2026.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RIO DE LA PLATA FLOOD CONTROL
PROJECT, SUPPLEMENTAL
CONTRACT 1
DORADO AND TOA BAJA, PUERTO
RICO
PRE-PROPOSAL SITE VISIT
RIO DE LA PLATA
LOCATION: Dorado and Toa Baja, PR, about 11 miles west of San Juan
PROJECT IMPLEMENTATION:
DORADO BRIDGE CWSP PROJECT (Ongoing) River channel widening and modifications (0.46 miles), construction of earthen levee (0.53 miles), and scour protection
ARTICULATED CONCRETE BLOCK MAT AND
TOE KEY (Substantially Complete) 500 feet of channel scour protection and toe key revetment
SUPPLEMENTAL CONTRACT 1
River channel widening and modifications (approx. 1.6 miles), construction of earthen levees (approx. 3.1 miles), four concrete culverts through levee, scour protection, and utility relocations
SUPPLEMENTAL CONTRACT 3
River channel widening and modifications (approx. 1.4 miles), construction of earthen levee (approx. 1.3 miles), scour protection, and utility relocations
SUPER-AQUEDUCT RELOCATION
Relocation of a 72-inch water supply aqueduct
Disposal Area
East Levee
West Levee
Disposal Area
Disposal Area
East Levee
Channel
Channel
72” Water Line
Dorado Bridge
PR HWY-2
PR HWY-22
Wetland Mitigation
RDLP CONTRACT 1
MAIN PROJECT FEATURES:
• 1,780,000 m3 channel excavation
• 772,000 m3 levee fill placement
• 160,000 m3 scour protection stone placement
• 4 – concrete culvert structures (2 - west levee, 2 - east levee)
• Pre-cast concrete pipe (5-7 feet in diameter)
• Cast-in-place concrete inlet and outlet head walls
• Composite flap gates (west levee culverts)
ADDITIONAL PROJECT FEATURES:
• Maintenance road on levee crest and within project boundaries
• Drainage ditches
• Utility relocations
• Water lines
• Sewer lines
• Electrical lines
• Material Management Areas for excavated material
• Remaining Wetland mitigation for the project
• Demolition of abandoned structures
Levee
Channel
Culverts
Culverts
CONTRACT 1 TYPICAL CROSS-SECTION
East Levee
Stone Protection
West Levee Stone Protection
Channel Centerline
Channel Centerline
WEST LEVEE CULVERT 3A
Key Details
• 5 - 84-inch Precast Culvert
• Flap Gates
• Cast-in-place Headwalls
WEST LEVEE CULVERT 11
Key Details
• 2 - 72-inch Precast Culvert
• Flap Gates
EAST LEVEE CULVERT 6A
Key Details
• 60-inch Precast Culvert
• Ungated
• Stone Energy Dissipation Basin
EAST LEVEE CULVERT 7
Key Details
• 48-inch Precast Culvert
• Ungated
• Stone Energy Dissipation Basin
SEISMIC REMEDIATION
Soft soils may require foundation treatment
Possible Options:
• Culvert 3A, 6A and 7– throughout foundation footprint
East Levee, stone columns eliminated and replaced with stage construction
Will promptly restore levee geometry in case of seismic induced deformations.
Include in O&M Manual for the project.
UTILITY RELOCATIONS
Sanitary Sewer
• 12-inch force main (Relocation)
• 8-inch sanitary (Protect in Place)
Potable Water (Treated Drinking Water)
• 12-inch (Protect in Place – Multiple Locations)
Electrical Distribution and Transmission Lines
• 8.32/4.8kV (Relocation)
• 38kV (Relocation)
Telecommunication
• None
CONSTRUCTION CONSIDERATIONS
• Coordination with two municipalities (Dorado and Toa Baja)
• Other concurrent USACE/non-USACE construction project
• Construction access
• Coordination with DTOP and PRHTA for maintenance of traffic
• Communication with La Plata Dam (PRASA)
• Release of water from dam may impact construction activities
• Utility relocations
• PRASA and LUMA
• Coordination with utility agencies to limit impacts to service
• Sufficient work limits for staging and field office
• High water events on La Plata River are short duration
CONTRACTING OVERVIEW
Jaclyn Yocum Contract Specialist
Renee Booth Contracting Officer
File Name
ACQUISITION APPROACH
• Solicitation No. W51DQV26RA002
• Type of contract: Firm-fixed-price Design-Bid-Build Construction
• Acquisition Method: FAR Part 15 Negotiations – Request for Proposal (RFP), Full and Open Competition (Unrestricted)
• Transmission Method: Electronically via Procurement Integrated Enterprise Environment (PIEE). Bids must be received by the Government no later than July 17, 2026, at 10:00 am (AST).
• Estimated Magnitude of Construction: $300,000,000 - $400,000,000
• North American Industry Classification System (NAICS): 237990, Other Heavy and Civil Engineering Construction
• Estimated Period of Performance: 1619 calendar days after receipt of the Notice to Proceed (NTP)
• Liquidated Damages (FAR 52.211-12): $23,940.00 for each calendar day of delay until the work is completed or accepted
• Performance of Work by the Contractor: 30%
PROJECT GENERAL INFO
• Technical Inquiries and Questions: shall be submitted via Bidder Inquiry in ProjNet at (https://www.projnet.org). ProjNet closes ten (10) calendar days prior to bid closing. Bidders inquiries must be entered into ProjNet for an official answer.
• Bid Guarantee: an electronic copy of the bid guarantee shall be submitted with the bid. The bid guarantee shall be 20% of bid price or $3,000,000, whichever is less.
• Payment and Performance Bonds: awardee must submit payment and performance bonds equal to the total bid price within 10 days of contract award.
• Note: Subcontracting Plan is required from Other than Small Business Firms (FAR Part 19)
PROJECT GENERAL INFORMATION
https://www.projnet.org/
• All amendments must be acknowledged in block 19 of the Standard Form (SF 1442) Solicitation
1. Make sure to monitor SAM.gov and PIEE for any amendments to be published.
AMENDMENTS
RESOURCES 17
• Systems for Award Management (SAM): www.sam.gov
• ProjNet: www.projnet.org Bidder Inquiry Key: H7UFYV-N7MD93
• Procurement Integrated Enterprise Environment (PIEE): https://piee.eb.mil
1. The only authorized transmission method of proposals in response to the subject solicitation is electronically via the Procurement Integrated Enterprise Environment (PIEE) website. No other transmission methods, such as email, facsimile, hand-carried, proprietary or DOD SAFE submissions, proposals submitted by mail, etc. will be accepted. Offers submitted via any other transmission method other than the PIEE website will not be evaluated.
2. The Offeror’s proposal/bid must be received by the Government no later than the date/time specified in the solicitation and cited above.
http://www.sam.gov/ http://www.projnet.org/ http://www.projnet.org/ http://www.projnet.org/ https://piee.eb.mil/ https://piee.eb.mil/ https://piee.eb.mil/ https://piee.eb.mil/ https://piee.eb.mil/ https://piee.eb.mil/
SITE VISIT – MEET LOCATION
Meet at
GAZEBO RIO DE LA PLATA,
Dorado
SITE VISIT PLAN
Site visit Coordinates:
Start:
18°27'27.7"N 66°15'31.3"W
Stop 2:
18°26'50.50"N 66°15'22.74"W
Stop 3:
18°26'10.28"N 66°15'16.25"W
Stop 4:
18°25'25.85"N 66°15'7.36"W
| RIO DE LA PLATA FLOOD CONTROL PROJECT, SUPPLEMENTAL CONTRACT 1��DORADO AND TOA BAJA, PUERTO RICO� |
| RIO DE LA PLATA |
| RDLP CONTRACT 1 |
| contract 1 Typical cross-section |
| West levee Culvert 3a |
| West levee culvert 11 |
| East levee culvert 6a |
| East levee culvert 7 |
| SEISMIC REMEDIATION |
| Utility relocations |
| Construction considerations |
| CONTRACTING OVERVIEW |
| Acquisition approach |
| PROJECT GENERAL INFO |
| Project General Information |
| AMENDMENTS |
| resources |
| Site visit – meet location |
| Site visit plan |
File details come from the government source that posted it. Updated .